c:userssean mackenziedocumentsfamiliesdenison phase i-site

7
M TO VFD ATS T1 Y 45KVA T CT PT G 52 27 47 49 49A 49T 50 G 51 50 51 59 64 90V J J M M SPD PC TC CP LC G (#) G Motor Load Fusible Safety Switch Switch xx/xx/xx = amps/poles/fuse Non-Fused Safety Switch Switch xx/xx = amps/poles Motor Starter Combination Disconnect and Motor Starter Manual Motor Starter with Thermal Overload Variable Frequency Drive Automatic Transfer Switch (plan view) Automatic Transfer Switch (one line) Bypass Automatic Transfer Switch MV Transformer Dry Type Transformer Current Transformer (CT) Potential Transformer (PT) Generator Circuit Breaker (rating as shown on drawings) Drawout Circuit Breaker (rating as shown on drawings) MV Circuit Breaker (rating as shown on drawings) MV Load Interrupter Switch Fusible Branch Switch Unit MV Fuse 600V Fuse Element Grounding Electrode System MV Surge Arrestor Lightning Surge Arrestor MV Termination Under Voltage Relay Phase Sequence Voltage Relay Thermal Relay Transformer Temperature Relay - Alarm Condition Transformer Temperature Relay - Trip Condition Instantaneous and Inverse Time Overcurrent Trip Relay Instantaneous and Inverse Time Overcurrent Trip Relay with Ground Fault Overvoltage Relay Ground Detector Relay Voltage Regulator Normally Open Contact Normally Closed Contact Ground Rod in Ground Well Junction Box Push Button Station Utility Meter Energy Monitoring & Power Meter Surge Protective Device Photocell Timeclock Control Panel Lighting Contactor Surface Mounted Panelboard Flush Mounted Panelboard Equipment Identification Tag 1) See equipment schedules for equipment type 2) (#) = Branch circuit as noted on drawing where indicated Legend Power Symbols Power Symbols (cont.) Conduit and Raceway Symbols Conduit Concealed Conduit Below Grade; in Slab On Grade; or Below Finished Floor Indicates Conduit Turning Up Indicates Conduit Turning Down Conduit with Bushing Conduit with Cap Flexible Conduit Conduit Homerun; Route to Indicated Panelboard, Switchboard, etc. P-1 = Panelboard and Branch Circuit Designation / / / = Cable Count P-1 Interior Lighting Symbols Recessed Fluorescent Light Fixture Down Light Decorative Wall Sconce Linear Fluorescent Wall Bracket Undercabinet Task Light Fluorescent Strip Light Lighting Track with Fixture Heads (length as shown on plans) Double-Head Emergency Light with Battery Pack Recessed Emergency Egress Light Fixture with Backup Power Ceiling Mounted Exit Sign (arrows and faces as shown on drawings) Wall Mounted Exit Sign (arrows and faces as shown on drawings) Duplex Receptacle Outlet: AC = Above Counter AFCI = Arc-Fault Circuit-Interrupter Protection AG = Above Counter GFCI GFCI = Ground-Fault Circuit-Interrupter Protection IG = Isolated Ground USB = Combination Duplex Power Outlet (2 outlets) with two USB Charger Outlets WG = Weather-Proof GFCI WP = Weather-Proof Duplex Receptacle Outlet, Ceiling Mounted Duplex Receptacle Outlet (connected to inverter power) Split-wired Duplex Receptacle Outlet (switched) Single Receptacle Outlet Single Receptacle Outlet (connected to inverter power) Double Duplex Receptacle Outlet Double Duplex Receptacle Outlet (connected to inverter power) Special Purpose Receptacle Outlet (rating as shown on dwgs) Multi-Outlet Plug Strip (type, outlets, and spacing as noted) Floor Mounted Duplex Receptacle Single Pole Switch: a, b, c, . etc. = indicates switch leg 3 = Three-way Switch 4 = Four-Way Switch D = Dimmer P = Pilot Light PS = Projection Screen Raise/Lower Operator Switch K = Key Operated WP = Weather-Proof While-In-Use m = Momentary Contact Switch - Lighting Control System Input Device Wiring Device Symbols Wall Mounted Occupancy Sensor - Adaptive Dual-Technology (unless noted otherwise) Ceiling Mounted Occupancy Sensor - Adaptive Dual-Technology (arrows indicate coverage pattern) Occupancy Sensor Power Pack Pole Mounted Area Light (fixture head configuration as shown) Exterior Lighting Symbols Smoke Detector CO Detector XXX C Wall Switch Occupancy Sensor - Two-Circuit Adaptive Dual-Technology (unless noted otherwise) Decorative Pole Mounted Area Light Floor Mounted Double Duplex Receptacle a OS OS OS PP Fire Alarm Symbols S CO E A F G H D B C I J K Subject to approval from Civil, utility box shall be min. tier 5 rated per ANSI/SCTE-77 and constructed of high density reinforced or polymer concrete box with non-settling shoulders positioned to maintain grade and facilitate back filling. Typical dimensions are shown above. Crushed rock in bottom of utility box shall meet ASTM C33, latest revision, size #67, 3/4" to #4. Rock quality to conform to quality specified in CDOT standard specfications for asphalt mixtures. Conduit set in bases shall extend 2" to 3" vertically from the top of the base. A plastic or metal conduit bushing shall be installed on the end of all conduit terminating within the base. Conduit shall enter through the sides of a pull box and shall leave the major portion of the box clear. Conduit entering utility boxes shall not extend more than 5" inside of utility box as measured along the longitudinal axis of the conduit. Conduit entering utility boxes shall be at least 6" above the crushed rock bottom of theservice hole. Conduit shall be sloped to drain as appropriate. At all outlets, conduits shall enterfrom the direction of the run. Lid shall be permanently marked to indicate underground electrical and secured with a tamper resistant bolt(s) and/or lockable attachment. UTILITY BOX DIMENSIONS #5 #6 #8 A 12 12 24 B 19 1/4 21 1/2 64 1/2 C 14 1/4 20 35 D 8 1/2 13 3/4 27 E 14 25 1/4 57 F 10 1/2 26 1/2 60 G 17 1/4 15 3/4 30 H 1 1 3 I 15 1/2 22 3/4 59 1/2 J 10 15 30 1/8 K 1 1/2 2 3 12" PER 2014 NEC TABLE 300.5 POWER CONDUCTORS OR CONDUIT. PROVIDE MIN. 7 1/2" OC SEPARATION BETWEEN CONDUIT. PROVIDE MIN. 12" SEPARATION BETWEEN DIRECT BURIED TRIPLEXED CIRCUITS. METALLIC WARNING TAPE FINISHED GRADE BACKFILL AND COMPACTION REQUIREMENTS PER CIVIL. RACEWAY, COVERAGE, TRENCH ZONE AND BEDDING MATERIAL TO COMPLY WITH 2014 NEC SECTION 300.5. _________________________ Consulting Engineers Mechanical Structural Energy reginc.com 970.349.1216 efficiency | sustainability | simplicity Resource Engineering Group Project number Engineered By Reviewed By please recycle these drawings E001 Electrical General Notes and Legend 2586 Jared Marchand, PE Denison Affordable Housing Breckenridge, CO Sean Mackenzie 1. The complete electrical installation shall be in accordance with the most recent adopted electrical codes. 2. Furnish all labor, materials, equipment and services necessary to construct and install complete and operational electrical systems indicated on the drawings. 3. Prior to bidding, visit the job site to review the existing utilities and systems related to the work and include in the bid proposal all labor and materials required for the electrical installation to be complete and operational. 4. Verify all existing site conditions in the field before commencement of the work and shall report any discrepancies and/or inconsistencies between the drawing, specifications and existing field conditions to the owner for clarifications before commencement of the work. 5. Provide ground conductors in all feeder and branch circuit wiring. 6. Provide typewritten directories for all electrical panels involved in this project. The panel directories shall reflect the as-built circuits. Enclose a copy in a transparent plastic cover and mounted on the inside of the panel door. 7. Support and anchor electrical equipment and feeders in accordance with International Building Code requirements. 8. Maintain at the job site, an up-to-date "as-built" drawing set. The "as-built" drawing set shall reflect all approved changes to the design drawings. The "as-built" drawing set shall be kept clean and in good condition and shall be turned over to the owner at the completion of the project. 9. Upon completion of work, the contractor perform a complete functional test to demonstrate to the user that the new installation is operating as intended. Any defects or deficiencies in the materials or installation work shall be corrected immediately by and at the contractor's expense. 10. Clean work area daily and remove all debris. Safe work area must always be maintained. At the completion of the project, the work area must be cleared of all debris to the satisfaction of the owner. 11. Replace any materials damaged by the contractor with new exact replacement materials, to the satisfaction of the owner. Contractor shall bear the total cost of such replacement. 12. Identify all conductors at each junction box, outlet box, cabinet, pull box, etc. with vinyl cloth self-adhesive tags showing panel and circuit numbers, circuit type, control wire numbers or other appropriate information. 13. Outlet locations shown on floor plans are approximate. All outlet locations to be coordinated with Architect and aligned with architectural features as required. Adjustments to layout and final locations of outlets may require additional outlets to ensure compliance with the NEC. General Notes A, AMP Ampere AC Alternating Current AC Above Counter Top AG Above Counter GFCI AIC Ampere Interrupting Capacity AFCI Arc Fault Circuit Interrupting AFD Adjustable Frequency Drive AFF Above Finished Floor AFG Above Finished Grade AHJ Authority Having Jurisdiction ATS Automatic Transfer Switch AF Frame Rating in Amperes AS Switch Rating in Amperes AT Trip Rating in Amperes AWG American Wire Gauge AV Audio Video C Conduit CL Centerline CKT Circuit CLG Ceiling DIST Distribution (E) Existing To Remain (ER) Existing To Be Relocated (EX) Existing To Be Removed ELEC Electrical ELEV Elevator EM Emergency EMT Electrical Metallic Tubing EP Explosion Proof EWC Electric Water Cooler FA Fire Alarm FAAP Fire Alarm Annunciator Panel FACP Fire Alarm Control Panel FATC Fire Alarm Terminal Cabinet FUT Future FVNR Full-voltage, Non-reversing FVR Full-voltage, Reversing GFCI Ground Fault Circuit Interrupting G, GND Ground IG Isolated Ground HID High Intensity Discharge HOA Hand-Off-Auto HP Horsepower HPF High Power Factor LPI Lightning Protection Institute MCB Main Circuit Breaker MLO Main Lugs Only MTS Manual Transfer Switch NC Normally Closed NEC National Electrical Code NEMA National Electrical Manufacturer's Association NL Night Light NO Normally Open NTS Not To Scale OFCI Owner Furnished Contractor Installed PB Pull Box Ø, PH Phase PNL Panel PVC Rigid Polyvinyl Chloride Conduit PTS Pneumatic Tube Station PWR Power RMC Galvanized Rigid Metal Conduit SPD Surge Protective Device SWBD Switchboard SWGR Switchgear TB Terminal Backboard TTB Telephone Terminal Backboard TEL Telephone TVSS Transient Voltage Surge Suppressor TYP Typical UNO Unless Noted Otherwise V Volt VA Volt Amperes W Watt WG Weatherproof GFCI WP Weatherproof XFMR Transformer Abbreviations Project Information Building Jurisdiction Town of Breckenridge Applicable Codes 2014 NEC-NFPA 70 Utility Company Xcel Energy Electrical Service 120/240V, 1ø, 3W Drawing Index E001 Electrical General Notes and Legend E002 Electrical Site Power Plan E003 Electrical Power One Line Diagram E004 Electrical Power Schedules E005 Electrical Power Schedules E006 Electrical Site Lighting Plan E007 Electrical Lighting One Line Diagram, Schedules Issued for Date Permit Set 03-21-17 N.T.S. 1 Utility Box Detail N.T.S. 2 Electrical Trench Detail

