crescent power limited - environmentclearance.nic.in · pulverized fuel - fired boiler, but can be...
TRANSCRIPT
CRESCENT POWER LIMITED
20 MW
EXTENSION PROJECT, PHASE-II
COAL WASHERY REJECT, SHALE AND JHAMA
COAL-BASED THERMAL POWER PROJECT
AT
SARISHATALI - ASANSOL
DISTRICT - BARDHAMAN
WEST BENGAL
INDIA
STUDY REPORT FOR PHASE-II EXTENSION UNIT
PREPARED BY
LAHMEYER INTERNATIONAL (INDIA) PVT. LTD.
LII-KEOE12022-00101-001 Rev-A Revised on Dec, 2013
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page i
TABLE OF CONTENTS
1. BACKGROUND AND OBJECTIVE ...............................................................1
1.1 PROJECT BACKGROUND ................................................................................1
1.2 SCOPE & OBJECTIVES OF THE STUDY..........................................................2
1.3 SITE VISIT ON 19.03.12 – SUBSEQUENT DISCUSSIONS ...............................2
2. GENERAL BACKGROUND AND SALIENT FEATURES ...........................4
2.1 SITE LOCATION AND ACCESS .......................................................................4
2.2 CLIMATE AND METEOROLOGICAL DATA ..................................................5
2.3 INPUT REQUIREMENTS ..................................................................................5
2.4 PLANT CAPACITY & AVAILABILITY .......................................................... 11
2.5 POWER OFF TAKE .......................................................................................... 11
2.6 POWER EVACUATION ................................................................................... 11
2.7 SITE SELECTION CRITERIA .......................................................................... 12
2.8 LAND ............................................................................................................... 12
2.8.1 Requirement....................................................................................................... 12
2.8.2 Availability ........................................................................................................ 12
2.9 WATER ............................................................................................................ 12
2.9.1 Cooling Water System ........................................................................................ 12
2.9.2 Selection of Type of Cooling Tower.................................................................... 12
2.10 FUELS .............................................................................................................. 13
2.10.1 Main Fuel Selection ........................................................................................... 13
2.10.2 Start-up & Flame Stabilization Fuel .................................................................. 14
2.11 ASH .................................................................................................................. 14
2.11.1 Quantity ............................................................................................................. 14
2.11.2 Utilisation and Disposal Options ....................................................................... 14
2.12 MAIN EQUIPMENT SELECTION ................................................................... 14
2.12.1 Capacity Selection of the Plant .......................................................................... 14
2.12.2 Configuration of the Proposed Plant .................................................................. 15
2.12.3 Steam Cycle Parameters .................................................................................... 15
2.12.4 Selection of SG Technology................................................................................ 16
2.12.5 Selection of Condenser ...................................................................................... 17
2.12.6 Selection of Thermodynamic Cycle .................................................................... 17
2.12.7 Equipment Sourcing ........................................................................................... 17
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page ii
2.12.8 Power Purchase Agreement ............................................................................... 17
3 ENERGY EVACUATION PLAN ................................................................... 19
3.1 TRANSMISSION INTERCONNECTION ......................................................... 19
4. MECHANICAL EQUIPMENT AND SYSTEM................................................. 21
4.1 STEAM GENERATOR AND ACCESSORIES ............................................................... 21
4.2 MAIN FUEL UNLOADING, TRANSPORTATION AND FEEDING SYSTEM ..................... 27
4.3 ASH HANDLING SYSTEM ..................................................................................... 31
4.4 PLANT WATER SYSTEM ...................................................................................... 33
5. ELECTRICAL SYSTEM AND EQUIPMENT ................................................... 39
5.1 ELECTRICAL SYSTEM ARRANGEMENT: ................................................... 39
5.2 CONSTRUCTION POWER: ............................................................................. 41
6.0 CONTROL AND INSTRUMENTATION SYSTEM ......................................... 43
6.1 DESIGN PHILOSOPHY .......................................................................................... 43
6.2 MAJOR CONTROL AND INSTRUMENTATION SYSTEMS ........................................... 43
6.3 DISTRIBUTED CONTROL SYSTEM (DCS) .............................................................. 44
6.3.1 Close Loop and Open Loop Control System ....................................................... 45
6.3.2 Operator Interface Units (OIU) ......................................................................... 46
6.3.3 Data Communication ......................................................................................... 46
6.3.4 Historical Storage and Retrieval (HSR) System .................................................. 46
6.3.5 Performance Calculation ................................................................................... 46
6.3.6 Sequence of Event Recorder (SER)..................................................................... 46
6.3.7 Alarm Annunciation System ............................................................................... 47
6.3.8 Electrical Systems Operation and Monitoring: ................................................... 47
6.3.9 System Programming and Documentation.......................................................... 47
6.4.2 STEAM TURBINE GENERATOR (STG) CONTROL SYSTEM ...................................... 48
6.5 ALTERNATIVE PHILOSOPHY ................................................................................ 48
6.6 DCS BASED BALANCE OF PLANT OFF SITE CONTROL SYSTEM: .............................. 48
6.7 STAND ALONE BALANCE OF PLANT OFF SITE CONTROL SYSTEMS ......................... 48
6.8 TURBINE SUPERVISORY INSTRUMENTATION SYSTEM............................................ 48
6.9 VIBRATION MONITORING SYSTEMS FOR HT DRIVES ............................................ 49
6.11 CONTROL PANEL / CONTROL DESK ..................................................................... 49
6.12 CONTROL ROOM EQUIPMENTS ............................................................................ 50
6.13 MEASURING INSTRUMENTS ................................................................................. 50
6.14 STEAM AND WATER ANALYSIS SYSTEM (SWAS) ................................................ 51
6.15 STACK EMISSION MONITORING SYSTEM .............................................................. 51
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page iii
6.16 AMBIENT AIR QUALITY MONITORING SYSTEM .................................................... 51
6.17 UNINTERRUPTIBLE POWER SUPPLY (UPS) AND DISTRIBUTION ............................. 51
6.18 FINAL CONTROL ELEMENTS ................................................................................ 52
6.19 INSTRUMENTATION & SPECIAL CABLES ............................................................... 52
6.20 MAINTENANCE AND CALIBRATION INSTRUMENTS ............................................... 52
6.21 ERECTION HARDWARE ........................................................................................ 52
7. CIVIL WORKS ................................................................................................. 54
7.1 LAND DEVELOPMENT ......................................................................................... 54
7.2 GEO-TECHNICAL INVESTIGATIONS....................................................................... 54
7.3 TOPOGRAPHICAL SURVEY ................................................................................... 55
7.4 PLANT LAYOUT .................................................................................................. 55
7.5 WATER INTAKE .................................................................................................. 55
7.6 PLANT BUILDINGS .............................................................................................. 56
7.7 PAVING AND PLINTH PROTECTION ....................................................................... 57
7.8 FOUNDATIONS .................................................................................................... 57
7.9 TRANSFORMER AREA .......................................................................................... 57
7.10 SWITCHYARD AREA ............................................................................................ 57
7.11 CHIMNEY ........................................................................................................... 57
7.12 RAW WATER RESERVOIR .................................................................................... 57
7.13 MISCELLANEOUS BUILDINGS .............................................................................. 58
7.14 SHALE, DEVOLATISED COAL (JHAMA) & WASHERY REJECT HANDLING SYSTEM .. 58
7.15 ASH HANDLING SYSTEM ..................................................................................... 60
7.16 PIPE & CABLE RACK & TRENCHES ....................................................................... 60
7.17 SEWERAGE SYSTEM ............................................................................................ 60
7.18 COOLING TOWER ................................................................................................ 60
7.19 LANDSCAPING .................................................................................................... 60
7.20 ASH UTILIZATION ............................................................................................... 60
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page iv
LIST OF EXHIBITS
Exhibit 1 : Coal Analysis Data
Exhibit 2 : Cost comparison WCC vs. ACC
LIST OF DRAWINGS
1A. LII-KEOE12022-00110-001-WCC, RA : Plot Plan
1B. LII-KEOE12022-00110-001-ACC, RA : Plot Plan
2A. LII-KEOE12022-40021-001-1(WCC), RA : Flow Diagram for Plant Water System
2B. LII-KEOE12022-40021-001-2 (ACC), RA : Flow Diagram for Plant Water System
3. LII-KEOE12022-40121-001, RA : Flow Diagram for Coal Handling System
4. LII-KEOE12022-20522-001_ : PID For Air Cooled Condenser System
5A. LII-KEOE12022-00027-001-1_ : Water Balance Diagram – Water cooled
condenser
5B. LII-KEOE12022-00027-001-2 : Water Balance Diagram – Air cooled
condenser
ANNEXURE
1. Site feedback & discussion on inputs during site visit on 19.03.2012 and subsequent
emails.
2. CPL comments & LII responses on Draft Study Report – Dated 03/05/2012.
3. Discussions during meeting on 07/05/2012 at CESC office and subsequent LII email
dtd 06/07/2012.
4. Discussions during meeting on 25/07/2012 at CPL office
REFERENCE DOCUMENT
DETAILED PROJECT REPORT (doc. no. LII-4236-000-T-001) Dated Aug 2007 for
Phase II of the Project prepared by LII.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
SECTION – 1
BACKGROUND AND OBJECTIVE
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 1
1. BACKGROUND AND OBJECTIVE
Crescent Power Limited (CPL), a subsidiary of Integrated Coal Mining Ltd (ICML), a
group company of CESC Ltd (RP-SG Group Company), is engaged in generation of
Power through its Sarishatali Power Plant. CPL proposes to enhance generating
capacity of this station by utilizing additional fuel resource available from ICML and
therefore intends to undertake a technical study which is being carried out
hereinafter in this report by LII.
1.1 PROJECT BACKGROUND
Integrated Coal Mining Limited (ICML) promoted by M/s CESC Ltd, has developed a
captive coal mine block in Sarishatali, Bardhaman district, West Bengal and has
washery with capacity 1 MTPA in close proximity of Sarishatali mine, which is
supplying washery Reject and Shale in existing atmospheric fluidized bed
combustion furnaces (also known as bubbling bed combustion furnace) for the
present 1x40 MW power plant, being installed by Crescent power Ltd. (CPL) at
Sarishatali.
Currently, the waste generation in the form of shale is as high as 0.25 million ton per
annum from the mine and another 0.4 to 0.5 million ton per year of rejects from the
washery (i.e. total fuel is 0.75 MTPA), which meets the requirement for present plant.
The mine also has substantial quantity of Devolatised coal (Jhama coal) of volatile
matter content of 8-10% which has high carbon content and is not suitable for
pulverized fuel - fired boiler, but can be burnt in AFBC or CFBC boilers.
Approximately 0.4-0.5 million tons of washery reject, 0.25 million tons of shale and
0.15 million tons of fuel per annum are available from ICML mine and coal washery
for a maximum period of 15 years from now.
With the above waste coal, one additional 20 MW unit with PLF 80% at the same
site is possible. Recent development of CFBC Boiler has the capacity to burn the
fuel efficiently to produce fly ash with low percentage of unburnt coal with an
opportunity of sale ability of the fly ash to cement plant manufacturers.
In respect to the above M/s. Lahmeyer International (India) Pvt. Ltd. has been
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 2
appointed for preparation of Study Report for Phase-II extension unit in the
designated area for future extension at the same site of CPL, with the involvement
of a proper mix of all the three types of coal (Washery Reject, Shale & Jhama) and
intention of sale of the ash to the local cement manufacturing outfits.
1.2 SCOPE & OBJECTIVES OF THE STUDY
Objective of the study is to establish the following:
1) Assessment of present feasibility of the extension unit in respect of fuel, water availability and ash disposal based on the feed back available from existing plant & mines.
2) Use of Jhama coal in Boiler, in addition to the present washery reject and shale in a proper mix.
3) Use of ash from proposed unit aiming to maximum sale-ability to local cement industry and brickfields.
4) Study of feed back from existing unit and incorporate necessary augmentation
5) Recommendation for Boiler technology
6) Study coal handling plant for use of three different type of coal.
Justification of 1x20 MW Unit (Phase-II) at the same site, where one no. 1x40 MW
unit is already under operation and many facilities will be common for both the units.
