construction documents structura- …. indicate welds by standard aws symbols, distinguishing...

71
OREGON STATE UNIVERSITY GOSS STADIUM – RIGHT FIELD BALCONY AND OMAHA ROOM RENOVATION CORVALIS, OREGON CONSTRUCTION DOCUMENTS STRUCTURA- STEE- P NTL HBrojec Nrt . 68. 7 570355 1 0 0323323508 / P NTL CrB©rBpcari 3508 SECTION 05 1200 STRUCTURAL STEEL PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Structural steel. 2. Grout. B. Related Sections include the following: 1. Section 01 4000 "Quality Requirements" for independent testing agency procedures and administrative requirements. 2. Section 05 3100 "Steel Decking" for field installation of shear connectors. 3. Section 05 5000 "Metal Fabrications" for miscellaneous steel fabrications not defined as structural steel. 4. Section 05 1213 “Architecturally Exposed Structural Steel” for architecturally exposed structural steel. 5. Section 05 5100 “Metal Stairs”. 6. [Section 09 9113 “Exterior Painting” and Section 09 9123 “Interior Painting”] [and] [Section 09 9600 "High-Performance Coatings"] for surface preparation and priming requirements. 7. Section 133419 "Metal Building Systems" for structural steel. 1.3 DEFINITIONS A. Structural Steel: Elements of structural-steel frame, as classified by AISC's "Code of Standard Practice for Steel Buildings and Bridges," that support design loads. B. Demand Critical Welds: Those welds, the failure of which would result in significant degradation of the strength and stiffness of the seismic load resisting system. 1. For moment frames, complete joint penetration welds in beam-to-column connections, including flange, web and shear plates. 2. For moment frames, complete joint penetration welds of column splices and of columns- to-base plates. 3. Other welds indicated as “Demand Critical” on the drawings. C. Protected Zone: Area of SLRS members defined in the drawings in which limitations apply to fabrication and attachments. Such limitations include:

Upload: donguyet

Post on 29-May-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

OREGON STATE UNIVERSITYGOSS STADIUM – RIGHT FIELD BALCONY AND OMAHA ROOM RENOVATION

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS STRUCTURA- STEE-P NTL HBrojec Nrt . 68. 7 570355 1 00323323508 / P NTL CrB©rBpcari 3508

SECTION 05 1200

STRUCTURAL STEEL

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes the following:

1. Structural steel.2. Grout.

B. Related Sections include the following:

1. Section 01 4000 "Quality Requirements" for independent testing agency procedures and administrative requirements.

2. Section 05 3100 "Steel Decking" for field installation of shear connectors.3. Section 05 5000 "Metal Fabrications" for miscellaneous steel fabrications not defined as

structural steel.4. Section 05 1213 “Architecturally Exposed Structural Steel” for architecturally exposed

structural steel.5. Section 05 5100 “Metal Stairs”.6. [Section 09 9113 “Exterior Painting” and Section 09 9123 “Interior Painting”] [and]

[Section 09 9600 "High-Performance Coatings"] for surface preparation and priming requirements.

7. Section 133419 "Metal Building Systems" for structural steel.

1.3 DEFINITIONS

A. Structural Steel: Elements of structural-steel frame, as classified by AISC's "Code of Standard Practice for Steel Buildings and Bridges," that support design loads.

B. Demand Critical Welds: Those welds, the failure of which would result in significant degradation of the strength and stiffness of the seismic load resisting system.

1. For moment frames, complete joint penetration welds in beam-to-column connections, including flange, web and shear plates.

2. For moment frames, complete joint penetration welds of column splices and of columns-to-base plates.

3. Other welds indicated as “Demand Critical” on the drawings.

C. Protected Zone: Area of SLRS members defined in the drawings in which limitations apply to fabrication and attachments. Such limitations include:

OREGON STATE UNIVERSITYGOSS STADIUM – RIGHT FIELD BALCONY AND OMAHA ROOM RENOVATION

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS STRUCTURA- STEE-P NTL HBrojec Nrt . 68. 7 570355 1 30323323508 / P NTL CrB©rBpcari 3508

1. Welded shear studs and decking attachments that penetrate the beam flange shall not be placed on beam flanges within the protected zone. Decking are spot welds are required to secure decking shall be permitted.

2. Within the protected zone, discontinuities created by fabrication or erection aids, air-arc gouging and thermal cutting shall be repaired as required by the engineer of record.

3. Welded, bolted, screwed or shot-in attachments for perimeter edge angles, exterior facades, partitions, duct work, piping or other construction shall not be placed within the protected zone.

D. Exposed Structural Steel: Members and connections exposed to view as indicated in the Contract Documents, or in this Specification.

E. Seismic Load Resisting System (SLRS): Assembly of structural elements in the building that resists seismic loads.

1.4 SUBMITTALS

A. Product Data: For each type of product indicated.

B. Shop Drawings: Show fabrication of structural-steel components.

1. Structural steel shop drawings shall contain sufficient detail and information to allow complete fabrication and erection of the structure without reference to the contract drawings either on the fabrication shop floor or at the project site. The steel detailer shall generate all shop drawing fabrication and installation details from the structural and architectural drawings and specifications. The use of reproductions or photocopies of the contract drawings shall not be permitted. When CAD or REVIT files are provided, it is the responsibility of the detailers to remove all information not directly relevant to the creation of the placing drawings as well as all references to the outside sources of the files.

a. Include details of cuts, connections, splices, camber, holes, and other pertinent data.

b. Include embedment drawings.c. Indicate welds by standard AWS symbols, distinguishing between shop and field

welds, and show size, length, and type of each weld.d. Indicate type, size, and length of bolts, distinguishing between shop and field bolts.

Identify pretensioned and slip-critical high-strength bolted connections.e. Additional seismic submittal requirements:

1) Identify members and connections that are part of the SLRS as indicated in the construction documents.

2) Locations of demand critical welds.3) Locations and dimensions of protected zones.4) Locations of slip critical bolts.5) Access hole dimensions, surface profile and finish requirements.6) Locations where backing bars and weld tabs are to be removed.7) Locations where supplemental fillet welds are required when backing is

permitted to remain.8) Connection assembly sequence where special precautions are required.9) Non-Destructive Testing (NDT) to be performed where required.

2. Shop drawing re-submittals shall clearly identify all revisions to previous submittals.

a. Heavy ink, clouded outlines (revision clouds) shall be drawn around revised areas of individual sheets.

OREGON STATE UNIVERSITYGOSS STADIUM – RIGHT FIELD BALCONY AND OMAHA ROOM RENOVATION

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS STRUCTURA- STEE-P NTL HBrojec Nrt . 68. 7 570355 1 n0323323508 / P NTL CrB©rBpcari 3508

b. Engineer/Architect will not review information outside of revision clouds on resubmitted drawings.

C. Welding Certificates.

D. Paint Compatibility Certificates: From manufacturers of topcoats applied over shop primers, certifying that shop primers are compatible with topcoats.

E. Qualification Data: For firms and persons specified in “Quality Assurance” Articles to demonstrate their capabilities and experience. Include lists of completed projects with project names and addresses, names and addresses of architects and owners, and other information specified.

F. Mill test reports for structural steel, including chemical and physical properties.

G. Product Test Reports: Signed by manufacturers certifying that the following products comply with requirements:

1. Bolts, nuts, and washers including mechanical properties and chemical analysis.2. Shear stud connectors.3. Shop primers.4. Nonshrink grout.

H. Source quality-control test reports.

I. Certified Manufacturer’s Test Reports

1. Charpy V-notch toughness as specified in part 2 of this Section for the following:a. Members and connections part of the SLRS.b. Demand Critical Welds.

J. Written Welding Procedure Specifications (WPSs): In accordance with AWS D1.1 requirements for each welded joint proposed for use whether prequalified or by testing. Include all welding that will be performed during fabrication (shop) and installation/erection (field) Include the following items as applicable for the welding process:

1. Indicate as-detailed configuration, and the maximum and minimum fit-up configurations.2. Identify specific electrode and manufacturer.3. List actual values of welding parameters to be used so clear instruction is provided to

welders.4. Steel specification(s) and grade(s) to be welded.5. Thickness range of materials to be joined.6. Type of joint.7. Type of weld.8. Size of weld.9. Position of welding.10. Flux and shielding gas.11. Electrode diameter.12. Voltage (except SMAW).13. Current (amperage) or wire feed speed.14. Travel speed.15. Minimum Preheat and Interpass Temperatures: Provide minimum preheat and interpass

temperature for all welds, including tack welds, in accordance with AWS D1.1, Table 3.2. The Contractor may specify higher minimum temperatures as a part of the WPS. Preheat and interpass temperatures lower than those required by AWS D1.1, Table 3.2,

OREGON STATE UNIVERSITYGOSS STADIUM – RIGHT FIELD BALCONY AND OMAHA ROOM RENOVATION

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS STRUCTURA- STEE-P NTL HBrojec Nrt . 68. 7 570355 1 40323323508 / P NTL CrB©rBpcari 3508

are permitted provided the WPS has been qualified by testing. Minimum preheat and interpass temperatures shall be verified at a distance of 3 inches from the joint or for materials over 3 inches in thickness at a distance equal to the thickness of the part.

16. Maximum Preheat and Interpass Temperatures: The maximum preheat and interpass temperature permitted is 550 degrees F, measured at a distance of 1 inch from the joint. This maximum temperature may not be increased with or without qualification testing.

17. Number and placement of passes.18. Technique (stringer or weave bead).19. Shielding gas flow rate.20. Charpy V-notch toughness as required by this specification.21. Other pertinent information specific to the weld.

K. Procedure Qualification Record (PQR): In accordance with AWS D1.1 for all procedures qualified by testing. For welds part of the SLRS qualification testing shall include Charpy V-notch (CVN) testing in accordance with AWS D1.8 and AISC 341-05 Appendix X. The notch specimen shall be located in the weld. If two different filler metals are used, including all tack welds and repairs, then additional CVN specimens shall be taken at the boundary of the two filler metals. Qualify all welds for the maximum heat input to be used on the project.

L. Manufacturer’s Certifications: For all welding electrodes, fluxes, and shielding gasses to be used. Certifications shall satisfy the applicable AWS A5 requirements.

M. Test Reports: Copies of reports of tests conducted on shop and field bolted and welded connections. Include data on type(s) of tests conducted and test results.

N. Surveys: Submit certified copies of each survey conducted by a registered land surveyor, showing elevations and locations of base plates and anchor bolts to receive structural steel, and final elevations and locations for major members. Indicate discrepancies between actual installation and contract documents.

O. Quality Assurance Agency Documents: The Agency responsible for quality assurance for members part of the SLRS shall submit QA documents as outlined in AISC 341-05 (seismic provisions) Appendix Q (Q4).

P. Maintain one copy of each document on-site.

1.5 QUALITY ASSURANCE

A. Installer Qualifications: The installer shall have at least five years experience in this size and type of structure.

B. Fabricator Qualifications: A qualified fabricator who participates in the AISC Quality Certification Program and is designated an AISC-Certified Plant, Category [STD] (standard for building structures).

1. Fabricator shall be registered with and approved by authorities having jurisdiction.

C. Welding Standards: Comply with applicable provisions and qualify procedures and personnel according to AWS D1.1, “Structural Welding Code-Steel”, and ASW D1.8, “Structural Welding Code – Seismic Supplement” for members part of the SLRS.

1. Present evidence that each welder has satisfactorily passed AWS qualification tests for welding processes involved and, if pertinent, has undergone recertification.

OREGON STATE UNIVERSITYGOSS STADIUM – RIGHT FIELD BALCONY AND OMAHA ROOM RENOVATION

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS STRUCTURA- STEE-P NTL HBrojec Nrt . 68. 7 570355 1 70323323508 / P NTL CrB©rBpcari 3508

2. Qualifications for Welding Work: Qualify welding personnel in accordance with AWS D1.1, "Qualification," (or approved equal).

a. Qualify welders in accordance with AWS D1.1 for each process, position, and joint configuration.

b. Welders who have not used the welding process for a period of 6 or more months shall be recertified.

c. If recertification of welders is required, retesting will be the Contractor's responsibility.

d. WPSs for each joint type shall indicate proper AWS qualification and be available where welding is performed.

e. Each welder performing demand critical welds shall be qualified by testing in accordance with AWS D1.8 Part 5.

f. Welders whose work fails to pass inspection shall be requalified before performing further welding.

D. Welding Inspectors doing work associated with the SLRS:

1. QC welding inspection personnel shall be Associate Welding Inspectors (AWI) or higher, as defined in AWS B5.1 “Standard for Qualification of Welding Inspectors”, or otherwise qualified under the provisions of AWS D1.1 Section 6.1.4 and to the satisfaction of the contractor’s QC plan by the fabricator/erector.

2. QA welding inspectors shall be welding inspectors (WI), or senior welding inspectors (SWI), as defined in AWS B5.1, except AWI’s may be used under the direct supervision of WI’s, on site and available when weld inspection is being conducted.

3. Non-destructive Testing Technicians: NDT technicians shall be qualified as follows:

a. In accordance with their employer’s written practice which shall meet or exceed the criteria of the American Society of Non-destructive Testing, Inc. SNT TC-1A “Recommended Practice for the Training and Testing of Non-destructive Personnel”, or of ANSI/ASNT CP-189, “Standard for the Qualification and Certification of Non-destructive Testing Personnel.”

b. Ultrasonic testing for QA may be performed only by UT technicians certified as ASNT Level III through examination by the ASNT, or certified as Level II by their employer for flaw detection. If the engineer of record approves the use of flaw sizing techniques, UT technicians shall also be qualified and certified by their employer for flaw sizing.

E. Comply with applicable provisions of the following specifications and documents:

1. AISC 303 "Code of Standard Practice for Steel Buildings and Bridges" (with exceptions noted in Part 1 of this Section).

2. AISC 341 "Seismic Provisions for Structural Steel Buildings" including Supplement No. 1.3. AISC 360 "Specification for Structural Steel Buildings, 13th edition.4. RCSC's "Specification for Structural Joints Using ASTM A 325 or A 490 Bolts."5. ASTM A 6 (ASTM A 6M) "Specification for General Requirements for Rolled Steel Plates,

Shapes, Sheet Piling, and Bars for Structural Use.”6. AISC 358-05, “Prequalified Connections for Special and Intermediate Steel Moment

Frames for Seismic Applications.”

F. Preinstallation Conference: Conduct conference at Project site to comply with requirements in Division 01 Section "Project Management and Coordination."

OREGON STATE UNIVERSITYGOSS STADIUM – RIGHT FIELD BALCONY AND OMAHA ROOM RENOVATION

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS STRUCTURA- STEE-P NTL HBrojec Nrt . 68. 7 570355 1 .0323323508 / P NTL CrB©rBpcari 3508

1.6 DELIVERY, STORAGE, AND HANDLING

A. Store materials to permit easy access for inspection and identification. Keep steel members off ground and spaced by using pallets, dunnage, or other supports and spacers. Protect steel members and packaged materials from erosion and deterioration.

1. Do not store materials on structure in a manner that might cause distortion, damage, or overload to members or supporting structures. Repair or replace damaged materials or structures as directed.

B. Store fasteners in a protected place in sealed containers with manufacturer's labels intact.

1. Fasteners may be repackaged provided Owner's testing and inspecting agency observes repackaging and seals containers.

2. Clean and relubricate bolts and nuts that become dry or rusty before use.3. Comply with manufacturers' written recommendations for cleaning and lubricating

ASTM F 1852 fasteners and for retesting fasteners after lubrication.

1.7 COORDINATION

A. Coordinate selection of shop primers with topcoats to be applied over them. Comply with paint and coating manufacturers' recommendations to ensure that shop primers and topcoats are compatible with one another.

B. Coordinate installation of anchorage items to be embedded in or attached to other construction without delaying the Work. Provide setting diagrams, sheet metal templates, instructions, and directions for installation.

1.8 EXCEPTIONS TO AISC CODE OF STANDARD PRACTICE FOR STEEL BUILDINGS AND BRIDGES

A. Add the following paragraph to Section 1.8.1 of the AISC Code of Standard Practice for Steel Buildings and Bridges:

“The Contractor shall have sole responsibility for site safety. The Fabricator and Erector shall review the Contract Documents and if the structure, as shown on those documents, is in conflict with the requirements of any safety regulations, the Fabricator shall notify the Structural Engineer of Record prior to commencing shop drawing production. If the Fabricator and/or Erector fail to notify the Structural Engineer of Record, as stated above, they shall become responsible for all costs for correcting such conflicts with the requirements of any and all safety regulations.”

B. Add the following paragraph to Sections 7.5.1 AND Section 7.5.3 of the AISC Code of Standard Practice for Steel Buildings and Bridges:

“The Owner’s Designated Representative for Construction shall prepare the Embedment Drawing. The Embedment Drawing shall be submitted to the Structural Engineer of Record for information only. The Structural Engineer of Record shall not be responsible for the review and approval of the Embedment Drawing.”

C. Add the following paragraph to Section 7.10.3 of the AISC Code of Standard Practice for Steel Buildings and Bridges:

OREGON STATE UNIVERSITYGOSS STADIUM – RIGHT FIELD BALCONY AND OMAHA ROOM RENOVATION

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS STRUCTURA- STEE-P NTL HBrojec Nrt . 68. 7 570355 1 80323323508 / P NTL CrB©rBpcari 3508

“The Erector shall have the sole responsibility for determining the means and methods used to properly and adequately brace the framing during erection.”

D. Revise the second paragraph of Section 7.10.3 of the AISC Code of Standard Practice for Steel Buildings and Bridges as follows:

“The Erector need not consider loads during erection that result from the performance of work by, or the acts of, others, except as specifically identified by the Owner’s Designated Representatives for Design and Construction, nor those that are unpredictable, such as loads due to hurricane, tornado, earthquake, explosion or collision. The Erector shall determine, furnish and install temporary supports to resist earthquake loads specified by the 2012 International Building Code for new buildings.”

E. Revise Section 7.14 of the AISC Code of Standard Practice for Steel Buildings and Bridges as follows:

“The correction of minor misfits by moderate amounts of reaming or grinding, welding or cutting, and the drawing of elements into line with drift pins, shall be considered to be normal erection operations. Errors that cannot be corrected using the foregoing means, or that require major welding, cutting or changes in member or Connection configuration, shall be promptly reported to the Owner’s Designated Representatives for Design and Construction and the Fabricator by the Erector, to enable the responsible entity to either correct the error or approve the most efficient and economical method of correction to be used by others.”

Particular note shall be paid to the commentary for this section of the AISC Code of Standard Practice for Steel Buildings and Bridges, which reads as follows:

“As used in this Section, the term “moderate” refers to the amount of reaming, grinding, welding or cutting that must be done on the project as a whole, not the amount that is required at an individual location. It is not intended to address limitations on the amount of material that is removed by reaming at an individual bolt hole, for example, which is limited by the bolt-hole size and tolerance requirements in the AISC and RCSC Specifications.”

