chapter ii mrp

Upload: erramesh1989

Post on 03-Apr-2018

232 views

Category:

Documents


2 download

TRANSCRIPT

  • 7/28/2019 Chapter II MRP

    1/43

    MATERAIALS REQUIREMENT

    PLANNING(MRP)

    VENKATESWARA RAO .KORASIGA

  • 7/28/2019 Chapter II MRP

    2/43

    Dependent demand

    lumpy

    MRP

    DETAILED SCHEDULE FOR

    RAW MATERIALS

    &

    COMPONENTS

    USED IN THE END PRODUCTS

    MASTER SCHEDULE

    FOR END ITEMS

  • 7/28/2019 Chapter II MRP

    3/43

    MRP Systems

    Commonly used method in industry to coordinate the

    production scheduling of end items and their associated subcomponents.

    Fords MRP systems is known as CMMS, common

    manufacturing management system.

    Required information to support an MRP system:

    Master Production Schedule (MPS)

    Bill of Material (BOM)

    Inventory Status Records by each part or component Lead times

    Item master data

  • 7/28/2019 Chapter II MRP

    4/43

    C1 C2 C3 Cn

    P1

    P2

    P3

    PN

    BASIC RAW MATERIAL

    COMPONENTS

    PRODUCTS

  • 7/28/2019 Chapter II MRP

    5/43

    MRP Systems

    Master Production Schedule (MPS):

    Example

    Production of 1000 no. 12468 staplers is planned for weeks 1, 2, and 3,

    followed by no more stapler production until week 6 in which 1500 staplers

    will be produced.

    Product: personal stapler no. 12468

    1 2 3 4 5 6

    Planned order releases 1000 1000 1000 0 0 1500

    Week

  • 7/28/2019 Chapter II MRP

    6/43

    MRP Systems

    Bill of Material (BOM): A listing of all components required for each end-

    item.

    Example personal stapler no. 12468. This stapler is assembled from 3

    sub-assemblies.

    Standard , Personal

    Stapler

    Base Assembly Top Jaw Bottom Jaw Top Assembly Pin Spring Assembly

    Base

    Plate

    Base

    Molding

    Jaw

    Support

    Stake

    Rivet

    Tension

    Plate

    Top Top

    Cover

    Locator

    Plate

    Stake

    Rivet

    Pin Copper

    Spring

    Slide

    Pin

    Slide

    Housing

    2 2

  • 7/28/2019 Chapter II MRP

    7/43

    MRP Systems

    Inventory Status Records: Dynamic information about the current level of

    inventory for all components designated in the BOM of each end item. In

    practice, accurate inventory levels are difficult to maintain.

    Example Component Inventory Status

    Top Assembly 1212Spring Assembly 1150

    Locator Plate 146

    Slide Pin 558

  • 7/28/2019 Chapter II MRP

    8/43

    MRP Systems

    Lead Times: the time from when an order to replenish a part is initiated until

    the part becomes available for use.

    Lead times in practice are variable, but for the MPS, a fixed value is applied,

    usually the mean plus some safety factor.

    Example Component Lead Time (weeks)Top Assembly 1

    Spring Assembly 1

    Locator Plate 2

    Slide Pin 1

  • 7/28/2019 Chapter II MRP

    9/43

    MRP Systems

    Item Master Data - unique data for each part or component. This data

    includes:

    unique part number

    annual demand

    nominal order quantity cost

    scrap rate

    production lead time

    resource requirements

    pointers to engineering drawings (if produced internally)

    vendor information (if purchased)etc

  • 7/28/2019 Chapter II MRP

    10/43

    MRP Systems

    Requirements explosion and order release plan:

    Example order release plan for personal stapler no. 12468

    Level One Planning Top Assembly

    0 1 2 3 4 5 6

    Top Assembly: Lead time = 1

    Gross Requirements 1000 1000 1000 1500

    Scheduled Receipts

    (Projected) On-hand 1212 212

    Net Requirements 788 1000 1500

    Planned Order Releases 788 1000 1500

    Week

  • 7/28/2019 Chapter II MRP

    11/43

    MRP Systems

    Requirements explosion and order release plan:

    Example order release plan for personal stapler no. 12468

    Level One Planning Spring Assembly

    0 1 2 3 4 5 6

    Spring Assembly: Lead time = 1

    Gross Requirements 1000 1000 1000 1500

    Scheduled Receipts

    (Projected) On-hand 1150 150

    Net Requirements 850 1000 1500Planned Order Releases 850 1000 1500

    Week

  • 7/28/2019 Chapter II MRP

    12/43

    MRP SystemsRequirements explosion and order release plan:

    Ex. order release plan for personal stapler no. 12468, an order for 750 locator

    plates is expected to arrive early in week 1

    * The 892 units released in week 1 will not arrive till week 3 unless some

    expedited actions occur

    Level Two Planning Spring Assembly

    0 1 2 3 4 5 6

    Locator Plate: Lead time = 2

    Gross Requirements 788 1000 1500

    Scheduled Receipts 750

    (Projected) On-hand 146 108

    Net Requirements 892 1500Planned Order Releases 892* 1500

    Week

  • 7/28/2019 Chapter II MRP

    13/43

    MRP SystemsRequirements explosion and order release plan:

    Ex. order release plan for personal stapler no. 12468, a batch of 650 slide

    pins is just about complete.

    Level Two Planning Spring Assembly

    0 1 2 3 4 5 6

    Slide Pins: Lead time = 1

    Gross Requirements 850 1000 1500

    Scheduled Receipts 650

    (Projected) On-hand 558 358

    Net Requirements 642 1500

    Planned Order Releases 642 1500

    Week

  • 7/28/2019 Chapter II MRP

    14/43

    MRP Systems

    Recall the requirements explosion and order release plan from Ex. order

    release plan for personal stapler no. 12468

    How might you allow for quality losses and or demand variability and lead-time

    variability?

    0 1 2 3 4 5 6

    Top Assembly: Lead time = 1

    Gross Requirements 1000 1000 1000 1500

    Scheduled Receipts

    (Projected) On-hand 1212 212

    Net Requirements 788 1000 1500

    Planned Order Releases 788 1000 1500

    Week

  • 7/28/2019 Chapter II MRP

    15/43

    MRP SystemsScrap losses recall on the item master data record, quality yield is a field

    which has been populated using historical data or a guess. If yield for the

    stapler top assembly is say 90%, then more units should be planned for release

    than are required for the planned end-items according to:

    Ex. If there is a 90% yield for for top assembly then:

    0 1 2 3 4 5 6

    Top Assembly: Lead time = 1Gross Requirements 1000 1000 1000 1500

    Scheduled Receipts

    (Projected) On-hand 1212 212

    Net Requirements 788 1000 1500

    Planned Order Releases 876 1111 1667

    Yeild = 90%

    yield

    reqnetreleaseorder

    .

  • 7/28/2019 Chapter II MRP

    16/43

    MRP SystemsSafety Stock and Safety Lead Time to protect against demand variability and

    lead time variablity, a safety factor may be applied. Numerous application a

    safety factors exist, the simplest may be multiply by some percentage.

    Ex. If a 15% safety factor has been identified for top assembly then:

    0 1 2 3 4 5 6

    Top Assembly: Lead time = 1Gross Requirements 1000 1000 1000 1500

    Scheduled Receipts

    (Projected) On-hand 1212 212

    Net Requirements 788 1000 1500

    Planned Order Releases 906 1150 1725

    Safety facotr = 15%

  • 7/28/2019 Chapter II MRP

    17/43

    MRP Systems

    Rough-Cut Capacity Planning:

    When developing an MPS, one must consider if the schedule is feasible based

    on the capacity of workcenters within the plant.

    This is performed by determining the number of hours impact on all

    workcenters required to produce the end item, and identified by time bucket.

  • 7/28/2019 Chapter II MRP

    18/43

    Rough-Cut Capacity Planning:

    For example, suppose for every unit of end item A that is planned for

    production, the following workcenters are impacted:

    Part C has a 2-week lead time, and uses both workcenter 200 and 300. Part D

    consists of part E which requires WC 300 and part F (a purchased component).

    MRP Systems

    C C

    A

    ED

    F

    -5 -4 -3 -2 -1 0

    OP#1

    WC200

    .10 hr/unit

    OP#2

    WC300

    .15 hr/unit

    Purchased

    WC200

    .20 hr/unit

    WC300

    .15 hr/unit

  • 7/28/2019 Chapter II MRP

    19/43

    MRP SystemsRough-Cut Capacity Planning:

    An aggregated, time phased profile for end item A and another end item B is

    shown below.

