chapter 4 - information and library network...
TRANSCRIPT
![Page 1: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/1.jpg)
1
CHAPTER 4
A POWER SYSTEM MODEL – TO STUDY
SCADA AUTOMATION AND DIGITAL NUMERICAL DISTANCE RELAY
CHAPTER CONTENTS
4.1 Design of the Power System Model, 87
4.2 Model’s Utility as a Benchmark, 88
4.3 Components mounted on the Model, 94
4.4 SCADA, 95
4.5 Power Flow Studies, 99
4.6 Fault Studies Using DND Relay, 103
4.7 Discussions and Conclusions, 105
4.1 DESIGN OF THE POWER SYSTEM MODEL
A Power System Model with SCADA (Supervisory Control and Data Acquisition)
Automation was designed and constructed to simulate overhead transmission line
faults. Experiments were conducted to study the working of the Digital Numerical
Distance Relay (DNDR) for its performance and utility by simulating different faults
on the transmission line.
This model comprised three phase generator, transmission lines (representing 400
kV, 500 km in two sections of 300 km and 200 km) and Resistive and inductive
loads. The model was provided with circuit breakers, reverse power relay, over
current relay for protection and DND Relay.
![Page 2: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/2.jpg)
2
Distance Numerical Relay (DNDR) has become vital device for the protection and
fault localization of modern transmission systems. Many of the existing transmission
lines which do not have DND Relays are now being modernized by adding on these
relays. The Power System Model provides complete information and know-how
about usage of the DND Relay and SCADA Automation and their utility in the real
systems to contribute to efficient and reliable maintenance management.
A basic prototype DND Relay was designed by utilizing a multifunction meter that
displayed voltage (V), current (A), V/A (which gives the impedance Z) value and
distance to fault in kilometer. The meter was designed for an input signal of voltage
between 70 to 250 volts and current rating from 0.3 to 10 Amperes. The reading Z is
divided by 0.33 (value of resistance and inductive reactance per kilometer) to obtain
distance to fault.
Image 4.1 Shows 400 kV Overhead High Voltage Transmission Lines
4.2. MODEL’S UTILITY AS A BENCH MARK
This Dynamic Model constructed comprising two, three phase Generators, four
Transmission lines, two Loads was found to be suitable benchmark design for
simulating the real system. The model could be operated both manually and through
remote data access and Supervisory Control using a computer (with SCADA
![Page 3: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/3.jpg)
3
software). It was suitable for the following:
1. FAULT MANAGEMENT: Different types of faults were simulated on the
transmission lines and distance to faults was obtained through DND Relay device
which was found to be satisfactory.
2. STUDY OF POWER FLOW: This was studied by interconnecting the network of
transmission lines to form the grid and operation was controlled manually and
through SCADA.
The functionality of the MPCB, MCB, Short circuit relay, Contactor, etc., mounted
on the model was also verified
SIMULATED STUDY CONDUCTED:
DATA OF SULTANPUR—LUCKNOW TRANSMISSION LINE
The RLC parameters of 400 KV EHV lines per km
Resistance 0.03 ohms / phase / Km
Inductance 1.00 m H / phase / Km
Inductive Reactance 0.33 ohms / phase / Km
Capacitance 12 n F / phase / Km
Y 3.7 x / phase / Km
Table 4.2 Data taken from: Sultanpur – Lucknow line (UP India)
The Sultanpur – Lucknow transmission line has capacity to carry 900 Amps of per
phase that is equal to a power of: V x I = 400 x1000 x 900 =360 MVA per phase
Parameters 300 km 200 km
Resistance 9 ohms 6 ohms
Inductance 300 Mh 200 mH
XL 99 Ohms 66 Ohms
Capacitance 3.6 micro Farads
(for pi 1.8 + 1.8)
2.4 micro Farads
(for pi 1.2 + 1.2)
![Page 4: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/4.jpg)
4
Table 4.3 RLC Parameters of 400 kV line for 300 km and 200 km Trans Lines
4.2.1. THE MODEL LAYOUT
The Power System Model constructed here has three panels, on the left (panel no 1)
comprises metering and Control of Generator no.1 and Load no.1 and on its front
desk the transmission lines 1 and 2. The panel on the extreme right (panel no 3)
comprises Metering and Control of Generator no.2, Load no. 2 and on the desk
Transmission lines 3 and 4 and each provided with respective MFM, MCB and
Relays. The central panel (Panel no 2) has a bus bar arrangement where the ends of
Generator 1 & 2, Load 1 & 2 and transmission line 1, 2, 3 & 4 are terminated and can
be interconnected through patch cords to form the desired circuit. The inductors,
resistors and other components are mounted behind the panel. The front layout of
the panel has only the controls. The dimensions of each panel are 2.5feet length with
a height of 5.5feet. This makes the total length of the equipment as 7.5 feet.