PART 2 - PRODUCTS

2.1 STRUCTURAL-STEEL MATERIALS

A. Structural Steel Shapes, and Bars: Refer to the General Structural Notes.

B. W-Shapes: Refer to the General Structural Notes.

C. Channels, Angles-Shapes: Refer to the General Structural Notes.

D. Plate and Bar: Refer to the General Structural Notes.

E. Corrosion-Resisting Structural Steel: ASTM A 588/A 588M, Grade 50 (345).

F. Cold-Formed Hollow Structural Sections: ASTM A 500, Grade B, structural tubing.

G. Welding Electrodes: Comply with AWS requirements.

1. Welding electrodes shall have a minimum tensile strength of 70 ksi using AWS A5 classification test.

OREGON STATE UNIVERSITYGOSS STADIUM – RIGHT FIELD BALCONY AND OMAHA ROOM RENOVATION

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS STRUCTURA- STEE-P NTL HBrojec Nrt . 68. 7 570355 1 60323323508 / P NTL CrB©rBpcari 3508

2. Welding filler metals, as supplied by the manufacturer, shall meet the requirements for H16 (16 mL diffusible hydrogen per 100 grams deposited weld metal) as tested using the mercury or gas chromatograph method as specified in AWS A4.3, "Standard Methods for Determination of Diffusible Hydrogen Content of Martensitic, Bainitic, and Ferritic Steel Weld Metal Produced by Arc Welding." The manufacturer’s Certificate of Conformance shall be considered adequate proof that the supplied electrodes meet this requirement, and no additional testing of filler metal samples or of production welds is required.

3. All low hydrogen electrodes shall be stored, handled, protected from atmospheric exposure and redried, if required, per AWS D1.1, 5.3.

4. FCAW electrodes shall be received in moisture-resistant packages that are undamaged. They shall be protected against contamination and injury during shipment and storage. Electrode packages shall remain effectively sealed against moisture until the electrode is required for use. When removed from the protective packaging and installed on machines, care shall be taken to protect the electrodes and coatings, if present, from deterioration or damage. Modification or lubrication of an electrode after manufacture for any reason is not permitted, except drying shall be permitted when recommended by the manufacturer.

5. Welds used in members and connections in the SLRS shall be made with a filler metal that can produce welds that have a minimum Charpy V-Notch (CVN) toughness of 20 ft-lbs at 0 degrees F, as determined by the appropriate AWS A5 classification test methods.

6. For welded joints defined as demand critical, welding filler metals shall provide the following minimum mechanical property requirements in the designated testing as described below:

a. Charpy V-Notch (CVN) Toughness: 20 ft-lb at -20 degrees F using AWS A5 classification test methods.

b. CVN Toughness: 40 ft-lb at 70 degrees F using AISC 341-05 (seismic provisions), Appendix X.

c. Yield Strength: 58 ksi minimum using the AWS A5 classification test.d. Elongation: 22 percent using the AWS A5 classification test

7. Electrodes for use with ASTM A588 base metal shall have strength, corrosion resistance and weathered appearance similar to that of the base metal.

2.2 BOLTS, CONNECTORS, AND ANCHORS

A. High-Strength Bolts, Nuts, and Washers: ASTM A 325 (ASTM A 325M), Type 1, heavy hex steel structural bolts; ASTM A 563 (ASTM A 563M) heavy hex carbon-steel nuts; and ASTM F 436 (ASTM F 436M) hardened carbon-steel washers.

1. Finish: Plain.

B. Shear Connectors: ASTM A 108, Grades 1015 through 1020, headed-stud type, cold-finished carbon steel; AWS D1.1, Type B.

C. Headed Anchor Rods: ASTM F 1554, Grade 36 straight.

1. Nuts: ASTM A 563 (ASTM A 563M) heavy hex carbon steel.2. Plate Washers: ASTM A 36/A 36M carbon steel.3. Washers: ASTM F 436 (ASTM F 436M) hardened carbon steel.4. Finish: Plain.

D. Threaded Rods: ASTM A 307, Grade A (ASTM F 568M, Property Class 4.6).

1. Nuts: ASTM A 563 (ASTM A 563M) heavy hex carbon steel.

OREGON STATE UNIVERSITYGOSS STADIUM – RIGHT FIELD BALCONY AND OMAHA ROOM RENOVATION

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS STRUCTURA- STEE-P NTL HBrojec Nrt . 68. 7 570355 1 90323323508 / P NTL CrB©rBpcari 3508

2. Washers: ASTM A 36/A 36M carbon steel.3. Finish: Plain.

2.3 PRIMER

A. Primer: Comply with [Section 099113 "Exterior Painting" and Section 099123 "Interior Painting."] [Section 099600 "High-Performance Coatings."] [Section 099113 "Exterior Painting," Section 099123 "Interior Painting," and Section 099600 "High-Performance Coatings."]

B. Primer: SSPC-Paint 25, Type [I] [II], zinc oxide, linseed oil, and alkyd.

C. Primer: SSPC-Paint 25 BCS, Type [I] [II], zinc oxide, linseed oil, and alkyd.

D. Primer: SSPC-Paint 23, latex primer.

E. Primer: Fabricator's standard lead- and chromate-free, nonasphaltic, rust-inhibiting primer complying with MPI #79 and compatible with topcoat.

F. Galvanizing Repair Paint: ASTM A 780.

2.4 GROUT

A. Nonmetallic, Non-Shrink Grout: ASTM C 1107, factory-packaged, nonmetallic aggregate grout, noncorrosive, nonstaining, mixed with water to consistency suitable for application and a 30-minute working time

2.5 FABRICATION

A. Structural Steel: Fabricate and assemble in shop to greatest extent possible. Fabricate according to AISC's "Code of Standard Practice for Steel Buildings and Bridges" (with exceptions noted in Part 1 of this Specification Section).

1. Camber structural-steel members where indicated.2. Fabricate beams with rolling camber up.3. Identify high-strength structural steel according to ASTM A 6/ A 6M and maintain

markings until structural steel has been erected.4. Mark and match-mark materials for field assembly.5. Complete structural-steel assemblies, including welding of units, before starting shop-

priming operations.6. Sandblast all exposed surfaces of weathering steel. Sandblasting shall be performed in

accordance with SSPC-SP6 “Commercial Blast Cleaning” SSPC’s Steel Structures Painting Manual. The appearance of the blast cleaned surface shall approximate Pictorial Standard Sa 2 of SSPC-VIS 1, “Pictorial Surface Preparation Standards for Painting Steel Surfaces” except no mill scale particles shall be allowed; only rust or mill scale stains down in the profile will be allowed. The use of acids to remove scale and stains in the field will not be permitted.

a. Exposed surfaces of steel contaminated with stains, oil, or foreign material after the above sand blasting cleaning process shall be promptly cleaned as directed by the Owner to preserve conditions for uniform weathering of steel.

OREGON STATE UNIVERSITYGOSS STADIUM – RIGHT FIELD BALCONY AND OMAHA ROOM RENOVATION

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS STRUCTURA- STEE-P NTL HBrojec Nrt . 68. 7 570355 1 050323323508 / P NTL CrB©rBpcari 3508

7. Store weathering steel in a location which will prevent uneven weathering. Store on blocking to prevent contact with ground.

B. Re-Entrant Corners: Provide ½-inch radius at all re-entrant corners, unless noted otherwise.

C. Thermal Cutting: Perform thermal cutting by machine to greatest extent possible.

1. Plane thermally cut edges to be welded to comply with requirements in AWS D1.1.

D. Bolt Holes: Cut, drill, or punch bolt holes perpendicular to metal surfaces.

E. Finishing: Accurately finish ends of columns and other members transmitting bearing loads.

F. Cleaning: Clean and prepare steel surfaces that are to remain unpainted according to SSPC-SP 3, "Power Tool Cleaning."

G. Shear Connectors: Prepare steel surfaces as recommended by manufacturer of shear connectors. Use automatic end welding of headed-stud shear connectors according to AWS D1.1 and manufacturer’s written instructions.

H. Holes: Provide holes required for securing other work to structural steel and for passage of other work through steel framing members.

1. Cut, drill, or punch holes perpendicular to steel surfaces. Do not enlarge holes by burning. Thermal cutting of holes is permitted with a surface roughness profile not exceeding 1,000 mico-inches as defined in ASME B46.1.

2. Base-Plate Holes: Cut, drill, mechanically thermal cut, or punch holes perpendicular to steel surfaces.

3. Weld threaded nuts to framing and other specialty items indicated to receive other work.

2.6 SHOP CONNECTIONS

A. High-Strength Bolts: Shop install high-strength bolts according to RCSC's "Specification for Structural Joints Using ASTM A 325 or A 490 Bolts" for type of bolt and type of joint specified.

B. Weld Connections: Comply with AWS D1.1 for welding procedure specifications, tolerances, appearance, and quality of welds and for methods used in correcting welding work. For connections part of the SLRS, comply with additional requirements of AWS D1.8 – seismic supplement.

1. For non-moment frame connections, remove backing bars or runoff tabs, back gouge, and grind steel smooth (for moment frames, reference Item 2 below).

2. For demand critical welds, comply with AWS D1.8 – seismic supplement including the following requirements:

a. Use electrodes specified for demand critical welds.b. At beam flange to column welds, remove bottom backing bars, back gouge, grind

smooth, and back weld with a 5/16 inch reinforcing fillet. c. Where top backing bars remain, a 5/16-inch fillet weld shall be placed between the

remaining fusible backing bar at the beam flange and the column. A reinforcing fillet shall not be placed between the backing bar and the underside of the beam flange.

d. Cut-off runoff plates (weld tabs) 1/8-inch from edges and grind smooth (not flush). The edges where weld tabs are removed shall be finished to a surface roughness

OREGON STATE UNIVERSITYGOSS STADIUM – RIGHT FIELD BALCONY AND OMAHA ROOM RENOVATION

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS STRUCTURA- STEE-P NTL HBrojec Nrt . 68. 7 570355 1 000323323508 / P NTL CrB©rBpcari 3508

of 500 micro-inches or better. The contour of the weld end shall provide a smooth transition to adjacent surfaces. Weld defects greater than 1/16 inch deep shall be excavated and repaired in compliance with an approved WPS.

e. All tack welds not incorporated into the final weld shall be removed.f. Bottom flange welding sequence: When using weld access holes to facilitate CJP

groove welds of beam bottom flanges to column flanges or continuity plates, the groove weld shall be sequenced as follows:

1) As far as practicable, starts and stops shall not be placed directly under the beam web.

2) Each layer shall be completed across the full width of the flange before beginning the next layer.

3) For each layer, the weld starts and stops shall be on the opposite side of the beam web, as compared to the previous layer.

3. For moment frame continuity plates, conform to AWS D1.8 – seismic supplement including the following requirements:

a. Steel backing used at continuity plate to column welds need not be removed. At column flanges, steel backing left in place shall be attached to the column flange using a continuous 5/16-inch fillet weld on the edge below the CJP groove weld. When backing is removed, the weld shall be backgouged and a 5/16-inch reinforcing fillet weld shall be provided to the column flange.

b. Weld tabs shall not be used for continuity plates at the weld ends adjacent to the column web/flange juncture. At these locations, weld layers shall be permitted to be transitioned at an angle of 0 to 45 measured from the vertical plane. The effective length of the weld shall be defined as that portion of the weld having full size. NDT is not required in this transition portion of the weld.

c. Where runoff tabs are used at the edge of the column flange, tabs shall be removed as specified for demand critical welds.

4. Assemble and weld built-up sections by methods that will maintain true alignment of axes without exceeding tolerances of AISC's "Code of Standard Practice for Steel Buildings and Bridges" for mill material.

5. Continuously seal joined members exposed to weather by continuous welds.6. Tack welds incorporated into the final weld and weld repairs of demand critical welds

shall be of the same quality as the final welds, including preheat requirements. The filler metals shall be identical, unless qualified by testing and meeting the requirements of Specification 051200, Part 1, "Submittals" article.

C. Erection Connections, etc: Place holes, plates, or other attachments required by the Erector so as not to interfere with or cause any other detrimental effect to structural members or their connections. Holes and attachments are not permitted in the “protected zone” as described in Section 1.3 and defined in the drawings.

D. Exposed Steel Shop Connections:

1. Grind exposed joints flush and smooth with adjacent finish surface. Make exposed joints butt tight, flush, and hairline. Ease exposed edges to small, uniform radius.

2. Continuously seal joined members by intermittent (stitch) welds and plastic filler.3. Verify that weld sizes, fabrication sequence, and equipment used will limit distortions to

allowable tolerances. Prevent weld show-through.4. Exposed mechanical fastenings: Flush countersunk screws or bolts; unobtrusively

located; consistent with design of component, except where noted otherwise.

OREGON STATE UNIVERSITYGOSS STADIUM – RIGHT FIELD BALCONY AND OMAHA ROOM RENOVATION

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS STRUCTURA- STEE-P NTL HBrojec Nrt . 68. 7 570355 1 030323323508 / P NTL CrB©rBpcari 3508

2.7 SHOP PRIMING

A. Shop prime steel surfaces except the following:

1. Surfaces to be field welded.

B. Surface Preparation: Clean surfaces to be painted. Remove loose rust and mill scale and spatter, slag, or flux deposits. Prepare surfaces according to the following specifications and standards:

1. SSPC-SP 3, "Power Tool Cleaning."

C. Exposed Steel Surface Preparation: Clean surfaces of exposed structural steel to the following specifications and standards:

1. SSPC-SP3, “Power Tool Cleaning”.

D. Priming: Immediately after surface preparation, apply primer according to manufacturer's written instructions and at rate recommended by SSPC to provide a dry film thickness of not less than 1.5 mils (0.038 mm). Use priming methods that result in full coverage of joints, corners, edges, and exposed surfaces.

1. Stripe paint corners, crevices, bolts, welds, and sharp edges.2. Apply two coats of shop paint to inaccessible surfaces after assembly or erection.

Change color of second coat to distinguish it from first.

E. Painting: Prepare steel and apply a 1-coat, nonasphaltic primer complying with SSPC-PS Guide 7.00, "Painting System Guide 7.00: Guide for Selecting One-Coat Shop Painting Systems," to provide a dry film thickness of not less than 1.5 mils (0.038 mm).

2.8 DIMENSIONAL TOLERANCES

A. Fabrication Tolerances: Unless otherwise noted, fabricate structural members to referenced AISC Specifications for allowable tolerances. Do not camber in excess of amounts shown on drawings.

2.9 SOURCE QUALITY CONTROL

A. Testing Agency: Owner will engage a qualified independent testing and inspection agency to inspect shop welds and high-strength bolted connections and tests, and to prepare test reports in accordance with “Testing and Inspection” Article 3.6.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify elevations of concrete- and masonry-bearing surfaces and locations of anchor rods, bearing plates, and other embedments, with steel erector present, for compliance with requirements.

OREGON STATE UNIVERSITYGOSS STADIUM – RIGHT FIELD BALCONY AND OMAHA ROOM RENOVATION

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS STRUCTURA- STEE-P NTL HBrojec Nrt . 68. 7 570355 1 0n0323323508 / P NTL CrB©rBpcari 3508

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Provide temporary shores, guys, braces, and other supports during erection to keep structural steel secure, plumb, and in alignment against temporary construction loads and loads equal in intensity to design loads. Remove temporary supports when permanent structural steel, connections, and bracing are in place, unless otherwise indicated.

1. Do not remove temporary shoring supporting composite deck construction until cast-in-place concrete has attained its design compressive strength.

3.3 ERECTION

A. Set structural steel accurately in locations and to elevations indicated and according to AISC 303 "Code of Standard Practice for Steel Buildings and Bridges" with exception noted in Part 1 of this Specification Section, and AISC 360 “Specification for Structural Steel Buildings”.

B. Base Plates: Clean concrete- and masonry-bearing surfaces of bond-reducing materials, and roughen surfaces prior to setting base plates. Clean bottom surface of base plates.

1. Set base plates for structural members on wedges, shims, or setting nuts as required.2. Weld plate washers to top of base plate.3. Snug-tighten anchor rods after supported members have been positioned and plumbed.

Do not remove wedges or shims but, if protruding, cut off flush with edge of base plate before packing with grout.

4. Promptly pack grout solidly between bearing surfaces and base plates so no voids remain. Neatly finish exposed surfaces; protect grout and allow to cure. Comply with manufacturer's written installation instructions for shrinkage-resistant grouts.

C. Align and adjust various members that form part of complete frame or structure before permanently fastening. Before assembly, clean bearing surfaces and other surfaces that will be in permanent contact with members. Perform necessary adjustments to compensate for discrepancies in elevations and alignment.

1. Level and plumb individual members of structure.2. Make allowances for difference between temperature at time of erection and mean

temperature when structure is completed and in service.

D. Splice members only where indicated.

E. Do not use thermal cutting during erection, unless it conforms to the requirements of AISC 360 Specification Sections M2.2 and M2.5.

F. Do not enlarge unfair holes in members by burning or using drift pins.

G. Reaming: Light drifting will be permitted to draw the parts together, but drifting to match unfair holes will not be permitted. Any enlargement of holes necessary to make connections in the field shall be done by reaming with twist drills, care being taken not to weaken the adjoining metal. If, in the judgement of the Engineer/Architect, the extent of the reaming is such that holes cannot be properly filled or accurately adjusted after reaming, the faulty member shall be discarded and replaced with a new one, and all costs and expenses resulting therefrom shall be paid by the Contractor.

OREGON STATE UNIVERSITYGOSS STADIUM – RIGHT FIELD BALCONY AND OMAHA ROOM RENOVATION

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS STRUCTURA- STEE-P NTL HBrojec Nrt . 68. 7 570355 1 040323323508 / P NTL CrB©rBpcari 3508

H. Cutting and Fitting: No cutting of sections, either flanges, webs, stems or angles shall be done by the Contractor without the consent of the Engineer/Architect, unless this cutting is particularly specified or shown on the drawings

I. Shear Connectors: Prepare steel surfaces as recommended by manufacturer of shear connectors. Use automatic end welding of headed-stud shear connectors according to AWS D1.1 and manufacturer's written instructions.

J. Corrective Measures

1. Any errors in locations or inaccuracies in the setting of anchor bolts, base plates, bearing plates, or other items of attachment or support for steel work shall be reported to the Engineer/Architect, and shall be corrected in a manner subject to the approval of the Engineer/Architect.

2. Any misfits due to errors in fabrication shall be reported immediately to the Engineer/Architect, along with proposed method of correction of same and Engineer/Architect approval obtained before proceeding with corrective measures.

3. No members shall be cut or burned without specific approval in writing.4. Bolted or welded connections, joints, or fastenings, which are classified as defective in

the opinion of the Engineer/Architect, shall be corrected by the Contractor in a manner subject to the Engineer/Architect’s approval.

K. Guardrails, Handrails and Ladders: All welds and sharp edges shall be ground smooth.

3.4 FIELD CONNECTIONS

A. High-Strength Bolts: Install high-strength bolts according to RCSC's "Specification for Structural Joints Using ASTM A 325 or A 490 Bolts" for type of bolt and type of joint specified.

B. Weld Connections: Comply with AWS D1.1 for welding procedure specifications, tolerances, appearance, and quality of welds and for methods used in correcting welding work. For connections part of the SLRS, comply with additional requirements of AWS D1.8 – seismic supplement.

1. Comply with AISC's "Code of Standard Practice for Steel Buildings and Bridges" (with exceptions noted in Part 1 of this Specification Section) for bearing, adequacy of temporary connections, alignment, and removal of paint on surfaces adjacent to field welds.

2. For non-moment frame connections, remove backing bars or runoff tabs, back gouge, and grind steel smooth (for moment frames, reference Item 5 below).

3. Assemble and weld built-up sections by methods that will maintain true alignment of axes without exceeding tolerances of AISC's "Code of Standard Practice for Steel Buildings and Bridges" for mill material.