    End Item A End Item B

    Period Period

    Workcenter 0 -1 -2 0 -1 -2

    100 0.05 0.05

    200 0.2 0.1 0.2 0.2

    300 0.15 0.15 0.3 0.15

    Aggregated time-phased load profiles for end items (Hrs/Unit)

  • 7/28/2019 Chapter II MRP

    20/43

    MRP SystemsRough-Cut Capacity Planning:

    Given a master production schedule for the facility:

    And the time-phased load profile, results in the total resource requirements

    End Item 1 2 3 4 5 6

    A 50 75 25 50 200B 75 125 100 150

    Period

    Workcenter -1 0 1 2 3 4 5 6

    100 6.25 3.75 7.5 7.5 10 7.5

    200 20 32.5 42.5 55 50 70 30

    300 18.75 41.25 33.75 63.75 67.5 52.5 45

    Period

  • 7/28/2019 Chapter II MRP

    21/43

    MRP Systems

    Master Production Schedule (MPS):

    Example

    Production of 1000 no. 12468 staplers is planned for weeks 1, 2, and 3,

    followed by no more stapler production until week 6 in which 1500 staplers

    will be produced.

    Product: personal stapler no. 124681 2 3 4 5 6

    Planned order releases 1000 1000 1000 0 0 1500

    Week

  • 7/28/2019 Chapter II MRP

    22/43

    MRP Systems

    Bill of Material (BOM): A listing of all components required for each end-

    item.

    Example personal stapler no. 12468. This stapler is assembled from 3

    sub-assemblies.

    Standard , Personal

    Stapler

    Base Assembly Top Jaw Bottom Jaw Top Assembly Pin Spring Assembly

    Base

    Plate

    Base

    Molding

    Jaw

    Support

    Stake

    Rivet

    Tension

    Plate

    Top Top

    Cover

    Locator

    Plate

    Stake

    Rivet

    Pin Copper

    Spring

    Slide

    Pin

    Slide

    Housing

    2 2

  • 7/28/2019 Chapter II MRP

    23/43

    MRP Systems

    Inventory Status Records: Dynamic information about the current level of

    inventory for all components designated in the BOM of each end item. In

    practice, accurate inventory levels are difficult to maintain.

    Example Component Inventory Status

    Top Assembly 1212Spring Assembly 1150

    Locator Plate 146

    Slide Pin 558

  • 7/28/2019 Chapter II MRP

    24/43

    MRP Systems

    Lead Times: the time from when an order to replenish a part is initiated until

    the part becomes available for use.

    Lead times in practice are variable, but for the MPS, a fixed value is applied,

    usually the mean plus some safety factor.

    Example Component Lead Time (weeks)Top Assembly 1

    Spring Assembly 1

    Locator Plate 2

    Slide Pin 1

  • 7/28/2019 Chapter II MRP

    25/43

    MRP Systems

    Item Master Data - unique data for each part or component. This data

    includes:

    unique part number

    annual demand

    nominal order quantity cost

    scrap rate

    production lead time

    resource requirements

    pointers to engineering drawings (if produced internally)

    vendor information (if purchased)etc

  • 7/28/2019 Chapter II MRP

    26/43

    MRP Systems

    Requirements explosion and order release plan:

    Example order release plan for personal stapler no. 12468

    Level One Planning Top Assembly

    0 1 2 3 4 5 6

    Top Assembly: Lead time = 1

    Gross Requirements 1000 1000 1000 1500

    Scheduled Receipts

    (Projected) On-hand 1212 212

    Net Requirements 788 1000 1500Planned Order Releases 788 1000 1500

    Week

  • 7/28/2019 Chapter II MRP

    27/43

    MRP Systems

    Requirements explosion and order release plan:

    Example order release plan for personal stapler no. 12468

    Level One Planning Spring Assembly

    0 1 2 3 4 5 6

    Spring Assembly: Lead time = 1

    Gross Requirements 1000 1000 1000 1500

    Scheduled Receipts

    (Projected) On-hand 1150 150

    Net Requirements 850 1000 1500Planned Order Releases 850 1000 1500

    Week

  • 7/28/2019 Chapter II MRP

    28/43

    MRP SystemsRequirements explosion and order release plan:

    Ex. order release plan for personal stapler no. 12468, an order for 750 locator

    plates is expected to arrive early in week 1

    * The 892 units released in week 1 will not arrive till week 3 unless some

    expedited actions occur

    Level Two Planning Spring Assembly

    0 1 2 3 4 5 6

    Locator Plate: Lead time = 2

    Gross Requirements 788 1000 1500

    Scheduled Receipts 750

    (Projected) On-hand 146 108

    Net Requirements 892 1500Planned Order Releases 892* 1500

    Week

  • 7/28/2019 Chapter II MRP

    29/43

    MRP SystemsRequirements explosion and order release plan:

    Ex. order release plan for personal stapler no. 12468, a batch of 650 slide

    pins is just about complete.

    Level Two Planning Spring Assembly

    0 1 2 3 4 5 6

    Slide Pins: Lead time = 1

    Gross Requirements 850 1000 1500

    Scheduled Receipts 650

    (Projected) On-hand 558 358

    Net Requirements 642 1500

    Planned Order Releases 642 1500

    Week

  • 7/28/2019 Chapter II MRP

    30/43

    MRP Systems

    Recall the requirements explosion and order release plan from Ex. order

    release plan for personal stapler no. 12468

    How might you allow for quality losses and or demand variability and lead-time

    variability?

    0 1 2 3 4 5 6

    Top Assembly: Lead time = 1

    Gross Requirements 1000 1000 1000 1500

    Scheduled Receipts

    (Projected) On-hand 1212 212

    Net Requirements 788 1000 1500

    Planned Order Releases 788 1000 1500

    Week

  • 7/28/2019 Chapter II MRP

    31/43

    MRP SystemsScrap losses recall on the item master data record, quality yield is a field

    which has been populated using historical data or a guess. If yield for the

    stapler top assembly is say 90%, then more units should be planned for release

    than are required for the planned end-items according to:

    Ex. If there is a 90% yield for for top assembly then:

    0 1 2 3 4 5 6

    Top Assembly: Lead time = 1Gross Requirements 1000 1000 1000 1500

    Scheduled Receipts

    (Projected) On-hand 1212 212

    Net Requirements 788 1000 1500

    Planned Order Releases 876 1111 1667

    Yeild = 90%

    yield

    reqnetreleaseorder .

  • 7/28/2019 Chapter II MRP

    32/43

    MRP SystemsSafety Stock and Safety Lead Time to protect against demand variability and

    lead time variablity, a safety factor may be applied. Numerous application a

    safety factors exist, the simplest may be multiply by some percentage.

    Ex. If a 15% safety factor has been identified for top assembly then:

    0 1 2 3 4 5 6

    Top Assembly: Lead time = 1Gross Requirements 1000 1000 1000 1500

    Scheduled Receipts

    (Projected) On-hand 1212 212

    Net Requirements 788 1000 1500

    Planned Order Releases 906 1150 1725

    Safety facotr = 15%

  • 7/28/2019 Chapter II MRP

    33/43

    MRP Systems

    Rough-Cut Capacity Planning:

    When developing an MPS, one must consider if the schedule is feasible based

    on the capacity of workcenters within the plant.

    This is performed by determining the number of hours impact on all

    workcenters required to produce the end item, and identified by time bucket.

  • 7/28/2019 Chapter II MRP

    34/43

    Rough-Cut Capacity Planning:

    For example, suppose for every unit of end item A that is planned for

    production, the following workcenters are impacted:

    Part C has a 2-week lead time, and uses both workcenter 200 and 300. Part D

    consists of part E which requires WC 300 and part F (a purchased component).

    MRP Systems

    C C

    A

    ED

    F

    -5 -4 -3 -2 -1 0

    OP#1

    WC200

    .10 hr/unit

    OP#2

    WC300

    .15 hr/unit

    Purchased

    WC200

    .20 hr/unit

    WC300

    .15 hr/unit

  • 7/28/2019 Chapter II MRP

    35/43

    MRP SystemsRough-Cut Capacity Planning:

    An aggregated, time phased profile for end item A and another end item B is

    shown below.