Upload: others

Post on 16-Oct-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: C:UsersSean MackenzieDocumentsFamiliesDenison Phase I-SITE

M

TO

VFD

ATS

T1

Y

45KVA

T

CT

PT

G

52

27

47

49

49A

49T

50G51

5051

59

64

90V

J J

M

M

SPD

PC

TC

CP

LC

G

(#)

G

Motor Load

Fusible Safety SwitchSwitch xx/xx/xx = amps/poles/fuse

Non-Fused Safety SwitchSwitch xx/xx = amps/poles

Motor Starter

Combination Disconnect and MotorStarter

Manual Motor Starter with ThermalOverload

Variable Frequency Drive

Automatic Transfer Switch (plan view)

Automatic Transfer Switch (one line)

Bypass Automatic Transfer Switch

MV Transformer

Dry Type Transformer

Current Transformer (CT)

Potential Transformer (PT)

Generator

Circuit Breaker (rating as shown ondrawings)

Drawout Circuit Breaker (rating asshown on drawings)

MV Circuit Breaker (rating as shownon drawings)

MV Load Interrupter Switch

Fusible Branch Switch Unit

MV Fuse

600V Fuse Element

Grounding Electrode System

MV Surge Arrestor

Lightning Surge Arrestor

MV Termination

Under Voltage Relay

Phase Sequence Voltage Relay

Thermal Relay

Transformer Temperature Relay -Alarm Condition

Transformer Temperature Relay -Trip Condition

Instantaneous and Inverse TimeOvercurrent Trip Relay

Instantaneous and Inverse TimeOvercurrent Trip Relay with Ground Fault

Overvoltage Relay

Ground Detector Relay

Voltage Regulator

Normally Open Contact

Normally Closed Contact

Ground Rod in Ground Well

Junction Box

Push Button Station

Utility Meter

Energy Monitoring & Power Meter

Surge Protective Device

Photocell

Timeclock

Control Panel

Lighting Contactor

Surface Mounted Panelboard

Flush Mounted Panelboard

Equipment Identification Tag1) See equipment schedules for equipment type2) (#) = Branch circuit as noted on drawing where indicated

Legend

Power Symbols Power Symbols (cont.)

Conduit and Raceway Symbols

Conduit Concealed

Conduit Below Grade; in Slab On Grade;or Below Finished Floor

Indicates Conduit Turning Up

Indicates Conduit Turning Down

Conduit with Bushing

Conduit with Cap

Flexible Conduit

Conduit Homerun; Route to IndicatedPanelboard, Switchboard, etc. P-1 = Panelboard and Branch Circuit

Designation / / / = Cable Count

P-1

Interior Lighting Symbols

Recessed Fluorescent Light Fixture

Down Light

Decorative Wall Sconce

Linear Fluorescent Wall Bracket

Undercabinet Task Light

Fluorescent Strip Light

Lighting Track with Fixture Heads(length as shown on plans)

Double-Head Emergency Light withBattery Pack

Recessed Emergency Egress LightFixture with Backup Power

Ceiling Mounted Exit Sign (arrowsand faces as shown on drawings)

Wall Mounted Exit Sign (arrows andfaces as shown on drawings)

Duplex Receptacle Outlet: AC =Above Counter AFCI =Arc-Fault Circuit-Interrupter Protection AG =Above Counter GFCI GFCI = Ground-Fault Circuit-Interrupter

Protection IG = Isolated Ground USB = Combination Duplex Power Outlet

(2 outlets) with two USB ChargerOutlets

WG =Weather-Proof GFCI WP = Weather-ProofDuplex Receptacle Outlet, Ceiling Mounted

Duplex Receptacle Outlet (connected toinverter power)

Split-wired Duplex Receptacle Outlet(switched)

Single Receptacle Outlet

Single Receptacle Outlet (connected toinverter power)

Double Duplex Receptacle Outlet

Double Duplex Receptacle Outlet (connectedto inverter power)

Special Purpose Receptacle Outlet (ratingas shown on dwgs)

Multi-Outlet Plug Strip (type, outlets, andspacing as noted)

Floor Mounted Duplex Receptacle

Single Pole Switch:a, b, c, . etc. = indicates switch leg3 = Three-way Switch4 = Four-Way SwitchD = DimmerP = Pilot LightPS = Projection Screen Raise/Lower Operator SwitchK = Key OperatedWP = Weather-Proof While-In-Usem = Momentary Contact Switch - Lighting Control System Input Device

Wiring Device Symbols

Wall Mounted Occupancy Sensor -Adaptive Dual-Technology (unless notedotherwise)

Ceiling Mounted Occupancy Sensor -Adaptive Dual-Technology (arrows indicatecoverage pattern)

Occupancy Sensor Power Pack

Pole Mounted Area Light (fixture headconfiguration as shown)

Exterior Lighting Symbols

Smoke Detector

CO Detector

XXX

C

Wall Switch Occupancy Sensor -Two-Circuit Adaptive Dual-Technology(unless noted otherwise)

Decorative Pole Mounted Area Light

Floor Mounted Double Duplex Receptacle

a

OS

OS

OS

PP

Fire Alarm Symbols

S

CO

E

A

F

G

H

D

BC

IJ

K

Subject to approval from Civil, utility box shall be min. tier 5 rated per ANSI/SCTE-77 and constructed of highdensity reinforced or polymer concrete box with non-settling shoulders positioned to maintain grade andfacilitate back filling. Typical dimensions are shown above. Crushed rock in bottom of utility box shall meetASTM C33, latest revision, size #67, 3/4" to #4. Rock quality to conform to quality specified inCDOT standard specfications for asphalt mixtures. Conduit set in bases shall extend 2" to 3" vertically from the top of the base. A plastic or metal conduit bushing shall be installed on the end of all conduitterminating within the base. Conduit shall enter through the sides of a pull box and shall leave the majorportion of the box clear. Conduit entering utility boxes shall not extend more than 5" inside of utility boxas measured along the longitudinal axis of the conduit. Conduit entering utility boxes shall be at least 6" above the crushed rock bottom of theservice hole. Conduit shall be sloped to drain as appropriate. At alloutlets, conduits shall enterfrom the direction of the run. Lid shall be permanently marked to indicateunderground electrical and secured with a tamper resistant bolt(s) and/or lockable attachment.