4. For demand critical welds, comply with AWS D1.8 – seismic supplement including the following requirements:

a. Use electrodes specified for demand critical welds.b. At beam flange to column welds, remove bottom backing bars, back gouge, grind

smooth, and back weld with a 5/16 inch reinforcing fillet,. c. Where top backing bars remain, a 5/16-inch fillet weld shall be placed between the

remaining fusible backing bar at the beam flange and the column. A reinforcing fillet shall not be placed between the backing bar and the underside of the beam flange.

OREGON STATE UNIVERSITYGOSS STADIUM – RIGHT FIELD BALCONY AND OMAHA ROOM RENOVATION

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS STRUCTURA- STEE-P NTL HBrojec Nrt . 68. 7 570355 1 070323323508 / P NTL CrB©rBpcari 3508

d. Cut-off runoff plates (weld tabs) 1/8-inch from edges and grind smooth (not flush). The edges where weld tabs are removed shall be finished to a surface roughness of 500 micro-inches or better. The contour of the weld end shall provide a smooth transition to adjacent surfaces. Weld defects greater than 1/16 inch deep shall be excavated and repaired in compliance with an approved WPS.

e. All tack welds not incorporated into the final weld shall be removed.f. Bottom flange welding sequence: When using weld access holes to facilitate CJP

groove welds of beam bottom flanges to column flanges or continuity plates, the groove weld shall be sequenced as follows:

1) As far as practicable, starts and stops shall not be placed directly under the beam web.

2) Each layer shall be completed across the full width of the flange before beginning the next layer.

3) For each layer, the weld starts and stops shall be on the opposite side of the beam web, as compared to the previous layer.

5. The use of copper backing bars are permitted in the WPS and welding under the following restrictions:

a. The maximum root opening shall not exceed 7/16-inch. Root openings exceeding 7/16-inch shall use steel or ceramic backing bars.

b. The WPS using copper backing bars shall be qualified by testing, per AWS D1.1, that they meet the following additional requirements:

1) The weld metal of the root pass shall be analyzed for copper content. Copper shall not exceed 0.15 percent.

2) The weld metal of the root shall be tested for Charpy V-notch toughness values per AWS D1.1, Annex 3, except the CVN specimen shall be taken a maximum of 1/16-inch from the bottom of the test plate. The weld metal shall meet or exceed 20 foot/pound at -20 degrees F.

6. Tack welds incorporated into the final weld and weld repairs of demand critical welds shall be of the same quality as the final welds, including preheat requirements. The filler metals shall be identical, unless qualified by testing and meeting the requirements of Specification 051200, Part 1, "Submittals" article.

7. FCAW electrodes shall be protected from atmospheric exposure as follows:

a. Electrodes not consumed within 24 hours of accumulated exposure outside closed or heated storage shall not be used for seismic critical welds.

b. Electrode spools shall be identified and monitored for total atmospheric exposure time. Electrodes that have been exposed for periods exceeding an accumulated 24 hours may be dried when manufacturer’s recommendations show that drying is effective at removing moisture and restoring electrodes to their designated diffusible hydrogen level. Dry as specified by the manufacturer. If the electrode or the electrode spool is damaged by baking, the electrode shall not be used.

8. Each Welder working on the project shall be assigned an identification symbol or mark. Each Welder shall mark or stamp this identification symbol at each weldment completed and inspected by the welder. Stamps, if used, shall be low-stress type. All welds shall be marked or stamped.

C. Erection Connections, etc: Place holes, plates, or other attachments required by the Erector so as not to interfere with or cause any other detrimental effect to structural members or their connections. Holes and attachments are not permitted in the “protected zone” as described in Section 1.3 and defined in the drawings.

D. Exposed Steel Field Connections:

OREGON STATE UNIVERSITYGOSS STADIUM – RIGHT FIELD BALCONY AND OMAHA ROOM RENOVATION

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS STRUCTURA- STEE-P NTL HBrojec Nrt . 68. 7 570355 1 0.0323323508 / P NTL CrB©rBpcari 3508

1. Grind exposed joints flush and smooth with adjacent finish surface. Make exposed joints butt tight, flush, and hairline. Ease exposed edges to small, uniform radius.

2. Continuously seal joined members by intermittent (stitch) welds and plastic filler.3. Verify that weld sizes, fabrication sequence, and equipment used will limit distortions to

allowable tolerances. Prevent weld show-through.4. Exposed mechanical fastenings: Flush countersunk screws or bolts; unobtrusively

located; consistent with design of component, except where noted otherwise.5. Remove erection bolts; fill holes with plug welds and grind smooth.

3.5 FIELD QUALITY CONTROL

A. Testing Agency: Owner will engage a qualified independent testing and inspecting agency to provide inspection and required tests, and to prepare test reports in accordance with “Testing and Inspection” Article 3.6 below.

3.6 TESTING AND INSPECTION

A. All structural steel work is subject to special inspection. Testing Agency and Inspector Requirements:

1. Special Inspector: Testing Agency shall provide qualified "Special Inspector" who will perform the inspection services.

2. Testing agency will conduct and interpret tests, and state in each report whether test specimens comply with or deviate from requirements.

3. Testing agency will notify the Owner and Engineer/Architect immediately of discrepancies in the work which are time-critical or affect the construction progress.

4. Personnel inspecting connections part of the SLRS shall be qualified per Section 1.5 “Quality Assurance”.

B. Fabrication Inspection: When approved by the Building Official, the Owner, and Engineer/Architect, full-time special inspection in the fabrication shop by the Owner's Testing Agency may be waived, subject to the following:

1. The Fabricator participates in the AISC Quality Certification Program and is designated an AISC-Certified Plant.

2. All shop inspection is provided by the Contractor, per the requirements herein, and is documented. Reports and test results are to be available for the Owner's Inspector to review.

3. A specific quality control plan for this project shall be developed and submitted to the Structural Engineer for approval prior to the prefabrication/pre-erection meeting.

4. Periodic inspection by the Owner's Inspection Agency is allowed by the Fabricator.5. Certified Plants: Continuous plant inspection is not required at plants producing

prefabricated steel products which are certified by the Building Official.

C. Contractor Responsibilities Related to Shop and Field Inspections:

1. Maintain complete records of all quality control and testing performed by the Contractor.2. Furnish all electrical power, turning or moving of members, hoisting, staging, and other

facilities required for inspection.3. Provide testing agency with access to places where structural steel work is being

fabricated or erected so required inspection and testing can be accomplished.4. Correct deficiencies in, or remove and replace structural steel that inspections and test

reports indicate do not comply with specified requirements.

OREGON STATE UNIVERSITYGOSS STADIUM – RIGHT FIELD BALCONY AND OMAHA ROOM RENOVATION

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS STRUCTURA- STEE-P NTL HBrojec Nrt . 68. 7 570355 1 080323323508 / P NTL CrB©rBpcari 3508

5. Additional testing, at Contractor's expense, will be performed to determine compliance of corrected work with specified requirements.

6. Grant Inspectors full authority to inspect all material and work that fails to conform in every respect to these specifications.

7. When required by Engineer/Architect or Owner’s Independent Testing Agency or Contractor’s engaged inspection organization, make adequate platforms available to the Inspector for the purpose of checking high-strength bolts and welds. Scaffolding shall be provided to ensure safe performance of this operation.

D. Shop and Field Tests and Inspections: Inspections and testing shall be performed as indicated in the Contract Documents. Additional requirements are as follows:

1. Welded Connections: In addition to visual inspection, welded connections will be tested and inspected as required by the Contract Documents and Specifications, according to AWS D1.1. Inspection procedures at Testing Agency’s option, are listed below:

a. Procedures

1) Liquid Penetrant Inspection: ASTM E 165.2) Magnetic Particle Inspection: ASTM E 709; performed on root pass and on

finished weld. Cracks or zones of incomplete fusion or penetration will not be accepted.

3) Radiographic Inspection: ASTM E 94 and ASTM E 142; minimum quality level "2-2T."

4) Ultrasonic Inspection: ASTM E 164.b. Inspector shall:

1) Verify Welding Procedure Specifications (WPSs) sheet has been provided and has been reviewed with each welder performing the weld. Welds not executed in conformance with the WPSs are rejectable.

2) Verify fit-up meets tolerances of WPSs and mark joint prior to welding.3) Verify welding consumables per WPSs.4) Verify welding qualification and identifications.5) Observe preheat and interpass temperatures, and weld pass sequence for

conformance with WPSs.6) Nondestructive test all complete penetration groove welds for conformance

with weld quality and standard of acceptance per requirements for testing of welds subject to tensile stress by ultrasonic methods in AWS D1.1. Pass sound through entire weld volume from two crossing directions to the extent feasible. Nondestructive test all complete penetration groove welds of beam flanges to column flanges and column stiffeners and cap plates, and all complete penetration groove welds of column splices and columns to base plates for conformance with weld quality and standard of acceptance per requirements for testing of welds by magnetic particle testing in AWS D.1 in addition to ultrasonic testing methods.

7) All partial penetration, fillet, and other remaining welds shall be visually inspected.

8) Where ultrasonic testing is performed, the entire weld shall be tested.c. Ultrasonically test base metal thicker than 1 1/2 inches after welding is completed

for discontinuities behind welds in accordance with IBC Section 1708.4.d. For connections part of the SLRS, including Demand Critical Welds, non-

destructive testing (NDT) requirements shall comply with AISC 341-05 (seismic provisions) Appendix Q (Q5.2).

e. For Demand Critical Welds, inspect removal of backup bars and runoff plates, preparatory grinding, and execution of reinforcing fillet.

OREGON STATE UNIVERSITYGOSS STADIUM – RIGHT FIELD BALCONY AND OMAHA ROOM RENOVATION

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS STRUCTURA- STEE-P NTL HBrojec Nrt . 68. 7 570355 1 060323323508 / P NTL CrB©rBpcari 3508

f. Test column webs for cracking using dye penetrant or magnetic particle test over 3-inch minimum zone above and below continuity (stiffener) plates after welding. All cracks shall be reported to the Engineer, repaired, and retested. No cracks will be permitted in the final construction.

2. Welded Headed Studs: In addition to visual inspection, welded headed stud connectors will be inspected and tested according to requirements of AWS D1.1 for stud welding and as follows:

a. Bend tests will be performed when visual inspections reveal either less than a continuous 360-degree flash or many cases requiring welding repairs to any welded headed stud connector.

b. Tests will be conducted on additional welded headed stud connectors when weld fracture occurs on shear connectors already tested, according to requirements of AWS D1.1.

3. All slide-bearing assemblies to be inspected for damage, and for scratched or soiled surfaces.

3.7 REPAIRS AND PROTECTION

A. Touchup Painting: After installation, promptly clean, prepare, and prime or reprime field connections, rust spots, and abraded surfaces of prime-painted joists and accessories and abutting structural steel.

1. Clean and prepare surfaces by SSPC-SP 2 hand-tool cleaning or SSPC-SP 3 power-tool cleaning.

2. Apply a compatible primer of same type as shop primer used on adjacent surfaces.

B. Touchup Painting: Cleaning and touchup painting are specified in Division 09 painting Section.

END OF SECTION 05 1200

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS METAL FABRICATIONS HNTB Project No. 66765 055000 - 1 12/29/2017 ©HNTB Corporation 2017

SECTION 05 5000 - METAL FABRICATIONS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Steel framing and supports for countertops. 2. Steel tube reinforcement for low partitions. 3. Steel framing and supports for mechanical and electrical equipment. 4. Steel framing and supports for applications where framing and supports are not specified

in other Sections. 5. Miscellaneous steel trim including steel angle corner guards, steel edgings, and loading-

dock edge angles. 6. Metal bollards. 7. Abrasive metal nosings. 8. Loose bearing and leveling plates for applications where they are not specified in other

Sections.

B. Products furnished, but not installed, under this Section include the following:

1. Anchor bolts, steel pipe sleeves, slotted-channel inserts, and wedge-type inserts indicated to be cast into concrete or built into unit masonry.

2. Steel weld plates and angles for casting into concrete for applications where they are not specified in other Sections.

C. Related Requirements:

1. Section 03 3000 "Cast-in-Place Concrete" for installing anchor bolts, steel pipe sleeves, slotted-channel inserts, wedge-type inserts, and other items cast into concrete.

2. Section 05 1200 "Structural Steel Framing."

1.3 COORDINATION

A. Coordinate selection of shop primers with topcoats to be applied over them. Comply with paint and coating manufacturers' written recommendations to ensure that shop primers and topcoats are compatible with one another.

B. Coordinate installation of metal fabrications that are anchored to or that receive other work. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS METAL FABRICATIONS HNTB Project No. 66765 055000 - 2 12/29/2017 ©HNTB Corporation 2017

1.4 ACTION SUBMITTALS

A. Product Data: For the following:

1. Nonslip aggregates and nonslip-aggregate surface finishes. 2. Metal nosings and treads. 3. Paint products. 4. Grout.

B. Shop Drawings: Show fabrication and installation details. Include plans, elevations, sections, and details of metal fabrications and their connections. Show anchorage and accessory items. Provide Shop Drawings for the following:

1. Steel framing and supports for countertops. 2. Steel tube reinforcement for low partitions. 3. Steel framing and supports for mechanical and electrical equipment. 4. Steel framing and supports for applications where framing and supports are not specified

in other Sections. 5. Miscellaneous steel trim including steel angle corner guards, steel edgings, and loading-

dock edge angles. 6. Metal bollards. 7. Abrasive metal nosings. 8. Loose steel lintels.

C. Delegated-Design Submittal: For ladders and alternating tread devices, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation.

1.5 INFORMATIONAL SUBMITTALS

A. Qualification Data: For professional engineer.

B. Mill Certificates: Signed by stainless-steel manufacturers, certifying that products furnished comply with requirements.

C. Welding certificates.

D. Paint Compatibility Certificates: From manufacturers of topcoats applied over shop primers, certifying that shop primers are compatible with topcoats.

E. Research/Evaluation Reports: For post-installed anchors, from ICC-ES.

1.6 QUALITY ASSURANCE

A. Welding Qualifications: Qualify procedures and personnel according to AWS D1.1/D1.1M, "Structural Welding Code - Steel."

B. Welding Qualifications: Qualify procedures and personnel according to the following:

1. AWS D1.1/D1.1M, "Structural Welding Code - Steel." 2. AWS D1.2/D1.2M, "Structural Welding Code - Aluminum." 3. AWS D1.6/D1.6M, "Structural Welding Code - Stainless Steel."

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS METAL FABRICATIONS HNTB Project No. 66765 055000 - 3 12/29/2017 ©HNTB Corporation 2017

1.7 FIELD CONDITIONS

A. Field Measurements: Verify actual locations of walls and other construction contiguous with metal fabrications by field measurements before fabrication.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Delegated Design: Engage a qualified professional engineer, as defined in Section 01 4000 "Quality Requirements," to design ladders and alternating tread devices.

B. Thermal Movements: Allow for thermal movements from ambient and surface temperature changes acting on exterior metal fabrications by preventing buckling, opening of joints, overstressing of components, failure of connections, and other detrimental effects.

1. Temperature Change: 120 deg F, ambient; 180 deg F, material surfaces.

2.2 METALS

A. Metal Surfaces, General: Provide materials with smooth, flat surfaces unless otherwise indicated. For metal fabrications exposed to view in the completed Work, provide materials without seam marks, roller marks, rolled trade names, or blemishes.

B. Steel Plates, Shapes, and Bars: ASTM A 36/A 36M.

C. Stainless-Steel Sheet, Strip, and Plate: ASTM A 240/A 240M or ASTM A 666, Type 304.

D. Stainless-Steel Bars and Shapes: ASTM A 276, Type 304.

E. Steel Tubing: ASTM A 500/A 500M, cold-formed steel tubing.

F. Steel Pipe: ASTM A 53/A 53M, Standard Weight (Schedule 40) unless otherwise indicated.

G. Slotted Channel Framing: Cold-formed metal box channels (struts) complying with MFMA-4.

1. Size of Channels: 1-5/8 by 1-5/8 inches. 2. Material: Galvanized steel, ASTM A 653/A 653M, structural steel, Grade 33, with G90

coating; 0.079-inch nominal thickness. 3. Material: Cold-rolled steel, ASTM A 1008/A 1008M, structural steel, Grade 33; 0.0677-

inch minimum thickness; hot-dip galvanized after fabrication.

H. Cast Iron: Either gray iron, ASTM A 48/A 48M, or malleable iron, ASTM A 47/A 47M, unless otherwise indicated.

2.3 FASTENERS

A. General: Unless otherwise indicated, provide Type 304 stainless-steel fasteners for exterior use and zinc-plated fasteners with coating complying with ASTM B 633 or ASTM F 1941, Class Fe/Zn 5, at exterior walls. Select fasteners for type, grade, and class required.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS METAL FABRICATIONS HNTB Project No. 66765 055000 - 4 12/29/2017 ©HNTB Corporation 2017

1. Provide stainless-steel fasteners for fastening aluminum. 2. Provide stainless-steel fasteners for fastening stainless steel.

B. Steel Bolts and Nuts: Regular hexagon-head bolts, ASTM A 307, Grade A; with hex nuts, ASTM A 563; and, where indicated, flat washers.

C. Steel Bolts and Nuts: Regular hexagon-head bolts, ASTM A 325, Type 3; with hex nuts, ASTM A 563, Grade C3; and, where indicated, flat washers.

D. Stainless-Steel Bolts and Nuts: Regular hexagon-head annealed stainless-steel bolts, ASTM F 593; with hex nuts, ASTM F 594; and, where indicated, flat washers; Alloy Group 1.

E. Anchor Bolts: ASTM F 1554, Grade 36, of dimensions indicated; with nuts, ASTM A 563; and, where indicated, flat washers.

1. Hot-dip galvanize or provide mechanically deposited, zinc coating where item being fastened is indicated to be galvanized.

F. Anchors, General: Anchors capable of sustaining, without failure, a load equal to six times the load imposed when installed in unit masonry and four times the load imposed when installed in concrete, as determined by testing according to ASTM E 488/E 488M, conducted by a qualified independent testing agency.

G. Cast-in-Place Anchors in Concrete: Either threaded type or wedge type unless otherwise indicated; galvanized ferrous castings, either ASTM A 47/A 47M malleable iron or ASTM A 27/A 27M cast steel. Provide bolts, washers, and shims as needed, all hot-dip galvanized per ASTM F 2329.

H. Post-Installed Anchors: Torque-controlled expansion anchors or chemical anchors.

1. Material for Interior Locations: Carbon-steel components zinc plated to comply with ASTM B 633 or ASTM F 1941, Class Fe/Zn 5, unless otherwise indicated.

2. Material for Exterior Locations and Where Stainless Steel Is Indicated: Alloy Group 1 stainless-steel bolts, ASTM F 593, and nuts, ASTM F 594.

I. Slotted-Channel Inserts: Cold-formed, hot-dip galvanized-steel box channels (struts) complying with MFMA-4, 1-5/8 by 7/8 inches by length indicated with anchor straps or studs not less than 3 inches long at not more than 8 inches o.c. Provide with temporary filler and tee-head bolts, complete with washers and nuts, all zinc-plated to comply with ASTM B 633, Class Fe/Zn 5, as needed for fastening to inserts.

2.4 MISCELLANEOUS MATERIALS

A. Shop Primers: Provide primers that comply with Section 09 9123 “Interior Painting" and Section 099600 “High-Performance Coatings.”