1.3 SITE VISIT ON 19.03.12 – SUBSEQUENT DISCUSSIONS
On 19.3.2012, Engineers from Lahmeyer International India visited site and
discussed with plant engineers regarding Phase-II extension (Annexure).
Subsequently dedicated meetings with exchange of observations and comments
from CPL have been held on 07-05-2012 and 25-07-2012 in order to update the
report for finalization. This report gives some recommendation based on the usage
of new fuel, boiler technology, feasibility and adaptation of air cooled condenser,
coal handling plant, plant water systems etc.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 3
SECTION – 2
GENERAL BACKGROUND AND SALIENT FEATURES
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 4
2. GENERAL BACKGROUND AND SALIENT FEATURES
Crescent Power Ltd. is generating 40 MW from the existing pit head power generating
units consisting of two AFBC boilers and one steam turbine. AFBC boiler is operating on
the fuel of ‘shale’ and ‘coal washery rejects’ produced from the ICML coal mine at the
site of Sarishatali, district of Bardhaman, West Bengal.
The proposed plant will be of sub-critical steam parameters and utilize mix of Washery
reject, Shale and Jhama coal sourced from ICML mines. Jhama coal is new addition
which is also different from shale & rejects, with higher hardness and less volatile matter
but higher GCV. Raw water requirement for extension unit shall be taken from Ajoy
River similar to existing arrangement of Unit #1. Plant consumptive water requirements
will be met by treating the river water. The ash will be collected in dry form. Suitable
system for ash utilization has been conceived like selling of fly ash to cement plants and
bottom ash for road construction, filling of mine areas, etc.
Basic inputs considered are as follows:
1) Doc no LII-4236-000-T-001-R0 dated August 2007: Detail Project Report (DPR).
2) Soil Investigation Report 808 dated Sept 2006 & 0124 (SK) Jan 2012.
3) Existing drawings and documents received from site during visit/discussion dated
19.03.2012.
4) Site feed back/discussion on inputs during site visit on 19.03.2012 (Annexure).
5) Meeting with CPL & LII on 07.05.2012 and 25.07.2012
6) Coal sampling analysis report of Jhama received from CPL on 26.07.2012.
2.1 SITE LOCATION AND ACCESS
The Project is planned to be build at Sarishatali, Asansol, West Bengal. Project Site is
located at a longitude 87º03’10’’ E and latitude 23º 47’ 07’’ N at Sarishatali near Asansol
in Bardhaman District of West Bengal, India. The proposed power station site is near to
the river Ajay.
The Project site is located about 11.5 km from the National Highway (NH– 2).
The nearest Railway Station, Baraboni of Eastern Railway, is around 6 km away from
project site. No railway linkage up to the power station is considered.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 5
Nearest commercial airport is Kolkata, the state capital at a distance of 190 Km and Air
Base in Panagarh at a distance of 58 Km. Nearest sea port is at Kolkata, which is about
240 kms from project site.
Available infrastructure at Kolkata Port is adequate for handling the offshore equipment
including major power plant equipment (turbine, generator etc.).
However, it is envisaged that Railway carriage will be used to transport bulk, capital
equipment and materials of the power plant project. Asansol is the nearest city 13 Km
from project site. No residential colony is envisaged to be built at the plant site.
There are no major archaeological, historical or religious sites located nearby. Therefore
the project site does not offer any negative impact on the local area, rather will have a
positive impact on socio economic conditions of the habitats around it.
2.2 CLIMATE AND METEOROLOGICAL DATA
The Meteorological and Ambient conditions Data for the Project – refer DPR (2007)
Based on the meteorological data followings shall be considered:
Design ambient dry bulb temperature : 50 º C
Minimum dry bulb temperature : 7 °C
Relative Humidity : 85 %,
(At site Max. dry bulb 48 ºC, Min. dry bulb 7 ºC)
Cooling tower Performance dry bulb temperature: 35ºC, RH of 60 % and cooling water
temperature of 33ºC.
Maximum intensity of rainfall: 80 mm in 1 Hr. (Rainfalls during the months June, July,
August, September are significant)
Design wind velocity is considered 47 m/sec.
2.3 INPUT REQUIREMENTS
2.3.1 Land
The proposed 2nd unit will be installed adjacent to 1st unit at the existing designated
area. The following major facilities would be considered common for both the units -
a. Shale, Jhama (Devolatised coal) and washery reject storage system. Handling
of the same will be similar to existing system and partly common.
b. Light diesel oil system.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 6
c. Raw water intake pump house and reservoir.
d. DM Plant
e. 132 KV Switchyard.
The designated land area, already acquired, will also accommodate the proposed
2nd unit within its balance of plant.
The plant layout is shown in the enclosed ‘Plot Plan’ Dwg No. LII -12022-110-001.
2.3.2 Water
Presently, twelve (12) nos. bore wells have been installed to cater raw water to the
plant from bed of river Ajay. Estimated total water quantity requirement for the
proposed extension unit is as below.
Option-1 (WCC with HCSD system): 281m3/hr.
Option-2 (ACC with HCSD system): 52m3/hr
Hence another twelve (12) nos.(for option-1) / four (4) nos.(for option-2) additional
bore wells of similar capacity as existing bore wells, will be the source of water for
both the units. The river water is presently brought to the plant by pipeline. Another
250 NB pipeline will be installed in phase-II to meet additional water requirement for
both the units.
The Water Balance Diagram for the Plant as shown in drawing no. LII-KEOE12022-
40021-101-1-RA (WCC) LII-KEOE-40021-101-2-RA (ACC),
2.3.3 Main Fuel
The project will be using substantial quantity of Washery Reject, Shale and Jhama
coal as its prime fuel supported by fuel oil (LDO) as secondary fuel for the station for
boiler start-up.
Shale, washery rejects and Jhama coal as a fuel have the following intrinsic
properties and calls for necessary measures in plant design:
- High moisture in washery reject and requirement of air drying.
- Very low heat value of Shale to be supplied in irregular sizes (up to minus 300
mm).
- Low volatile matter and high calorific value of Jhama coal to be supplied in
irregular sizes (up to minus 300 mm).
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 7
- Washery rejects shall be received in (-) 80 mm size.
Accordingly, the following features in system design need to be adopted:
- In-plant storage of 7 days would be planned for washery rejects to permit time for
natural air drying.
- For shale and Jhama coal, primary crushing to a size of (-) 80 mm would be
necessary and then stacked in stockpile for combined feeding of both the fuels to
secondary crusher, where fuel would be crushed to the desired size of (-) 6 mm.
- High erosive ash components mainly aluminum silicates and iron oxides in
Unsorted Jhama Coal may cause furnace erosion and fluidization problems. Also
Chlorine content in fuel being very high will cause high temperature corrosion in
superheater. Hence boiler manufacturers recommend not to fire Unsorted Jhama
Coal. Further it has also been recommended that the firing of sorted Jhama coal
be restricted upto 35%.due to high chlorine and erosive metal content in ash of
Jhama coal.
The typical analysis of Washery Reject, Shale and Jhama coals are shown in
Exhibit -1
Requirement of Coal for a CFBC Boiler vis-à-vis fuel flexibility
For generation of 1x 20 MW with 85% PLF coal requirement in million tones per
annum (MTPA)
The subject of coal requirement and availability has been discussed at length during
meeting on 07.05.2012 and the following two options in respect of coal availability
have been concluded for 15 years period for the proposed 1 x 20 MW extension unit
in Phase-II.
Option-1: (figures in tones)
Coal type Total Qty. Available Consumption-
Unit#1
Qty. Available – Unit #2
Shale 250000 180000 70000
Rejects 500000 (1.5mt@33%) 280000 220000
Jhama - 0 88500
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 8
Option-2: (figures in tones)
Coal type Total Qty. Available Consumption-
Unit#1
Qty. Available–Unit #2
Shale 250000 180000 70000
Rejects 400000 (1.2mt@33%) 280000 120000
Jhama 150000 0 150000
Maximum Available Quantity for Unit #2: (figures in tones)
Coal type Max. Qty. Available
Shale 70000
Rejects 220000
Jhama 150000
Notes:
1. Based on the tentative analysis data of Jhama coal, and the mix ratio of the three
types of coal recommended by the boiler manufacturers to attain less than 2%
unburnt carbon in fly ash, desired for the sale-ability of ash, it was observed that
the boiler steaming capacity will be limited to 95 tph meaning an equivalent unit
capacity of 20MW, with a substantial leftover quantity of Jhama and Shale (ref LII
email dtd 06.07.2012).
2. Subsequently based on the discussions during meeting on 25.07.2012, where
maximum utilization of the available coal was opined by CPL, with the relaxation
on unburnt carbon in fly ash to 4% . Accordingly, the precise coal data for Jhama
based on coal sampling analysis (as received from CPL) was given to boiler
manufacturers for an update in this respect.
The following table is a consolidation of the data furnished by the boiler
manufacturers in respect of the coal availability and the corresponding unburnt
carbon percentage with proposed boiler design pressure of 89 kg/cm2, (g),
temperature 515±5º C.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 9
Coal Quantity Available
Guaranteed Steaming capacity TPH at 89 kg/cm²(g) & 515 ± 5
0C
TPA Single CFBC Boiler Two CFBC Boiler
Option Shale Rejects Jhama
(Sorted) Jhama (Un
Sorted)
Un burnt carbon in fly
ash TPH
Effy (indicative) *
TPH Effy
(indicative)*
A-1 70000 120000 150000
≤ 3.1%
154 87.0 77 87.0
A-2 70000 120000 150000 133 86.3 66.5 86.3
B-1 70000 220000 150000 189 86.8 94.5 86.8
B-2 70000 220000 150000 165 85.4 82.5 85.4
C-1 70000 220000 88500 159 86.7 79.5 86.7
C-2 70000 220000 88500 145 86.3 72.5 86.3
Adequacy of Source of Fuel
Coal available for 15 years from now for proposed CFBC and existing AFBC Boiler
are indicated in above table option-1 & option-2, with the mention of the maximum
dedicated quantity available for Unit #2.
Since the plant life has been considered as 25 years for financial study in the DPR
(2007), the Units will operate with ICML coal for another 15 years from now, and
thereafter need to outsource washery reject, shale & Jhama for the remaining 10
years.
Required fuel quantity for 15 years with guaranteed unburnt carbon less than
3.1% for 156 TPH (WCC) /164 TPH (ACC) Boiler for 40MW unit with 10% margin
in steaming capacity guarantee point is as below:
Jhama (sorted): 150000 TPA
Washery Reject: 220,000 TPA
Shale: 70,000 TPA
Transportation of Coal
As being done for the present 1x40 MW unit, washery rejects is supplied from the
coal washery, located within one (1) Km from the site, by conveyor. Raw coal shale
and Jhama coal will be transported by Trucks / Dumpers from the Mines to the
power plant. Same will continue for 1 x20 MW Unit #2.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 10
LDO, which is the start-up fuel, is being supplied by IOCL, Durgapur. Same will
continue for proposed unit-II.
2.3.4 During discussion with plant engineers, the following points have been listed for
consideration in the proposed plant:
1) Fly ash unutilised in the existing plant is not saleable due to its 9-10% unburnt
carbon. Fly ash with ≤4% unburnt carbon is saleable to cement factories as
discussed in meeting on 25.07.12. Efforts shall be made to produce fly ash with less
than 4 % unburnt carbon.
2) Existing coal handling system operates both conveyors for 12 hours in general, and
this increases during monsoon. It was suggested to design the coal handling system
with 30% moisture content for the proposed unit.
3) Existing unit bed ash is handled through scrapper conveyor (one unit under
construction) and fly ash will be handled by HCSD method (under construction).
Proposed unit should have dry ash handling system both for fly & bed ash.
Mechanised bed ash system with bed ash silo has been envisaged. Fly ash silo shall
have HCSD provision in addition to fly ash disposal system in case utilisation is
hampered.
4) Existing filter water tank is inadequate. Extension unit filter water tank capacity
should be minimum 200cum.
5) Extension unit DM water tank capacity shall be minimum 200 cum in addition to
existing 180 cum.
6) Optimisation of coal conveyor with bunker location is to be looked into.