UTILITY BOX DIMENSIONS

#5 #6 #8

A 12 12 24B 19 1/4 21 1/2 64 1/2C 14 1/4 20 35D 8 1/2 13 3/4 27E 14 25 1/4 57F 10 1/2 26 1/2 60G 17 1/4 15 3/4 30H 1 1 3I 15 1/2 22 3/4 59 1/2J 10 15 30 1/8K 1 1/2 2 3

12"

PER 2014 NEC TABLE 300.5

POWER CONDUCTORS ORCONDUIT. PROVIDE MIN. 7 1/2" OCSEPARATION BETWEEN CONDUIT.PROVIDE MIN. 12" SEPARATIONBETWEEN DIRECT BURIED TRIPLEXEDCIRCUITS.

METALLIC WARNING TAPE

FINISHED GRADE

BACKFILL AND COMPACTIONREQUIREMENTS PER CIVIL.

RACEWAY, COVERAGE, TRENCH ZONEAND BEDDING MATERIAL TO COMPLYWITH 2014 NEC SECTION 300.5.

_________________________

Consulting EngineersMechanical ▪ Structural ▪ Energy

reginc.com ▪ 970.349.1216

efficiency | sustainability | simplicity

Resource Engineering Group

Project number

Engineered By

Reviewed By

please recycle these drawings

E001

Electrical General Notesand Legend

2586

Jared Marchand, PE

DenisonAffordableHousing

Breckenridge, CO

Sean Mackenzie

1. The complete electrical installation shall be in accordance with the most recent adopted electrical codes.2. Furnish all labor, materials, equipment and services necessary to construct and install complete and operational electrical systems

indicated on the drawings.3. Prior to bidding, visit the job site to review the existing utilities and systems related to the work and include in the bid proposal all

labor and materials required for the electrical installation to be complete and operational.4. Verify all existing site conditions in the field before commencement of the work and shall report any discrepancies and/or

inconsistencies between the drawing, specifications and existing field conditions to the owner for clarifications beforecommencement of the work.

5. Provide ground conductors in all feeder and branch circuit wiring.6. Provide typewritten directories for all electrical panels involved in this project. The panel directories shall reflect the as-built circuits.

Enclose a copy in a transparent plastic cover and mounted on the inside of the panel door.7. Support and anchor electrical equipment and feeders in accordance with International Building Code requirements.8. Maintain at the job site, an up-to-date "as-built" drawing set. The "as-built" drawing set shall reflect all approved changes to the

design drawings. The "as-built" drawing set shall be kept clean and in good condition and shall be turned over to the owner at thecompletion of the project.

9. Upon completion of work, the contractor perform a complete functional test to demonstrate to the user that the new installation isoperating as intended. Any defects or deficiencies in the materials or installation work shall be corrected immediately by and at thecontractor's expense.

10. Clean work area daily and remove all debris. Safe work area must always be maintained. At the completion of the project, the workarea must be cleared of all debris to the satisfaction of the owner.

11. Replace any materials damaged by the contractor with new exact replacement materials, to the satisfaction of the owner. Contractorshall bear the total cost of such replacement.

12. Identify all conductors at each junction box, outlet box, cabinet, pull box, etc. with vinyl cloth self-adhesive tags showing panel andcircuit numbers, circuit type, control wire numbers or other appropriate information.

13. Outlet locations shown on floor plans are approximate. All outlet locations to be coordinated with Architect and aligned witharchitectural features as required. Adjustments to layout and final locations of outlets may require additional outlets to ensurecompliance with the NEC.

General Notes

A, AMP AmpereAC Alternating CurrentAC Above Counter TopAG Above Counter GFCIAIC Ampere Interrupting CapacityAFCI Arc Fault Circuit InterruptingAFD Adjustable Frequency DriveAFF Above Finished FloorAFG Above Finished GradeAHJ Authority Having JurisdictionATS Automatic Transfer SwitchAF Frame Rating in AmperesAS Switch Rating in AmperesAT Trip Rating in AmperesAWG American Wire GaugeAV Audio VideoC ConduitCL CenterlineCKT CircuitCLG CeilingDIST Distribution(E) Existing To Remain(ER) Existing To Be Relocated(EX) Existing To Be RemovedELEC ElectricalELEV ElevatorEM EmergencyEMT Electrical Metallic TubingEP Explosion ProofEWC Electric Water CoolerFA Fire AlarmFAAP Fire Alarm Annunciator PanelFACP Fire Alarm Control PanelFATC Fire Alarm Terminal CabinetFUT FutureFVNR Full-voltage, Non-reversingFVR Full-voltage, ReversingGFCI Ground Fault Circuit InterruptingG, GND GroundIG Isolated GroundHID High Intensity DischargeHOA Hand-Off-AutoHP HorsepowerHPF High Power FactorLPI Lightning Protection InstituteMCB Main Circuit BreakerMLO Main Lugs OnlyMTS Manual Transfer SwitchNC Normally ClosedNEC National Electrical CodeNEMA National Electrical Manufacturer's AssociationNL Night LightNO Normally OpenNTS Not To ScaleOFCI Owner Furnished Contractor InstalledPB Pull BoxØ, PH PhasePNL PanelPVC Rigid Polyvinyl Chloride ConduitPTS Pneumatic Tube StationPWR PowerRMC Galvanized Rigid Metal ConduitSPD Surge Protective DeviceSWBD SwitchboardSWGR SwitchgearTB Terminal BackboardTTB Telephone Terminal BackboardTEL TelephoneTVSS Transient Voltage Surge SuppressorTYP TypicalUNO Unless Noted OtherwiseV VoltVA Volt AmperesW WattWG Weatherproof GFCIWP WeatherproofXFMR Transformer

Abbreviations

Project Information

Building Jurisdiction Town of BreckenridgeApplicable Codes 2014 NEC-NFPA 70Utility Company Xcel EnergyElectrical Service 120/240V, 1ø, 3W

Drawing IndexE001 Electrical General Notes and Legend

E002 Electrical Site Power Plan

E003 Electrical Power One Line Diagram

E004 Electrical Power Schedules

E005 Electrical Power Schedules

E006 Electrical Site Lighting Plan

E007 Electrical Lighting One Line Diagram,Schedules

Issued for Date

Permit Set 03-21-17

N.T.S.1

Utility Box Detail

N.T.S.2

Electrical Trench Detail

Page 2: C:UsersSean MackenzieDocumentsFamiliesDenison Phase I-SITE

BLDG 16

BLDG 17

XFMR-D11

XFMR-D12

XFMR-D13

XFMR-D14

XFMR-D15

BLDG 14

BLDG 15

BLDG 18

BLDG 19BLDG 03

BLDG 02

BLDG 01

BLDG 04

BLDG 05

BLDG 09

BLDG 13

BLDG 08

BLDG 12

BLDG 11BLDG 06

BLDG 10

BLDG 07

XFMR-D16

XFMR- D18

XFMR-D19

A

B

C

D

A

B

C

A

B

C

A

B

C

A

B

C

D

A

B

C

D

A

B

C

D

A

B

C

A

B

C

D

A

B

C

D

A

B

C

D

A

B

C

A

B

C

ABC

A

B

C

A

B

C

A

B

C

S-01

S-02

S-03

S-04

S-05

S-09

S-08

S-07

S-06

S-10

S-11

S-12

S-13

S-14

S-15

S-18

S-19

LM3

LM1-Town

LM4

LM2-Town

(See Site Lighting)

(See Site Lighting)

(See Site Lighting)

(See Site Lighting)

SL4

SL2

SL3

SL11

1

P

P

P

P

P

2

3

3

3

S-16

S-17

3

Trash/Storage

Trash

Trash/Storage/Carport

1

1

4

4

General notes this sheet:

1. Primary utility distribution design by Xcel Energy TBD. Based on correspondence withXcel Energy, assume typical transformer rating to be 100kVA, 29.6kA AFC, Z=1.4%.

2. Electrical design for BLDG 16 and BLDG 17 to be provided in future revision.3. Current design does not show distribution to accessory buildings (i.e. storage, trash,

carports). Please provide alternate pricing for the following distribution strategies:(A) Provide a 100 A combination meter/breaker unit for each accessory

building with capacity to provide branch circuiting per Architect. Assume50' of additional trenching beyond what's currently shown on E002.

(B) Provide a 100 A NEMA 1 house panel in each accessory building with capacity to provide branch circuiting per Architect. House panel to be fedfrom L3 and L4 combination meter breakers. Assume 250' of additionaltrenching beyond what's currently shown on E002.