PANEL NO 1 PANEL NO 2 PANEL NO 3
GENERATOR 1 /LOAD 1 BUS BAR GENERATOR 2 /LOAD 2 METERING ETC FOR METERING ETC FOR TRANS LINE 1 &2 ON THE DESK TRANS LINE 3 & 4 ON DESK
![Page 5: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/5.jpg)
5
Image 4.4 shows the 3 panels joined together
![Page 6: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/6.jpg)
6
Figure 4.5 shows the block diagram of circuit
connection of the Power System Model
The power system model simulating 400 kV, 500 km transmission line system was
designed with scaled down parameters of Base Values to co-relate the parameters of
the study obtained on the model to the real system. The Power System Model
comprised 2 nos. of 400 volts, three phase motor-generator sets provided with motor
drives, reverse power relay, short circuit relay with circuit breakers for their
protection. Three phase digital Multi Function Meters (MFM) displayed voltage,
current, power factor, frequency, active and reactive power. The multifunction
meters also had RS485 port for data communication with computer software.
![Page 7: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/7.jpg)
7
4.2.1.1 THE MOTOR-ALTERNATOR CONTROL PANEL
The two 3 Phase / 3 kVA motor alternator sets (Generator supply 1and 2) have a
separate Control Panel with digital meters and variac arrangement to control speed
and excitation of motor-generator and another variac for varying the voltage.
4.2.1.2 CENTRAL PANEL
This panel has interconnecting arrangement linking generator, load and transmission
lines. It can be referred to as the main Bus Bars.
1. There are two Red color (on / off) switches marked as Area 1 & Area II to control
the respective supply.
2. This panel has Banana Sockets in (R-Red, Y- Yellow and B- Blue) colors where
the two ends of generator, transmission line and loads terminate. These can be
interconnected to form the grid network
3. The Green Sockets are the earth points.
4. The RYB Switches on the panel of Generator, Transmission Line and Load of
Area I and Area II control the circuit connectivity of the Central Panel. For example
even if patch cords are connected to RYB of Generator to RYB of Transmission Line
to RYB of Load, the voltage and current will not flow unless the RYB Switches of
Generator, Transmission Line, and Load of Area (I) are in ON position. The status of
the continuity between the Generator, Transmission Line, and Load is through the
LED Lights that will glow on the central panel. The same system is for Area (II).
4.2.1.3 THE DESK OF THE CENTRAL PANEL
3-Phase Digital Numerical Distance Relay [DNDR] is provided with connection in
series between the generator and sending ends of Transmission Line RYB
respectively. The DNDR is calibrated to read distance to fault when a fault is created
at any point on the Transmission Line. The calibrated values are: Z = V/ I in ohms.
Distance to fault: D = Z / 0.33 in kilometers
![Page 8: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/8.jpg)
8
4.2.1.4 TRANSMISSION LINE PANEL
The transmission line (TL) was provided with the digital MFM with RS485 Port
with similar display and arrangements for communication like the one used in Panel
1. The TL configuration is in the form of a pi-section with RLC values as shown in
table no 4.3. One MFM is provided at the Sending end of the TL and another at the
Receiving end of the last section. The transmission line is provided with Digital
Numerical Distance Relay (DNDR). It performs two functions: 1) Gives Protection
to the transmission line 2) Provides distance to fault.
4.2.2 BASE VALUES OF THE REAL SYSTEM
Base power: 20 MVA
Base Voltage: 200 kV
I = 20MVA/ 200 kV = Base Current: 100 Amps -------------------- (1)
Z = 200kV/100 A = Base Impedance: 2000 ohms
The Base Impedance of 2000 Ohms of Real System and the same value on the model
co-relates conversion made to real system as indicated in equation (2)
4.2.3 BASE VALUES OF THE SCALED DOWN SYSTEM
(ON THE MODEL)
400 Volts of the 3 phase generator output is stepped down
to 100 volts / phase for the 3 phase through a three phase transformer
Base Voltage: 100 Volts per phase ----------------------- (2)
V/Z = 100/2000 = Base Current: 50 mA
50 mA represents 20MVA Power in real system
and 100 Volts represents 200kV of real system see equation (1)
Base Impedance: 2000 ohms
Frequency: 50 Hz
Lower voltage for the base is preferable as it permits the model to represent higher
data of Generator, Transmission Line & Loads for power flow values of a grid
network. This gives the relationship between the Base values of Real System and the
![Page 9: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/9.jpg)
9
Base Values of the Model. It means the current of 50 mA on the model at 100 volts
represents 100 Amps of the real system and 50 mA represents 20 MVA power of the
real system.