7) During discussion CPL also requested to consider the following for extension unit:
a) Margin on Boiler (20% Unit MCR), Turbine (10% Unit MCR) capacity.
b) Additional DG set requirement
c) Soot blowing system, if CFBC
d) Air cooled condenser, if feasible.
e) TG shaft mounted MOP
f) Dearator pegging system not required
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 11
g) DC jacking oil pump
h) 50% steam dumping provision
i) Screw compressor in IA & Ash Compressor system
Note: During study with fuel availability, Boiler margin (a above) can be achieved
up to 20% in case of water cooled condenser option while for air cooled
condenser option it will be 15%.
2.4 PLANT CAPACITY & AVAILABILITY
The steam parameters for the proposed unit, which is not identical to unit-1, have
been considered as follows:
Parameter Unit Value
Option-1-WCC Option-2-ACC
Power at Generator Terminal MW 40 40
Boiler Capacity (MCR) TPH 156 164
Steam temp. at SH outlet Deg. C 515 +/ 5 deg C 515 +/ 5 deg C
Steam pressure at SH outlet Kg/cm2 (g) 89 89
Main Steam Pressure at
Turbine Inlet
Ata 87 87
Main Steam Temperature at
Turbine Inlet
º C 510 510
Main Steam flow at Turbine
Inlet
TPH 155.3 163.5
Exhaust Steam Pressure Ata 0.12 0.22
2.5 POWER OFF TAKE
The proposed 1x20 MW (Phase-II) is planned to evacuate energy from the station of
1x 60 (40 + 20) MW, through state grid. With Shale, Jhama and Washery Rejects as
fuel, the energy production cost from the station will also be substantially low.
2.6 POWER EVACUATION
No additional outgoing line feeder bays are envisaged for evacuation of power from
the proposed 20 MW Unit. Power will be evacuated at 132 kV from the existing
feeder bays of the 132 kV switchyard of the existing 40 MW Unit.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 12
However, two (2) nos. additional bays, one each for Generator Transformer # GT2 &
Station Transformer #ST2 are envisaged.
2.7 SITE SELECTION CRITERIA
The proposed unit will be installed adjacent to the present unit within the same site,
where the available land area is adequate. Hence, new site selection and/or catering
to the requirements/criterion is not relevant for the project.
2.8 LAND
2.8.1 Requirement
The land for the present and proposed units is already acquired. Hence, no
additional land is required for the proposed unit.
2.8.2 Availability
The land area is adequate to meet the Plant requirements, including green belt
development.
2.9 WATER
Presently, twelve (12) nos. bore wells have been installed to cater raw water to the
plant from bed of river Ajay. Estimated total water quantity requirement for the
proposed extension unit is as below.
Option-1 (WCC with HCSD system): 281 m3/hr.
Option-2 (ACC with HCSD system): 52 m3/hr
Hence either twelve (12) nos. (for option-1) or four (4) nos. (for option-2) additional
bore well of similar capacity as existing bore wells, will be the source of water for
both the units.
2.9.1 Cooling Water System
Closed cooling water system with cooling will be envisaged to minimize the
consumptive water requirement for the plant and hence optimum drawl of water from
the river.
2.9.2 Selection of Type of Cooling Tower
DPR has already explained that Air cooled condenser will cause for high investment
but the requirement of plant water is less than water cooled condenser. Space for
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 13
both the options water cooled condenser & air cooled condenser are available as
shown in respective plot plan drawings. Adaptation of specific option between WCC
and ACC shall have to be selected before finalization of the specification. The ACC
system design has been considered based on ambient temperature of 42 deg C.
Accordingly, during the extreme summer with higher ambient temperature, the plant
capacity will be reduced.
2.10 FUELS
The plant has been identified for firing of Shale, Jhama and Washery Reject coals.
Hence the primary fuel of the plant for power generation is coal in mix of three
ingredients namely, Washery Rejects (50%), Shale (16%) & Jhama (34%).
2.10.1 Main Fuel Selection
Integrated Coal Mining Limited (ICML) promoted by M/s CESC Ltd, has developed a
captive coal mine block in Sarishatali, Bardhaman district, West Bengal, for the
purpose of supplying coal to the thermal power station. ICML has installed washery
plant and use rejects for the existing plant.
The mine also has substantial quantity of Jhama coal (heat affected coal) of volatile
matter content of 8-10% but has high carbon content.
Such inferior quality of fuel available at this rate, however, can be burnt in
atmospheric fluidized bed combustion furnaces (also known as bubbling bed
combustion furnace) and Circulating Fluidized Boiler efficiently. Depending upon the
process deployed, moderately high combustion efficiency can be attained in such
furnace. Steam generation by deploying AFBC combustion process can attain an
efficiency figure of 80% and by CFBC the same can be attained 82 to 87%.
Thus, with utilization of Shale, Jhama and Washery Reject coals, the energy cost
from the station using CFBC Boiler will be considerably lower.
The expected coal quality is enclosed as Exhibit No. 1.
Boiler efficiency for the desired mix of coal is as below:
34% Jhama (sorted) + 16% Shaly coal + 50% Washery Rejects: 86.8%
Before finalization of the specification, a proper coal sampling of Jhama, Washery
Reject and Shale and analysis indicating GCV, HGI, Sieve Analysis, density,
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 14
proximate and ultimate analysis on as received basis is to be done for submission to
Boiler manufacturer for accurate design of the Boiler.
2.10.2 Start-up & Flame Stabilization Fuel
LDO shall be used for Cold Boiler start up only.
2.11 ASH
2.11.1 Quantity
Considering an ash content of about 65%, the estimated maximum ash generation in
the plant is approximately 39 TPH for proposed CFB Boiler.
2.11.2 Utilisation and Disposal Options
As per the MOEF notification dtd 14.09.1999, a new coal based power station should
make plans for utilization of 100% fly ash, in phased manner, within 9 years of
commissioning.
Being located close to the mine, ash generated from the station is proposed to fill-up
the mine progressively. Moreover, there are number of cement industries and
brickfields in the vicinity who would be interested in obtaining ash from the station.
Considering the above mode of disposal of bed ash as mine fill and fly ash usage in
other industries, no land would be procured for ash disposal from the station. Thus
100% utilization of ash will be achieved. To achieve the utilization, unburnt carbon in
the fly ash is to be reduced to less than 4% to ensure sale ability for cement plants.
Boiler manufacturers have to guarantee this fly ash quality. Bed ash is to be used in
roads & mine filling.
2.12 MAIN EQUIPMENT SELECTION
2.12.1 Capacity Selection of the Plant
The station is presently receiving Shale from Sarishatali mine to the tune of 0.25
MTPA and Washery Rejects from ICML’s washery @ 0.5 MTPA. This caters to the
present 1x40 MW unit at a load factor of 80%.
Approximately 0.25 MTPA of shale, 0.4-0.5 MTPA of washery reject and 0.15MTPA
of Jhama are available from ICML mines for another 15 years from now. With the
available fuel mixing of jhama, washery reject and shale the unit can generate steam
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 15
in the range of 189 TPH, 515 ºC and 89 ata which is a suitable match for a 40MW
steam turbine.
As gathered from the discussion with Boiler manufacturers, the optimum choice is to
adopt CFBC Boiler as against AFBC due to the following;
a) To limit the unburnt carbon in fly ash to a figure of ≤4% which is needed for its
sale ability / commercial value.
b) Inherent advantage of CFBC Boiler with respect to efficiency, scale of
economics, superior combustion technology and reliability.
CFBC Boiler in the range of 150 to 180 TPH single boiler is in operation in India for
more than 20 years and it is proven by BHEL, IJT, Thermax, Thyssen krupp etc.
Thus, the proposed extension plant has been selected with an installed capacity of
1x20 MW with CFBC Boiler. A detail discussion is presented cl no 2.12.4.
Jhama, Shale & washery reject requirement per year is 0.15, 0.07 & 0.22 MTPA
respectively, for 1x 20 MW extension project, i.e. 0.44 MTPA mix of jhama, shale &
washery design coal, which has higher GCV 2271 Kcal/kg.
2.12.2 Configuration of the Proposed Plant
Configuration of the proposed plant is single 189 TPH CFBC Boiler with a single
Turbine. Two Boilers with one turbine configuration is not economically feasible, for
the following reasons:
a) Recommended by manufacturers
b) Boiler rating of 189 tph of CFBC design has become standardized and well
proven
c) Reduced auxiliary power consumption
d) Optimization of space requirement
e) Improved efficiency
f) Overall economics
2.12.3 Steam Cycle Parameters
The primary factors, which govern the steam cycle selection are - efficiency,
equipment cost and the fuel price. With higher steam parameters, the investment
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 16
cost goes up on account of increase in the cost of SG and turbine island equipment,
but efficiency improves.
As per the present 1x40 MW Unit, the proposed unit will generally operate around 87
ata, 510 deg C main steam temperature. This steam parameter range is proven and
standard units are available with such parameters. Therefore considering optimum
cost economic aspect, the selection of the unit is in order.
Typical heat balance diagram with the above steam parameters is available in the
DPR (2007).
The heat cycle consists of a steam turbine with, condensate pumps, low-pressure
and high-pressure feed water heaters, a desecrating feed water heater, and electric
motor driven feed water pumps.
Heat rejection is accomplished by either a closed loop circulating water system
utilizing an induced draft cooling tower to supply cooling water to a condenser
operating at an absolute pressure of 0.12 Ata. Or an air cooled condenser operating
at an absolute pressure of 0.22 Ata.
2.12.4 Selection of SG Technology
Steam generators using either pulverized coal (PC) combustion technology or
Fluidized Bed Combustion (FBC) Technology are available. FBC is a mature
technology with more than 300 FBC boilers in operation world wide ranging from 5
MW to 250 MW. The FBC technology is principally of value for low grade, high ash
coals which are difficult to pulverize, and which may have variable combustion
characteristics. The advantage of fuel flexibility of FBC units made it a popular
choice for different installations.
Existing plant is running two AFBC boilers with fuel shale & washery reject.
Proposed boiler shall burn shale, reject and new fuel jhama coal which is harder but
with higher GCV. Existing unit cannot utilize ash for its higher percentage of unburnt
carbon. Proposed CFB boiler shall guarantee unburnt carbon less than 3.1%. As
discussed in previous sections, adequate Shale, Jhama coal and Washery Reject
coal will be available in nearby mines. Hence, CFBC boiler has been envisaged for
the proposed extension unit for generation of 189 TPH steam at 89 ata, 515ºC to
produce 20MW. Moreover, 1x40 MW AFBC unit is presently installed at the same
site.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 17
All the emissions will be maintained as per the PCB norms.
2.12.5 Selection of Condenser
Refer Sl. no. 2.9.2
2.12.6 Selection of Thermodynamic Cycle
During site visit & discussion with plant engineers, certain points like selection
criterion of boiler margin as 20% MCR, VWO margin as 10% MCR, and bypass
dumping capacity of 50% have been addressed – refer Clause 2.3.4 (7) above. All
these criteria will be finalized before preparation of specification as these are related
to cost implication only.
2.12.7 Equipment Sourcing
The existing 40MW unit has been installed on EPC basis. The proposed plant (Unit
#2) is also deliberated to be supplied, erected and commissioned on EPC basis. It is
prudent to order the same EPC contractor for the proposed unit.
2.12.8 Power Purchase Agreement
Power Purchase Agreement (PPA) is to be established between CPL and power
purchaser, for sale and purchase of the power.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 18
SECTION – 3
ENERGY EVACUATION PLAN
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 19
3. ENERGY EVACUATION PLAN
3.1 TRANSMISSION INTERCONNECTION
No additional outgoing line feeder bays are envisaged for evacuation of power from
the proposed 20 MW Unit. Power will be evacuated at 132 kV from the existing
feeder bays of the 132 kV switchyard of the existing 40 MW Unit.
However, two (2) nos. additional bays, one each for Generator Transformer # GT2 &
Station Transformer #ST2 are envisaged.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 20
SECTION – 4
MECHANICAL EQUIPMENT AND SYSTEMS
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 21
4. MECHANICAL EQUIPMENT AND SYSTEM
4.1 Steam Generator and Accessories
a) Steam Generator
The steam generator units proposed for the station will be semi-outdoor, natural
circulation, circulating fluidized bed furnace (CFBC) with over bed fuel feeding
system, balanced draft, single drum, dry bottom type with two-pass
configuration. Steam generating plant, complete with all auxiliaries, accessories
and controls, for supplying steam to the turbine generator set of nominal
capacity 40 MW operating on unit system with the steam generator feeding to
one TG set. CFBC boiler shall have cyclone separator or internal recirculation
arrangement of lighter unburnt particles back to fluidized bed for further
combustion. The steam generator parameter will match the TG set requirement.