_________________________

Consulting EngineersMechanical ▪ Structural ▪ Energy

reginc.com ▪ 970.349.1216

efficiency | sustainability | simplicity

Resource Engineering Group

Project number

Engineered By

Reviewed By

please recycle these drawings

E002

Electrical Site Power Plan

2586

Jared Marchand, PE

DenisonAffordableHousing

Breckenridge, CO

Sean Mackenzie

Issued for Date

Permit Set 03-21-17

1" = 30'-0"1

Site Power Plan

Sheet Notes:

1. Reference sheet E007 for site lighting feeder schedule.

2. Electrical utility box, typ. Reference detail 01/E001 for more information.

3. Underground feeder sizing assumes each service is run independently in conduit. Consult with engineer if multiple services in a shared conduit is the preferred

installation method.

4. Town monitored site lighting meter centers (L-1 & L2) to be pedestal mounted.

1

2

3

4

Page 3: C:UsersSean MackenzieDocumentsFamiliesDenison Phase I-SITE

M

M

M

M

S

T

Xcel PadmountTransformer

(ref. Site Power Plan)

GroundingSchematic

G

J1

J2

J2

J1

Detail notes this sheet:

Reference Site Power Plan for specific utility transformer source.

Pad-mounted transformer furnished by Xcel Energy. Coordinate constructionrequirements with Xcel Energy. Assumes 100kVA, 29.6A AFC, Z=1.4% transformerrating per coordination with Loren Vawser, Designer, Xcel Energy - Mountain Division.

Provide one meter center for each townhouse building. Reference drawing E002for locations and feeder routing.

All individual dwelling unit metering and disconnects to be hot sequenced. ReferenceMeter Center Schedules for number and rating of Dwelling Unit Panels to be meteredper building type.

Reference Meter Center Schedules for dwelling unit panel ratings and requirements.

Grounding electrode conductor to include connection to water or fire protection mainwithin first 5 feet of pipe entrance per NEC Art. 250.68 (C)(1) and 250.52 (A)(1).

Grounding electrode conductor to include connection to concrete-encased electrode perNEC Art. 250.66 (B) and 250.52 (A)(3).

Grounding electrode conductor to include connection to supplemental ground rod perNEC Art. 250.66 (A) , 250.52 (A)(5) and 250.53.

Provide grounding bar at service entrance to distribute grounding connection(s) toapplicable electrodes as shown.

Intersystem bonding termination to be provided at service entrance per NEC Art.250.94.

1

2

3

4

5

6

7

UtilityPrimary

XX/2

XX/2

XX/2

XX/2

T

M01-M19

U

01-19,A-D

MAIN LUG TERMINAL BOX

Service Lateral(see Feeder Schedule)

Meter CenterAvailableFault Current(see Short CircuitSchedule)

Unit Feeder(see Feeder Schedule)

Dwelling Unit PanelAvailable Fault Current(see Short Circuit Schedule)

Dwelling Unit Panels

METER PACK

METER CENTER(see Meter Center Schedules for specifications)

P

1

2

3

4

5

6

7

8

9

10

Grounding Conductor(Ref. Grounding & BondingSchedule for building specificconductor size)

A

Unit Feed

B

C

D

8

9

10

General notes this sheet:

1. All equipment subject to approval by Xcel Energy prior to installation. Reference XcelEnergy's "Standard for Electric Installation and Use", most current edition, for equipmentstandards and guidlines.

_________________________

Consulting EngineersMechanical ▪ Structural ▪ Energy

reginc.com ▪ 970.349.1216

efficiency | sustainability | simplicity

Resource Engineering Group

Project number

Engineered By

Reviewed By

please recycle these drawings

E003

Electrical Power One LineDiagram

2586

Jared Marchand, PE

DenisonAffordableHousing

Breckenridge, CO

Sean Mackenzie

Issued for Date

Permit Set 03-21-17N.T.S.

1Site Power One-Line Diagram

Page 4: C:UsersSean MackenzieDocumentsFamiliesDenison Phase I-SITE

_________________________

Consulting EngineersMechanical ▪ Structural ▪ Energy

reginc.com ▪ 970.349.1216

efficiency | sustainability | simplicity

Resource Engineering Group

Project number

Engineered By

Reviewed By

please recycle these drawings

E004

Electrical PowerSchedules

2586

Jared Marchand, PE

DenisonAffordableHousing

Breckenridge, CO

Sean Mackenzie

Issued for Date

Permit Set 03-21-17

E-Feeder Schedule

Feeder No. Description Feeder Conductors Ground Conductor Conduit Size Conductor Ampacity Calc. Load AmpacityCalc. Distance

(feet)Voltage Drop (by

run)

S-01 Building Service Lateral - BLDG# 01 1 Run [3-350 kcmil AL] 2 1/2" 250 A 183 A 200' 2.2%

S-02 Building Service Lateral - BLDG# 02 1 Run [3-250 kcmil AL] 2" 205 A 181 A 133' 1.9%

S-03 Building Service Lateral - BLDG# 03 1 Run [3-350 kcmil AL] 2 1/2" 250 A 234 A 125' 1.4%

S-04 Building Service Lateral - BLDG# 04 2 Run [3-3/0 AL] 2" 310 A 183 A 195' 2.6%

S-05 Building Service Lateral - BLDG# 05 2 Run [3-3/0 AL] 2" 310 A 271 A 86' 1.3%

S-06 Building Service Lateral - BLDG# 06 2 Run [3-3/0 AL] 2" 310 A 271 A 49' 0.7%

S-07 Building Service Lateral - BLDG# 07 2 Run [3-3/0 AL] 2" 310 A 271 A 71' 1.1%

S-08 Building Service Lateral - BLDG# 08 2 Run [3-3/0 AL] 2" 310 A 223 A 200' 2.5%

S-09 Building Service Lateral - BLDG# 09 2 Runs [3-4/0 AL] 2" 360 A 271 A 224' 2.7%

S-10 Building Service Lateral - BLDG# 10 2 Runs [3-4/0 AL] 2" 360 A 271 A 214' 1.7%

S-11 Building Service Lateral - BLDG# 11 1 Run [3-350 kcmil AL] 2 1/2" 250 A 223 A 210' 2.3%

S-12 Building Service Lateral - BLDG# 12 2 Run [3-3/0 AL] 2" 310 A 223 A 177' 2.7%

S-13 Building Service Lateral - BLDG# 13 2 Runs [3-4/0 AL] 2" 360 A 271 A 232' 2.3%

S-14 Building Service Lateral - BLDG# 14 1 Run [3-250 kcmil AL] 2" 205 A 182 A 139' 2.4%

S-15 Building Service Lateral - BLDG# 15 1 Run [3-250 kcmil AL] 2" 205 A 182 A 137' 1.5%

S-16 Building Service Lateral - BLDG# 16 TBD 0" 0 A 0 A 46' --

S-17 Building Service Lateral - BLDG# 17 TBD 0" 0 A 0 A 47' --

S-18 Building Service Lateral - BLDG# 18 1 Run [3-250 kcmil AL] 2" 205 A 201 A 77' 1.2%

S-19 Building Service Lateral - BLDG# 19 1 Run [3-250 kcmil AL] 2" 205 A 201 A 69' 1.1%

U¹ Dwelling Unit Feeder, typ. 1 Run [3-#1 AWG Cu, Type THHN] 1-#8 AWG Cu, Type THHN 1 1/2" 110 A 85 A 66' 1.4%

6. All electrical equipment to have 75ºC rated equipment lugs and terminals.

5. Installing contractor to coordinate with Architect and Xcel Energy for device labeling requirements.

4. All means of disconnect shall be hot sequenced.

3. Meter sockets shall be constructed of steel and equiped with ringless style covers, insulating track-resistant polycarbonate safety shield, and padlock seals per Xcel standards.

2. Metering cabinet shall have permanent barriers and separate covers to isolate unit disconnect switch and wiring area from the metering area per Xcel standards.

1. Meter center devices (metering cabinet, terminal box, meter sockets, and accessories) subject to approval of Xcel Energy.

Meter Center Notes:

Dwelling Unit - General Loads 21915 VA 43.90% 9620 VA Total Est. Demand Current: 182 A

Electric Range - 3.5 kW to 8.75 kW 15000 VA 55.00% 8250 VA Total Conn. Current: 277 A

Electric Clothes Dryer 15000 VA 100.00% 15000 VA Total Est. Demand: 43727 VA

Dwelling Unit - Appliance Loads 14475 VA 75.00% 10856 VA Total Conn. Load: 66390 VA

Load Classification Connected Load Demand Factor Estimated Demand Service Totals

Building Service Load Schedule:

5. Unit panel BB ratings shown are minimum ratings, typical. Higher rated panels may be provided at contractor's option.

4. Contractor to determine final number of circuit spaces required, alotting minimum 10% for spare capacity.

3. Reference architectural floorplans for specific locations.

2. All dwelling unit panels shall have a minimum fault current rating of 10kAIC. Reference Short Circuit Schedule for maximum available fault current.