B. Galvanizing Repair Paint: High-zinc-dust-content paint complying with SSPC-Paint 20 and compatible with paints specified to be used over it.

C. Bituminous Paint: Cold-applied asphalt emulsion complying with ASTM D 1187/D 1187M.

D. Nonshrink, Nonmetallic Grout: Factory-packaged, nonstaining, noncorrosive, nongaseous grout complying with ASTM C 1107/C 1107M. Provide cementitious grout specifically recommended

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS METAL FABRICATIONS HNTB Project No. 66765 055000 - 5 12/29/2017 ©HNTB Corporation 2017

by manufacturer for interior and exterior applications. Products containing gypsum are not acceptable.

E. Concrete: Comply with requirements in Section 03 3000 "Cast-in-Place Concrete" for normal-weight, air-entrained, concrete with a minimum 28-day compressive strength of 3000 psi.

2.5 FABRICATION, GENERAL

A. Shop Assembly: Preassemble items in the shop to greatest extent possible. Disassemble units only as necessary for shipping and handling limitations. Use connections that maintain structural value of joined pieces. Clearly mark units for reassembly and coordinated installation.

B. Cut, drill, and punch metals cleanly and accurately. Remove burrs and ease edges to a radius of approximately 1/32 inch unless otherwise indicated. Remove sharp or rough areas on exposed surfaces.

C. Form bent-metal corners to smallest radius possible without causing grain separation or otherwise impairing work.

D. Form exposed work with accurate angles and surfaces and straight edges.

E. Weld corners and seams continuously to comply with the following:

1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals.

2. Obtain fusion without undercut or overlap. 3. Remove welding flux immediately. 4. At exposed connections, finish exposed welds and surfaces smooth and blended so no

roughness shows after finishing and contour of welded surface matches that of adjacent surface.

F. Form exposed connections with hairline joints, flush and smooth, using concealed fasteners or welds where possible. Where exposed fasteners are required, use Phillips flat-head (countersunk) fasteners unless otherwise indicated. Locate joints where least conspicuous.

G. Fabricate seams and other connections that are exposed to weather in a manner to exclude water. Provide weep holes where water may accumulate.

H. Cut, reinforce, drill, and tap metal fabrications as indicated to receive finish hardware, screws, and similar items.

I. Provide for anchorage of type indicated; coordinate with supporting structure. Space anchoring devices to secure metal fabrications rigidly in place and to support indicated loads.

J. Where units are indicated to be cast into concrete or built into masonry, equip with integrally welded steel strap anchors, 1/8 by 1-1/2 inches, with a minimum 6-inch embedment and 2-inch hook, not less than 8 inches from ends and corners of units and 24 inches o.c., unless otherwise indicated.

2.6 MISCELLANEOUS FRAMING AND SUPPORTS

A. General: Provide steel framing and supports not specified in other Sections as needed to complete the Work.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS METAL FABRICATIONS HNTB Project No. 66765 055000 - 6 12/29/2017 ©HNTB Corporation 2017

B. Fabricate units from steel shapes, plates, and bars of welded construction unless otherwise indicated. Fabricate to sizes, shapes, and profiles indicated and as necessary to receive adjacent construction.

1. Fabricate units from slotted channel framing where indicated. 2. Furnish inserts for units installed after concrete is placed.

2.7 SHELF ANGLES

A. Fabricate shelf angles from steel angles of sizes indicated and for attachment to concrete framing. Provide horizontally slotted holes to receive 3/4-inch bolts, spaced not more than 6 inches from ends and 24 inches o.c., unless otherwise indicated.

1. Provide mitered and welded units at corners. 2. Provide open joints in shelf angles at expansion and control joints. Make open joint

approximately 2 inches larger than expansion or control joint.

B. For cavity walls, provide vertical channel brackets to support angles from backup masonry and concrete.

C. Galvanize and prime shelf angles located in exterior walls.

D. Furnish wedge-type concrete inserts, complete with fasteners, to attach shelf angles to cast-in-place concrete.

2.8 METAL LADDERS

A. General:

1. Comply with ANSI A14.3. 2. For elevator pit ladders, comply with ASME A17.1/CSA B44.

B. Steel Ladders:

1. Space siderails 16 inches apart unless otherwise indicated. 2. Siderails: Continuous, 3/8-by-2-1/2-inch steel flat bars, with eased edges. 3. Rungs: 3/4-inch-diameter steel bars. 4. Fit rungs in centerline of siderails; plug-weld and grind smooth on outer rail faces. 5. Provide nonslip surfaces on top of each rung by coating with abrasive material

metallically bonded to rung.

a. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:

1) Harsco Industrial IKG, a division of Harsco Corporation. 2) SlipNOT Metal Safety Flooring; W.S. Molnar Company.

6. Provide platforms as indicated fabricated from welded or pressure-locked steel bar grating, supported by steel angles. Limit openings in gratings to no more than 1/2 inch in least dimension.

7. Support each ladder at top and bottom and not more than 60 inches o.c. with welded or bolted steel brackets.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS METAL FABRICATIONS HNTB Project No. 66765 055000 - 7 12/29/2017 ©HNTB Corporation 2017

8. Galvanize and prime exterior ladders, including brackets.

2.9 ELEVATOR PIT SUMP COVERS

A. Fabricate from welded or pressure-locked steel bar grating Limit openings in gratings to no more than 1/2 inch in least dimension.

B. Provide steel angle supports as indicated.

2.10 MISCELLANEOUS STEEL TRIM

A. Unless otherwise indicated, fabricate units from steel shapes, plates, and bars of profiles shown with continuously welded joints and smooth exposed edges. Miter corners and use concealed field splices where possible.

B. Provide cutouts, fittings, and anchorages as needed to coordinate assembly and installation with other work.

1. Provide with integrally welded steel strap anchors for embedding in concrete or masonry construction.

C. Galvanize exterior miscellaneous steel trim.

2.11 METAL BOLLARDS

A. Fabricate metal bollards from Schedule 40 steel pipe.

1. Cap bollards with 1/4-inch-thick steel plate.

B. Prime bollards with primer specified in Section 099600 "High-Performance Coatings."

2.12 ABRASIVE METAL NOSINGS

A. Cast-Metal Units: Cast iron, with an integral-abrasive, as-cast finish consisting of aluminum oxide, silicon carbide, or a combination of both. Fabricate units in lengths necessary to accurately fit openings or conditions.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

a. American Safety Tread Co., Inc. b. Balco, Inc. c. Granite State Casting Co. d. Safe-T-Metal Company, Inc. e. Wooster Products Inc.

2. Nosings: Cross-hatched units, 1-1/2 by 1-1/2 inches, for casting into concrete.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS METAL FABRICATIONS HNTB Project No. 66765 055000 - 8 12/29/2017 ©HNTB Corporation 2017

B. Extruded Units: Aluminum, with abrasive filler consisting of aluminum oxide, silicon carbide, or a combination of both, in an epoxy-resin binder. Fabricate units in lengths necessary to accurately fit openings or conditions.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:

a. American Safety Tread Co., Inc. b. Balco, Inc. c. Granite State Casting Co. d. Nystrom, Inc. e. Wooster Products Inc.

2. Provide ribbed units, with abrasive filler strips projecting 1/16 inchabove aluminum extrusion.

3. Nosings: Square-back units, 3 incheswide, for casting into concrete steps. 4. Nosings: Two-piece units, 3 incheswide, with subchannel for casting into concrete steps.

C. Provide anchors for embedding units in concrete, either integral or applied to units, as standard with manufacturer.

D. Drill for mechanical anchors and countersink. Locate holes not more than 4 inches from ends and not more than 12 inches o.c., evenly spaced between ends, unless otherwise indicated. Provide closer spacing if recommended by manufacturer.

1. Provide two rows of holes for units more than 5 inches wide, with two holes aligned at ends and intermediate holes staggered.

E. Apply bituminous paint to concealed surfaces of cast-metal units.

F. Apply clear lacquer to concealed surfaces of extruded units.

2.13 LOOSE BEARING AND LEVELING PLATES

A. Provide loose bearing and leveling plates for steel items bearing on masonry or concrete construction. Drill plates to receive anchor bolts and for grouting.

B. Galvanize plates.

C. Prime plates with primer specified in Section 09 9600 "High-Performance Coatings."

2.14 LOOSE STEEL LINTELS

A. Fabricate loose steel lintels from steel angles and shapes of size indicated for openings and recesses in masonry walls and partitions at locations indicated. Fabricate in single lengths for each opening unless otherwise indicated. Weld adjoining members together to form a single unit where indicated.

B. Size loose lintels to provide bearing length at each side of openings equal to 1/12 of clear span, but not less than 8 inches unless otherwise indicated.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS METAL FABRICATIONS HNTB Project No. 66765 055000 - 9 12/29/2017 ©HNTB Corporation 2017

C. Galvanize and prime loose steel lintels located in exterior walls.

2.15 STEEL WELD PLATES AND ANGLES

A. Provide steel weld plates and angles not specified in other Sections, for items supported from concrete construction as needed to complete the Work. Provide each unit with no fewer than two integrally welded steel strap anchors for embedding in concrete.

2.16 FINISHES, GENERAL

A. Finish metal fabrications after assembly.

B. Finish exposed surfaces to remove tool and die marks and stretch lines, and to blend into surrounding surface.

2.17 STEEL AND IRON FINISHES

A. Galvanizing: Hot-dip galvanize items as indicated to comply with ASTM A 153/A 153M for steel and iron hardware and with ASTM A 123/A 123M for other steel and iron products.

1. Do not quench or apply post galvanizing treatments that might interfere with paint adhesion.

B. Preparation for Shop Priming Galvanized Items: After galvanizing, thoroughly clean railings of grease, dirt, oil, flux, and other foreign matter, and treat with metallic phosphate process.

C. Shop prime iron and steel items not indicated to be galvanized unless they are to be embedded in concrete, sprayed-on fireproofing, or masonry, or unless otherwise indicated.

1. Shop prime with universal shop primer unless indicated.

D. Preparation for Shop Priming: Prepare surfaces to comply with requirements indicated below:

1. Exterior Items: SSPC-SP 6/NACE No. 3, "Commercial Blast Cleaning." 2. Items Indicated to Receive Zinc-Rich Primer: SSPC-SP 6/NACE No. 3, "Commercial

Blast Cleaning." 3. Items Indicated to Receive Primers Specified in Section 09 9600 "High-Performance

Coatings": SSPC-SP 6/NACE No. 3, "Commercial Blast Cleaning." 4. Other Items: SSPC-SP 3, "Power Tool Cleaning."

E. Shop Priming: Apply shop primer to comply with SSPC-PA 1, "Paint Application Specification No. 1: Shop, Field, and Maintenance Painting of Steel," for shop painting.

1. Stripe paint corners, crevices, bolts, welds, and sharp edges.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS METAL FABRICATIONS HNTB Project No. 66765 055000 - 10 12/29/2017 ©HNTB Corporation 2017

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Cutting, Fitting, and Placement: Perform cutting, drilling, and fitting required for installing metal fabrications. Set metal fabrications accurately in location, alignment, and elevation; with edges and surfaces level, plumb, true, and free of rack; and measured from established lines and levels.

B. Fit exposed connections accurately together to form hairline joints. Weld connections that are not to be left as exposed joints but cannot be shop welded because of shipping size limitations. Do not weld, cut, or abrade surfaces of exterior units that have been hot-dip galvanized after fabrication and are for bolted or screwed field connections.

C. Field Welding: Comply with the following requirements:

1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals.

2. Obtain fusion without undercut or overlap. 3. Remove welding flux immediately. 4. At exposed connections, finish exposed welds and surfaces smooth and blended so no

roughness shows after finishing and contour of welded surface matches that of adjacent surface.

D. Fastening to In-Place Construction: Provide anchorage devices and fasteners where metal fabrications are required to be fastened to in-place construction. Provide threaded fasteners for use with concrete and masonry inserts, toggle bolts, through bolts, lag screws, wood screws, and other connectors.

E. Provide temporary bracing or anchors in formwork for items that are to be built into concrete, masonry, or similar construction.

F. Corrosion Protection: Coat concealed surfaces of aluminum that come into contact with grout, concrete, masonry, wood, or dissimilar metals with the following:

1. Cast Aluminum: Heavy coat of bituminous paint. 2. Extruded Aluminum: Two coats of clear lacquer.

3.2 INSTALLING MISCELLANEOUS FRAMING AND SUPPORTS

A. General: Install framing and supports to comply with requirements of items being supported, including manufacturers' written instructions and requirements indicated on Shop Drawings.

B. Anchor supports for overhead doors securely to, and rigidly brace from, building structure.

C. Support steel girders on solid grouted masonry, concrete, or steel pipe columns. Secure girders with anchor bolts embedded in grouted masonry or concrete or with bolts through top plates of pipe columns.

1. Where grout space under bearing plates is indicated for girders supported on concrete or masonry, install as specified in "Installing Bearing and Leveling Plates" Article.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS METAL FABRICATIONS HNTB Project No. 66765 055000 - 11 12/29/2017 ©HNTB Corporation 2017

D. Install pipe columns on concrete footings with grouted baseplates. Position and grout column baseplates as specified in "Installing Bearing and Leveling Plates" Article.

1. Grout baseplates of columns supporting steel girders after girders are installed and leveled.

3.3 INSTALLING METAL BOLLARDS

A. Fill metal-capped bollards solidly with concrete and allow concrete to cure seven days before installing.

B. Anchor bollards in place with concrete footings. Center and align bollards in holes 3 inches above bottom of excavation. Place concrete and vibrate or tamp for consolidation. Support and brace bollards in position until concrete has cured.

3.4 INSTALLING NOSINGS, TREADS, AND THRESHOLDS

A. Center nosings on tread widths unless otherwise indicated.

B. For nosings embedded in concrete steps or curbs, align nosings flush with riser faces and level with tread surfaces.

C. Seal thresholds exposed to exterior with elastomeric sealant complying with Section 079200 "Joint Sealants" to provide a watertight installation.

3.5 INSTALLING BEARING AND LEVELING PLATES

A. Clean concrete and masonry bearing surfaces of bond-reducing materials, and roughen to improve bond to surfaces. Clean bottom surface of plates.

B. Set bearing and leveling plates on wedges, shims, or leveling nuts. After bearing members have been positioned and plumbed, tighten anchor bolts. Do not remove wedges or shims but, if protruding, cut off flush with edge of bearing plate before packing with nonshrink grout. Pack grout solidly between bearing surfaces and plates to ensure that no voids remain.

3.6 ADJUSTING AND CLEANING

A. Touchup Painting: Immediately after erection, clean field welds, bolted connections, and abraded areas. Paint uncoated and abraded areas with the same material as used for shop painting to comply with SSPC-PA 1 for touching up shop-painted surfaces.

1. Apply by brush or spray to provide a minimum 2.0-mil dry film thickness.

B. Galvanized Surfaces: Clean field welds, bolted connections, and abraded areas and repair galvanizing to comply with ASTM A 780/A 780M.

END OF SECTION 05 5000

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS METAL PAN STAIRS HNTB Project No. 66765 055113 - 1 12/29/2017 ©HNTB Corporation 2017

SECTION 05 5113 - METAL PAN STAIRS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Preassembled steel stairs with concrete-filled treads. 2. Steel tube railings attached to metal stairs. 3. Steel tube handrails attached to walls adjacent to metal stairs. 4. Railing gates at the level of exit discharge.

B. Related Requirements:

1. Section 03 3000 "Cast-in-Place Concrete" for concrete fill for stair treads and platforms. 2. Section 05 5213 "Pipe and Tube Railings" for pipe and tube railings. 3. Section 05 5100 “Decorative Metal Railings” for cable guard railings.

1.3 COORDINATION

A. Coordinate selection of shop primers with topcoats to be applied over them. Comply with paint and coating manufacturers' written recommendations to ensure that shop primers and topcoats are compatible with one another.

B. Coordinate installation of anchorages for metal stairs. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation.

C. Coordinate locations of hanger rods and struts with other work so that they do not encroach on required stair width and are within the fire-resistance-rated stair enclosure.

1.4 ACTION SUBMITTALS

A. Shop Drawings: Include plans, elevations, sections, details, and attachments to other work.

B. Delegated-Design Submittal: For stairs and railings, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation.

1.5 INFORMATIONAL SUBMITTALS

A. Welding certificates.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS METAL PAN STAIRS HNTB Project No. 66765 055113 - 2 12/29/2017 ©HNTB Corporation 2017

B. Paint Compatibility Certificates: From manufacturers of topcoats applied over shop primers certifying that shop primers are compatible with topcoats.

1.6 QUALITY ASSURANCE

A. Installer Qualifications: Fabricator of products.

B. Welding Qualifications: Qualify procedures and personnel according to the following:

1. AWS D1.1/D1.1M, "Structural Welding Code - Steel." 2. AWS D1.3/D1.3M, "Structural Welding Code - Sheet Steel."

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:

1. Alfab, Inc. 2. American Stair, Inc. 3. Lapeyre Stair Inc. 4. Pacific Stair Corporation.

2.2 PERFORMANCE REQUIREMENTS

A. Delegated Design: Engage a qualified professional engineer, as defined in Section 01 4000 "Quality Requirements," to design stairs and railings.

B. Structural Performance of Stairs: Metal stairs shall withstand the effects of gravity loads and the following loads and stresses within limits and under conditions indicated:

1. Uniform Load: 100 lbf/sq. ft. 2. Concentrated Load: 300 lbf applied on an area of 4 sq. in. 3. Uniform and concentrated loads need not be assumed to act concurrently. 4. Stair Framing: Capable of withstanding stresses resulting from railing loads in addition to

loads specified above. 5. Limit deflection of treads, platforms, and framing members to L/360 or 1/4 inch,

whichever is less.

C. Structural Performance of Railings: Railings shall withstand the effects of gravity loads and the following loads and stresses within limits and under conditions indicated:

1. Handrails and Top Rails of Guards:

a. Uniform load of 50 lbf/ft. applied in any direction. b. Concentrated load of 200 lbf applied in any direction. c. Uniform and concentrated loads need not be assumed to act concurrently.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS METAL PAN STAIRS HNTB Project No. 66765 055113 - 3 12/29/2017 ©HNTB Corporation 2017

2. Infill of Guards:

a. Concentrated load of 50 lbf applied horizontally on an area of 1 sq. ft. b. Infill load and other loads need not be assumed to act concurrently.

D. Seismic Performance of Stairs: Metal stairs shall withstand the effects of earthquake motions determined according to ASCE/SEI 7.

1. Component Importance Factor: 1.5.

2.3 METALS

A. Metal Surfaces, General: Provide materials with smooth, flat surfaces unless otherwise indicated. For components exposed to view in the completed Work, provide materials without seam marks, roller marks, rolled trade names, or blemishes.

B. Steel Plates, Shapes, and Bars: ASTM A 36/A 36M.

C. Steel Tubing: ASTM A 500 (cold formed) or ASTM A 513.

D. Cast Iron: Either gray iron, ASTM A 48/A 48M, or malleable iron, ASTM A 47/A 47M, unless otherwise indicated.

E. Uncoated, Cold-Rolled Steel Sheet: ASTM A 1008/A 1008M, either commercial steel, Type B, or structural steel, Grade 25, unless another grade is required by design loads; exposed.

F. Uncoated, Hot-Rolled Steel Sheet: ASTM A 1011/A 1011M, either commercial steel, Type B, or structural steel, Grade 30, unless another grade is required by design loads.