Capacity of steam generating unit would be 189 TPH so as to ensure adequate
margin over the requirement of turbine at VWO condition in order to cater to (a)
auxiliary steam requirement for soot blowing operation, and also for start-up of
the future unit (optional), (b) de-rating of the steam generating units after
prolonged use. The steam generators would be designed to operate with “the
HP heaters out of service” condition (resulting in lower feed water temperature
at economiser inlet) and deliver steam to meet the turbo-generator requirement
at base load. Economiser section of the boiler would be non-steaming type with
provision for recirculation during startup, chemical cleaning etc. Superheater
section would be divided in convection and radiant zones and designed so as to
maintain rated steam temperature of 515 °C (±5°C) at the outlet over a control
range of 60% to 100% of MCR load. Main steam de-superheating station would
be provided with arrangement for spraying water tapped off from feed water
piping. The steam generator will be conservatively designed for satisfactory,
continuous and reliable operation at high efficiency with the range of shale,
washery reject and jhama coal mix expected for this station (GCV ranging
between 1800 to 2600 KCal/Kg) without any requirement of support fuel for
flame stabilization etc. within its control range. Furnace would be conservatively
designed to allow adequate residence time for the fuel to burn completely. The
design air and flue gas velocities would be carefully selected to minimize
erosion of pressure parts and other vital components. The pressure parts will be
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 22
designed as per ISO/ASME Sec.1 and would conform to the current Indian
Boiler Regulation (IBR). The boiler furnace and flue gas passages would be
designed for low gas velocities in order to minimize erosion or slagging.
The basic parameters of steam generator are furnished in the table at the end of
this clause.
Since, maximum furnace temperature in a CFBC boiler is kept within 950 °C,
NOX generation in the Steam Generator would be low. Maximum NOX emission
from the unit is not expected to be more than 750 ppm of NOX (equivalent NO2)
including thermal NOX produced during the entire operating range of Steam
Generator.
With low sulphur content in fuel, SO2 generated from the combustion and
emitted through the flue gas would be reasonably low. We have not considered
limestone feeding due to low sulphur content in all the fuels, in similar lines with
the existing Unit/ Plant. A 100 m high stack proposed is expected to bring down
the ground level concentration of SO2 based on 24-hourly average to a
minimum.
The Steam Generator and auxiliaries will perform continuously within noise
limits as per relevant standard specification but not more than 85 dB at 1 meter
from any equipment or sub-equipment and at 1.5 meter height. .
Indicative main parameters for the Steam Generator at relevant conditions are
given in the following Table:
Table 4.1
Plant Performance Parameters
Parameter Unit Value (WCC) Value (ACC)
\Boilers per unit No. 1 1
Main Steam Flow TPH 156 164
Main Steam at SH Outlet:
a) Pressure Ata 89 89
b) Temperature ºC 510 (+/- 5) 510 (+/- 5)
Feed water inlet temp. into
Economizer °C 200 205
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 23
To arrive at actual BMCR capacity, the following margins will be considered over
the above TMCR (to cater auxiliary steam requirement for soot blowing and
normal degradation of steam generating unit after prolong use):
• Margin available for BMCR capacity is 20% in case of water cooled
condenser option and 15% for air cooled condenser option.
The combustion chamber and coal burner system will be so designed to ensure
uniform heat absorption in the furnace and the furnace exit gas temperature
about 50ºC less than the initial deformation temperature of ash considering an
excess air amount of approximately 15-20%. The SG design will take care of the
aspect of minimum NOx emission level while designing the burner systems. Soot
blowers are not installed; however provision shall be kept for installation of soot
blowers in future.
b) Modes of Operation and Control
The SG with its auxiliary equipment is one of the principal components fixing the
dynamic capacity limits of the power plant. In order to be able to follow the
required operation regime and above all the high requirements for the support in
frequency variation, measures will be taken to ensure rapid availability after
various start-up procedures and optimum load-following capability.
The superheater outlet temperature will be kept constant within the load range
from 60 % to 100 % of SG Maximum Continuous Rating (BMCR).
For operation & control please refer Clause no 6.0
c) Steam and Feed Water System
Feed water from the feed control station will enter into steam drum for converting
into steam. Economizer will be provided in the feed water line after the feed
control station to raise the feed water temperature before feed water goes to
steam drum. The economizer outlet temperature will be kept slightly less than
saturation temperature to avoid steaming in the economizer.
Steam drum will be provided with necessary safety valves, drain and vent valves
of adequate capacity along with necessary instruments. Membrane/ panel of
water walls, riser, down comers will be provided in the SG for effective utilization
of heat flux from the furnace zone to convert feed water into steam.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 24
Steam produced in water walls flows from the drum to the superheater and to the
outlet header through the main steam line to the inlet connection of the high-
pressure steam turbine throttle valves. A connection for providing turbine seal
steam from the Main Steam System will be included, if required, by the turbine
manufacturer.
Main steam temperature will be controlled by two / three stage spray type
attemperators as per the standard practice of the manufacturer. The spray water
for the attemperators will be taken from the feed water circuit.
Desuperheating spray water is supplied from the feed water circuit.
Safety valves, relief vent valves, and piping are provided for system operation
and overpressure protection. The design and manufacture of the SG will conform
to IBR and ASME regulation/code.
d) Auxiliary Steam
Users of auxiliary steam include the deaerator pegging steam during start-up
operation, soot blower (optional), the turbine seal system etc.
The Auxiliary Steam System supplies reduced pressure and temperature steam
to power station steam users that do not require steam at main steam conditions.
Two low capacity Pressure Reducing and De-superheating (PRDS) are proposed
for the Unit. One PRDS will be used for SJAE steam requirement. Steam for the
same will be drawn from main steam header. This PRDS reduces the pressure
and temperature to 11kg/cm2 (a) and 350 deg C respectively. Another PRDS will
be used for Desecrator pegging steam. High pressure PRDS will be used for
Turbine bypass during load throw off condition. This will reduce the main steam
Pressure and Temperature to 6 kg/cm2 (a) and 200 deg C respectively.
e) Draft System
Draft system is envisaged to have two (2) nos. Forced/Secondary Draft (FD/SA)
fans two (2) nos. of Induced Draft (ID) fans and two (2) nos. of Primary Air (PA)
fans of matching capacity, with each fan rated for 60% of BMCR capacity. The
FD/SA fans may be of variable pitch control aerofoil or centrifugal type with
silencer at air inlet. The ID fans would be variable speed (with hydraulic device or
equivalent) backward curved blade-type. The equipment should be complete with
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 25
lube oil, hydraulic regulations and all other accessories required for continuous
operation. All equipment would be suitable for outdoor installation.
Air pre-heaters of tubular type would be provided. Two (2) numbers each of
primary and secondary air heaters will be provided for the boiler.
f) Fuel Feed Systems
Fuel firing system will be designed to burn maximum particle size of 6 mm with
fine content (less than 1 mm size) not exceeding 40%.
Steam Generator unit would be equipped with suitable shale, Jhama coal and
washery reject mix firing arrangement comprising bunkers, positive displacement
type (e.g. drag link or scrapper) raw fuel feeders in over-bed, primary air fans,
fuel and air pipes, burners etc. as necessary. The feed control for the fuel would
be done either on manual mode or automatic mode and controlled as per the
plant load and composition of the fuel mix. Provision of feeding bed material
would be provided, comprising bed material silo, feeders (screw feeders or
equivalent) with necessary controls. The firing system would ensure load
variation from 30-100% BMCR without any stabilizing fuel. The steam generating
units will be provided with arrangement for start up by light diesel oil. After
achieving the appropriate temperature profile in the furnace design fuel would be
fed to the furnace.
g) Bed Ash Extraction System
The scheme proposes, dry extraction and disposal of bed ash via bed ash
cooler, bed ash collection hoppers, ash transmittal vessels and ash conveying
pipe upto the bed ash silo.
h) Start-up Fuel Oil System
Light Diesel Oil (LDO) will be secondary fuel used only for start-up for coal
ignition Two (2) nos. 100% capacity fuel oil pumping units are provided for the
steam generators of the existing unit. One (1) additional pump of same capacity
will be installed to augment the fuel oil system, to meet the fuel oil requirement
for the Unit #2 (Phase II).
Since, the auxiliary fuel oil requirement of AFBC boiler is quite low, the light oil
handling, storage and forwarding system would be planned as common for both
the present and proposed units. One (1) no. 30 m3 capacity storage tank along
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 26
with pumps, strainers at suction and discharge, valves, controls, instrumentation,
drain oil tank, etc. as required is installed in Phase-I. Another tank of same
capacity will be installed in Phase-II. The oil will be supplied from the nearest
depot by road tankers.
i) Electro Static Precipitator (ESP)
Each steam generating unit would be provided with one (1) no. electrostatic
precipitator. Each precipitator will have two parallel gas paths, any of which can
be isolated for maintenance as and when required, keeping the other path in
operation. Each path will have adequate number of fields in series for collection
of fly ash. The overall efficiency of ESP should not be less than 99.99% with one
field remaining as operational standby. The ESP would have adequate number
of ash hoppers provided with electric heaters. The control of ESP would be
based on microprocessor using semi-pulse device. The design of ESP will be
such that the outlet dust-burden does not exceed 50 mg/Nm3 at BMCR with
worst fuel mix.
j) Soot Blowing System (Optional)
The boiler will have provision for installation of automatic sequential electrically
operated type steam soot blowers with facility of manual retraction in emergency
for on-load cleaning of the heat transfer surfaces.
k) Boiler Structures and Accessories
The complete boiler will be top supported type and would be provided with all
supporting steel structures, platforms, galleries, elevator and stairways for easy
approach and maintenance of the unit. Adequate weather protection would be
provided for instruments and operating personnel. Necessary lining and
insulation along with fixing materials to limit outside surface temperature to a
safe level would be provided. Monorails and hoists required for handling heavy
equipment, motors, fans etc. would be supplied along with the steam-generating
unit for ease of maintenance.
l) Bed Material filling system
Provision shall be kept for separate silo for bed material and bucket system for
filling the silo. Pipe line arrangement from silo to boiler bed with gates,
accessories shall be made.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 27
4.2 Main Fuel Unloading, Transportation and Feeding System
a Design Criteria and Assumptions
The Fuel Handling Plant for the station is designed to operate with shale, Jhama
with washery rejects available from mine and washery are located within a
kilometer of the project site. While shale and jhama coal will be supplied in
dumper, washery rejects shall be transported in conveyor. For the purpose of
equipment selection, fuel quality mentioned in Exhibit-1 of the report has been
adopted.
Adequate redundancy has been adopted to ensure uninterrupted operation of the
system. The followings are the salient points of design basis of the Fuel Handling
Plant:
b System Description
The scheme of the proposed Fuel Handling System is shown in Drawing No.LII-
KEOE-12022-40121-001, Rev-A. The layout is shown in the Plot Plan (Dwg. No.
LII-KEOE12022-00110-001, Rev-A.
For the proposed station, twelve (12) hours of operation in a day would be
adopted for the fuel handling system. The system design considers new stream
of conveyors for conveying shale and jhama coal from either the primary crusher
outlet or the stockyard and washery rejects directly from stockyard to proposed
Unit #2 (Phase-II), via secondary crusher for Phase-II.
One single stream 300TPH capacity along with primary crusher, screen and
vibrating feeder has been envisaged from reclaim hoppers of Jhama and shale
unloading yard to stock pile for general shift operation only. Two stream of
conveyors 150 TPH capacity along with secondary crusher, screen, vibrating
feeder, fixed tripper conveyors have been considered from reclaim hoppers of
secondary crusher to bunker level feeding for 12 hrs of operation. Two streams
of conveying in Phase-I, shall have a provision for feeding arrangement to
proposed unit –II at the bunker level, in case of exigency. Primary crusher
300TPH has been considered with a view to feed jhama coal to existing Unit-I
also in future for AFBC.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 28
Shale, Jhama coal and washery reject shall be fed successively and
predetermined ration on weight basis on same belt for preparation of good mix in
the crusher.