1. All residential unit panels to be NEMA 1, 10 kAIC, 240/120V, 1PH, 3W, MLO unless otherwise noted

Dwelling Unit Panel Notes:

P-3 Unit Type: #3 100 A 100 A 2 17126 VA 71 A

P-2 Unit Type: #3 100 A 100 A 2 17126 VA 71 A

P-1 Unit Type: #3 100 A 100 A 2 17126 VA 71 A

Unit Panel Schedule Circuit Notes Unit Panel BB RatingService Disconnect (CB)

Rating Poles Loads

Dwelling Unit Service Schedule:

Enclosure: NEMA 3R

Mounting: Surface Wires: 3 Min. Terminal Bus Rating: 200 A

Supply From: See Site Power Plan Phases: 1 Metering Type: 320/400A, 5 terminal, lever bypass meter socket

Location: See Site Power Plan Volts: 120/240 Single A.I.C. Rating: See Short Circuit Schedule

Meter Center: Typ. Building Type - A1 (Bldg.# 14,15)

6. All electrical equipment to have 75ºC rated equipment lugs and terminals.

5. Installing contractor to coordinate with Architect and Xcel Energy for device labeling requirements.

4. All means of disconnect shall be hot sequenced.

3. Meter sockets shall be constructed of steel and equiped with ringless style covers, insulating track-resistant polycarbonate safety shield, and padlock seals per Xcel standards.

2. Metering cabinet shall have permanent barriers and separate covers to isolate unit disconnect switch and wiring area from the metering area per Xcel standards.

1. Meter center devices (metering cabinet, terminal box, meter sockets, and accessories) subject to approval of Xcel Energy.

Meter Center Notes:

Dwelling Unit - General Loads 42057 VA 39.64% 16670 VA Total Est. Demand Current: 223 A

Electric Range - 3.5 kW to 8.75 kW 15000 VA 55.00% 8250 VA Total Conn. Current: 375 A

Electric Clothes Dryer 15000 VA 100.00% 15000 VA Total Est. Demand: 53422 VA

Dwelling Unit - Appliance Loads 18003 VA 75.00% 13502 VA Total Conn. Load: 90060 VA

Load Classification Connected Load Demand Factor Estimated Demand Service Totals

Building Service Load Schedule:

5. Unit panel BB ratings shown are minimum ratings, typical. Higher rated panels may be provided at contractor's option.

4. Contractor to determine final number of circuit spaces required, alotting minimum 10% for spare capacity.

3. Reference architectural floorplans for specific locations.

2. All dwelling unit panels shall have a minimum fault current rating of 10kAIC. Reference Short Circuit Schedule for maximum available fault current.

1. All residential unit panels to be NEMA 1, 10 kAIC, 240/120V, 1PH, 3W, MLO unless otherwise noted

Dwelling Unit Panel Notes:

P-3 Unit Type: #4 125 A 125 A 2 20357 VA 85 A

P-2 Unit Type: #4 125 A 125 A 2 20357 VA 85 A

P-1 Unit Type: #4 125 A 125 A 2 20357 VA 85 A

Unit Panel Schedule Circuit Notes Unit Panel BB RatingService Disconnect (CB)

Rating Poles Loads

Dwelling Unit Service Schedule:

Enclosure: NEMA 3R

Mounting: Surface Wires: 3 Min. Terminal Bus Rating: 400 A

Supply From: See Site Power Plan Phases: 1 Metering Type: 320/400A, 5 terminal, lever bypass meter socket

Location: See Site Power Plan Volts: 120/240 Single A.I.C. Rating: See Short Circuit Schedule

Meter Center: Typ. Building Type - A2 (Bldg.# 8,11,12)

E-Grounding & Bonding Conductor ScheduleFeeder No. Description Ground Conductor

J1 Bonding Jumper 1-#6 AWG Cu

J2 Bonding Jumper 1-#4 AWG Cu

G1 Grounding Conductor - BLDG-# 01 1-1/0 AL

G2 Grounding Conductor - BLDG-# 02 1-#2 AWG AL

G3 Grounding Conductor - BLDG-# 03 1-1/0 AL

G4 Grounding Conductor - BLDG-# 04 1-1/0 AL

G5 Grounding Conductor - BLDG-# 05 1-1/0 AL

G6 Grounding Conductor - BLDG-# 06 1-3/0 AL

G7 Grounding Conductor - BLDG-# 07 1-3/0 AL

G8 Grounding Conductor - BLDG-# 08 1-3/0 AL

G9 Grounding Conductor - BLDG-# 09 1-3/0 AL

G10 Grounding Conductor - BLDG-# 10 1-3/0 AL

G11 Grounding Conductor - BLDG-# 11 1-1/0 AL

G12 Grounding Conductor - BLDG-# 12 1-1/0 AL

G13 Grounding Conductor - BLDG-# 13 1-3/0 AL

G14 Grounding Conductor - BLDG-# 14 1-#2 AWG AL

G15 Grounding Conductor - BLDG-# 15 1-#2 AWG AL

G16 Grounding Conductor - BLDG-# 15 1-#2 AWG AL

G17 Grounding Conductor - BLDG-# 15 1-#2 AWG AL

G18 Grounding Conductor - BLDG-# 18 1-#2 AWG AL

G19 Grounding Conductor - BLDG-# 19 1-#2 AWG AL

E-Short Circuit Schedule

Point DescriptionShort Circuit (ISC

SYM RMS)Line-Line

Voltage (V)Length ofRun (L)