G. Galvanized-Steel Sheet: ASTM A 653/A 653M, G90 coating, either commercial steel, Type B, or structural steel, Grade 33, unless another grade is required by design loads.

H. Aluminum Extrusions: ASTM B 221, Alloy 6063-T6.

I. Aluminum Castings: ASTM B 26/B 26M, Alloy 443.0-F.

2.4 FASTENERS

A. General: Provide zinc-plated fasteners with coating complying with ASTM B 633 or ASTM F 1941, Class Fe/Zn 12 for exterior use, and Class Fe/Zn 5 where built into exterior walls. Select fasteners for type, grade, and class required.

B. Bolts and Nuts: Regular hexagon-head bolts, ASTM A 307, Grade A; with hex nuts, ASTM A 563; and, where indicated, flat washers.

C. Anchor Bolts: ASTM F 1554, Grade 36, of dimensions indicated; with nuts, ASTM A 563; and, where indicated, flat washers.

1. Provide mechanically deposited or hot-dip, zinc-coated anchor bolts for stairs indicated to be galvanized.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS METAL PAN STAIRS HNTB Project No. 66765 055113 - 4 12/29/2017 ©HNTB Corporation 2017

D. Post-Installed Anchors: Torque-controlled expansion anchors or chemical anchors capable of sustaining, without failure, a load equal to six times the load imposed when installed in unit masonry and four times the load imposed when installed in concrete, as determined by testing according to ASTM E 488/E 488M, conducted by a qualified independent testing agency.

1. Material for Interior Locations: Carbon-steel components zinc plated to comply with ASTM B 633 or ASTM F 1941, Class Fe/Zn 5, unless otherwise indicated.

2. Material for Exterior Locations and Where Stainless Steel Is Indicated: Alloy Group 1 (A1) stainless-steel bolts, ASTM F 593 (ASTM F 738M), and nuts, ASTM F 594 (ASTM F 836M).

2.5 MISCELLANEOUS MATERIALS

A. Shop Primers: Provide primers that comply with Section 09 9113 "Exterior Painting" and Section 09 9123 "Interior Painting."

B. Shop Primer for Galvanized Steel: Primer formulated for exterior use over zinc-coated metal and compatible with finish paint systems indicated.

C. Galvanizing Repair Paint: High-zinc-dust-content paint complying with SSPC-Paint 20 and compatible with paints specified to be used over it.

D. Bituminous Paint: Cold-applied asphalt emulsion complying with ASTM D 1187/D 1187M.

E. Concrete Materials and Properties: Comply with requirements in Section 03 3000 "Cast-in-Place Concrete" for normal-weight, air-entrained, ready-mix concrete with a minimum 28-day compressive strength of 3000 psi (20 MPa) unless otherwise indicated.

F. Welded Wire Reinforcement: ASTM A 185/A 185M, 6 by 6 inches (152 by 152 mm), W1.4 by W1.4, unless otherwise indicated.

2.6 FABRICATION, GENERAL

A. Provide complete stair assemblies, including metal framing, hangers, struts, railings, clips, brackets, bearing plates, and other components necessary to support and anchor stairs and platforms on supporting structure.

1. Join components by welding unless otherwise indicated. 2. Use connections that maintain structural value of joined pieces.

B. Preassembled Stairs: Assemble stairs in shop to greatest extent possible. Disassemble units only as necessary for shipping and handling limitations. Clearly mark units for reassembly and coordinated installation.

C. Cut, drill, and punch metals cleanly and accurately. Remove burrs and ease edges to a radius of approximately 1/32 inch (1 mm) unless otherwise indicated. Remove sharp or rough areas on exposed surfaces.

D. Form bent-metal corners to smallest radius possible without causing grain separation or otherwise impairing work.

E. Form exposed work with accurate angles and surfaces and straight edges.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS METAL PAN STAIRS HNTB Project No. 66765 055113 - 5 12/29/2017 ©HNTB Corporation 2017

F. Weld connections to comply with the following:

1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals.

2. Obtain fusion without undercut or overlap. 3. Remove welding flux immediately. 4. Weld exposed corners and seams continuously unless otherwise indicated. 5. At exposed connections, finish exposed welds to comply with NOMMA's "Voluntary Joint

Finish Standards" for Type 3 welds: partially dressed weld with spatter removed.

G. Form exposed connections with hairline joints, flush and smooth, using concealed fasteners where possible. Where exposed fasteners are required, use Phillips flat-head (countersunk) screws or bolts unless otherwise indicated. Locate joints where least conspicuous.

2.7 STEEL-FRAMED STAIRS

A. NAAMM Stair Standard: Comply with "Recommended Voluntary Minimum Standards for Fixed Metal Stairs" in NAAMM AMP 510, "Metal Stairs Manual," Commercial Class, unless more stringent requirements are indicated.

B. Stair Framing:

1. Fabricate stringers of steel plates or channels.

a. Provide closures for exposed ends of channel stringers.

2. Construct platforms of steel plate or channel headers and miscellaneous framing members as needed to comply with performance requirements.

3. Weld or bolt stringers to headers; weld or bolt framing members to stringers and headers. If using bolts, fabricate and join so bolts are not exposed on finished surfaces.

4. Where stairs are enclosed by gypsum board shaft-wall assemblies, provide hanger rods or struts to support landings from floor construction above or below. Locate hanger rods and struts where they do not encroach on required stair width and are within the fire-resistance-rated stair enclosure.

5. Where masonry walls support metal stairs, provide temporary supporting struts designed for erecting steel stair components before installing masonry.

C. Metal Pan Stairs: Form risers, subtread pans, and subplatforms to configurations shown from steel sheet of thickness needed to comply with performance requirements, but not less than 0.067 inch (1.7 mm).

1. Steel Sheet: Galvanized-steel sheet. 2. Directly weld metal pans to stringers; locate welds on top of subtreads where they are

concealed by concrete fill. Do not weld risers to stringers. 3. Shape metal pans to include nosing integral with riser. 4. Provide subplatforms of configuration indicated or, if not indicated, the same as

subtreads. Weld subplatforms to platform framing.

a. Smooth Soffit Construction: Construct subplatforms with flat metal under surfaces to produce smooth soffits.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS METAL PAN STAIRS HNTB Project No. 66765 055113 - 6 12/29/2017 ©HNTB Corporation 2017

2.8 STAIR RAILINGS

A. Steel Tube Railings: Fabricate railings to comply with requirements indicated for design, dimensions, details, finish, and member sizes, including wall thickness of tube, post spacings, and anchorage, but not less than that needed to withstand indicated loads.

1. Rails and Posts: 1-5/8-inch- (41-mm-) diameter top and bottom rails and 1-1/2-inch- (38-mm-) square posts.

2. Gates: Form gates from steel tube of same size and shape as top rails, with infill to match guards. Provide with spring hinges for fastening to wall and overlapping stop with rubber bumper to prevent gate from opening in direction opposite egress.

B. Welded Connections: Fabricate railings with welded connections. Cope components at connections to provide close fit, or use fittings designed for this purpose. Weld all around at connections, including at fittings.

1. Finish welds to comply with NOMMA's "Voluntary Joint Finish Standards" for Type 2 welds: completely sanded joint, some undercutting and pinholes are okay as shown in NAAMM AMP 521.

C. Form changes in direction of railings as follows:

1. By bending.

D. For changes in direction made by bending, use jigs to produce uniform curvature for each repetitive configuration required. Maintain cross section of member throughout entire bend without buckling, twisting, cracking, or otherwise deforming exposed surfaces of components.

E. Close exposed ends of railing members with prefabricated end fittings.

F. Provide wall returns at ends of wall-mounted handrails unless otherwise indicated. Close ends of returns unless clearance between end of rail and wall is 1/4 inch (6 mm) or less.

G. Connect posts to stair framing by direct welding unless otherwise indicated.

H. Brackets, Flanges, Fittings, and Anchors: Provide wall brackets, end closures, flanges, miscellaneous fittings, and anchors for interconnecting components and for attaching to other work. Furnish inserts and other anchorage devices for connecting to concrete or masonry work.

1. For galvanized railings, provide galvanized fittings, brackets, fasteners, sleeves, and other ferrous-metal components.

2. For nongalvanized railings, provide nongalvanized ferrous-metal fittings, brackets, fasteners, and sleeves, except galvanize anchors embedded in exterior masonry and concrete construction.

3. Provide type of bracket with flange tapped for concealed anchorage to threaded hanger bolt and that provides 1-1/2-inch (38-mm) clearance from inside face of handrail to finished wall surface.

I. Fillers: Provide fillers made from steel plate, or other suitably crush-resistant material, where needed to transfer wall bracket loads through wall finishes to structural supports. Size fillers to suit wall finish thicknesses and to produce adequate bearing area to prevent bracket rotation and overstressing of substrate.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS METAL PAN STAIRS HNTB Project No. 66765 055113 - 7 12/29/2017 ©HNTB Corporation 2017

2.9 FINISHES

A. Finish metal stairs after assembly.

B. Galvanizing: Hot-dip galvanize items as indicated to comply with ASTM A 153/A 153M for steel and iron hardware and with ASTM A 123/A 123M for other steel and iron products.

1. Do not quench or apply post galvanizing treatments that might interfere with paint adhesion.

2. Fill vent and drain holes that are exposed in the finished Work, unless indicated to remain as weep holes, by plugging with zinc solder and filing off smooth.

C. Preparation for Shop Priming: Prepare uncoated ferrous-metal surfaces to comply with SSPC-SP 3, "Power Tool Cleaning."

D. Apply shop primer to uncoated surfaces of metal stair components, except those with galvanized finishes and those to be embedded in concrete or masonry unless otherwise indicated. Comply with SSPC-PA 1, "Paint Application Specification No. 1: Shop, Field, and Maintenance Painting of Steel," for shop painting.

PART 3 - EXECUTION

3.1 INSTALLING METAL PAN STAIRS

A. Fastening to In-Place Construction: Provide anchorage devices and fasteners where necessary for securing metal stairs to in-place construction. Include threaded fasteners for concrete and masonry inserts, through-bolts, lag bolts, and other connectors.

B. Cutting, Fitting, and Placement: Perform cutting, drilling, and fitting required for installing metal stairs. Set units accurately in location, alignment, and elevation, measured from established lines and levels and free of rack.

C. Install metal stairs by welding stair framing to steel structure or to weld plates cast into concrete unless otherwise indicated.

D. Provide temporary bracing or anchors in formwork for items that are to be built into concrete, masonry, or similar construction.

E. Fit exposed connections accurately together to form hairline joints. Weld connections that are not to be left as exposed joints but cannot be shop welded because of shipping size limitations. Do not weld, cut, or abrade surfaces of exterior units that have been hot-dip galvanized after fabrication and are for bolted or screwed field connections.

F. Field Welding: Comply with requirements for welding in "Fabrication, General" Article.

G. Place and finish concrete fill for treads and platforms to comply with Section 03 3000 "Cast-in-Place Concrete."

1. Install abrasive nosings with anchors fully embedded in concrete. Center nosings on tread width.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS METAL PAN STAIRS HNTB Project No. 66765 055113 - 8 12/29/2017 ©HNTB Corporation 2017

3.2 INSTALLING RAILINGS

A. Adjust railing systems before anchoring to ensure matching alignment at abutting joints. Space posts at spacing indicated or, if not indicated, as required by design loads. Plumb posts in each direction. Secure posts and rail ends to building construction as follows:

1. Anchor posts to steel by welding or bolting to steel supporting members. 2. Anchor handrail ends to concrete and masonry with steel round flanges welded to rail

ends and anchored with postinstalled anchors and bolts.

B. Attach handrails to wall with wall brackets. Locate brackets as indicated or, if not indicated, at spacing required to support structural loads. Secure wall brackets to building construction as follows:

1. For concrete and solid masonry anchorage, use drilled-in expansion shields and hanger or lag bolts.

2. For hollow masonry anchorage, use toggle bolts. 3. For steel-framed partitions, use self-tapping screws fastened to steel framing or to

concealed steel reinforcements.

3.3 ADJUSTING AND CLEANING

A. Touchup Painting: Cleaning and touchup painting of field welds, bolted connections, and abraded areas of shop paint are specified in Section 09 9600 "High-Performance Coatings."

B. Galvanized Surfaces: Clean field welds, bolted connections, and abraded areas and repair galvanizing to comply with ASTM A 780/A 780M.

END OF SECTION 05 5113

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS PIPE AND TUBE RAILINGS HNTB Project No. 66765 055213 - 1 12/29/2017 ©HNTB Corporation 2017

SECTION 05 5213 - PIPE AND TUBE RAILINGS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Steel pipe and tube railings.

B. Related Requirements:

1. Section 05 7300 "Decorative Metal Railings" for ornamental railings.

1.3 COORDINATION

A. Coordinate selection of shop primers with topcoats to be applied over them. Comply with paint and coating manufacturers' written recommendations to ensure that shop primers and topcoats are compatible with one another.

B. Coordinate installation of anchorages for railings. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation.

C. Schedule installation so wall attachments are made only to completed walls. Do not support railings temporarily by any means that do not satisfy structural performance requirements.

1.4 ACTION SUBMITTALS

A. Product Data: For the following:

1. Manufacturer's product lines of mechanically connected railings. 2. Railing brackets. 3. Grout, anchoring cement, and paint products.

B. Shop Drawings: Include plans, elevations, sections, details, and attachments to other work.

C. Samples: For each type of exposed finish required.

1. Sections of each distinctly different linear railing member, including handrails, top rails, posts, and balusters.

2. Fittings and brackets.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS PIPE AND TUBE RAILINGS HNTB Project No. 66765 055213 - 2 12/29/2017 ©HNTB Corporation 2017

3. Assembled Sample of railing system, made from full-size components, including top rail, post, handrail, and infill. Sample need not be full height.

a. Show method of connecting and finishing members at intersections.

D. Delegated-Design Submittal: For railings, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation.

1.5 INFORMATIONAL SUBMITTALS

A. Qualification Data: For testing agency.

B. Welding certificates.

C. Paint Compatibility Certificates: From manufacturers of topcoats applied over shop primers certifying that shop primers are compatible with topcoats.

D. Product Test Reports: For pipe and tube railings, for tests performed by a qualified testing agency, according to ASTM E 894 and ASTM E 935.

E. Evaluation Reports: For post-installed anchors, from ICC-ES.

1.6 QUALITY ASSURANCE

A. Welding Qualifications: Qualify procedures and personnel according to the following:

1. AWS D1.1/D1.1M, "Structural Welding Code - Steel."

1.7 DELIVERY, STORAGE, AND HANDLING

A. Protect mechanical finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipping.

1.8 FIELD CONDITIONS

A. Field Measurements: Verify actual locations of walls and other construction contiguous with metal fabrications by field measurements before fabrication.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Delegated Design: Engage a qualified professional engineer, as defined in Section 01 4000 "Quality Requirements," to design railings, including attachment to building construction.

B. Structural Performance: Railings, including attachment to building construction, shall withstand the effects of gravity loads and the following loads and stresses within limits and under conditions indicated:

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS PIPE AND TUBE RAILINGS HNTB Project No. 66765 055213 - 3 12/29/2017 ©HNTB Corporation 2017

1. Handrails and Top Rails of Guards:

a. Uniform load of 50 lbf/ ft. applied in any direction. b. Concentrated load of 200 lbf applied in any direction. c. Uniform and concentrated loads need not be assumed to act concurrently.

C. Thermal Movements: Allow for thermal movements from ambient and surface temperature changes.

1. Temperature Change: 120 deg F, ambient; 180 deg F.

2.2 METALS, GENERAL

A. Metal Surfaces, General: Provide materials with smooth surfaces, without seam marks, roller marks, rolled trade names, stains, discolorations, or blemishes.

B. Brackets, Flanges, and Anchors: Cast or formed metal of same type of material and finish as supported rails unless otherwise indicated.

1. Provide type of bracket with flange tapped for concealed anchorage to threaded hanger bolt and that provides 1-1/2-inch clearance from inside face of handrail to finished wall surface.

2.3 STEEL AND IRON

A. Tubing: ASTM A 500 (cold formed) or ASTM A 513.

B. Pipe: ASTM A 53/A 53M, Type F or Type S, Grade A, Standard Weight (Schedule 40), unless another grade and weight are required by structural loads.

1. Provide galvanized finish for exterior installations and where indicated.

C. Plates, Shapes, and Bars: ASTM A 36/A 36M.

D. Cast Iron: Either gray iron, ASTM A 48/A 48M, or malleable iron, ASTM A 47/A 47M, unless otherwise indicated.

2.4 FASTENERS

A. General: Provide the following:

1. Ungalvanized-Steel Railings: Plated steel fasteners complying with ASTM B 633 or ASTM F 1941, Class Fe/Zn 5 for zinc coating.

2. Hot-Dip Galvanized Railings: Type 304 stainless-steel or hot-dip zinc-coated steel fasteners complying with ASTM A 153/A 153M or ASTM F 2329 for zinc coating.

3. Provide exposed fasteners with finish matching appearance, including color and texture, of railings.

B. Fasteners for Anchoring Railings to Other Construction: Select fasteners of type, grade, and class required to produce connections suitable for anchoring railings to other types of construction indicated and capable of withstanding design loads.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS PIPE AND TUBE RAILINGS HNTB Project No. 66765 055213 - 4 12/29/2017 ©HNTB Corporation 2017

C. Fasteners for Interconnecting Railing Components:

1. Provide concealed fasteners for interconnecting railing components and for attaching them to other work, unless otherwise indicated.

2. Provide tamper-resistant flat-head machine screws for exposed fasteners unless otherwise indicated.

D. Post-Installed Anchors: Torque-controlled expansion anchors or chemical anchors capable of sustaining, without failure, a load equal to 6 times the load imposed when installed in unit masonry and 4 times the load imposed when installed in concrete, as determined by testing according to ASTM E 488/E 488M, conducted by a qualified independent testing agency.

1. Material for Interior Locations: Carbon-steel components zinc-plated to comply with ASTM B 633 or ASTM F 1941, Class Fe/Zn 5, unless otherwise indicated.

2. Material for Exterior Locations and Where Stainless Steel Is Indicated: Alloy Group 1 (A1) stainless-steel bolts, ASTM F 593 (ASTM F 738M), and nuts, ASTM F 594 (ASTM F 836M).

2.5 MISCELLANEOUS MATERIALS

A. Welding Rods and Bare Electrodes: Select according to AWS specifications for metal alloy welded.

B. Etching Cleaner for Galvanized Metal: Complying with MPI#25.

C. Galvanizing Repair Paint: High-zinc-dust-content paint complying with SSPC-Paint 20 and compatible with paints specified to be used over it.

D. Shop Primers: Provide primers that comply with Section 09 9113 "Exterior Painting" and Section 09 9123 "Interior Painting."

E. Shop Primer for Galvanized Steel: Primer formulated for exterior use over zinc-coated metal and compatible with finish paint systems indicated.

F. Intermediate Coats and Topcoats: Provide products that comply with Section 09 9113 "Exterior Painting" and Section 09 9123 "Interior Painting."

G. Bituminous Paint: Cold-applied asphalt emulsion complying with ASTM D 1187/D 1187M.

H. Nonshrink, Nonmetallic Grout: Factory-packaged, nonstaining, noncorrosive, nongaseous grout complying with ASTM C 1107/C 1107M. Provide grout specifically recommended by manufacturer for interior and exterior applications. No Gypsum content allowed.