Shale/ Jhama coal, on receipt at plant end by dumpers at (-) 300 mm size, would
be fed to the primary crusher house via one new conveyor (300TPH) which will
be installed for proposed unit-II to carry Shale/ Jhama coal from dumping area to
Primary Crusher House, which will also be installed new for the proposed unit-II.
Here, the size would be reduced to (-) 80 mm. The primary crushing unit would
be equipped with one vibrating screens followed by two (1 working + 1 standby)
rotary breakers (one for jhama and one for shale) or single crusher (Jhama &
shale). Crushed coal received from either crusher or single crusher shall be
stacked at stockyard by tripper conveyors in two different locations. Crushed
shale/Jhama coal would thereafter be led either to crushed shale/ Jhama coal
pile by conveyor, which will be installed new for proposed unit-II or to the
secondary crusher house, which will be installed new for proposed unit-II.
Washery rejects, received at the plant by Tripper cum Spreader conveyor, in
sizes (-) 80 mm would contain surface moisture due to the floatation process
adopted in the washery. Washery rejects would be spread in the yard with
bulldozer to permit water evaporation and dried fuel would be directly fed to the
secondary crusher. Shale/ Jhama coal after primary crushing and washery
rejects after adequate drying shall be fed to the surge hopper of the secondary
crusher house to permit mixing. Fuel thus mixed shall be crushed in the
secondary crushers via screens and then conveyed to the powerhouse to feed
fuel-bunkers. Recycling shall be used to ensure the feed size of the fuel as (-) 6
mm. The oversized component of the screens shall be recycled back the
secondary crusher by high lift conveyors.
The secondary crushers, vibrating screen, bunker conveyor and high lift
conveyor shall be provided with standby units.
Transfer points at suitable locations between new reclaim hoppers and
Secondary crusher House (Phase-II) and between secondary crusher House and
boiler bunkers (phase-II) shall be located.
Considering the magnitude of fuel requirement of upto 60 TPH (with worst fuel)
feeding by pay loaders to the ground hoppers is considered adequate for the
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 29
unit. In view of proximity of fuel source, a stock of 7 days’ requirement of shale,
Jhama coal and washery rejects is also considered adequate. The system
design would consider that for either type of fuel, the power generating block
could be operated at MCR. This arrangement would be operational under
exigency conditions.
Crushed fuel from secondary crusher would be transported to the bunkers by the
inclined conveyors which will finally feed the bunker level conveyors via fixed
tripper conveyors.
The conveyor structure from the stackyard through secondary crusher to the
bunker level will be installed. Bunkers will have a storage capacity of about 16
hours’ fuel requirement for the boiler. The bunkers will be provided with rod and
slide gates, arch breakers, etc. to facilitate operation. Necessary belt weighing at
bunker level conveyors, electro-mechanical and capacitance type level
indicators, fuel sampling units, flap gates etc. would be provided in the system as
required.
C Salient Features of the System
The major equipment for the fuel handling plant for the proposed unit-II are listed
below:
1. Belt conveyors : 1) One stream conveyor line of 300 TPH
from the ground hopper of the unloading
stackyard to the stock pile area through
primary crusher. One tripper shall stack
jhama & shale in two different locations.
2) Two stream of conveyor line of 150TPH
from stockyard to bunker level through
secondary crusher and transfer points
and finally fixed tripper belt conveyors to
bunker hoppers.
2. Vibrating feeders : 300 TPH (-300mm) for conveyer upstream
of primary crusher and 150 TPH for
conveyer upstream of secondary crusher
(-80mm) capacity each as required
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 30
3. In-line magnetic separators : Qty as required by the system
4. Vibrating screens : 300 TPH (-80mm) (Primary Crusher House)
and 250 TPH (-6mm) at upstream of
secondary crusher
5. Primary Crusher (Cap. 300TPH)
Rotary breaker type : 2 x 100 % single roll crusher
6. Secondary Crusher (Cap. 150 TPH) : 2 x 100 % Hammer mill
7. High lift crusher : 100 TPH (2 x 100 %)
8. Fixed Tripper Belt Conveyor : As required
(Cap. 150 TPH)
Other Salient Features:
Metering of Coal
Adequate number of electronic belt scales would be provided on conveyors at
appropriate places to monitor the inflow of coal quantity into the plant and the coal
feed to the bunkers.
Coal Sampling System
Coal sampler will be provided in the junction tower to collect the coal samples for
analysis of the raw coal received in the station and feeding to the bunkers.
Tramp Iron Detection and Removal
Tramp iron and other magnetic materials would be removed by means of In-line
magnetic separators provided on the head pulleys of conveyors leading to the
crusher house
Fire Protection
Fire hydrants will be provided at all tunnel entry points, junction towers/crusher
house, bunker gallery and along the overhead conveyors. Fire hydrants would also
be placed along the periphery of the fuel stock pile for fire fighting.
Dust Control
Suitable pollution control measures like dust extraction and dust suppression
systems will be provided at different transfer points and crusher houses and
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 31
ventilation system to supply fresh air in underground tunnels will be provided. In
addition, roof extraction fans will be provided in essential areas like crusher house
and SG bunker floors. Pressurized ventilation with unitary air filter unit will be
provided for control room and MCC buildings of coal handling plant.
Stockpile area will be provided with automatic garden type sprinklers for dust
suppression as well as to reduce spontaneous ignition of the coal stockpiles.
Necessary water distribution network for drinking and service water with pumps,
piping, tanks, valves etc. will be provided for distributing water at all transfer points,
crusher house, control rooms etc.
Controls
A centralized control room with microprocessor based control system (PLC) has
been envisaged for operation of the coal handling plant. Except locally control
equipment like travelling tripper, dust extraction/ dust suppression / ventilation
equipment, sump pumps, water distribution system etc., all other in-line equipment
will have provision for local control as well. All necessary interlocks, control panels,
MCC’s, mimic diagrams etc. will be provided for safe and reliable operation of the
coal handling plant.
4.3 Ash Handling System
To meet the requirement of the prevailing environmental norms of the State
Pollution Control Board (WBPCB) and Central Pollution Control Board (CPCB)
guideline, the system considers extraction and disposal of ash in dry form for the
proposed station.
The quantum of ash generation would depend on the plant load factor and the
quality of fuel. In keeping with the designed system capacity envisaged for fuel
handling plant, worst fuel parameters from the source mentioned earlier is used for
equipment selection of the Ash Handling Plant.
The Ash Handling System control room will be located adjacent to ESP control
room for ease of operation.
For the design of the Ash Handling System, the following data has been
considered.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 32
Table – 4.2
Design Parameter for Ash Handling Plant
Parameter Value
Hourly Shale, Jhama coal and/or washery rejects firing rate
for 1 no. 189 TPH boiler at BMCR condition
59.1 TPH
Total % ash content in fuel, considered for design of ash
handling system 65.46 %
Ash Generation for boiler 39 TPH
Distribution of total ash produced for design of ash
handling system
a) Bed ash 20%
b) Fly ash 90%
Generation of Ash in both boilers, based on above ratio
a) Bed ash 7.8 TPH
b) Fly ash 34.8 TPH
Design capacity of Ash handling system (considering 50%
margin)
a) Bed ash 12 TPH
b) Fly ash 52 TPH
Capacity & Time Cycle
In case of CFBC boilers, bed ash generation may go up to 20% of total ash
generated, but Fly Ash generation will increase to 90%. Considering the quantum of
ash generated, intermittent ash removal arrangement with necessary storage
hoppers to hold ash for 8 hours is envisaged. Bed ash extraction for 2 hours per
shift and fly ash evacuation in 4-4.5 hours/shift has been considered.
Bed Ash Handling System
In Drawing No.LII-4236-406-W-101 of DPR (2007), the schemes proposed for the
ash handling plant of the station is shown. The scheme proposes, dry extraction
and disposal of bed ash via bed ash cooler, bed ash collection hoppers, ash
transmittal vessels and ash conveying pipe up to the bed ash silo.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 33
Fly Ash Handling System
Fly ash from ESP, air heater and economizer collection hoppers and stack hoppers
would be conveyed through pressurized conveying system to the F.A. silos. As
shown in the above drawing, conveying air compressors would be used to transfer
both bed ash and fly ash to the respective silos. De-ashing from fly ash hoppers
would operate on an auto sequence mode with total operation time spanning 4 to
4.5 hours in a shift. One stream of pneumatic conveying extraction system have
been considered for the boilers. The ash would be conveyed through pressure
conveying system up to the fly ash silo located near the eastern boundary of the
plant. The design capacity of the pressure conveying system would be optimized to
suit this requirement.
Dry fly ash would thereafter be transported in trucks from the silos to mine for
backfilling. An additional nozzle is provided below the silos for adopting any other
mode of transport in future. Normally, dry disposal mode would be operational.
Provision is kept for selling ash from the dry ash disposal spout of silo to the
possible users. A small quantity of water will be sprinkled to moisten the ash in the
silo unloaders prior to loading in the trucks for disposal.
4.4 Plant Water System
The plant water system will be designed to supply cooling water make-up based on
cycle of concentration 4 and other consumptive water requirement for the proposed
1x20 MW Unit. A closed cooling water system employing Induced draft-cooling tower
has been envisaged for the proposed unit to minimize the plant water intake
requirement.
Scheme for proposed Plant Water system is shown in the DPR-2007 Drawing No.
LII-4236-401-W-101: Water Balance Diagram and Dwg. No. LII-4236-405-W-102:
Flow Diagram for Plant water System. However some change has been made drg no
LII-KEOE12022-40021-001-1(WCC)R-A & LII-KEOE12022-40021-001-2 (ACC), R-
A: Plant water System & LII-KEOE12022-00027-001-1(WCC)R-A & LII-
KEOE12022-00027-001-2 (ACC), R-A: Water Balance Diagram attached with this
report. The total plant water requirement for both the units is indicated in Table-.
Recently CPL is going to install High concentration slurry ash disposal (HCSD)
system in Unit#1 for filling the Ash in open mines. Out of 41 cum/hr required for
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 34
HCSD system, cooling tower blow down gives 20 cum/hr and balance water is being
drawn from existing system. Provision for One more HCSD for Unit #2 has been
envisaged in line with Unit #1. Additional water requirement for this can be supplied
from the existing system.
4.4.1 River Water Intake Water System
Raw water would be drawn from river bed through bore wells. With consumptive
water requirement is represented in table below, it is estimated that either 12nos. (if
WCC) or 4 nos.(if ACC) pumps will be additionally installed in Phase-II, considering
that ten (12) nos. bore well pumps already installed in Phase-I. This will ensure
adequate redundancy. Raw water would then be collected in a semi-underground
reservoir near to river. From this reservoir, raw water is presently being pumped to
plant by four (4) nos. of pumps (2W +2S) to in-plant raw water reservoir. Additional
either 4 nos. (2W+2S) for WCC or 2 (1W+1SB) nos. intake pumps shall be installed
in Phase-II.
Sl. No.
Items Unit Unit#1 Unit#2
Remark WCC With HCSD
WCC with HCSD
ACC with HCSD
1 Plant Water m3/hr 180+41.5
(for HCSD) 181 52
2 Bore wells nos. 10+2 (for HCSD)
12 4
As discussed in meeting on 25.07.12, water received from existing 10 pumps (5W+5SB) is 175m3/hr. Hence capacity of each pump available 17.5m3/hr
3
Second pipe line from Intake reservoir to Plant
NB 250 250 250
As discussed in meeting on 25.07.12 additional 250 NB pipe shall be consider for proposed unit
4 Raw water Reservoir pump (outside plant)
nos. 2+2 2+2 1+1
As discussed in meeting on 25.07.12, water received from existing 4 pumps (2W+2SB) is 173m3/hr
5 Raw water Reservoir pump (outside plant)
nos. 1+1 1+1 1+1 Pump capacity for ACC option shall be less than existing
The cross-country raw water intake pipeline covering a route length of about 5 Km.
is of mild steel construction with wrapping & coating and provided with cathodic
protection.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 35
One number 250 mm dia. raw water intake pipe line is already installed for supplying
raw water from outside plant reservoir to in-plant raw water reservoir already
existing and common for both Phase-I & II. Another 250 mm dia. raw water intake
pipeline will be installed in Phase-I to augment the flow of raw water to the in-plant
raw water reservoir.