1A Dwelling Unit Panel 4416 240 V 37

1B Dwelling Unit Panel 4169 240 V 43

1C Dwelling Unit Panel 3880 240 V 51

2A Dwelling Unit Panel 4629 240 V 43

2B Dwelling Unit Panel 4629 240 V 43

2C Dwelling Unit Panel 5413 240 V 29

3A Dwelling Unit Panel 5550 240 V 61

3B Dwelling Unit Panel 5550 240 V 38

3C Dwelling Unit Panel 4318 240 V 38

3D Dwelling Unit Panel 4318 240 V 61

4A Dwelling Unit Panel 4364 240 V 37

4B Dwelling Unit Panel 4122 240 V 43

4C Dwelling Unit Panel 3839 240 V 51

5A Dwelling Unit Panel 7271 240 V 28

5B Dwelling Unit Panel 6084 240 V 40

5C Dwelling Unit Panel 4540 240 V 65

5D Dwelling Unit Panel 4199 240 V 73

6A Dwelling Unit Panel 7914 240 V 23

6B Dwelling Unit Panel 5231 240 V 29

6C Dwelling Unit Panel 3139 240 V 57

6D Dwelling Unit Panel 2126 240 V 68

7A Dwelling Unit Panel 7647 240 V 28

7B Dwelling Unit Panel 6345 240 V 40

7C Dwelling Unit Panel 4636 240 V 66

7D Dwelling Unit Panel 4322 240 V 73

8A Dwelling Unit Panel 4370 240 V 41

8B Dwelling Unit Panel 4370 240 V 41

8C Dwelling Unit Panel 5120 240 V 26

9A Dwelling Unit Panel 5820 240 V 28

9B Dwelling Unit Panel 5034 240 V 40

9C Dwelling Unit Panel 3895 240 V 66

9D Dwelling Unit Panel 3671 240 V 73

10A Dwelling Unit Panel 6225 240 V 23

10B Dwelling Unit Panel 4435 240 V 29

10C Dwelling Unit Panel 2834 240 V 57

10D Dwelling Unit Panel 1981 240 V 68

11A Dwelling Unit Panel 4404 240 V 41

11B Dwelling Unit Panel 4404 240 V 41

11C Dwelling Unit Panel 5166 240 V 26

12A Dwelling Unit Panel 4729 240 V 41

12B Dwelling Unit Panel 4729 240 V 41

12C Dwelling Unit Panel 5620 240 V 26

13A Dwelling Unit Panel 5449 240 V 28

13B Dwelling Unit Panel 4754 240 V 40

13C Dwelling Unit Panel 3756 240 V 65

13D Dwelling Unit Panel 3520 240 V 73

14A Dwelling Unit Panel 6271 240 V 16

14B Dwelling Unit Panel 5181 240 V 31

14C Dwelling Unit Panel 4503 240 V 44

15A Dwelling Unit Panel 6321 240 V 16

15B Dwelling Unit Panel 5216 240 V 31

15C Dwelling Unit Panel 4529 240 V 44

18A Dwelling Unit Panel 4035 240 V 73

18B Dwelling Unit Panel 5820 240 V 39

18C Dwelling Unit Panel 6791 240 V 28

19A Dwelling Unit Panel 4119 240 V 73

19B Dwelling Unit Panel 5995 240 V 39

19C Dwelling Unit Panel 7032 240 V 28

M01 Meter Center - BLDG 01 7074 240 V 200

M02 Meter Center - BLDG 02 8509 240 V 133

M03 Meter Center - BLDG 03 10769 240 V 125

M04 Meter Center - BLDG 04 8946 240 V 145

M05 Meter Center - BLDG 05 13782 240 V 86

M06 Meter Center - BLDG 06 17897 240 V 49

M07 Meter Center - BLDG 07 15199 240 V 71

M08 Meter Center - BLDG 08 7419 240 V 224

M09 Meter Center - BLDG 09 9360 240 V 200

M10 Meter Center - BLDG 10 8932 240 V 214

M11 Meter Center - BLDG 11 7517 240 V 210

M12 Meter Center - BLDG 12 8516 240 V 177

M13 Meter Center - BLDG 13 8437 240 V 232

M14 Meter Center - BLDG 14 8244 240 V 139

M15 Meter Center - BLDG 15 8330 240 V 137

M16 Meter Center - BLDG 15 TBD 240 V 46

M17 Meter Center - BLDG 15 TBD 240 V 47

M18 Meter Center - BLDG 18 12156 240 V 77

M19 Meter Center - BLDG 19 12949 240 V 69

T Transformer - Typ. 29600 240 V --

Page 5: C:UsersSean MackenzieDocumentsFamiliesDenison Phase I-SITE

_________________________

Consulting EngineersMechanical ▪ Structural ▪ Energy

reginc.com ▪ 970.349.1216

efficiency | sustainability | simplicity

Resource Engineering Group

Project number

Engineered By

Reviewed By

please recycle these drawings

E005

Electrical PowerSchedules

2586

Jared Marchand, PE

DenisonAffordableHousing

Breckenridge, CO

Sean Mackenzie

Issued for Date

Permit Set 03-21-17

6. All electrical equipment to have 75ºC rated equipment lugs and terminals.

5. Installing contractor to coordinate with Architect and Xcel Energy for device labeling requirements.

4. All means of disconnect shall be hot sequenced.

3. Meter sockets shall be constructed of steel and equiped with ringless style covers, insulating track-resistant polycarbonate safety shield, and padlock seals per Xcel standards.

2. Metering cabinet shall have permanent barriers and separate covers to isolate unit disconnect switch and wiring area from the metering area per Xcel standards.

1. Meter center devices (metering cabinet, terminal box, meter sockets, and accessories) subject to approval of Xcel Energy.

Meter Center Notes:

Dwelling Unit - General Loads 28260 VA 41.90% 11841 VA Total Est. Demand Current: 234 A

Electric Range - 3.5 kW to 8.75 kW 20000 VA 50.00% 10000 VA Total Conn. Current: 364 A

Electric Clothes Dryer 20000 VA 100.00% 20000 VA Total Est. Demand: 56241 VA

Dwelling Unit - Appliance Loads 19200 VA 75.00% 14400 VA Total Conn. Load: 87460 VA

Load Classification Connected Load Demand Factor Estimated Demand Service Totals

Building Service Load Schedule:

5. Unit panel BB ratings shown are minimum ratings, typical. Higher rated panels may be provided at contractor's option.

4. Contractor to determine final number of circuit spaces required, alotting minimum 10% for spare capacity.

3. Reference architectural floorplans for specific locations.

2. All dwelling unit panels shall have a minimum fault current rating of 10kAIC. Reference Short Circuit Schedule for maximum available fault current.

1. All residential unit panels to be NEMA 1, 10 kAIC, 240/120V, 1PH, 3W, MLO unless otherwise noted

Dwelling Unit Panel Notes:

P-4 Unit Type: #3 100 A 100 A 2 17126 VA 71 A

P-3 Unit Type: #3 100 A 100 A 2 17126 VA 71 A

P-2 Unit Type: #1 100 A 100 A 2 16920 VA 71 A

P-1 Unit Type: #1 100 A 100 A 2 16920 VA 71 A

Unit Panel Schedule Circuit Notes Unit Panel BB RatingService Disconnect (CB)

Rating Poles Loads

Dwelling Unit Service Schedule:

Enclosure: NEMA 3R

Mounting: Surface Wires: 3 Min. Terminal Bus Rating: 400 A

Supply From: See Site Power Plan Phases: 1 Metering Type: 320/400A, 5 terminal, lever bypass meter socket

Location: See Site Power Plan Volts: 120/240 Single A.I.C. Rating: See Short Circuit Schedule

Meter Center: Typ. Building Type - C1 (Bldg.# 3)

6. All electrical equipment to have 75ºC rated equipment lugs and terminals.

5. Installing contractor to coordinate with Architect and Xcel Energy for device labeling requirements.

4. All means of disconnect shall be hot sequenced.

3. Meter sockets shall be constructed of steel and equiped with ringless style covers, insulating track-resistant polycarbonate safety shield, and padlock seals per Xcel standards.

2. Metering cabinet shall have permanent barriers and separate covers to isolate unit disconnect switch and wiring area from the metering area per Xcel standards.

1. Meter center devices (metering cabinet, terminal box, meter sockets, and accessories) subject to approval of Xcel Energy.

Meter Center Notes:

Dwelling Unit - General Loads 21435 VA 44.10% 9452 VA Total Est. Demand Current: 181 A

Electric Range - 3.5 kW to 8.75 kW 15000 VA 55.00% 8250 VA Total Conn. Current: 274 A

Electric Clothes Dryer 15000 VA 100.00% 15000 VA Total Est. Demand: 43521 VA

Dwelling Unit - Appliance Loads 14425 VA 75.00% 10819 VA Total Conn. Load: 65860 VA

Load Classification Connected Load Demand Factor Estimated Demand Service Totals

Building Service Load Schedule:

5. Unit panel BB ratings shown are minimum ratings, typical. Higher rated panels may be provided at contractor's option.

4. Contractor to determine final number of circuit spaces required, alotting minimum 10% for spare capacity.

3. Reference architectural floorplans for specific locations.

2. All dwelling unit panels shall have a minimum fault current rating of 10kAIC. Reference Short Circuit Schedule for maximum available fault current.

1. All residential unit panels to be NEMA 1, 10 kAIC, 240/120V, 1PH, 3W, MLO unless otherwise noted

Dwelling Unit Panel Notes:

P-3 Unit Type: #3 100 A 100 A 2 17126 VA 71 A

P-2 Unit Type: #3 100 A 100 A 2 17126 VA 71 A

P-1 Unit Type: #1 100 A 100 A 2 16920 VA 71 A

Unit Panel Schedule Circuit Notes Unit Panel BB RatingService Disconnect (CB)

Rating Poles Loads

Dwelling Unit Service Schedule:

Enclosure: NEMA 3R

Mounting: Surface Wires: 3 Min. Terminal Bus Rating: 200 A

Supply From: See Site Power Plan Phases: 1 Metering Type: 320/400A, 5 terminal, lever bypass meter socket

Location: See Site Power Plan Volts: 120/240 Single A.I.C. Rating: See Short Circuit Schedule

Meter Center: Typ. Building Type - C2 (Bldg.# 2)

6. All electrical equipment to have 75ºC rated equipment lugs and terminals.

5. Installing contractor to coordinate with Architect and Xcel Energy for device labeling requirements.

4. All means of disconnect shall be hot sequenced.

3. Meter sockets shall be constructed of steel and equiped with ringless style covers, insulating track-resistant polycarbonate safety shield, and padlock seals per Xcel standards.

2. Metering cabinet shall have permanent barriers and separate covers to isolate unit disconnect switch and wiring area from the metering area per Xcel standards.

1. Meter center devices (metering cabinet, terminal box, meter sockets, and accessories) subject to approval of Xcel Energy.

Meter Center Notes:

Dwelling Unit - General Loads 43209 VA 39.51% 17073 VA Total Est. Demand Current: 271 A

Electric Range - 3.5 kW to 8.75 kW 20000 VA 50.00% 10000 VA Total Conn. Current: 447 A

Electric Clothes Dryer 20000 VA 100.00% 20000 VA Total Est. Demand: 65076 VA

Dwelling Unit - Appliance Loads 24004 VA 75.00% 18003 VA Total Conn. Load: 107213 VA

Load Classification Connected Load Demand Factor Estimated Demand Service Totals

Building Service Load Schedule:

5. Unit panel BB ratings shown are minimum ratings, typical. Higher rated panels may be provided at contractor's option.

4. Contractor to determine final number of circuit spaces required, alotting minimum 10% for spare capacity.

3. Reference architectural floorplans for specific locations.

2. All dwelling unit panels shall have a minimum fault current rating of 10kAIC. Reference Short Circuit Schedule for maximum available fault current.

1. All residential unit panels to be NEMA 1, 10 kAIC, 240/120V, 1PH, 3W, MLO unless otherwise noted

Dwelling Unit Panel Notes:

P-4 Unit Type: #5 150 A 150 A 2 19291 VA 80 A

P-3 Unit Type: #4 175 A 175 A 2 17786 VA 74 A

P-2 Unit Type: #4 175 A 175 A 2 17786 VA 74 A

P-1 Unit Type: #1 100 A 100 A 2 16920 VA 71 A

Unit Panel Schedule Circuit Notes Unit Panel BB RatingService Disconnect (CB)

Rating Poles Loads

Dwelling Unit Service Schedule:

Enclosure: NEMA 3R

Mounting: Surface Wires: 3 Min. Terminal Bus Rating: 400 A

Supply From: See Site Power Plan Phases: 1 Metering Type: 320/400A, 5 terminal, lever bypass meter socket

Location: See Site Power Plan Volts: 120/240 Single A.I.C. Rating: See Short Circuit Schedule

Meter Center: Typ. Building Type - D1 (Bldg.# 5,6,13)

6. All electrical equipment to have 75ºC rated equipment lugs and terminals.

5. Installing contractor to coordinate with Architect and Xcel Energy for device labeling requirements.

4. All means of disconnect shall be hot sequenced.

3. Meter sockets shall be constructed of steel and equiped with ringless style covers, insulating track-resistant polycarbonate safety shield, and padlock seals per Xcel standards.