2.6 FABRICATION

A. General: Fabricate railings to comply with requirements indicated for design, dimensions, member sizes and spacing, details, finish, and anchorage, but not less than that required to support structural loads.

B. Shop assemble railings to greatest extent possible to minimize field splicing and assembly. Disassemble units only as necessary for shipping and handling limitations. Clearly mark units for reassembly and coordinated installation. Use connections that maintain structural value of joined pieces.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS PIPE AND TUBE RAILINGS HNTB Project No. 66765 055213 - 5 12/29/2017 ©HNTB Corporation 2017

C. Cut, drill, and punch metals cleanly and accurately. Remove burrs and ease edges to a radius of approximately 1/32 inch (1 mm) unless otherwise indicated. Remove sharp or rough areas on exposed surfaces.

D. Form work true to line and level with accurate angles and surfaces.

E. Fabricate connections that are exposed to weather in a manner that excludes water. Provide weep holes where water may accumulate.

F. Cut, reinforce, drill, and tap as indicated to receive finish hardware, screws, and similar items.

G. Connections: Fabricate railings with either welded or nonwelded connections unless otherwise indicated.

H. Welded Connections: Cope components at connections to provide close fit, or use fittings designed for this purpose. Weld all around at connections, including at fittings.

1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals.

2. Obtain fusion without undercut or overlap. 3. Remove flux immediately. 4. At exposed connections, finish exposed surfaces smooth and blended so no roughness

shows after finishing and welded surface matches contours of adjoining surfaces.

I. Nonwelded Connections: Connect members with concealed mechanical fasteners and fittings. Fabricate members and fittings to produce flush, smooth, rigid, hairline joints.

1. Fabricate splice joints for field connection using an epoxy structural adhesive if this is manufacturer's standard splicing method.

J. Form Changes in Direction as Follows:

1. By bending or by inserting prefabricated elbow fittings.

K. For changes in direction made by bending, use jigs to produce uniform curvature for each repetitive configuration required. Maintain cross section of member throughout entire bend without buckling, twisting, cracking, or otherwise deforming exposed surfaces of components.

L. Close exposed ends of railing members with prefabricated end fittings.

M. Provide wall returns at ends of wall-mounted handrails unless otherwise indicated. Close ends of returns unless clearance between end of rail and wall is 1/4 inch (6 mm) or less.

N. Brackets, Flanges, Fittings, and Anchors: Provide wall brackets, flanges, miscellaneous fittings, and anchors to interconnect railing members to other work unless otherwise indicated.

1. At brackets and fittings fastened to plaster or gypsum board partitions, provide crush-resistant fillers or other means to transfer loads through wall finishes to structural supports and prevent bracket or fitting rotation and crushing of substrate.

O. Provide inserts and other anchorage devices for connecting railings to concrete or masonry work. Fabricate anchorage devices capable of withstanding loads imposed by railings. Coordinate anchorage devices with supporting structure.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS PIPE AND TUBE RAILINGS HNTB Project No. 66765 055213 - 6 12/29/2017 ©HNTB Corporation 2017

P. For railing posts set in concrete, provide stainless-steel sleeves not less than 6 inches (150 mm) long with inside dimensions not less than 1/2 inch (13 mm) greater than outside dimensions of post, with metal plate forming bottom closure.

Q. For removable railing posts, fabricate slip-fit sockets from stainless-steel tube or pipe whose ID is sized for a close fit with posts; limit movement of post without lateral load, measured at top, to not more than one-fortieth of post height. Provide socket covers designed and fabricated to resist being dislodged.

1. Provide chain with eye, snap hook, and staple across gaps formed by removable railing sections at locations indicated. Fabricate from same metal as railings.

R. Toe Boards: Where indicated, provide toe boards at railings around openings and at edge of open-sided floors and platforms. Fabricate to dimensions and details indicated.

2.7 STEEL AND IRON FINISHES

A. Galvanized Railings:

1. Hot-dip galvanize exterior steel railings, including hardware, after fabrication. 2. Comply with ASTM A 123/A 123M for hot-dip galvanized railings. 3. Comply with ASTM A 153/A 153M for hot-dip galvanized hardware. 4. Do not quench or apply post galvanizing treatments that might interfere with paint

adhesion. 5. Fill vent and drain holes that are exposed in the finished Work, unless indicated to remain

as weep holes, by plugging with zinc solder and filing off smooth.

B. For galvanized railings, provide hot-dip galvanized fittings, brackets, fasteners, sleeves, and other ferrous components.

C. Preparing Galvanized Railings for Shop Priming: After galvanizing, thoroughly clean railings of grease, dirt, oil, flux, and other foreign matter, and treat with etching cleaner.

D. For nongalvanized-steel railings, provide nongalvanized ferrous-metal fittings, brackets, fasteners, and sleeves; however, galvanize anchors to be embedded in exterior concrete or masonry.

E. Preparation for Shop Priming: Prepare uncoated ferrous-metal surfaces to comply with requirements indicated below:

1. Exterior Railings: SSPC-SP 6/NACE No. 3, "Commercial Blast Cleaning." 2. Other Railings: SSPC-SP 3, "Power Tool Cleaning."

F. Primer Application: Apply shop primer to prepared surfaces of railings unless otherwise indicated. Comply with requirements in SSPC-PA 1, "Shop, Field, and Maintenance Painting of Steel," for shop painting. Primer need not be applied to surfaces to be embedded in concrete or masonry.

1. Shop prime uncoated railings with primers specified in Section 09 9600 "High-Performance Coatings" unless indicated.

2. Do not apply primer to galvanized surfaces.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS PIPE AND TUBE RAILINGS HNTB Project No. 66765 055213 - 7 12/29/2017 ©HNTB Corporation 2017

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine plaster and gypsum board assemblies, where reinforced to receive anchors, to verify that locations of concealed reinforcements are clearly marked for Installer. Locate reinforcements and mark locations if not already done.

3.2 INSTALLATION, GENERAL

A. Fit exposed connections together to form tight, hairline joints.

B. Perform cutting, drilling, and fitting required for installing railings. Set railings accurately in location, alignment, and elevation; measured from established lines and levels and free of rack.

1. Do not weld, cut, or abrade surfaces of railing components that are coated or finished after fabrication and that are intended for field connection by mechanical or other means without further cutting or fitting.

2. Set posts plumb within a tolerance of 1/16 inch in 3 feet (2 mm in 1 m). 3. Align rails so variations from level for horizontal members and variations from parallel

with rake of steps and ramps for sloping members do not exceed 1/4 inch in 12 feet (6 mm in 3.5 m).

C. Control of Corrosion: Prevent galvanic action and other forms of corrosion by insulating metals and other materials from direct contact with incompatible materials.

D. Adjust railings before anchoring to ensure matching alignment at abutting joints.

E. Fastening to In-Place Construction: Use anchorage devices and fasteners where necessary for securing railings and for properly transferring loads to in-place construction.

3.3 RAILING CONNECTIONS

A. Nonwelded Connections: Use mechanical or adhesive joints for permanently connecting railing components. Seal recessed holes of exposed locking screws using plastic cement filler colored to match finish of railings.

B. Welded Connections: Use fully welded joints for permanently connecting railing components. Comply with requirements for welded connections in "Fabrication" Article whether welding is performed in the shop or in the field.

C. Expansion Joints: Install expansion joints at locations indicated but not farther apart than required to accommodate thermal movement. Provide slip-joint internal sleeve extending 2 inches (50 mm) beyond joint on either side, fasten internal sleeve securely to one side, and locate joint within 6 inches (150 mm) of post.

3.4 ANCHORING POSTS

A. Use metal sleeves preset and anchored into concrete for installing posts. After posts are inserted into sleeves, fill annular space between post and sleeve with nonshrink, nonmetallic grout, mixed and placed to comply with anchoring material manufacturer's written instructions.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS PIPE AND TUBE RAILINGS HNTB Project No. 66765 055213 - 8 12/29/2017 ©HNTB Corporation 2017

B. Form or core-drill holes not less than 5 inches (125 mm) deep and 3/4 inch (20 mm) larger than OD of post for installing posts in concrete. Clean holes of loose material, insert posts, and fill annular space between post and concrete with nonshrink, nonmetallic grout, mixed and placed to comply with anchoring material manufacturer's written instructions.

C. Cover anchorage joint with flange of same metal as post, attached to post with set screws.

D. Leave anchorage joint exposed with anchoring material flush with adjacent surface.

E. Anchor posts to metal surfaces with oval flanges, angle type, or floor type as required by conditions, connected to posts and to metal supporting members as follows: 1. For steel pipe railings, weld flanges to post and bolt to metal supporting surfaces.

F. Install removable railing sections, where indicated, in slip-fit metal sockets cast in concrete.

3.5 ATTACHING RAILINGS

A. Anchor railing ends at walls with round flanges anchored to wall construction and welded to railing ends or connected to railing ends using nonwelded connections.

B. Attach railings to wall with wall brackets, except where end flanges are used. Locate brackets as indicated or, if not indicated, at spacing required to support structural loads.

C. Secure wall brackets and railing end flanges to building construction as follows: 1. For concrete and solid masonry anchorage, use drilled-in expansion shields and hanger

or lag bolts. 2. For hollow masonry anchorage, use toggle bolts. 3. For steel-framed partitions, use hanger or lag bolts set intowood backing between studs.

Coordinate with stud installation to locate backing members.

3.6 ADJUSTING AND CLEANING

A. Touchup Painting: Immediately after erection, clean field welds, bolted connections, and abraded areas of shop paint, and paint exposed areas with the same material as used for shop painting to comply with SSPC-PA 1 requirements for touching up shop-painted surfaces. 1. Apply by brush or spray to provide a minimum 2.0-mil (0.05-mm) dry film thickness.

B. Touchup Painting: Cleaning and touchup painting of field welds, bolted connections, and abraded areas of shop paint are specified in Section 09 9113 "Exterior Painting" and Section 09 9123 "Interior Painting."

C. Galvanized Surfaces: Clean field welds, bolted connections, and abraded areas, and repair galvanizing to comply with ASTM A 780/A 780M.

3.7 PROTECTION

A. Protect finishes of railings from damage during construction period with temporary protective coverings approved by railing manufacturer. Remove protective coverings at time of Substantial Completion.

END OF SECTION 05 5213

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE METAL HNTB Project No. 66765 057000 - 1 12/29/2017 ©HNTB Corporation 2017

SECTION 057000 - DECORATIVE METAL

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Decorative custom drink rails. 2. Metal reveals at wall paneling.

B. Related Requirements:

1. Section 057300 "Decorative Metal Railings" for decorative metal railings. 2. Section 057500 "Decorative Formed Metal" for decorative metal items made from sheet

metal.

1.3 COORDINATION

A. Coordinate installation of anchorages for decorative metal items. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation.

1.4 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1.5 ACTION SUBMITTALS

A. Product Data: For each type of product, including finishing materials.

B. Sustainable Design Submittals:

1. Product Data for Credit MR 4: For products having recycled content, provide documentation indicating percentages by weight of post-consumer and pre-consumer recycled content. Include statement indicating costs for each product having recycled content.

2. Product Data for Credit MR 5: For products and materials that comply with requirements for regional materials, provide documentation indicating location and distance from Project of material manufacturer and point of extraction, harvest, or recovery for each raw material. Include statement indicating cost for each regional material and the fraction by

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE METAL HNTB Project No. 66765 057000 - 2 12/29/2017 ©HNTB Corporation 2017

weight that is considered regionalShop Drawings: Show fabrication and installation details for decorative metal.

3. Include plans, elevations, component details, and attachment details. 4. Indicate materials and profiles of each decorative metal member, fittings, joinery, finishes,

fasteners, anchorages, and accessory items.

C. Patterns, Models, or Plaster Castings: Made from proposed patterns for each design of custom casting required.

D. Samples for Initial Selection: For products involving selection of color, texture, or design including mechanical finishes.

E. Samples for Verification: For each type of exposed finish.

1. Sections of linear shapes.

1.6 INFORMATIONAL SUBMITTALS

A. Qualification Data: For fabricator.

B. Mill Certificates: Signed by manufacturers of stainless-steel certifying that products furnished comply with requirements.

C. Welding certificates.

1.7 QUALITY ASSURANCE

A. Fabricator Qualifications: A firm experienced in producing decorative metal similar to that indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

B. Installer Qualifications: Fabricator of products.

C. Welding Qualifications: Qualify procedures and personnel according to the following:

1. AWS D1.1/D1.1M, "Structural Welding Code - Steel." 2. AWS D1.2/D1.2M, "Structural Welding Code - Aluminum." 3. AWS D1.3/D1.3M, "Structural Welding Code - Sheet Steel." 4. AWS D1.6/D1.6M, "Structural Welding Code - Stainless Steel."

D. Mockups: Build mockups to verify selections made under Sample submittals, to demonstrate aesthetic effects, and to set quality standards for fabrication and installation.

1. Subject to compliance with requirements, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion.

1.8 DELIVERY, STORAGE, AND HANDLING

A. Store decorative metal in a well-ventilated area, away from uncured concrete and masonry, and protected from weather, moisture, soiling, abrasion, extreme temperatures, and humidity.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE METAL HNTB Project No. 66765 057000 - 3 12/29/2017 ©HNTB Corporation 2017

B. Deliver and store cast-metal products in wooden crates surrounded by enough packing material to ensure that products are not cracked or otherwise damaged.

1.9 FIELD CONDITIONS

A. Field Measurements: Verify actual locations of walls and other construction contiguous with decorative metal by field measurements before fabrication and indicate measurements on Shop Drawings.

PART 2 - PRODUCTS

2.1 METALS, GENERAL

A. Metal Surfaces, General: Use materials with smooth, flat surfaces unless otherwise indicated. Use materials without seam marks, roller marks, rolled trade names, stains, discolorations, or blemishes.

2.2 ALUMINUM

A. Fabricate products from alloy and temper recommended by aluminum producer and finisher for type of use and finish indicated, and with strength and durability properties for each aluminum form required not less than that of alloy and temper designated below.

B. Bars and Shapes: ASTM B 221, Alloy 6063-T5/T52.

C. Pipe and Round Tubing: ASTM B 429/B 429M, Alloy 6063-T6.

D. Tubing: ASTM B 210, Alloy 6063-T832.

E. Plate and Sheet: ASTM B 209.

F. Forgings: ASTM B 247, Alloy 6061-T6.

G. Castings: ASTM B 26/B 26M, Alloy A356.0-T6.

2.3 STAINLESS STEEL

A. Tubing: ASTM A 554, Grade MT 304.

B. Pipe: ASTM A 312/A 312M, Grade TP 304.

C. Castings: ASTM A 743/A 743M, Grade CF 8 or Grade CF 20.

D. Sheet, Strip, Plate, and Flat Bar: ASTM A 666, Type 304.

E. Bars and Shapes: ASTM A 276, Type 304.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE METAL HNTB Project No. 66765 057000 - 4 12/29/2017 ©HNTB Corporation 2017

2.4 STEEL AND IRON

A. Tubing: ASTM A 500/A 500M (cold formed) or ASTM A 513, Type 5 (mandrel drawn).

B. Bars: Hot-rolled, carbon steel complying with ASTM A 29/A 29M, Grade 1010.

C. Plates, Shapes, and Bars: ASTM A 36/A 36M.

D. Cast Iron: Either gray iron, ASTM A 48/A 48M, or malleable iron, ASTM A 47/A 47M unless otherwise indicated.

E. Steel Sheet, Cold Rolled: ASTM A 1008/A 1008M, either commercial steel or structural steel, exposed.

2.5 FASTENERS

A. Fastener Materials: Unless otherwise indicated, provide the following:

1. Aluminum Items: Type 304 stainless-steel fasteners. 2. Stainless-Steel Items: Type 304 stainless-steel fasteners. 3. Uncoated-Steel Items: Plated steel fasteners complying with ASTM B 633,

Class Fe/Zn 25 for electrodeposited zinc coating where concealed, Type 304 stainless-steel fasteners where exposed.

4. Galvanized-Steel Items: Plated steel fasteners complying with ASTM B 633, Class Fe/Zn 25 for electrodeposited zinc coating.

5. Dissimilar Metals: Type 304 stainless-steel fasteners.

B. Fasteners for Anchoring to Other Construction: Unless otherwise indicated, select fasteners of type, grade, and class required to produce connections suitable for anchoring indicated items to other types of construction indicated.

C. Provide concealed fasteners for interconnecting components and for attaching decorative metal items to other work unless otherwise indicated.

D. Post-Installed Anchors: Fastener systems with an evaluation report acceptable to authorities having jurisdiction, based on ICC-ES AC193.

1. Material for Interior Locations: Carbon-steel components zinc plated to comply with ASTM B 633 or ASTM F 1941, Class Fe/Zn 5 unless otherwise indicated.

2. Material for Exterior Locations and Where Stainless Steel Is Indicated: Alloy Group 1 stainless-steel bolts, ASTM F 593, and nuts, ASTM F 594.

2.6 MISCELLANEOUS MATERIALS

A. Welding Rods and Bare Electrodes: Select according to AWS specifications for metal alloy welded.

1. For aluminum, provide type and alloy as recommended by producer of metal to be welded and as required for color match, strength, and compatibility in fabricated items.

B. Etching Cleaner for Galvanized Metal: Complying with MPI#25.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE METAL HNTB Project No. 66765 057000 - 5 12/29/2017 ©HNTB Corporation 2017

C. Galvanizing Repair Paint: High-zinc-dust-content paint complying with SSPC-Paint 20 and compatible with paints specified to be used over it.

D. Shop Primers: Provide primers that comply with Section 099123 "Interior Painting" and Section 099600 "High-Performance Coatings."

E. Bituminous Paint: Cold-applied asphalt emulsion complying with ASTM D 1187/D 1187M.

2.7 FABRICATION, GENERAL

A. Assemble items in the shop to greatest extent possible to minimize field splicing and assembly. Disassemble units only as necessary for shipping and handling limitations. Clearly mark units for reassembly and coordinated installation. Use connections that maintain structural value of joined pieces.

B. Form decorative metal to required shapes and sizes, true to line and level with true curves and accurate angles and surfaces. Finish exposed surfaces to smooth, sharp, well-defined lines and arris.

C. Form bent-metal corners to smallest radius possible without causing grain separation or otherwise impairing the Work.

D. Form simple and compound curves in bars, pipe, tubing, and extruded shapes by bending members in jigs to produce uniform curvature for each configuration required; maintain cross section of member throughout entire bend without buckling, twisting, cracking, or otherwise deforming exposed surfaces.

E. Cut, drill, and punch metals cleanly and accurately. Remove burrs and ease edges to a radius of approximately 1/32 inch unless otherwise indicated. Remove sharp or rough areas on exposed surfaces.

F. Mill joints to a tight, hairline fit. Cope or miter corner joints. Fabricate connections that will be exposed to weather in a manner to exclude water.

G. Provide weep holes where water may accumulate. Locate weep holes in inconspicuous locations.

H. Provide necessary rebates, lugs, and brackets to assemble units and to attach to other work. Cut, reinforce, drill, and tap as needed to receive finish hardware, screws, and similar items unless otherwise indicated.

I. Comply with AWS for recommended practices in shop welding. Weld behind finished surfaces without distorting or discoloring exposed side. Clean exposed welded joints of flux, and dress exposed and contact surfaces.

1. Where welding cannot be concealed behind finished surfaces, finish joints to comply with NOMMA's "Voluntary Joint Finish Standards" for Type 1 Welds: no evidence of a welded joint.