The available data on raw water analysis is given in Exhibit-4 of DPR (2007). It may
be noted that as raw water would be drawn from river bed, total suspended solid
(TSS) is expected to be reasonably low other than in rainy season.
Availability of River bed water for the extension unit needs to be examined and
confirmed by competent authorities. Besides the pumping arrangement including
river bed bore well locations are also required to be finalised in consultation with the
aforesaid authorities.
4.4.2 Raw Water Distribution System
The station is having 7 days raw water storage facility at the plant which can cater
to any exigency condition in water supply system.
The present raw water pump house shall be extended or new pump house is to be
erected to accommodate the new raw water intake pumps required for Phase-II.
At the inlet of in-plant raw water reservoir, a cascade aerator will be provided to
oxidize the iron present in the raw water. Raw water from the in-plant reservoir
would be pumped by raw water supply pumps primarily to supply water to cooling
tower as make-up. Two (2) nos. pumps are presently installed in phase-I. Additional
two (2) nos. pumps ( same capacity of existing phase -1 for WCC option or smaller
capacity for ACC option) will be installed in phase-II. A static mixer would be
provided on the discharge of raw water pumps, where Sodium Hypochlorite would
be dosed to precipitate out Fe as Fe(OH)3. One branch will be taken to Cooling
Tower through ‘Make-up water Filter cum SSF’. Another branch from the in-plant
raw water pump discharge main header will be taken to filtered water storage tank
through a filter. The above filters will remove the solids from the raw water streams.
The requirement of Potable water, Service water and DM water would be catered
from filtered water tank.
The filtered water tank 80 cum is located in the water treatment area and common
for both the units of Phase-I & II. From the discussion, it is observed one more filter
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 36
water tank of capacity 200 cum is required to be installed for Phase-II extension.
4.4.3 Circulating Water (CW) System
From the raw water analysis available, it may be noted that the total dissolved solid
in the raw water is reasonably low and with acidulation/dosing a favourable cycle of
concentration could be attained. For the purpose of estimation of the study a cycle
of concentration of four (4) has been adopted.
On the basis of available parameter of turbine generator set and considering a
differential temperature across the condenser as 9 °C cooling water in circulation is
estimated at 7830 m3/hr for unit -2, which includes the requirement of auxiliary
cooling circuit. But for Air cooled condenser only 460 m3/hr for the auxiliary cooling
circuit. The makeup water requirement for the Induced Draft Cooling Towers at full
load will be around 174 m3/hr (if WCC) or 10 m3/hr (if ACC) for unit-2. The cooling
tower blow down is expected to be about 39.6 m3/hr (if WCC) or 2.3 m3/hr (if ACC)
for unit-2. The raw water would be used as cooling media for condenser cooling (for
water cooled condenser) and auxiliary cooling circuit. For water cooled condenser
cooling water would be pumped from the cooling tower basin by 3x 50% capacity
cooling water pumps to take care of condenser heat load. Through a separate set of
auxiliary cooling water pumps (2 x 100% capacity) the heat load of heat exchangers
of auxiliary equipment of TG and SG auxiliaries would be dissipated and the return
hot water would be fed to the circulating water return header.
For Air cooled condenser only 2x100% capacity auxiliary cooling water pumps to
take care the heat of heat exchangers of auxiliary equipment of TG and SG
auxiliaries.
4.4.4 DM Plant and Heat Cycle Make-Up System
Total power cycle make up requirement including regeneration will be 4.5m³/h for
each unit of power plant. The present DM plant capacity (10 m³/h) is adequate for
requirement of both phase-I and phase-II units. However, another chain for identical
DM plant of 10 m3 capacity will be installed as common standby. One (1) no. DM
tank is already installed in Phase-I. One (1) no. additional DM tank shall be installed
in Phase-II.
4.4.5 Service Water & Potable Water System
Various consumption points like air washer unit make-up, various pump gland seals,
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 37
ventilation system, etc. to be suitably integrated and interfaced with the unit of
phase-I facility.
For potable water supply to the station, to be suitably integrated and interfaced with
the unit of Phase–I facility of filtered water with necessary chlorine dozing is
envisaged. On apportioned basis, about 1 m3/hr of potable water may need to be
supplied for proposed plant of phase-II potable use. Filtered water from the filter
water storage tank would be supplied for air-conditioning system make up and DG
set cooling, pump capacity of existing system of phase-I unit would be augmented
to cater the requirement of phase-II unit for use as common system.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 38
SECTION – 5
ELECTRICAL SYSTEM AND EQUIPMENT
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 39
5. ELECTRICAL SYSTEM AND EQUIPMENT
5.1 ELECTRICAL SYSTEM ARRANGEMENT:
The scheme for the proposed 20 MW Unit is envisaged as similar to that of the
existing 40 MW Unit considering the requirements of efficient and reliable operation
of the plant in start-up, normal as well as adverse system condition.
The generation voltage is envisaged at 11 kV, similar to the existing one and the
generator will be directly connected to existing 132 kV outdoor switchyard through
11/138 kV generator transformer for evacuation of power. To evacuate power to
Ganrui Substation of WBSETCL and to receive start up power for power plant
auxiliaries the existing 132 kV outdoor switchyard will be augmented to
accommodate two (2) nos. bays. The additional 20 MW from proposed Unit will be
evacuated to Ganrui Substation of WBSETCL through existing double circuit 132
kV overhead line.
In order to accommodate extra 20 MW power, the adequacy of the existing double
circuit line as mentioned above and the present capacity of Ganrui Substation of
WBSETCL shall be checked by necessary electrical system studies. Moreover
necessary coordination may be done by CPL with WBSETCL in this regard.
Start-up power requirement for the proposed 20 MW Unit will be made available in
the following two ways:
a. Through 132kV System via 132/6.9kV Station Transformer.
b. From 6.6 kV switchgear of existing 40 MW Unit, for initial start up only.
The house load power will also be available directly from generator terminal
through one (1) no. 11/6.9 kV Unit Auxiliary Transformer (UAT).
Capacity of the Station Transformer for the proposed unit shall be such that it can
take the entire start up load of the existing as well as proposed unit during the
absence of the existing Station Transformer.
Unit Auxiliary Transformer for proposed unit shall also be sized to take care of the
unit load of both the unit during absence of the existing Unit Auxiliary Transformer.
Necessary fast bus change over facility shall need to be provided between the
existing 6.6kV Switch Gear as well as proposed 6.6kV Switch Gear.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 40
In the existing intake water system, there are 10 nos. 13kW bore well pumps and 4
nos., 55kW raw water pumps. For the proposed 20MW, 10 nos., 13kW bore well
pumps and 2 nos., 55kW raw water pumps are also envisaged. The existing
system is being fed by 1 no. 11/0.415kV, 315kVA & 1 no. 11/0.415kV, 100kVA
Transformer. Another 1 no. 11/0.415kV, 315kVA transformer is in stand-by mode.
To take care of new loads, separate 1 no. 11/0.415kV, 315 kVA & 1 no.
11/0.415kV, 100kVA Transformer are envisaged. A new 415V MCC is also
envisaged within the intake pump house adjacent to the existing 415V MCC.
Manual / Auto change over facility is also envisaged between the above three nos.
(2 nos. existing & 1 no. new) 315 kVA transformer feeders. Between the present
running 315kVA transformer and the new 315kVA transformer, if any one will be
out of service, then the present stand-by transformer will automatically come into
service. In the existing system, maximum 6 nos., 13kW bore well pumps and 2
nos., 55kW raw water pumps are running. After considering 2 nos.100kVA and
three nos. 315kVA transformer, it has been observed that the overall running load
is well under the incoming fuse rating of 200A (As per the existing intake fault
calculation report). Therefore, no modification is required for the existing 11kV O/H
line. However, further verification can be done during detail engineering.
The auxiliary power supply system will consist of one (1) no. 6.6 kV station
switchgear, 2x100%, adequately rated, 6.6/0.433 kV Station auxiliary transformer,
2x100%, adequately rated, and associated 415 V PCC & MCC. Provision for
auto/manual changeover from one supply to another will be kept. Downstream LT
distribution to various load centres will be done from 415 V PCC. 2 nos. 6.6/0.433
kV Transformers for CHP PCC are envisaged.
A separate emergency 415 V, 3-ph, 50 Hz Diesel Generator (DG) Set is envisaged
for emergency power supply during shut down of the proposed 20 MW Unit. One no.
emergency MCC will be provided to cater all emergency loads. In case of total AC
power failure, the Diesel generator will start automatically and supply power to 415V
Unit Emergency Switchgear where all essential loads are connected. Provision will
be made for synchronizing 415V Unit Emergency Switchgear with the respective 415
V Unit auxiliary Switchgear for testing and taking in/out of the DG, as required.
For supply of unit and station auxiliary loads of the proposed 20 MW Unit, the
following voltage levels have been envisaged:
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 41
� 6.6 kV level through 11/6.9 kV unit auxiliary transformer and 132/6.9kV Station
Transformer
� 415V level through 6.6/0.433 kV station auxiliary transformers.
� 415V emergency power through Emergency DG set of proposed 20 MW Unit.
� 240V, single phase, 50Hz , AC UPS system for Control and instrumentation.
� 110V DC for emergency drives, lighting, control and protection systems.
6.6/0.433kV auxiliary transformers of suitable ratings will be provided to meet 415 V
Unit / station load requirements of the proposed 20 MW Unit. All 415 V switchgears
will have 2 x 100% incoming feeders, to be supplied by 2 x 100% 6.6/0.433kV
auxiliary transformers, and bus section aliser to achieve maximum redundancy and
reliability during operation.
The design concept of the electrical auxiliary system as a whole is based on the
requirements for the safe and reliable operation of the Plant with provision for easy
maintenance. The design and performance requirements of equipment will be
generally as per latest Indian Standards and the Codes of Practice, IEC
Recommendation. Indian Electricity Rules, wherever applicable will also apply.
5.2 CONSTRUCTION POWER:
For construction activities, power supply from 6.6 kV switchgear of existing 40 MW
Unit has been envisaged.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 42
SECTION – 6
CONTROL AND INSTRUMENTATION SYSTEMS
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 43
6.0 CONTROL AND INSTRUMENTATION SYSTEM
6.1 Design Philosophy
The control and instrumentation system for the proposed 20 MW Unit with CFBC
technology has been envisaged to be similar to that of existing 40 MW Unit and will be
designed to ensure safe, efficient and reliable operation of the plant under all regimes
of operation, namely start up, shutdown, normal operation, part load operation and
under emergency conditions resulting in cost effective power generation with optimum
fuel consumption and reduced emission levels.
The operation, control and monitoring system envisaged for the plant would be based
on a state of the art microprocessor based Distributed Control System (DCS).
All BOP off-site systems will be controlled and monitored through the DCS.
Monitoring and operation of Plant Electrical Systems will be carried out from the DCS
Operator Stations in the Central Control Room.
Plant abnormal conditions will be alarmed through the Operator Interface Units and
window annunciator. Alarm printer will be provided to print out all alarms with time
tagging and in the chronological order.
Sequence of Event Recording function will be provided for recording and printing
occurrence of events in a chronological order for quick diagnostic of fault and remedial
action.
DCS will perform online performance calculations to determine plant/equipment
efficiency and to detect and alarm unit / equipment malfunctions.
Redundant soft link interfacing provision and seamless integration with Phase-I DCS
has been envisaged for the new DCS of Phase-II.
6.2 Major Control and Instrumentation Systems
The major components of Control and Instrumentation system of the unit will comprise
of the following:
• Distributed Control System (DCS)
• DCS based Steam Generator Control and Protection System or as per
manufacturer’s standard design interfacing with the Plant DCS.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 44
• DCS based Steam Turbine Generator Control and Protection System or as per
STG manufacturer’s standard design interfacing with the Plant DCS.
• DCS based control system for specified plant BOP off-site packages
• Turbine Supervisory Instrumentation system for STG
• Central Control Room, Control Desk and Electrical Control panel
• Measuring Instruments & flow elements
• Steam and Water Analysis System (SWAS)
• Stack Emissions Monitoring System
• Stand alone BOP off site Package control system
• Uninterruptible Power Supply and Distribution
• Final Control Elements
• Instrumentation & special cables
• Maintenance and Calibration Instruments
• Erection Hardware
6.3 Distributed Control System (DCS)
An integrated functionally Distributed Control System (DCS), synthesized from one
general family of interchangeable multifunction hardware has been envisaged for the
proposed 20 MW Unit.