2. Metering cabinet shall have permanent barriers and separate covers to isolate unit disconnect switch and wiring area from the metering area per Xcel standards.

1. Meter center devices (metering cabinet, terminal box, meter sockets, and accessories) subject to approval of Xcel Energy.

Meter Center Notes:

Dwelling Unit - General Loads 43209 VA 39.51% 17073 VA Total Est. Demand Current: 271 A

Electric Range - 3.5 kW to 8.75 kW 20000 VA 50.00% 10000 VA Total Conn. Current: 447 A

Electric Clothes Dryer 20000 VA 100.00% 20000 VA Total Est. Demand: 65076 VA

Dwelling Unit - Appliance Loads 24004 VA 75.00% 18003 VA Total Conn. Load: 107213 VA

Load Classification Connected Load Demand Factor Estimated Demand Service Totals

Building Service Load Schedule:

5. Unit panel BB ratings shown are minimum ratings, typical. Higher rated panels may be provided at contractor's option.

4. Contractor to determine final number of circuit spaces required, alotting minimum 10% for spare capacity.

3. Reference architectural floorplans for specific locations.

2. All dwelling unit panels shall have a minimum fault current rating of 10kAIC. Reference Short Circuit Schedule for maximum available fault current.

1. All residential unit panels to be NEMA 1, 10 kAIC, 240/120V, 1PH, 3W, MLO unless otherwise noted

Dwelling Unit Panel Notes:

P-4 Unit Type: #5 150 A 150 A 2 19291 VA 80 A

P-3 Unit Type: #4 175 A 175 A 2 17786 VA 74 A

P-2 Unit Type: #4 175 A 175 A 2 17786 VA 74 A

P-1 Unit Type: #1 100 A 100 A 2 16920 VA 71 A

Unit Panel Schedule Circuit Notes Unit Panel BB RatingService Disconnect (CB)

Rating Poles Loads

Dwelling Unit Service Schedule:

Enclosure: NEMA 3R

Mounting: Surface Wires: 3 Min. Terminal Bus Rating: 400 A

Supply From: See Site Power Plan Phases: 1 Metering Type: 320/400A, 5 terminal, lever bypass meter socket

Location: See Site Power Plan Volts: 120/240 Single A.I.C. Rating: See Short Circuit Schedule

Meter Center: Typ. Building Type - D2 (Bldg.# 7,9,10)

6. All electrical equipment to have 75ºC rated equipment lugs and terminals.

5. Installing contractor to coordinate with Architect and Xcel Energy for device labeling requirements.

4. All means of disconnect shall be hot sequenced.

3. Meter sockets shall be constructed of steel and equiped with ringless style covers, insulating track-resistant polycarbonate safety shield, and padlock seals per Xcel standards.

2. Metering cabinet shall have permanent barriers and separate covers to isolate unit disconnect switch and wiring area from the metering area per Xcel standards.

1. Meter center devices (metering cabinet, terminal box, meter sockets, and accessories) subject to approval of Xcel Energy.

Meter Center Notes:

Dwelling Unit - General Loads 27687 VA 42.04% 11640 VA Total Est. Demand Current: 201 A

Electric Range - 3.5 kW to 8.75 kW 15000 VA 55.00% 8250 VA Total Conn. Current: 315 A

Electric Clothes Dryer 15000 VA 100.00% 15000 VA Total Est. Demand: 48280 VA

Dwelling Unit - Appliance Loads 17853 VA 75.00% 13390 VA Total Conn. Load: 75540 VA

Load Classification Connected Load Demand Factor Estimated Demand Service Totals

Building Service Load Schedule:

5. Unit panel BB ratings shown are minimum ratings, typical. Higher rated panels may be provided at contractor's option.

4. Contractor to determine final number of circuit spaces required, alotting minimum 10% for spare capacity.

3. Reference architectural floorplans for specific locations.

2. All dwelling unit panels shall have a minimum fault current rating of 10kAIC. Reference Short Circuit Schedule for maximum available fault current.

1. All residential unit panels to be NEMA 1, 10 kAIC, 240/120V, 1PH, 3W, MLO unless otherwise noted

Dwelling Unit Panel Notes:

E-3 Unit Type: #4 175 A 175 A 2 20357 VA 85 A

E-2 Unit Type: #2 100 A 100 A 2 17786 VA 74 A

E-1 Unit Type: #2 100 A 100 A 2 17786 VA 74 A

Unit Panel Schedule Circuit Notes Unit Panel BB RatingService Disconnect (CB)

Rating Poles Loads

Dwelling Unit Service Schedule:

Enclosure: NEMA 3R

Mounting: Surface Wires: 3 Min. Terminal Bus Rating: 400 A

Supply From: See Site Power Plan Phases: 1 Metering Type: 320/400A, 5 terminal, lever bypass meter socket

Location: See Site Power Plan Volts: 120/240 Single A.I.C. Rating: See Short Circuit Schedule

Meter Center: Typ. Building Type - E (Bldg.# 18,19)

6. All electrical equipment to have 75ºC rated equipment lugs and terminals.

5. Installing contractor to coordinate with Architect and Xcel Energy for device labeling requirements.

4. All means of disconnect shall be hot sequenced.

3. Meter sockets shall be constructed of steel and equiped with ringless style covers, insulating track-resistant polycarbonate safety shield, and padlock seals per Xcel standards.

2. Metering cabinet shall have permanent barriers and separate covers to isolate unit disconnect switch and wiring area from the metering area per Xcel standards.

1. Meter center devices (metering cabinet, terminal box, meter sockets, and accessories) subject to approval of Xcel Energy.

Meter Center Notes:

Dwelling Unit - General Loads 22542 VA 43.65% 9840 VA Total Est. Demand Current: 183 A

Electric Range - 3.5 kW to 8.75 kW 15000 VA 55.00% 8250 VA Total Conn. Current: 279 A

Electric Clothes Dryer 15000 VA 100.00% 15000 VA Total Est. Demand: 43983 VA

Dwelling Unit - Appliance Loads 14525 VA 75.00% 10894 VA Total Conn. Load: 67067 VA

Load Classification Connected Load Demand Factor Estimated Demand Service Totals

Building Service Load Schedule:

5. Unit panel BB ratings shown are minimum ratings, typical. Higher rated panels may be provided at contractor's option.

4. Contractor to determine final number of circuit spaces required, alotting minimum 10% for spare capacity.

3. Reference architectural floorplans for specific locations.

2. All dwelling unit panels shall have a minimum fault current rating of 10kAIC. Reference Short Circuit Schedule for maximum available fault current.

1. All residential unit panels to be NEMA 1, 10 kAIC, 240/120V, 1PH, 3W, MLO unless otherwise noted

Dwelling Unit Panel Notes:

P-3 Unit Type: #6 100 A 100 A 2 17382 VA 72 A

P-2 Unit Type: #3 100 A 100 A 2 17126 VA 71 A

P-1 Unit Type: #3 100 A 100 A 2 17126 VA 71 A

Unit Panel Schedule Circuit Notes Unit Panel BB RatingService Disconnect (CB)

Rating Poles Loads

Dwelling Unit Service Schedule:

Enclosure: NEMA 3R

Mounting: Surface Wires: 3 Min. Terminal Bus Rating: 200 A

Supply From: See Site Power Plan Phases: 1 Metering Type: 320/400A, 5 terminal, lever bypass meter socket

Location: See Site Power Plan Volts: 120/240 Single A.I.C. Rating: See Short Circuit Schedule

Meter Center: Typ. Building Type - B (Bldg.# 1,4)

Page 6: C:UsersSean MackenzieDocumentsFamiliesDenison Phase I-SITE

S-4

S-4

S-3

S-2B

S-2B

S-2B

S-2B

S-2B

S-2B

S-2B

S-4

S-3

S-4

S-4

S-1

S-2

S-2B

S-2B

S-2S-2

S-2

S-2

S-3

LM1-Town

LM3

LM2-Town

LM4

BLDG 16(Future)

BLDG 17(Future)

BLDG 14

BLDG 15

BLDG 18

BLDG 19BLDG 03

BLDG 02

BLDG 01

BLDG 04

BLDG 05

BLDG 09

BLDG 13

BLDG 08

BLDG 12

BLDG 11BLDG 06

BLDG 10

BLDG 07

A

B

C

D

A

B

C

A

B

C

A

B

C

A

B

C

D

A

B

C

D

A

B

C

D

A

B

C

A

B

C

D

A

B

C

D

A

B

C

D

A

B

C

A

B

C

ABC

A

B

C

A

B

C

A

B

C

L5

L5

L6

L5

L5

L5L3

L3

L4

L4

L4

L4

L1

L2

L6

L4

L3

1

11

1

L2

L2

L2

L1

General notes this sheet:

1. Lighting control by others.2. Fixture selection and layout illustrated on these plans were designed by Architect.3. Load center and service sizing assumes 50A capacity for house loads to be coordinated. Final

sizing TBD.