J. Provide castings that are sound and free of warp, cracks, blowholes, or other defects that impair strength or appearance. Grind, wire brush, sandblast, and buff castings to remove seams, gate marks, casting flash, and other casting marks.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE METAL HNTB Project No. 66765 057000 - 6 12/29/2017 ©HNTB Corporation 2017

2.8 METAL REVEALS

A. Fabricate metal reveals for wood paneling from 3/4-by-3/4-by-0.025-inch brake-formed, stainless-steel channels. Drill for mounting screws 6 inches from ends of channels and not more than 24 inches o.c. Locate mounting screws at same heights for all channels. Provide black-finished, hex-socket, wafer-head screws for mounting reveals.

2.9 FINISHES, GENERAL

A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for recommendations for applying and designating finishes.

B. Protect mechanical finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipping.

2.10 ALUMINUM FINISHES

A. Finish designations prefixed by AA comply with the system established by the Aluminum Association for designating aluminum finishes.

B. Clear Anodic Finish: AAMA 611, AA-M12C22A41, Class I, 0.018 mm or thicker.

C. Baked-Enamel or Powder-Coat Finish: AAMA 2603 except with a minimum dry film thickness of 1.5 mils. Comply with coating manufacturer's written instructions for cleaning, conversion coating, and applying and baking finish.

1. Color and Gloss: As selected by Architect from manufacturer's full range.

D. High-Performance Organic Finish: Three-coat fluoropolymer finish complying with AAMA 2605 and containing not less than 70 percent PVDF resin by weight in color coat. Prepare, pretreat, and apply coating to exposed metal surfaces to comply with coating and resin manufacturers' written instructions.

1. Color and Gloss: As selected by Architect from manufacturer's full range.

2.11 STAINLESS-STEEL FINISHES

A. Surface Preparation: Remove tool and die marks and stretch lines, or blend into finish.

B. Directional Satin Finish: No. 4.

C. When polishing is completed, passivate and rinse surfaces. Remove embedded foreign matter and leave surfaces chemically clean.

2.12 STEEL AND IRON FINISHES

A. Galvanizing: Hot-dip galvanize products made from rolled, pressed, and forged steel shapes, castings, plates, bars, and strips indicated to be galvanized to comply with ASTM A 123/A 123M.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE METAL HNTB Project No. 66765 057000 - 7 12/29/2017 ©HNTB Corporation 2017

1. Hot-dip galvanize steel and iron hardware indicated to be galvanized to comply with ASTM A 153/A 153M.

2. Do not quench or apply post-galvanizing treatments that might interfere with paint adhesion.

3. Fill vent and drain holes that will be exposed in finished Work, unless indicated to remain as weep holes, by plugging with zinc solder and filing off smooth.

B. Preparing Galvanized Items for Shop Priming: After galvanizing, thoroughly clean decorative metal of grease, dirt, oil, flux, and other foreign matter, and treat with etching cleaner.

C. Preparing Nongalvanized Items for Shop Priming: Prepare uncoated ferrous-metal surfaces to comply with SSPC-SP 6/NACE No. 3, "Commercial Blast Cleaning."

D. Primer Application: Apply shop primer to prepared surfaces of items unless otherwise indicated. Comply with requirements in SSPC-PA 1, "Paint Application Specification No. 1: Shop, Field, and Maintenance Painting of Steel," for shop painting. Primer need not be applied to surfaces to be embedded in concrete or masonry.

1. Shop prime uncoated ferrous-metal surfaces with primers specified in Section 099123 "Interior Painting." unless primers specified in Section 099600 "High-Performance Coatings" are indicated.

2. Do not apply primer to galvanized surfaces.

E. Shop-Painted Finish: Comply with Section 099600 "High-Performance Coatings."

1. Color: As selected by Architect from manufacturer's full range.

F. Powder-Coat Finish: Prepare, treat, and coat galvanized metal to comply with resin manufacturer's written instructions and as follows:

1. Prepare galvanized metal by thoroughly removing grease, dirt, oil, flux, and other foreign matter.

2. Treat prepared metal with zinc-phosphate pretreatment, rinse, and seal surfaces. 3. Apply thermosetting polyester or acrylic urethane powder coating with cured-film

thickness not less than 1.5 mils. 4. Color: As selected by Architect from manufacturer's full range.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates and conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of decorative metal.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 INSTALLATION, GENERAL

A. Provide anchorage devices and fasteners where needed to secure decorative metal to in-place construction.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE METAL HNTB Project No. 66765 057000 - 8 12/29/2017 ©HNTB Corporation 2017

B. Perform cutting, drilling, and fitting required to install decorative metal. Set products accurately in location, alignment, and elevation, measured from established lines and levels. Provide temporary bracing or anchors in formwork for items to be built into concrete, masonry, or similar construction.

C. Fit exposed connections accurately together to form tight, hairline joints or, where indicated, uniform reveals and spaces for sealants and joint fillers. Where cutting, welding, and grinding are required for proper shop fitting and jointing of decorative metal, restore finishes to eliminate evidence of such corrective work.

D. Do not cut or abrade finishes that cannot be completely restored in the field. Return items with such finishes to the shop for required alterations, followed by complete refinishing, or provide new units as required.

E. Install concealed gaskets, joint fillers, insulation, and flashings as work progresses.

F. Restore protective coverings that have been damaged during shipment or installation. Remove protective coverings only when there is no possibility of damage from other work yet to be performed at same location.

1. Retain protective coverings intact; remove coverings simultaneously from similarly finished items to preclude nonuniform oxidation and discoloration.

G. Field Welding: Comply with applicable AWS specification for procedures of manual shielded metal arc welding and requirements for welding and for finishing welded connections in "Fabrication, General" Article. Weld connections that are not to be left as exposed joints but cannot be shop welded because of shipping size limitations.

H. Control of Corrosion: Prevent galvanic action and other forms of corrosion by insulating metals and other materials from direct contact with incompatible materials.

1. Coat concealed surfaces of aluminum that will be in contact with grout, concrete, masonry, wood, or dissimilar metals, with a heavy coat of bituminous paint.

3.3 INSTALLING METAL REVEALS AT WALL PANELING

A. Install metal reveals between wood panels as paneling is installed. Secure to wood grounds with specified screws.

3.4 CLEANING AND PROTECTION

A. Unless otherwise indicated, clean metals by washing thoroughly with clean water and soap, rinsing with clean water, and drying with soft cloths.

B. Touchup Painting: Cleaning and touchup painting of field welds, bolted connections, and abraded areas of shop paint are specified in Section 099123 "Interior Painting," and Section 099600 "High-Performance Coatings."

C. Galvanized Surfaces: Clean field welds, bolted connections, and abraded areas and repair galvanizing to comply with ASTM A 780/A 780M.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE METAL HNTB Project No. 66765 057000 - 9 12/29/2017 ©HNTB Corporation 2017

D. Protect finishes of decorative metal from damage during construction period with temporary protective coverings approved by decorative metal fabricator. Remove protective covering at time of Substantial Completion.

E. Restore finishes damaged during installation and construction period so no evidence remains of correction work. Return items that cannot be refinished in the field to the shop; make required alterations and refinish entire unit, or provide new units.

END OF SECTION 057000

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE METAL RAILINGS HNTB Project No. 66765 057300 - 1 12/29/2017 ©HNTB Corporation 2017

SECTION 05 7300 - DECORATIVE METAL RAILINGS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Steel and iron decorative railings with stainless-steel wire-rope guard infill.

B. Related Requirements:

1. Section 05 5113 "Metal Pan Stairs" for stairs requiring decorative metal railings and guards.

1.3 DEFINITIONS

A. Railings: Guards, handrails, and similar devices used for protection of occupants at open-sided floor areas and for pedestrian guidance and support, visual separation, or wall protection.

1.4 COORDINATION AND SCHEDULING

A. Coordinate selection of shop primers with topcoats to be applied over them. Comply with paint and coating manufacturers' written instructions to ensure that shop primers and topcoats are compatible.

B. Coordinate installation of anchorages for railings. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver items to Project site in time for installation.

C. Schedule installation so wall attachments are made only to completed walls. Do not support railings temporarily by any means that do not meet structural performance requirements.

1.5 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1.6 ACTION SUBMITTALS

A. Product Data: For the following:

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE METAL RAILINGS HNTB Project No. 66765 057300 - 2 12/29/2017 ©HNTB Corporation 2017

1. Manufacturer's product lines of railings assembled from standard components. 2. Grout, anchoring cement, and paint products.

B. Shop Drawings: Include plans, elevations, sections, and attachment details.

1. For illuminated railings, include wiring diagrams and roughing-in details.

C. Samples for Initial Selection: For products involving selection of color, texture, or design.

D. Samples for Verification: For each type of exposed finish required.

1. Sections of each distinctly different linear railing member, including handrails, top rails, posts, and balusters.

2. Fittings and brackets. 3. Welded connections. 4. Assembled Samples of railing systems, made from full-size components, including top

rail, post, handrail, and infill. Show method of finishing members at intersections. Samples need not be full height.

E. Delegated-Design Submittal: For installed products indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation.

1.7 INFORMATIONAL SUBMITTALS

A. Qualification Data: For professional engineer.

B. Mill Certificates: Signed by manufacturers of stainless-steel products certifying that products furnished comply with requirements.

C. Welding certificates.

D. Product Test Reports: Based on evaluation of comprehensive tests performed by a qualified testing agency, according to ASTM E 894 and ASTM E 935.

E. Evaluation Reports: For post-installed anchors, from ICC-ES.

1.8 QUALITY ASSURANCE

A. Welding Qualifications: Qualify procedures and personnel according to the following:

1. AWS D1.1/D1.1M, "Structural Welding Code - Steel."

1.9 FIELD CONDITIONS

A. Field Measurements: Verify actual locations of walls and other construction contiguous with railings by field measurements before fabrication and indicate measurements on Shop Drawings.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE METAL RAILINGS HNTB Project No. 66765 057300 - 3 12/29/2017 ©HNTB Corporation 2017

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Steel and Iron Decorative Railings:

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:

a. Blum, Julius & Co., Inc. b. Braun, J. G., Company; The Wagner Companies. c. Livers Bronze Co. d. Wagner, R & B, Inc.

B. Source Limitations: Obtain each type of railing from single source from single manufacturer.

C. Product Options: Information on Drawings and in Specifications establishes requirements for system's aesthetic effects and performance characteristics. Aesthetic effects are indicated by dimensions, arrangements, alignment, and profiles of components and assemblies as they relate to sightlines, to one another, and to adjoining construction. Performance characteristics are indicated by criteria subject to verification by one or more methods, including structural analysis, preconstruction testing, field testing, and in-service performance.

1. Do not modify intended aesthetic effects, as judged solely by Architect, except with Architect's approval. If modifications are proposed, submit comprehensive explanatory data to Architect for review.

2.2 PERFORMANCE REQUIREMENTS

A. Delegated Design: Engage a qualified professional engineer, as defined in Section 01 4000 "Quality Requirements," to design railings, including attachment to building construction.

B. General: In engineering railings to withstand structural loads indicated, determine allowable design working stresses of railing materials based on the following:

1. Aluminum: The lesser of minimum yield strength divided by 1.65 or minimum ultimate tensile strength divided by 1.95.

2. Copper Alloys: 60 percent of minimum yield strength. 3. Stainless Steel: 60 percent of minimum yield strength. 4. Steel: 72 percent of minimum yield strength.

C. Structural Performance: Railings, including attachment to building construction, shall withstand the effects of gravity loads and the following loads and stresses within limits and under conditions indicated:

1. Handrails and Top Rails of Guards:

a. Uniform load of 50 lbf/ft. applied in any direction. b. Concentrated load of 200 lbf applied in any direction. c. Uniform and concentrated loads need not be assumed to act concurrently.

2. Infill of Guards:

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE METAL RAILINGS HNTB Project No. 66765 057300 - 4 12/29/2017 ©HNTB Corporation 2017

a. Concentrated load of 50 lbf applied horizontally on an area of 1 sq. ft.. b. Infill load and other loads need not be assumed to act concurrently.

D. Thermal Movements: Allow for thermal movements from ambient and surface temperature changes acting on exterior railings by preventing buckling, opening of joints, overstressing of components, failure of connections, and other detrimental effects.

1. Temperature Change: 120 deg F, ambient; 180 deg F, material surfaces.

2.3 METALS, GENERAL

A. Metal Surfaces, General: Provide materials with smooth surfaces, without seam marks, roller marks, rolled trade names, stains, discolorations, or blemishes.

B. Brackets, Flanges, and Anchors: Same metal and finish as supported rails unless otherwise indicated.

1. Provide cast-metal brackets with flange tapped for concealed anchorage to threaded hanger bolt.

2. Provide either formed- or cast-metal brackets with predrilled hole for exposed bolt anchorage.

3. Provide formed-steel brackets with predrilled hole for bolted anchorage and with snap-on cover that matches rail finish and conceals bracket base and bolt head.

4. Provide extruded-aluminum brackets with interlocking pieces that conceal anchorage. Locate set screws on bottom of bracket.

2.4 STAINLESS STEEL

A. Wire Rope and Fittings:

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

a. Cable Connection (The). b. Feeney Wire Rope & Rigging. c. Secosouth, Inc.

2. Wire Rope: 1-by-19 wire rope made from wire complying with ASTM A 492, Type 316. 3. Wire-Rope Fittings: Connectors of types indicated, fabricated from stainless steel, and

with capability to sustain, without failure, a load equal to minimum breaking strength of wire rope with which they are used.

2.5 STEEL AND IRON

A. Tubing: ASTM A 500/A 500M (cold formed) or ASTM A 513.

B. Bars: Hot-rolled, carbon steel complying with ASTM A 29/A 29M, Grade 1010.

C. Plates, Shapes, and Bars: ASTM A 36/A 36M.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE METAL RAILINGS HNTB Project No. 66765 057300 - 5 12/29/2017 ©HNTB Corporation 2017

D. Cast Iron: Either gray iron, ASTM A 48/A 48M, or malleable iron, ASTM A 47/A 47M, unless otherwise indicated.

2.6 FASTENERS

A. Fastener Materials: Unless otherwise indicated, provide the following:

1. Stainless-Steel Components: Type 304 stainless-steel fasteners. 2. Uncoated Steel Components: Plated-steel fasteners complying with ASTM B 633,

Class Fe/Zn 25 for electrodeposited zinc coating where concealed; Type 304 stainless-steel fasteners where exposed.

3. Galvanized-Steel Components: Plated-steel fasteners complying with ASTM B 633, Class Fe/Zn 25 for electrodeposited zinc coating.

4. Dissimilar Metals: Type 304 stainless-steel fasteners.

B. Fasteners for Anchoring to Other Construction: Select fasteners of type, grade, and class required to produce connections suitable for anchoring railings to other types of construction indicated and capable of withstanding design loads.

C. Provide concealed fasteners for interconnecting railing components and for attaching railings to other work unless.

D. Post-Installed Anchors: Fastener systems with working capacity greater than or equal to the design load, according to an evaluation report acceptable to authorities having jurisdiction, based on ICC-ES AC193 or ICC-ES AC308.

1. Material for Interior Locations: Carbon-steel components zinc plated to comply with ASTM B 633 or ASTM F 1941, Class Fe/Zn 5, unless otherwise indicated.

2. Material for Exterior Locations and Where Stainless Steel Is Indicated: Alloy Group 1 stainless-steel bolts, ASTM F 593, and nuts, ASTM F 594.

2.7 MISCELLANEOUS MATERIALS

A. Welding Rods and Bare Electrodes: Select according to AWS specifications for metal alloy welded.

1. For aluminum railings, provide type and alloy as recommended by producer of metal to be welded and as required for color match, strength, and compatibility in fabricated items.

B. Galvanizing Repair Paint: High-zinc-dust-content paint complying with SSPC-Paint 20 and compatible with paints specified to be used over it.

C. Nonshrink, Nonmetallic Grout: Factory-packaged, nonstaining, noncorrosive, nongaseous grout complying with ASTM C 1107/C 1107M. Provide grout specifically recommended by manufacturer for interior and exterior applications.

2.8 FABRICATION

A. General: Fabricate railings to comply with requirements indicated for design, dimensions, member sizes and spacing, details, finish, and anchorage, but not less than that required to support structural loads.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE METAL RAILINGS HNTB Project No. 66765 057300 - 6 12/29/2017 ©HNTB Corporation 2017

B. Assemble railings in the shop to greatest extent possible to minimize field splicing and assembly. Disassemble units only as necessary for shipping and handling limitations. Clearly mark units for reassembly and coordinated installation. Use connections that maintain structural value of joined pieces.

C. Make up wire-rope assemblies in the shop to field-measured dimensions with fittings machine swaged. Minimize amount of turnbuckle take-up used for dimensional adjustment so maximum amount is available for tensioning wire ropes. Tag wire-rope assemblies and fittings to identify installation locations and orientations for coordinated installation.

D. Cut, drill, and punch metals cleanly and accurately. Remove burrs and ease edges to a radius of approximately 1/32 inch unless otherwise indicated. Remove sharp or rough areas on exposed surfaces.

E. Form work true to line and level with accurate angles and surfaces.

F. Fabricate connections that will be exposed to weather in a manner to exclude water. Provide weep holes where water may accumulate. Locate weep holes in inconspicuous locations.

G. Cut, reinforce, drill, and tap as indicated to receive finish hardware, screws, and similar items.

H. Connections: Fabricate railings with welded connections unless otherwise indicated.

I. Welded Connections: Cope components at connections to provide close fit, or use fittings designed for this purpose. Weld all around at connections, including at fittings.

1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals.

2. Obtain fusion without undercut or overlap. 3. Remove flux immediately. 4. At exposed connections, finish exposed welds to comply with NOMMA's "Voluntary Joint

Finish Standards" for Type 1 welds; no evidence of a welded joint.

J. Form changes in direction as follows:

1. As detailed.

K. Provide wall returns at ends of wall-mounted handrails unless otherwise indicated. Close ends of returns, unless clearance between end of rail and wall is 1/4 inch or less.

L. Brackets, Flanges, Fittings, and Anchors: Provide wall brackets, flanges, miscellaneous fittings, and anchors to interconnect railing members to other work unless otherwise indicated.

1. At brackets and fittings fastened to plaster or gypsum board partitions, provide crush-resistant fillers, or other means to transfer loads through wall finishes to structural supports and to prevent bracket or fitting rotation and crushing of substrate.

M. Provide inserts and other anchorage devices for connecting railings to concrete or masonry work. Fabricate anchorage devices capable of withstanding loads imposed by railings. Coordinate anchorage devices with supporting structure.

N. For railing posts set in concrete, provide [steel] [stainless-steel] sleeves not less than 6 inches long with inside dimensions not less than 1/2 inch greater than outside dimensions of post, with metal plate forming bottom closure.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE METAL RAILINGS HNTB Project No. 66765 057300 - 7 12/29/2017 ©HNTB Corporation 2017

O. Toe Boards: Where indicated, provide toe boards at railings around openings and at edge of open-sided floors and platforms. Fabricate to dimensions and details indicated.

2.9 GENERAL FINISH REQUIREMENTS

A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" recommendations for applying and designating finishes.

B. Protect mechanical finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipment.

C. Appearance of Finished Work: Noticeable variations in same piece are not acceptable. Variations in appearance of abutting or adjacent pieces are acceptable if they are within one-half of the range of approved Samples. Variations in appearance of other components are acceptable if they are within the range of approved Samples and are assembled or installed to minimize contrast.