Experiments were conducted by simulating 400 kV for a 500 km TL length. The
simulated RLC parameters of the transmission line were taken from Sultanpur -
Lucknow line. Fault was created at the End of the transmission line to verify the
maximum current flowing through the line under a short circuit fault between line to
ground. The results were obtained on a three phase transmission line by sending 100
volts per phase for all the 3 phases.
4.3 COMPONENTS MOUNTED ON THE MODEL
List of components Generator
Panel I &
Panel II
Load
Panel
I & II
Transmission
Line Panel I
& Panel II
DC Motor
Alternator
Control Panel
Desk of
Central
Panel
Dimmer stat 2
MPCB 2
Multi Function Meter 2 2 4 3
Over Current Relay 2 2 4 3
Miniature Circuit Breaker 2 6 8
R, Y, B Switches 6 6 12 3
Rotary Switch 2 6
Resistors 4 12
Inductors 4 12
Capacitors 4
Numerical Distance Relay 1
DC Motor, 5HP 220V/ 1500 rpm 2
AC Alternator 3phase / 3kVA,
415V
2
![Page 10: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/10.jpg)
10
4.4 SCADA (SUPERVISORY CONTROL AND DATA ACQUISITION)
4.4.1 HARDWARE
SCADA implementation on this Power System Model comprised of:
1. Programmable Logic Controller (PLC) controls the relays as and when the
command from the computer is received and PLC also acquires data from the
communication ports of the Power System Model and transmits to the computer.
2. Five sets of Relays (each relay set comprising eight relay points) are connected to
the PLC and controlled by the computer via PLC. These relays are for control as
well as to check the status of signal reaching at different nodes.
3. 24 Volts DC supply (SMPS -Switched Mode Power Supply) supplies power to
PLC for its function.
4. Computer with the programmed Software is the main controlling and data
acquiring station where the user operates the required functions, that is, controlling
the Power System Model.
The figure 4.6A shows that the computer is connected to the PLC to acquire the data
on the computer and all the control settings and options for the operation of the
model are sent to the PLC from the computer. The PLC operates on 24 Volts DC
supply and controls all five relay sets connected to the power system model.
The relays can perform:
a. The ON / OFF functions
b. Selection function
c. Monitor the status of signal
All the Multi-Function Meters are provided with RS485 ports. Positive and negative
points are connected in series and then finally connected to the PLC. The PLC is then
set to recognize and identify and save each meters’ IP address and then acquire the
data in sequence. This information is transferred to the computer software.
![Page 11: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/11.jpg)
11
Communication wire
Figure 4.6A shows the block diagram of
SCADA Hardware used for the Power System Model
PLC
Computer
With
SCADA
Relay 1
Relay 2
Relay 3 Relay 5
Relay 4
24 V DC
![Page 12: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/12.jpg)
12
4.4.2 SOFTWARE
The front end design of the software displayed on the desktop computer screen is
shown in the image 4.6B. It can be seen that it is a replica of the Power System
Model therefore it is more user friendly because the controlling and data displayed
can be identified and controlled easily. On this model the SCADA is controlling the
ON / OFF function of generator, load and transmission lines for coupling and
decoupling. The status of every node is monitored for the power reaching at circuit
breakers, over current relays, rotary switches and central panel.
In the screen image 4.6B on the extreme left are generator 1, load 1, transmission line
1 & 2 and on extreme right generator 2, load 2, transmission line 3 & 4. There are
contactors and RYB illuminated push buttons which are selectable and control the
coupling and decoupling of the circuit. The ELR, OCR, MCB nodes status points are
monitored for whether the voltage supply has reached the bus bars or not. The central
portion of the image gets lighted up with red, yellow and blue color indicating that
the voltage has reached the bus bars.
The entire control, monitoring the status of all nodes and data acquisition is for all
the three phases. There is also option provided to select auto / manual operation. In
the auto mode the entire system is controlled by SCADA and manual mode the
SCADA functions gets defunct. The F.SCRN option enlarges the particular area to
full screen.
![Page 13: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/13.jpg)
13
SOFTWARE LAYOUT OF THE MODEL ON THE COMPUTER SCREEN
Figure 4.6B shows layout on the computer screen for
Data Acquisition and Control
![Page 14: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/14.jpg)
14
4.5 SECTION A - POWER FLOW STUDIES
EXPERIMENT 1:
This experiment comprises one generator, one 300 km transmission line, one 200 km
transmission line and one load (see figure 4.1A). Here the power flow study was
made to examine the functionality of power transmission from generator to load via
the transmission lines.