_________________________

Consulting EngineersMechanical ▪ Structural ▪ Energy

reginc.com ▪ 970.349.1216

efficiency | sustainability | simplicity

Resource Engineering Group

Project number

Engineered By

Reviewed By

please recycle these drawings

E006

Electrical Site LightingPlan

2586

Jared Marchand, PE

DenisonAffordableHousing

Breckenridge, CO

Sean Mackenzie

1" = 30'-0"1

Site Lighting

Issued for Date

Permit Set 03-21-17

Sheet Notes:

1. Reference sheet E002 for site lighting service feeder callout and routing.1

Page 7: C:UsersSean MackenzieDocumentsFamiliesDenison Phase I-SITE

M

SL

T

Combination Meter Breaker, NEMA 3R, min. 100A BB, 125A MCB, 240/120V, 10 kAIC

L1thruL4

20/2

Detail notes this sheet:

Pad-mounted transformer furnished by Xcel Energy. Coordinate constructionrequirements with Xcel Energy. Assume transformer 100kVA, 29.6kA, Z=1.4%. RefereceE002 Site Power Plan for meter specific service transformer.

Provide combination meter breaker per Xcel Energy's Standard for area lightinginstallation and house loads per Architect. Name next to pedestal shown on E006Site Lighting Plan indicates responsible party for meter bill.

Town units (2 total) are not metered and shall mounted per Town Breckenridge. House metered units (2 total)shall be surface mounted. Reference E006 Site Lighting Plan for locations.

Individual site lighting circuits shall be provided maximum over-current protection of 20A,10 kAIC, 2-pole. Contractor to coordinate with Architect any additional house loads to beprovided by meter breaker, alotting minimum 10% for spare capacity.

Meter socket to be a 320/400A, 5 terminal, ringless, with lever bypass. Contractor to cqoordinate detailedconstruction requirements with Xcel Energy.

Means of service disconnect shall be hot sequenced.

Grounding electrode conductor to include connection to concrete-encased electrode perNEC Art. 250.66 (B) and 250.52 (A)(3).

Grounding electrode conductor to include connection to supplemental ground rod perNEC Art. 250.66 (A) , 250.52 (A)(5) and 250.53.

Provide grounding bar at service entrance to distribute grounding connection(s) toapplicable electrodes as shown.

1

2

3

4

5

6

Xcel PadmountTransformer

(ref. Site Power Plan)

100/2

L

Site LightingCircuit

L

7

8

9

L L

Service Lateral Feeder(see Site Power Plan & Feeder Schedule)

L

L

Site Lighting Circuit(see Site LightingFeeder Schedule)

Site LightingCircuit

Site LightingCircuit

Meter Center AvailableFault Current(see Site Lighting ShortCircuit Schedule)

MeterSocket

Load Center

20/2 20/2

1

2 3

4

56

7

8

9

44

GroundingSchematic

LG1

LG2

LG1

T

2

1'-6"

VE

RIF

Y D

EP

TH

OF

PO

LE

BA

SE

WIT

HT

HE

CIV

IL E

NG

INE

ER

2"

Adapter as required

ALUMIMUM POLE SEESCHEDULE FOR POLEHEIGHT & DIAMETER

FLUSH HANDHOLE & COVER

ANCHOR BOLTS, see note 5

5,000 PSI GROUT CHAMFER

SONOTUBE FORM

FINISHED GRADE

UNDISTURBED EARTH

CONDUIT INSTALLEDBELOW FROST DEPTH

4 #5 REBAR

#3 TIES AT 12" O.C.

Notes:1. Light and pole varies, see site lighting plan for fixture type.2. Coordinate base plate, cover, and anchor bolt spacing per manufacturer

requirements.3. Verify the bury depth and diameter of the sonotube with the civil engineer prior to

purchasing the equipment.4. The electrical contractor shall install "snake" or "canister" vibration dampers in

all poles, obtain dampers from pole manufacturer for each aluminum pole.5. Install waterproof breakaway fuseholder for use in roadway and street lighting.6. Anchor bolts shall be 1"ø x 10" with a 4" hook (40"). For post-pour installations,

use 1"ø all-thread with minimum 8" embedment using Simpson SET epoxy orequivalent.

BASE COVER

General notes this sheet:

1. Lighting control by others.2. Fixture selection and layout illustrated on these plans were designed by Architect.3. Load center and service sizing assumes 50A capacity for house loads to be coordinated. Final

sizing TBD.

_________________________

Consulting EngineersMechanical ▪ Structural ▪ Energy

reginc.com ▪ 970.349.1216

efficiency | sustainability | simplicity

Resource Engineering Group

Project number

Engineered By

Reviewed By

please recycle these drawings

E007

Electrical Lighting OneLine Diagram, Schedules

2586

Jared Marchand, PE

DenisonAffordableHousing

Breckenridge, CO

Sean Mackenzie

Issued for Date

Permit Set 03-21-17

E-Lighting Fixture ScheduleID Fixture Type Description Specification Lamping Voltage Mounting

S-1 Parking Lot Light Streetworks GAN-AE-01-LED-U-T4FT 56W LED 240 V Pole Mounted

S-2 Street Light PROV-T3-32 LED 3K-700-BLK-LDL-PCA-T ED-17, 70W 240 V Pole Mounted

S-2B Crosswalk/Intersection Light TBD per Town TBD, 70W 240 V Pole Mounted

S-3 Building Entry/Patio Sconce Hi-Lite Mfg. Co. H-15106B 9W LED (Medium Base) 240 V Wall Mounted

S-4 Private Road Light TBD TBD, 70W 240 V Pole Mounted

E-Site Lighting Feeder Schedule

FeederNo. Description

FeederConductors

GroundConductor Conduit Size

Line-LineVoltage (V)

ConductorAmpacity Load (VA)

Calc.Distance

(feet)Voltage Drop(cumulative)

SL1 Metering Unit Serivce Lateral - Meter L1 (Town) 3-#2 AWG AL 1" 240 V 90 A 60 30 0.5%

SL2 Metering Unit Serivce Lateral - Meter L2 (Town) 3-#2 AWG AL 1" 240 V 90 A 60 153 2.4%

SL3 Metering Unit Serivce Lateral - Meter L3 (House) 3-#2 AWG AL 1" 240 V 90 A 60 50 0.8%

SL4 Metering Unit Serivce Lateral - Meter L4 (House) 3-#2 AWG AL 1" 240 V 90 A 60 187 2.9%

L1 Lighting Circuit 1 3-#8 AWG AL 1-#10 AWG Cu 1/2" 240 V 40 A 70 49 0.22%

L1 Lighting Circuit 1 3-#8 AWG AL 1-#10 AWG Cu 1/2" 240 V 40 A 70 49 0.22%

L2 Lighting Circuit 2 3-#8 AWG AL 1-#10 AWG Cu 1/2" 240 V 40 A 140 78 0.48%

L2 Lighting Circuit 2 3-#8 AWG AL 1-#10 AWG Cu 1/2" 240 V 40 A 140 78 0.48%

L2 Lighting Circuit 2 3-#8 AWG AL 1-#10 AWG Cu 1/2" 240 V 40 A 140 78 0.48%

L2 Lighting Circuit 2 3-#8 AWG AL 1-#10 AWG Cu 1/2" 240 V 40 A 140 78 0.48%

L3 Lighting Circuit 3 3-#8 AWG AL 1-#10 AWG Cu 1/2" 240 V 40 A 210 135 0.23%

L4 Lighting Circuit 4 3-#8 AWG AL 1-#10 AWG Cu 1/2" 240 V 40 A 70 85 0.49%

L6 Lighting Circuit 6 3-#8 AWG AL 1-#10 AWG Cu 1/2" 240 V 40 A 210 54 0.02%

E-Site Lighting Short Circuit Schedule

Point DescriptionShort Circuit (ISC

SYM RMS)Line-Line

Voltage (V)Length ofRun (L)

L1 Site Lighting Metering Unit - L1 (Town) 9936 240 V 30

L2 Site Lighting Metering Unit - L2 (Town) 2668 240 V 153

L3 Site Lighting Metering Unit - L3 (House) 6886 240 V 50

L4 Site Lighting Metering Unit - L4 (House) 2219 240 V 187

T Utility Transformer - Typ. 29600 240 V --

E-Site Lighting Grounding & Bonding Conductor ScheduleFeeder No. Description Ground Conductor

LG1 Metering Unit - Grounding Conductor 1-#6 AWG Cu

LG2 Metering Unit - Grounding Conductor 1-#8 AWG Cu

N.T.S.1

Site Lighting One-Line DiagramN.T.S.

2Light Base Detail