Distributed Control System (DCS) for the plant will consists of following basic
functions / Subsystems:
• Close Loop and Open Loop Control Systems, which include Interlock and
Protection systems, Sequential Controls, Plant Automation features and
Measurement Systems
• SG & TG control configured in separate and individual Functional Groups in the
Plant DCS.
• CHP, AHP and DM Plant controls through Remote DCS I/O Systems.
• Operator Interface Units (OIU) in Central and local Control Rooms
• Plant Data Communication System including Fiber Optic Communication
between the Central Control Room and the Local Control rooms.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 45
• Historical Storage and Retrieval
• Plant Performance Calculations
• Sequence of Events Recording System.
• Alarm Annunciation System
DCS shall be provided as a minimum with dual redundant processor subsystem
including CPU, memory and power supply. Redundancy shall be provided such that,
in case of failure of the main processor, the standby processor shall take over
automatically and vice-versa. The changeover shall be bump less and shall not
result any process or system upset.
In case of failure of complete processor system i.e., both processors outputs shall take
fail safe state automatically.
DCS will be of Open Architecture type having high system availability and reliability.
The DCS will provide a comprehensive integrated control and monitoring system to
operate, control and monitor the Circulating Fluidized Bed Steam Generator &
auxiliaries, Steam Turbine-Generator & auxiliaries and power cycle equipment and
auxiliaries including operation and monitoring of Coal Handling, Ash Handling, DM
Water Plants and monitoring of other Balance Of Plant (BOP) off-site systems with a
hierarchically and functionally distributed structure.
All open loop and close loop modulating control functions for the main plant including
Steam Generator and the Steam Turbine Generator and their auxiliaries along with
power cycle equipment and systems will be implemented into the DCS so that
centralized operation of the main plant and associated auxiliaries is possible. DCS will
also include sequential start up, shutdown of the major auxiliaries of Steam Generator,
Steam Turbine and power cycle Equipment and Systems.
The control functions will be backed up by protection, interlocks and safety functions.
This would cause pre-planned actions in cases where unsafe conditions develop faster
than the control capability of modulating controls or before the operator can be
expected to respond to the plant upset conditions in any regime of plant operation.
6.3.1 Close Loop and Open Loop Control System
The control system along with its measurement system will perform functions of Closed
Loop Control System (CLCS), Open Loop Control System (OLCS) including protection
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 46
functions, measurement and monitoring of signals and alarm function.
Close loop controls such as Fuel flow control, Furnace pressure & air flow control,
Drum level control, Hot well level control, Heater level control, Deaerator Level Control,
Make-up water Control, recirculation control etc will be configured in the DCS.
Start / stop sequence control and protections of ID & FD Fans, Boiler feed pump,
Condensate extraction pump, HP/LP heaters, Make-up water pumps, equipment
cooling water pumps and all motorized drives will be configured in the DCS.
6.3.2 Operator Interface Units (OIU)
Operator Interface Unit will consist of Operator Terminals (OT) based on latest PC or
Work Station with redundant communication link, 21” Colour Graphic LCD (TFT)
Monitor, Keyboard and mouse, printers.
Dot Matrix, Colour Printers etc. will be provided for generation of logs, reports,
Graphics pages and miscellaneous printouts.
6.3.3 Data Communication
Different subsystems of the DCS are interconnected through redundant bus
communication system. This includes redundant data Bus, redundant Plant Data
Highway and other applicable bus subsystems. The communication bus system will
be in hot redundant configuration with no loss of data or loss of communication in
case of failure of one bus.
6.3.4 Historical Storage and Retrieval (HSR) System
Historical Storage and Retrieval system (HSR) will collect and store data and
parameters including trends, alarms and events from DCS database periodically and
automatically to removable DVD / optical disk data storage devices, once every 24
hours for long term storage and retrieval.
6.3.5 Performance Calculation
Plant Performance Calculations will be done by automatically retrieving data from
plant data highways. Facility to display all data related to Performance Calculations
will be provided on Operator Interface Units (OIU)
6.3.6 Sequence of Event Recorder (SER)
Sequence of events recording system (SER) of 1 milli sec resolution with adequate
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 47
redundancy features will be provided as an integral part of DCS to log trips, cause of
trips and other important faults to diagnose the cause of plant trip.
6.3.7 Alarm Annunciation System
The alarm systems will contain all alarms for a safe and reliable operation of the
plant. The alarm system will cover all pre trip and trip alarms related to unit and to
auxiliaries. The alarms will be displayed on DCS Operator Interface Unit and will be
printed on alarm printer chronologically.
6.3.8 Electrical Systems Operation and Monitoring:
Suitable hardwired / software communication interface will be provided between
Plant electrical control, protection and synchronizing systems and DCS.
Monitoring, Operation and Control of new 132 kV bays of the proposed 20MW unit
will be carried out by the new 132 kV bay control units as well as by the existing
DCS. For that, required modification shall need to be done in the new Control Room.
6.3.9 System Programming and Documentation
The engineering workstation will be an integrated system providing facilities for the full
application engineering of the control and automation system including the operator
interface. This includes all the functional software and hardware engineering, as well as
all field component configuration and connection, cabling and termination engineering,
and VDU display and report configuration.
6.4.1 Steam Generator (SG) Control System:
The Steam Generator control system will include the following major functional blocks:
• Burner Management System with Flame Scanning System.
• Furnace Bed Temperature Control
• Furnace Bed Level Control
• Steam Temperature Control
• Drum Level Control
• Auxiliary pressure reducing and desuperheating station (APRDS) Control
System.
• Coal Feeder Control System
• Steam Generator Auxiliaries Controls
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 48
• Soot blower Control System (if envisaged)
The Steam Generator control and protection system is configured in the Plant DCS.
6.4.2 Steam Turbine Generator (STG) Control System
The STG control system will typically include the following functional groups:
• Electro hydraulic Governing Control System (EHGC)
• Turbine Protection System (TPS)
• Turbo-supervisory Instrumentation (TSI)
• Turbine Bypass Control System
• STG Auxiliaries Control System
The Steam Turbine Generator control & protection system is configured in the Plant
DCS.
6.5 Alternative Philosophy
Alternatively, if proprietary SG & STG control system by manufacturer is provided, it will
be complete with all the functional blocks described above with operating interface
arrangement. The control system will have redundant software link with the Plant DCS
and some of the critical signals for protection of the SG and STG will be hardwired to
the plant DCS.
6.6 DCS based Balance of Plant off site control system:
The control, interlock, protection and start / stop operation for all the BOP packages
will be realized in the Plant DCS. Local and Remote DCS Operator Work Stations
will be provided for both local and remote monitoring and operation.
6.7 Stand Alone Balance of Plant off site control systems
Compressed Air System, Air conditioning and Ventilation System, Fire Detection
System, Chemical Dosing System etc. will be carried out from their stand alone
control system like PLC / Relay based Local Control Systems.
6.8 Turbine Supervisory Instrumentation system
Turbine Supervisory Instrumentation (TSI) will be complete with all Vibration
Sensors, Amplifiers, Special Cables and monitors with all necessary equipment and
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 49
accessories.
TSI parameters will be connected by hardwired link to DCS for centralized
monitoring.
6.9 Vibration Monitoring Systems for HT Drives
Vibration Monitoring Systems complete with Sensors, Amplifiers, Special Cables and
monitors with all necessary equipment and accessories will be provide for the HT
Drive equipment like CW Pumps etc. The Vibration Monitoring parameters will be
hardwired to Plant DCS for centralized monitoring.
6.10 SCADA
A separate SCADA shall be envisaged for control & monitoring of intake submersible
pumps. Soft-link shall be provided between Plant DCS & SCADA for monitoring the
same from Plant DCS.
6.11 Control Panel / Control Desk
Control Panel
A freestanding unit control panel will include Measuring Instruments, Annunciation
windows, Recorders, Push Button stations, Emergency consoles for Boiler and STG
etc.
Power house building shall be extended and new Central Equipment Room (CER)
shall be created in the extended power house building. All required I&C and
electrical panels shall be placed in the new Central Equipment Room
Control Desk
The Control Desk will house Operator Interface Units (OIUs), including Monitor,
Keyboard, Mouse and the Emergency pushbuttons for Tripping of Boiler, Steam
Turbine. The Control Desk will also house Telephone Hand set for communications.
Power house building shall be extended and new Central Control Room (CCR) shall
be created in the extended power house building and all required Control Desks &
HMI’s shall be placed in the new Central Control Room. Fire alarm panel and panel
for public address system shall also be located in the new Central Control Room.
The existing public address system and EPABX system can be upgraded and
extended up-to unit-2. However being an old system availability of spares in future
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 50
may be an issue and to be addressed by the supplier. Or a new public address
system and EPABX system shall be installed for the new unit and same can be
extended to unit-1 for exchange of information avoiding physical interaction between
two systems.
6.12 Control Room Equipments
The new central control room will be sized to accommodate additional staff and
observers for commissioning, testing, start-up and emergency situations.
The new control room will house the following various equipments as a minimum:
• Control Panels, Control Desk (UCD), Work-station with all required accessories
and printers in the new Central Control room.
• DCS system cabinets and electrical relay cabinets and other systems panels (as
required) in the new Control Equipment room
• Shift charge Engineer’s monitor with keyboard/ mouse and printer in new Shift
Charge Engineer’s room.
• Engineering Work Station with keyboard / mouse along with the Color Graphic
printer in new System Maintenance Engineer room.
Public Address System panels, Fire alarm system panels etc will be suitably housed
in new Central Control room.
6.13 Measuring Instruments
Microprocessor based reliable HART compatible Smart Transmitters with adequate
redundancy, the Pressure/ Differential pressure/ Temperature/ Flow switches,
Thermocouples and RTDs will be used as primary Instruments for measurement of
various process parameters.
Local Gauges like Pressure, Temperature and Level Gauges will be provided for
local indication of the process. Process Switches will be provided for alarm
monitoring and protection and interlock purposes. Various flow sensors like Orifice
plates, flow nozzles, etc. will be used for measurement of flow.
Flue Gas oxygen measurement will be carried out by in-situ Zirconium Oxide Type
Sensor.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 51
6.14 Steam and Water Analysis System (SWAS)
A centralized comprehensive Steam and Water Analysis System (SWAS) for each
unit will be provided for continuous on line monitoring of water and steam purity in
the plant cycle. Measurements of Conductivity, pH, Hydrazine, Dissolved Oxygen
and Silica will be provided.
The SWAS room will be suitably located in the Main Plant Building.
Analyzer output signals from the SWAS Panel will be hardwired to the Plant DCS for
centralized monitoring.
6.15 Stack Emission Monitoring System
Continuous Emissions Monitoring System (CEMS) for monitoring of Flue gas
Emissions from the Stacks of the Plant will be provided, which will consist of the
following analyser Instruments:
• Oxides of Nitrogen NOx
• Sulphur Dioxide SO2,
• Carbon Monoxide CO
• Stack Opacity Monitor.
The emission parameters will be hardwired to Plant DCS for centralized monitoring.
6.16 Ambient Air Quality Monitoring System
Analytical Instruments for Ambient Air Quality Monitoring will also be provided to
check upon the ambient air quality around the Power Plant as per MOEF / Pollution
Control Board guide lines.
6.17 Uninterruptible Power Supply (UPS) and Distribution
Uninterrupted power supply (UPS) system in which 2 UPS operate in sharing mode
will be provided to cater to single phase, 230 / 120 V AC 50 Hz, 2 wire power supply
requirements of instrumentation and control systems viz. DCS Cabinets, man-
machine interface equipment, analysers, instruments mounted on the unit control
panel and other independent systems. Other voltages required will be derived from
the UPS source. The UPS system will be housed in a separate room suitably located
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 52
in the Main Plant Building.
6.18 Final Control Elements
Final control elements will be provided with electro - pneumatic positioners,
electronic position transmitter of 4-20 mA output, air lock relay, air filter regulator,
hand wheel, limit switches, solenoid valves and other accessories in accordance
with the system requirements.
