complex connections rick chorley
TRANSCRIPT
132kV Connection
A First for N.S.W Coal Mining
Introduction
• Where is Boggabri – Situated between Gunnedah and Narrabri in north west N.S.W approx. 115km West from Tamworth.
• Boggabri Coal Operations commenced mining in 2006 • A significant expansion of site infrastructure was undertaken in 2014/2015 • The 132kV connection was a joint project by Transgrid and Boggabri Coal
Operations. • Included was 15kM of single structure, double circuit, 132kV transmission line,
132kV switching station and the 132kv/11kV substation.
Overview • Boggabri Coal Operations were an LV customer (HV was
managed by the utility) at inception. • Site demand was below 2MVA • An 11kV rural feeder from Boggabri Substation was the
only mine supply source. The service extended over 25kM (voltage regulation was required).
• Expansion of site infrastructure required power system demand exceeding the 11kV capability.
• Overall site demand increased to 8MVA (design capacity) • Local services could not meet the demand – Transmission
was the only option.
Why 132kV Connection
? A first for Mining and Transgrid
Network Layout
Network Connection
Boggabri Coal Substation
Network Connection
Protection Schemes
Inter tripping
• 132kV trip signals are duplicated through protection relays from Boggabri Coal to Transgrid
– Zone Protection (overcurrent, short circuit etc) – TX Differential – Emergency stops – Fire system – Back up Earth Leakage – Neutral Earth Resistor failure via NER monitor. – Transformer Protection (Oil temp, explosion, winding temp, over pressure) – Arc Fault Detection (11kv Bus)
• Protection devices, Circuit breakers, are in Transgrids Switching Station. • Faults are cleared by transgrid for all 132kV primary protection or
Intertrip faults
Logic Diagram Example
Load shed Arrangements
• Transmission systems demand stability • Transgrid Load shed scheme means exactly what is
sounds like • 4 Tiers are implemented which shed different load
blocks • Bus voltage is monitored at the switching station for
trip signal initiations
EARTHING
• Common earthing system between Transgrid and Boggabri Coal • Design requirements - Allowable touch and step voltages were
derived from different standards
• Transgrid – AS2067 ( Calculated) • Boggabri Coal – AS3007 (step/touch potentials v’s clearance times)
• Transfer voltage levels required separation between
“mine infrastructure area” and the 132kV facility. A 164M exclusion zone has been established for earthed services entering this zone.
EARTHING
Challenges • Design was completed by Transmission orientated Engineers with a different approach to mining
“Risk management base” • Design review was undertaken by a QLD based engineering company • Disconnect between project team and the end user of the facility • System operation – original design philosophy was to run 2 x 10MVA TX’s in parallel which allowed
for a 65kA fault level on the 415V system (terminals of the 3MVA TX supply) • Fundamental protection schemes, secondary systems, required further development prior to
energistaion. • HV and LV services crossing operational boundaries. Boggabri Coal and Transgrid share HV and LV
services originating on both sides of the installation. • Differences in isolation procedures, including hardware between both Transgrid and Boggabri Coal • Transgrid having a major facility “next door” to the mine substation. • Unrestricted earth fault levels on the 132kV connection (max 15kA) – transfer voltages • Reliance of primary protection clearing faults is by the utility – No 132kV protective devices are
owned or operated by Boggabri Coal Operations.
Advantages • Transgrid monitoring
• Transgrid system control monitor the status of Transgrid equipment, including the 132kV circuit breakers, 24/7
• Remote operation of 132kV circuit breakers from Transgrid system control
• Stability of Supply • The 132kV connection is part of the overall, north west area “Ring Main”. This means the system is very
stable and subject to minimal outages or faults.
• Reduced Arc Flash Categories • Increased equipment clearances (above 3M) and protection schemes allow for arc
flash categories to be reduced
Key Outcomes
• Transgrid and Boggabri Coal Operating agreement implemented This document identifies
– Equipment isolation instructions, each piece of equipment has an agreed isolation procedure – Communication protocol’s – Key contacts for events – Use and transaction of “High Voltage Equipment Outage” permits.
• Connection Agreement – Highlights the obligations of each party – Deals with access and safety scenarios . – Modifications to the agreed installation and protection settings are dealt with here
• Operational and Maintenance, hazard identification and risk analysis via consultation with designer, supplier, installer, operator and utility (Transgrid).
– This process expedited the risk mitigation process due to designer information being supplied by key engineers
• Designer based training for operational staff – Maintenance, Isolation and Operational documents were developed and used as training material
for electrical staff by the designer. Training was delivered onsite.
Recommendations
• Where plant and installations are being constructed, for the purpose of mining operations, statutory functions should be involved in the key decisions.
• Collaboration with mining and transmission industries requires further development. Mindsets are differing around system operations and protection functions.
Thank You!