Page 1: Chesser House Sustainability Project · 2015. 7. 26. · Chesser House: • 12 Storey commercial office building, located in Adelaide’s CBD. • Constructed in the late 1980s. •

Chesser House Sustainability ProjectSustainability Project

Presenter: Peter Stokoe

System Solutions Engineering

Page 2: Chesser House Sustainability Project · 2015. 7. 26. · Chesser House: • 12 Storey commercial office building, located in Adelaide’s CBD. • Constructed in the late 1980s. •

Project Overview 1

Aims:

• Provide a report which assesses and compares various energy and greenhouse gas saving techniques for commercial office buildings.

• Provide recommendations based on comparison for possible upgrades which would achieve the desired possible upgrades which would achieve the desired NABERS Energy (base building) rating at Chesser House.

• Provide comments on the suitability of each concept to other commercial office buildings, along with estimated reductions in energy consumption where possible.

Page 3: Chesser House Sustainability Project · 2015. 7. 26. · Chesser House: • 12 Storey commercial office building, located in Adelaide’s CBD. • Constructed in the late 1980s. •

Project Overview 2

Chesser House:

• 12 Storey commercial office building, located in Adelaide’s CBD.

• Constructed in the late 1980s.

• Recently completed several energy efficiency upgrades, energy efficiency upgrades, with further upgrades planned.

• Estimated to currently be achieving a NABERS energy (Base Building) rating of 4 stars. (At time of study, estimate was 3.5 stars).

Images sourced from private collection

Page 4: Chesser House Sustainability Project · 2015. 7. 26. · Chesser House: • 12 Storey commercial office building, located in Adelaide’s CBD. • Constructed in the late 1980s. •

Methodology 1

Completing the study involved 4 key stages:

• Data collection and site familiarisation phase· Drawings· Technical data· Metering data

• Detailed research phase· Focusing on ‘innovative’ concepts· Focusing on ‘innovative’ concepts

• Modeling and calculation phase

• Reporting phase· Comparative results included

Page 5: Chesser House Sustainability Project · 2015. 7. 26. · Chesser House: • 12 Storey commercial office building, located in Adelaide’s CBD. • Constructed in the late 1980s. •

Business As Usual:

Sustainable Practice:

Stretch Objectives:

Methodology 2

Each concept was allocated into 1 of 3 categories:

Page 6: Chesser House Sustainability Project · 2015. 7. 26. · Chesser House: • 12 Storey commercial office building, located in Adelaide’s CBD. • Constructed in the late 1980s. •

Methodology 3

Business As Usual:

• Re-Commissioning and Re-Tuning• Heat Recovery Ventilation• High Efficiency Lighting• Outdoor Air Economy Cycle Systems• Part Load Performance• Metering• Gas Fired Technologies• Gas Fired Technologies• Pressure Independent Characterised Control Valves

Images sourced from pierlite.com.au, belimo.com.au & supplier

Page 7: Chesser House Sustainability Project · 2015. 7. 26. · Chesser House: • 12 Storey commercial office building, located in Adelaide’s CBD. • Constructed in the late 1980s. •

Methodology 4

Sustainable Practice:

• High Efficiency Thermal Insulation• Lighting Control• Chilled Beams• Glass Coatings• Cogeneration• Regenerative Lift Braking Systems• Occupant Comfort Control• Occupant Comfort Control• Shaw Method of Air Conditioning• Fuel Cells• Absorption Chillers• Indirect Evaporative Cooling• Natural Ventilation• Induction VAV Technology

Images sourced from cfcl.com.au, seeley.com.au & supplier

Page 8: Chesser House Sustainability Project · 2015. 7. 26. · Chesser House: • 12 Storey commercial office building, located in Adelaide’s CBD. • Constructed in the late 1980s. •

Methodology 5

Stretch Objectives:

• Geothermal Systems• Innovative Shading• Air Engines• Green Walls/Roofs• Phase Change Materials• Building Integrated Photo Voltaic • Solar Air Conditioning• Solar Air Conditioning• Energy Enhanced Gas• Fibre Optic Solar Lighting• Wind Energy

Images sourced from csiro.au & adshelinfrastructure.com.au

Page 9: Chesser House Sustainability Project · 2015. 7. 26. · Chesser House: • 12 Storey commercial office building, located in Adelaide’s CBD. • Constructed in the late 1980s. •

Outstanding concepts:

• Re -commissioning and re-tuning• Part load performance• Improved metering• Lighting control• Glass coatings• Cogeneration

Key Findings 1

• Cogeneration

Page 10: Chesser House Sustainability Project · 2015. 7. 26. · Chesser House: • 12 Storey commercial office building, located in Adelaide’s CBD. • Constructed in the late 1980s. •

Outstanding concepts:

• SMAC• Fuel cells• Indirect evaporative cooling• Building Integrated Photovoltaic• Energy Enhanced Gas

Key Findings 2

Page 11: Chesser House Sustainability Project · 2015. 7. 26. · Chesser House: • 12 Storey commercial office building, located in Adelaide’s CBD. • Constructed in the late 1980s. •

Key Findings 3

Final Recommendations:

• Implement re-commissioning/re-tuning• Improve metering• Upgrade base building lighting• Implement a lighting control strategy• Install fuel cells• Install building integrated photovoltaic cells• Install building integrated photovoltaic cells

Images sourced from cfcl.com.au & adshelinfrastructure.com.au

Page 12: Chesser House Sustainability Project · 2015. 7. 26. · Chesser House: • 12 Storey commercial office building, located in Adelaide’s CBD. • Constructed in the late 1980s. •

Key Findings 4

Estimated savings:

Whole Building:Total Reduction in Electricity Consumption: 168,110kWhrTotal Reduction in Greenhouse Gas Emissions: 125.66t

Base Building:Total Reduction in Electricity Consumption: 122,410kWhrTotal Reduction in Electricity Consumption: 122,410kWhrTotal Reduction in Greenhouse Gas Emissions: 84.01tPercentage Electricity Consumption: 12.5%Percentage Greenhouse Gas Emissions: 8.6%

Increase in NABERS Energy (base building) Rating from 3.5 to 4 stars (at time of study)

Page 13: Chesser House Sustainability Project · 2015. 7. 26. · Chesser House: • 12 Storey commercial office building, located in Adelaide’s CBD. • Constructed in the late 1980s. •

Conclusion

Achievements:

• Completion of the project gave Chesser Properties an insight into potential ways to achieve their desired NABERS energy rating.

• A document has now been produced which can potentially assist others in the industry who wish to potentially assist others in the industry who wish to increase their NABERS energy rating.