D. Provide exposed fasteners with finish matching appearance, including color and texture, of railings.

2.10 STEEL AND IRON FINISHES

A. Galvanized Railings:

1. Hot-dip galvanize exterior steel and iron railings, including hardware, after fabrication. 2. Comply with ASTM A 123/A 123M for hot-dip galvanized railings. 3. Comply with ASTM A 153/A 153M for hot-dip galvanized hardware. 4. Do not quench or apply post-galvanizing treatments that might interfere with paint

adhesion. 5. Fill vent and drain holes that are exposed in the finished Work, unless indicated to remain

as weep holes, by plugging with zinc solder and filing off smooth.

B. For galvanized railings, provide hot-dip galvanized fittings, brackets, fasteners, sleeves, and other ferrous components.

C. Powder-Coat Finish: Prepare, treat, and coat galvanized metal to comply with resin manufacturer's written instructions and as follows:

1. Prepare galvanized metal by thoroughly removing grease, dirt, oil, flux, and other foreign matter.

2. Treat prepared metal with zinc-phosphate pretreatment, rinse, and seal surfaces. 3. Apply thermosetting polyester or acrylic urethane powder coating with cured-film

thickness not less than 1.5 mils. 4. Color: As selected by Architect from manufacturer's full range.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE METAL RAILINGS HNTB Project No. 66765 057300 - 8 12/29/2017 ©HNTB Corporation 2017

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine plaster and gypsum board assemblies, where reinforced to receive anchors, to verify that locations of concealed reinforcements have been clearly marked for Installer. Locate reinforcements and mark locations if not already done.

3.2 INSTALLATION, GENERAL

A. Fit exposed connections together to form tight, hairline joints.

B. Perform cutting, drilling, and fitting required for installing railings. Set railings accurately in location, alignment, and elevation; measured from established lines and levels and free of rack.

1. Do not weld, cut, or abrade surfaces of railing components that have been coated or finished after fabrication and that are intended for field connection by mechanical or other means without further cutting or fitting.

2. Set posts plumb within a tolerance of 1/16 inch in 3 feet. 3. Align rails so variations from level for horizontal members and variations from parallel

with rake of steps and ramps for sloping members do not exceed 1/4 inch in 12 feet.

C. Control of Corrosion: Prevent galvanic action and other forms of corrosion by insulating metals and other materials from direct contact with incompatible materials.

D. Adjust railings before anchoring to ensure matching alignment at abutting joints.

E. Fastening to In-Place Construction: Use anchorage devices and fasteners where necessary for securing railings and for properly transferring loads to in-place construction.

3.3 RAILING CONNECTIONS

A. Welded Connections: Use fully welded joints for permanently connecting railing components. Comply with requirements for welded connections in "Fabrication" Article whether welding is performed in the shop or in the field.

B. Expansion Joints: Install expansion joints at locations indicated but not farther apart than required to accommodate thermal movement. Provide slip-joint internal sleeve extending 2 inches beyond joint on either side, fasten internal sleeve securely to one side, and locate joint within 6 inches of post.

3.4 ANCHORING POSTS

A. Use steel pipe sleeves preset and anchored into concrete for installing posts. After posts have been inserted into sleeves, fill annular space between post and sleeve with nonshrink, nonmetallic grout, mixed and placed to comply with anchoring material manufacturer's written instructions.

B. Form or core-drill holes not less than 5 inches deep and 3/4 inch larger than OD of post for installing posts in concrete. Clean holes of loose material, insert posts, and fill annular space

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE METAL RAILINGS HNTB Project No. 66765 057300 - 9 12/29/2017 ©HNTB Corporation 2017

between post and concrete with nonshrink, nonmetallic grout, mixed and placed to comply with anchoring material manufacturer's written instructions.

C. Leave anchorage joint exposed with 1/8-inch buildup, sloped away from post.

D. Anchor posts to metal surfaces with flanges, angle type, or floor type as required by conditions, connected to posts and to metal supporting members as follows:

1. For steel railings, weld flanges to posts and bolt to metal-supporting surfaces.

E. Install removable railing sections, where indicated, in slip-fit metal sockets cast in concrete.

3.5 ATTACHING RAILINGS

A. Anchor railing ends to concrete and masonry with brackets on underside of rails connected to railing ends and anchored to wall construction with anchors and bolts.

B. Anchor railing ends to metal surfaces with flanges bolted to metal surfaces and welded to railing ends.

C. Attach handrails to walls with wall brackets except where end flanges are used. Provide brackets with 1-1/2-inch clearance from inside face of handrail and finished wall surface. Locate brackets as indicated or, if not indicated, at spacing required to support structural loads.

1. Use type of bracket with flange tapped for concealed anchorage to threaded hanger bolt. 2. Locate brackets as indicated or, if not indicated, at spacing required to support structural

loads.

D. Secure wall brackets and railing end flanges to building construction as follows:

1. For concrete and solid masonry anchorage, use drilled-in expansion shields and hanger or lag bolts.

2. For hollow masonry anchorage, use toggle bolts. 3. For wood stud partitions, use hanger or lag bolts set into wood backing between studs.

Coordinate with carpentry work to locate backing members. 4. For steel-framed partitions, use hanger or lag bolts set into fire-retardant-treated wood

backing between studs. Coordinate with stud installation to locate backing members. 5. For steel-framed partitions, fasten brackets directly to steel framing or concealed steel

reinforcements using self-tapping screws of size and type required to support structural loads.

6. For steel-framed partitions, fasten brackets with toggle bolts installed through flanges of steel framing or through concealed steel reinforcements.

3.6 FIELD QUALITY CONTROL

A. Testing Agency: Owner may engage a qualified testing agency to perform tests and inspections and to prepare test reports. Payment for these services will be made by Owner.

B. Extent and Testing Methodology: Testing agency will randomly select completed railing assemblies for testing that are representative of different railing designs and conditions in the completed Work. Test railings according to ASTM E 894 and ASTM E 935 for compliance with performance requirements.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE METAL RAILINGS HNTB Project No. 66765 057300 - 10 12/29/2017 ©HNTB Corporation 2017

C. Remove and replace railings where test results indicate that they do not comply with specified requirements unless they can be repaired in a manner satisfactory to Architect and comply with specified requirements.

D. Perform additional testing and inspecting, at Contractor's expense, to determine compliance of replaced or additional work with specified requirements.

3.7 PROTECTION

A. Protect finishes of railings from damage during construction period with temporary protective coverings approved by railing manufacturer. Remove protective coverings at time of Substantial Completion.

B. Restore finishes damaged during installation and construction period so no evidence remains of correction work. Return items that cannot be refinished in the field to the shop; make required alterations and refinish entire unit, or provide new units.

END OF SECTION 05 7300

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE FORMED METAL HNTB Project No. 66765 057500 - 1 12/29/2017 ©HNTB Corporation 2017

SECTION 05 7500 - DECORATIVE FORMED METAL

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Beam wraps. 2. Closures and trim. 3. Filler panels between dissimilar construction.

B. Related Requirements:

1. Section 07 6200 "Sheet Metal Flashing and Trim" for items made of formed metal for flashings and trim.

1.3 COORDINATION

A. Coordinate installation of anchorages for decorative formed metal items. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver items to Project site in time for installation.

B. Coordinate installation of decorative formed metal with adjacent construction to ensure that wall assemblies, flashings, trim, and joint sealants, are protected against damage from the effects of weather, age, corrosion, and other causes of deterioration.

1.4 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1.5 ACTION SUBMITTALS

A. Product Data: For each type of product, including finishing materials.

B. Shop Drawings: Show fabrication and installation details for decorative formed metal.

1. Include plans, elevations, component details, and attachment details. 2. Indicate materials and profiles of each decorative formed metal member, fittings, joinery,

finishes, fasteners, anchorages, and accessory items.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE FORMED METAL HNTB Project No. 66765 057500 - 2 12/29/2017 ©HNTB Corporation 2017

C. Samples for Initial Selection: For products involving selection of color, texture, or design, including mechanical finishes.

D. Samples for Verification: For each type of exposed finish required, prepared on 6-inch-square Samples of metal of same thickness and material indicated for the Work.

E. Delegated-Design Submittal: For installed products indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation.

1.6 INFORMATIONAL SUBMITTALS

A. Coordination Drawings: For decorative formed metal elements that house items specified in other Sections. Show dimensions of housed items, including locations of housing penetrations and attachments, and necessary clearances.

B. Qualification Data: For Installer, fabricator, anodic finisher, powder-coating applicator, and professional engineer.

C. Mill Certificates: Signed by stainless-steel manufacturers certifying that products furnished comply with requirements.

D. Evaluation Reports: For post-installed anchors, from ICC-ES.

1.7 CLOSEOUT SUBMITTALS

A. Maintenance Data.

1.8 QUALITY ASSURANCE

A. Fabricator Qualifications: A firm experienced in producing decorative formed metal similar to that indicated for this Project and with a record of successful in-service performance as well as sufficient production capacity to produce required units.

B. Anodic Finisher Qualifications: A firm experienced in successfully applying anodic finishes of type indicated and that employs competent control personnel to conduct continuing, effective quality-control program to ensure compliance with requirements.

C. Installer Qualifications: Fabricator of products.

D. Mockups: Build mockups to verify selections made under Sample submittals, to demonstrate aesthetic effects, and to set quality standards for fabrication and installation.

1. Subject to compliance with requirements, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion.

1.9 DELIVERY, STORAGE, AND HANDLING

A. Deliver decorative formed metal products wrapped in protective coverings and strapped together in suitable packs or in heavy-duty cartons. Remove protective coverings before they stain or bond to finished surfaces.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE FORMED METAL HNTB Project No. 66765 057500 - 3 12/29/2017 ©HNTB Corporation 2017

B. Store products on elevated platforms in a dry location.

1.10 FIELD CONDITIONS

A. Field Measurements: Verify actual locations of walls, columns, beams, and other construction contiguous with decorative formed metal by field measurements before fabrication and indicate measurements on Shop Drawings.

PART 2 - PRODUCTS

2.1 SHEET METAL

A. General: Fabricate products from sheet metal without pitting, seam marks, roller marks, stains, discolorations, or other imperfections where exposed to view on finished units.

B. Aluminum Sheet: Flat sheet complying with ASTM B 209, alloy and temper recommended by aluminum producer and finisher for type of use and finish indicated, and with strength and durability properties of not less than Alloy 5005-H32.

2.2 MISCELLANEOUS MATERIALS

A. Sealants, Interior: Nonsag, paintable, nonstaining, latex sealant complying with ASTM C 834; of type and grade required to seal joints in decorative formed metal; and as recommended in writing by decorative formed metal manufacturer.

B. Fasteners: Fabricated from same basic metal and alloy as fastened metal unless otherwise indicated. Do not use metals that are incompatible with materials joined.

1. Provide concealed fasteners for interconnecting decorative formed metal items and for attaching them to other work unless otherwise indicated.

2. Provide Phillips flat-head machine screws for exposed fasteners unless otherwise indicated.

C. Structural Anchors: For applications indicated to comply with certain design loads, provide fastener systems with working capacity greater than or equal to the design load, according to an evaluation report acceptable to authorities having jurisdiction, based on ICC-ES AC193 or ICC-ES AC308.

D. Nonstructural Anchors: For applications not indicated to comply with design loads, provide fastener systems with an evaluation report acceptable to authorities having jurisdiction, based on ICC-ES AC193 or ICC-ES AC308.

E. Anchor Materials:

1. Material for Interior Locations: Carbon-steel components zinc plated to comply with ASTM B 633 or ASTM F 1941, Class Fe/Zn 5, unless otherwise indicated.

F. Sound-Deadening Materials:

1. Insulation: Unfaced, mineral-fiber blanket insulation complying with ASTM C 665, Type I, and passing ASTM E 136 test.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE FORMED METAL HNTB Project No. 66765 057500 - 4 12/29/2017 ©HNTB Corporation 2017

2. Mastic: Cold-applied asphalt emulsion complying with ASTM D 1187/D 1187M.

G. Backing Materials: Provided or recommended by decorative formed metal manufacturer.

H. Laminating Adhesive: Adhesive recommended by metal fabricator that will fully bond metal to metal, will prevent telegraphing and oil-canning, and is compatible with substrate and noncombustible after curing.

1. Contact Adhesive: VOC content of not more than 80 g/L when calculated according to 40 CFR 59, Subpart D (EPA Method 24).

2. Metal-to-Metal Adhesive: VOC content of not more than 30 g/L when calculated according to 40 CFR 59, Subpart D (EPA Method 24).

3. Multipurpose Construction Adhesive: VOC content of not more than 70 g/L when calculated according to 40 CFR 59, Subpart D (EPA Method 24).

4. Special-Purpose Contact Adhesive: (Contact adhesive used to bond melamine-covered board, metal, unsupported vinyl, ultrahigh molecular weight polyethylene, and rubber or wood veneer, 1/16 inch thick or less, to any surface): 250 g/L.

I. Isolation Coating: Manufacturer's standard alkali-resistant coating.

2.3 FABRICATION, GENERAL

A. Shop Assembly: Preassemble decorative formed metal items in shop to greatest extent possible to minimize field splicing and assembly. Disassemble units only as necessary for shipping and handling limitations. Clearly mark units for reassembly and coordinated installation.

B. Coordinate dimensions and attachment methods of decorative formed metal items with those of adjoining construction to produce integrated assemblies with closely fitting joints and with edges and surfaces aligned unless otherwise indicated.

C. Form metal to profiles indicated, in maximum lengths to minimize joints. Produce flat, flush surfaces without cracking or grain separation at bends. Fold back exposed edges of unsupported sheet metal to form a 1/2-inch-wide hem on the concealed side, or ease edges to a radius of approximately 1/32 inch and support with concealed stiffeners.

D. Increase metal thickness or reinforce with concealed stiffeners, backing materials, or both, as needed to provide surface flatness equivalent to stretcher-leveled standard of flatness and sufficient strength for indicated use.

1. Support joints with concealed stiffeners as needed to hold exposed faces of adjoining sheets in flush alignment.

E. Build in straps, plates, and brackets as needed to support and anchor fabricated items to adjoining construction. Reinforce decorative formed metal items as needed to attach and support other construction.

F. Provide support framing, mounting and attachment clips, splice sleeves, fasteners, and accessories needed to install decorative formed metal items.

G. Where welding or brazing is indicated, weld or braze joints and seams continuously. Grind, fill, and dress to produce smooth, flush, exposed surfaces in which joints are not visible after finishing is completed.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE FORMED METAL HNTB Project No. 66765 057500 - 5 12/29/2017 ©HNTB Corporation 2017

1. Use welding and brazing procedures that will blend with and not cause discoloration of metal being joined.

2.4 BEAM WRAPS

A. Form beam wraps from metal of type and thickness indicated below. Fabricate to fit tightly to adjoining construction.

1. Aluminum Sheet: 0.063 inch.

a. Finish: To match adjacent storefront system.

B. Fabricate with sealant stop angle to retain backer rod and sealant.

2.5 CLOSURES AND TRIM

A. Form closures and trim from metal of type and thickness indicated below. Fabricate to fit tightly to adjoining construction.

1. Aluminum Sheet: 0.063 inch.

a. Finish: Baked enamel or powder coat or clear anodic.

2. Closures and trim may be fabricated from prefinished metal sheet in lieu of finishing after fabrication provided unfinished edges are concealed from view and not exposed to weather.

B. Conceal fasteners where possible; otherwise, locate where they are as inconspicuous as possible. Size fasteners to support closures and trim, with fasteners spaced to prevent buckling or waviness in finished surfaces.

C. Drill and tap holes needed for securing closures and trim to other surfaces.

D. Incorporate gaskets where indicated or needed for concealed, continuous seal at abutting surfaces.

E. Miter or cope trim members at corners and reinforce with bent metal splice plates to form tight joints.

2.6 GENERAL FINISH REQUIREMENTS

A. Complete mechanical finishes of flat sheet metal surfaces before fabrication where possible. After fabrication, finish all joints, bends, abrasions, and other surface blemishes to match sheet finish.

B. Protect mechanical finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipping.

C. Apply organic and anodic finishes to formed metal after fabrication unless otherwise indicated.

D. Finish items indicated on Drawings after assembly.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE FORMED METAL HNTB Project No. 66765 057500 - 6 12/29/2017 ©HNTB Corporation 2017

E. Appearance of Finished Work: Variations in appearance of abutting or adjacent pieces are acceptable if they are within one-half of the range of approved Samples. Noticeable variations in the same piece are not acceptable. Variations in appearance of other components are acceptable if they are within the range of approved Samples and are assembled or installed to minimize contrast.

2.7 ALUMINUM FINISHES

A. Clear Anodic Finish: AAMA 611, AA-M12C22A41, Class I, 0.018 mm or thicker.

B. Baked-Enamel or Powder-Coat Finish: AAMA 2603 except with a minimum dry film thickness of 1.5 mils. Comply with coating manufacturer's written instructions for cleaning, conversion coating, and applying and baking finish.

1. Color and Gloss: As selected by Architect from manufacturer's full range.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of decorative formed metal.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 INSTALLATION

A. Locate and place decorative formed metal items level and plumb and in alignment with adjacent construction. Perform cutting, drilling, and fitting required to install decorative formed metal.

1. Do not cut or abrade finishes that cannot be completely restored in the field. Return items with such finishes to the shop for required alterations, followed by complete refinishing, or provide new units as required.

B. Use concealed anchorages where possible. Provide brass or lead washers fitted to screws where needed to protect metal surfaces and to make a weathertight connection.

C. Form tight joints with exposed connections accurately fitted together. Provide reveals and openings for sealants and joint fillers as indicated.

D. Install concealed gaskets, joint fillers, insulation, sealants, and flashings, as the Work progresses, to make exterior decorative formed metal items weatherproof.

E. Install concealed gaskets, joint fillers, sealants, and insulation, as the Work progresses, to make interior decorative formed metal items soundproof or lightproof as applicable to type of fabrication indicated.

F. Corrosion Protection: Apply bituminous paint or other permanent separation materials on concealed surfaces where metals would otherwise be in direct contact with substrate materials that are incompatible or could result in corrosion or deterioration of either material or finish.

OREGON STATE UNIVERSITY GOSS STADIUM - CLUB AND LOGE SEATING

CORVALIS, OREGON

CONSTRUCTION DOCUMENTS DECORATIVE FORMED METAL HNTB Project No. 66765 057500 - 7 12/29/2017 ©HNTB Corporation 2017

3.3 ADJUSTING AND CLEANING

A. Unless otherwise indicated, clean metals by washing thoroughly with water and soap, rinsing with clean water, and drying with soft cloths.

B. Touchup Painting: Immediately after erection, clean field welds, bolted connections, and abraded areas of shop paint and paint exposed areas with the same material as used for shop painting to comply with SSPC-PA 1 for touching up shop-painted surfaces.

1. Apply by brush or spray to provide a minimum 2.0-mil dry film thickness.

C. Restore finishes damaged during installation and construction period so no evidence remains of correction work. Return items that cannot be refinished in the field to the shop; make required alterations and refinish entire unit or provide new units.

3.4 PROTECTION

A. Protect finishes of decorative formed metal items from damage during construction period. Remove temporary protective coverings at time of Substantial Completion.

END OF SECTION 05 7500