All IGV shall have operating wheel for local operation and locking arrangements for
online maintenance.
6.19 Instrumentation & Special cables
Individual pair shielded and overall shielded twisted pair colour coded copper cables
will be used for analog signals and overall shielded cables would be used for digital
signals. All these cables will be FRLS and unarmoured. The conductor size of the
field cables from field instrument to Junction Box will be of 1.5 mm2 and that for
Multipair / Multicore cables from Junction Box to the Control Room will be of 0.5
mm2.
6.20 Maintenance and Calibration Instruments
One set of Maintenance and Calibration Equipment for instrumentation and control
system will be provided. This would consist of calibration equipment such as hand-
held calibrator for smart transmitters, electronic test bench, pneumatic test benches,
dead weight tester, manometers, air sets, RCL Bridge, digital channel simulator,
logic probe, testing meters / devices / calibrators for at site testing and calibration,
etc.
6.21 Erection Hardware
All required installation hardware including impulse pipes, tubes, valves, manifolds,
fittings, cable trays, holders, angles and conduits etc. required for proper installation
and interconnection of instrumentation and control system will be provided.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 53
SECTION – 7
CIVIL WORKS
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 54
7. CIVIL WORKS
This Civil work for plant will cover design and construction of all civil, structural and
architectural works including site development/formation, foundation & super-
structure required for all equipments, buildings & structures, all necessary
infrastructural works required and associated works that are necessary for the
construction, operation and maintenance of the Power Plant.
The civil work broadly includes site grading , all excavation, back filling, piling work,
concrete work (plain and reinforced), structural steel work, water proofing, roads,
drainage, paving, sanitary, plumbing, all architectural and finishing work as required
for the Project.
7.1 Land Development
The land is fairly flat, sparsely vegetated with trees / small shrubs. However,
depending upon the topographical survey, the reduced levels / elevation of various
finished ground level, finished floor levels, will be finalized. A thorough study of
terrain elevation will be made. The roads / storm water / sewage system will be
planned by taking care of all relevant data. The systems thus planned will not be
having any maintenance problems later. In case of minor cutting / excavations /
filling is required, the same would be carried out to arrive a levelled surface. The
major cutting and filling shall be carried out in the extended portion of coal stock pile
area, cooling tower area. Rest of the proposed area shall also be cut and filled as
required to maintain the desired finished grade level.
7.2 Geo-technical Investigations
The power plant area is basically an agricultural land, nearby to open cast coal mine.
The sub-soil at site is basically a residual soil formed due to physical and chemical
disintegration of parent rock ie., argillaceous and carbonaceous shale. The average
depth of residual soil including the top graded soil is about 3.23m. The soil cover is
underlain by completely weathered and highly weathered rock formation for a total
thickness of about 3.0 m. Detailed Soil Investigation will be carried out before
commencement of engineering design. Adequate numbers of borehole test shall be
carried out at every individual location for heavy static equipment foundation (e.g.-
ESP, Boiler foundation etc), vibrating equipment (e.g.-TG foundation, crusher
foundation etc) and major structures & buildings such as chimney, ash silos, cooling
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 55
structures, TG building, Crusher house etc. As the proposed site was initially
undulated with numbers of major ups and downs and it is subsequently filled up with
soil, special care shall be taken in design of foundation for heavy equipment and
major structures, specially located in filled up soil to maintain the serviceability as
well as safety of foundations & structures.
As the adjoining area being surrounded by open cast coal mines, the aspect of
vibration arising from blasting disturbance from mines is to be considered.
7.3 Topographical Survey
The topographical survey will be conducted and the general information on land
terrain will be ascertained to plan necessary infrastructure facilities.
7.4 Plant Layout
The plot plan obtained from DPR (LII-4236-000-T-001, R0) dated August 2007 has
been modified and necessary changes have been incorporated in the revised one
(DRG NO:- LII-KEOE-12022-00110-001-WCC & LII-KEOE-12022-00110-001-ACC,
Rev-A). Necessary modifications have been made in coal stock pile area, ash
storage area, raw water reservoir area & BTG area. A pump house for unit-II is also
added in raw water reservoir.
The land for the plant is already acquired.
The layout indicates the area for proposed unit and other additional facilities.
All plant roads, culverts and rain water drainage shall be provided as depicted in
DPR. In addition to the above, an approach road to coal yard needs to be provided.
7.5 Water Intake
The raw water intake facility by providing bore holes in the river bank has been
already located. The same facility shall be augmented for phase-II. The water pipe
lines will be suitably supported on concrete / steel supports on its route to the plant.
Wherever cross over bridges are required, the same will be planned by meeting
statutory requirements.
Flow diagram (dwg. no. LII-KEOE12022-40121-001, Rev-A) has been modified
showing the necessary augmentation required for phase-II.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 56
7.6 Plant Buildings
a) Main Plant Building
Main Plant Building in the Power Block area is proposed to be a continuation of
the present building. This proposed building will comprise of Main Power House
Building (turbo-generator bay, and Electrical bay / SG Feed Pump, Heater and
Deaerator bay, Central control room, Control equipment room etc.). The building
would be a non-basement structure. The Steam Turbine Generator and auxiliary
equipment will be located in the A-B bay of the building having 17 metres span
and is accommodated in a length of 45 metres, which includes one unloading /
maintenance bay. The heaters are accommodated in the B-C bay (heater bay)
having a span of 10.5 metres.
The turbine - generator bay would have three floors - ground floor at 0.00 M
level, mezzanine floor and operating floor. Localised O & M platforms at required
levels would be provided. The desecrator would be located at roof level in the B-
C bay (heater bay). Road and rail access will be provided to the unloading and
maintenance bays for unloading TG components and auxiliary equipment.
The General Arrangement of the Main Plant Building and the sectional view is
indicated in Drawing No. LII-4236-203-W-102 RA and LII-4236-203-W-101 R-A in
DPR (2007).
The building will be of RCC column-framed structures with steel roof beam but
with RCC roof slabs. Brick wall up to 3.0 metres above operating floor level and
side cladding with insulated metal sheet above this level has been considered.
Intermediate steel columns and brick wall at gable end of existing power house
will be removed. Existing EOT cranes (40T/5T) with main and auxiliary hooks of
specified capacity will be used in the new TG bay for erection and maintenance
work of the equipment. The roof of TG bay will be provided with permanent metal
decking sheet of minimum 0.8 mm thickness with zinc phosphate coating and
primer on both sides to act as a permanent shuttering for cast-in-situ RCC slab.
In all other areas roof and floor will be provided with cast-in-situ RCC slab. All
floors of turbine hall (except operating floor and control rooms) will be provided
with non-metallic hardener topping. Operating floor will be provided with IPS floor
finish with floor hardener.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 57
b) SG Foundations / ESP Foundations
One no. SG and one no.. ESP’s and one no. boiler will be located on the back
side of electrical building. The boilers will have intermediate connecting corridors
between the boilers and control / Electrical building.
c) Auxiliary Buildings
Auxiliary buildings include compressor house, ESP Control room building, Air
washer room, AHP Compressor building, Fuel Oil Pump House, Switchgear &
Control building etc. which will be constructed as specified. Any other building
not mentioned above but required as per system will be provided.
7.7 Paving and Plinth Protection
Paving/plinth protection works around building and in main plat area will be
considered as delineated in DPR.
7.8 Foundations
Foundation for all equipments, tanks, structures and buildings will be considered as
depicted in DPR.
7.9 Transformer area
Civil works in transformer area will be carried out as mentioned in the DPR.
7.10 Switchyard area
Civil works in switchyard area will be done as described in the DPR.
7.11 Chimney
Civil works for RCC chimney will be carried out as mentioned in the DPR.
7.12 Raw Water Reservoir
The existing raw water reservoir will be common for both the units. A partition dam is
being constructed in the middle of this reservoir to make two separate chambers. A
common chamber with RCC wall is being constructed surrounding the existing pump
house. This common chamber will be connected to both the reservoirs by means of
sluice gates. A new pump house for phase-II can be constructed beside the existing
one within the common chamber.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 58
7.13 Miscellaneous Buildings
Table below indicates list of major buildings / structures planned in the power plant
and type construction:
Table
Misc. Plant Buildings / Structures
SL No Building /Structure Remarks/Type of
Construction
1 ESP Control Room Ground plus one floor; RCC
construction with brick wall.
Roof will be of RCC slab.
2 Air washer room Structural steel column
construction with brick wall.
Roof will be of RCC slab.
3 Ash water and ash slurry pump
house
Structural steel construction
with RCC roof and brick wall
4 CW pump house RCC construction with brick
wall and precoated galvalume
sheet for roof
7.14 Shale, Devolatised Coal (Jhama) & Washery Reject Handling System
The shale, devolatised coal (Jhama) & washery reject handling plant will have the
following structures:
a. Conveyor tunnel and grizzly hopper.
b. Transfer tower foundations.
c. Conveyor trestle foundations.
d. Primary crusher with screen is proposed in RCC structure.
e. Secondary crusher with screen is proposed in RCC structure.
f. Open shale, Devolatised coal (Jhama) & washery reject storage yard and one
separate coal shed for shale
g. Dust extraction system foundation.
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 59
h. Approach road to coal yard
• Transfer Points
Transfer points will be provided at every change of direction of the conveyors.
Approx. four nos. transfer points are required as per present plant lay-out.
Transfer points will have structural steel frameworks with RCC roof and floors.
Cladding will be of sheet metal.
• Conveyor Galleries
Overhead conveyor galleries will be of structural steel frame with metal sheet
roofing and cladding. Walkways are to be provided at the sides of and between
conveyors. The galleries will be supported on steel trestles which will have RCC
foundations.
• Primary Crusher House
Separate buildings will be provided for housing the primary crushers. This
building will be of structural steel framework with RCC flooring and metal
cladding. The crushers will utilize a vibration isolation system with spring
assembly and visco dampers.
• Secondary Crusher House
Separate buildings will be provided for housing the Secondary crushers. This
building will be of structural steel framework with RCC flooring and metal
cladding. The crushers will utilize a vibration isolation system with spring
assembly and visco dampers.
• Fuel Storage Area
The existing fuel storage area is common for both units.
Crusher structure will be RCC framed structure. Its geometry will be decided to suit
vendor’s GA drawings. The crusher house will be provided with 1.2 m high brick
masonry parapet wall at all floors and above it 1 m portion will be open. The
remaining portion below the upper floor and opening will be provided with louvered
type GI sheeting.
The size of covered shed for shale will be provided as per design requirement.
Covered shed for such coal storage will have roof trusses supported on RCC
columns. Top sheeting will be of GI sheet. Side sheeting of 1.0 m height from eaves
Study Report
CPL Sarishatali 20 MW
Extension Project, Phase-II
CPL
LII-KEOE12022-00101-001 Rev-A Page 60
level shall be provided if necessary. The ground floor will be provided with
compacted soil and interlocking bricks / concrete blocks as flooring.
7.15 Ash Handling System
Two RCC ash silos (one for bed ash and one for fly ash) required for ash handling
system. RCC Ash silos and pipe racks will be provided for fly ash handling system.
Pipe trenches as required will be provided in compressor house.
Ash conveying pipe and a RCC silo will be provided for bed ash and Fly ash
handling system. Both fly ash and bed ash from silos will be unloaded in trucks and
with soil cover and sprinkler system.
7.16 Pipe & Cable rack & trenches
Civil & structural works for all pipe and cable racks & trenches in plant area will be
carried out as mentioned in the DPR.
7.17 Sewerage system
Civil works for sewerage system in all over plant will be carried out as delineated in
the DPR.
7.18 Cooling Tower
Civil works for cooling tower will be carried out as mentioned in the DPR.
Alternately, Air Cooled Condenser foundation and auxiliary cooling tower 1x20 MW
structure will be provided in case Air Cooled Condensing system is used.
7.19 Landscaping
Landscaping works in all over plant area will be carried out as described in the
DPR.
7.20 Ash Utilization
The ash generated in the station will be primarily used for sale in cement plants and
brickfields in the locality. Provision will be kept for balance, if any for mine filling (at
Sarishatali) through HCSD system. Complete utilization of ash may thus be
assured. No storage area of ash is therefore envisaged inside the plant.