    End Item A End Item B

    Period Period

    Workcenter 0 -1 -2 0 -1 -2

    100 0.05 0.05

    200 0.2 0.1 0.2 0.2

    300 0.15 0.15 0.3 0.15

    Aggregated time-phased load profiles for end items (Hrs/Unit)

  • 7/28/2019 Chapter II MRP

    36/43

    MRP SystemsRough-Cut Capacity Planning:

    Given a master production schedule for the facility:

    And the time-phased load profile, results in the total resource requirements

    End Item 1 2 3 4 5 6

    A 50 75 25 50 200B 75 125 100 150

    Period

    Workcenter -1 0 1 2 3 4 5 6

    100 6.25 3.75 7.5 7.5 10 7.5

    200 20 32.5 42.5 55 50 70 30

    300 18.75 41.25 33.75 63.75 67.5 52.5 45

    Period

  • 7/28/2019 Chapter II MRP

    37/43

    MRP SystemsRough-Cut Capacity Planning:

    Given this rough cut capacity plan, and the knowledge that you operate a single

    shift 10 hours a day, and 6 days a week, do you foresee a problem? If so, how

    might you adjust?

    Workcenter -1 0 1 2 3 4 5 6

    100 6.25 3.75 7.5 7.5 10 7.5

    200 20 32.5 42.5 55 50 70 30

    300 18.75 41.25 33.75 63.75 67.5 52.5 45

    Period

  • 7/28/2019 Chapter II MRP

    38/43

    MRP SystemsCapacity Requirements Planning (CRP):

    Similar to rough cut capacity planning, but includes details such as current

    inventory levels and the impact of lot-sizing decisions.

    Ex. Assume initial inventory levels:

    Then net MPS becomes:

    On-Hand Inventory

    A 100

    B 125

    End Item 1 2 3 4 5 6

    A 25 25 50 200

    B 75 100 150

    Period

  • 7/28/2019 Chapter II MRP

    39/43

    MRP SystemsCapacity Requirements Planning:

    From the net MPS, the workstation loading levels by part:

    Therefore capacity plan is:

    Are there any concerns?

    0 1 2 3 4 5 6

    WC100-A 1.25 1.25 2.5 3 12 10 0

    WC200-A 0 5 7.5 22.5 0 0 0WC300-A 0 3.75 7.5 11.25 45 20 0

    WC100-B 0 3.75 5 0 37.5 30 0

    WC200-B 0 0 15 35 7.5 0 30

    WC300-B 0 0 22.5 41.25 20 30 22.5

    Period

    0 1 2 3 4 5 6

    WC100 1.25 5 7.5 3 49.5 40 0

    WC200 0 5 22.5 57.5 7.5 0 30

    WC300 0 3.75 30 52.5 65 50 22.5

    Period

  • 7/28/2019 Chapter II MRP

    40/43

    MRP Systems

    Master Production Schedule (MPS): Planned production quantities for end-

    items in each time period of the planning horizon.

    Planning horizon length of time over which to plan the production

    schedule. This length of time must exceed the cumulative lead time to

    replenish an end-item through all production stages.

    Time period (or time bucket) smallest unit of time in which end-item

    production is schedule. In practice, time buckets of one week are typical

    used.

    EVOLUTION OF MRP

  • 7/28/2019 Chapter II MRP

    41/43

    EVOLUTION OF MRP

    Manufacturing

    ResourcePlanning

    Links up the closed loop MRP system with the financial

    systems of the company

    (Links functions

    -Capacity planning

    -Inventory management

    -Shop floor control

    -MRP)

    Improved

    computational

    efficiency of

    computers

    Unrealistic M/c

    schedules, ignoring

    plant capacities

    Not only plans prioritiesbut provides feedback to

    executing the priority plan

    AN IMPROVED ORDERING METHOD

    PRIORITY PLANNING

    CLOSED LOOP MRP

    MRP II

  • 7/28/2019 Chapter II MRP

    42/43

    Gross & Net requirements

    report

    Capacity vs

    Load report

    Shop floor

    Planning

    report

    Production Order

    Status & exceptions

    report

    Service

    Parts

    requirements

    Sales

    forecasts

    Customer

    orders

    Inventory

    transactions

    Master

    Production

    schedule

    Engg.

    changes

    InventoryRecord

    file

    MRP

    PROCESSOR

    Bill ofMaterials

    file

    OUT PUT

    REPORTS

  • 7/28/2019 Chapter II MRP

    43/43