Experiment Figure no 4.1A
In the above figure there is a Generator, Transmision Line divided
into two section one in 300 km and the other 200 km, and one Load.
This is a three phase (RYB) system which represents the power flow.
The experiment was conducted by operating the model manually and through
SCADA. The generator voltage was kept at 100V. The generator current, power and
other data was seen on MFM. The functionality of the related componants mounted
on the model was verified through this experiment.
![Page 15: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/15.jpg)
15
EXPERIMENT 2:
This experiment comprises two generators, three transmission lines and two loads.
Power flow was studied in Area (I) G1, TL1 and L1 and G2, TL2 and L2 in Area (II)
and there is a TL 3 which is a Tie Line that interconnects the two areas. In this power
flow study the importance of direction of power flow and synchronization of the two
generators were studied. See figure 4.2A.
Experiment Figure no 4.2A
The figure shows the circuit of power system where two generators, two loads
and three transmssion line are interconnected.
In this experiment the synchronization between two generators is achieved and
process is studied, here a synchroscope was used for monitoring synchronization.
The main factors which have to be controlled to achieve synchronizing state are:
Frequency, Voltage and Phase Angle. These factors can be controlled by speed and
excitation of motor generator and voltage regulation through voltage regulating
![Page 16: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/16.jpg)
16
variac. This is necessary because exactly at that time the circuit breaker is switched
on to join the tie line connected between the two generators. Without synchronization
the two generators should not be connected to the bus bar as it may swing the
alternator. There is Reverse Power Relay placed for protection to prevent power flow
in reverse direction.
Figure no 4.2B
The generator is provided with reverse power relay for its protection.
Figure 4.2A shows the circuit that was tested using the maximum configuration
provided on the equipment i.e. two generator, three transmission line and two loads.
At load bus 1 and load bus 2 are interconnected by a Tie Line to demonstrate the
flow of power from bus 1 to bus 2. This was achieved by keeping the Voltage at load
bus 1 higher than the load bus 2. The following information was obtained from the
test. The power generated by the alternator 1 was 4 Ampere at 250 volts where as
![Page 17: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/17.jpg)
17
the load 1 was 3 Amperes, therefore the 1 Ampere power could be diverted through
the Tie Line to the load bus 2 to supply the load 2 of 3 Ampere capacity, whereas the
generator 2 contributed 2 Ampere. The process here was controlled manually as well
as through computer command.
PARALLELING AC GENERATORS
Most electrical power grids and distribution systems have more than one AC
generator operating at one time. Normally, two or more generators are operated in
parallel in order to supply the demand of power. Three conditions must be met
prior to paralleling of (or synchronizing) AC generators:
1. Their terminal voltages must be equal. If the voltages of the two AC
generators are not equal, one of the AC generators would act as a reactive load to the
other AC generator. This causes high currents to be exchanged between
the two machines, possibly causing generator or distribution system damage.
2. Their frequencies must be equal. A mismatch in frequencies of the two AC
generators will cause the generator with the lower frequency to act as a load on the
other generator a condition referred to as motoring.
3. Their output voltages must be in phase. A mismatch in the phases will
develop opposing voltages. The worst case would be 180° out of phase, resulting
in an opposing voltage between the two generators of twice the output voltage. This
high voltage can cause damage to the generators and distribution system due to high
currents.
During paralleling operations, voltages of the two generators that are to be
paralleled are indicated through the use of voltmeters. Frequency matching is
accomplished through the use of output frequency meters.
Phase matching is accomplished through the use of a synchroscope, a device that
senses the two frequencies and gives an indication of phase differences and a
relative comparison of frequency differences.
4.6 SECTION B - FAULT STUDIES USING DND RELAY
![Page 18: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/18.jpg)
18
EXPERIMENT 3
Different types of faults were studied which frequently occur in the transmission
lines which are:
1. Double Line Fault (Figure 4.6.1)
2. Triple line Fault (Figure 4.6.2)
3. Line to Ground Fault (Figure 4.6.3)
4. Double Line to Ground Fault (Figure 4.6.4)
5. Triple Line to Ground Fault (Figure 4.6.5)
Here the purpose of simulating the faults was to study the functions of DNDR which
would trip the circuit and indicate the distance to fault.
Figure 4.6.1 Figure 4.6.2
Double Line Fault Triple Line Fault
![Page 19: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/19.jpg)
19
Figure 4.6.3 Figure 4.6.4 Figure 4.6.5
Line to Ground Fault Double Line to Triple Line to
Ground Fault Ground Fault
Figure
no.
Fault Type Distance to Fault in km indicated
by the DNDR
300 km
Transmission Line
500 km (300+200 km)
Transmission Line
4.6.1 Double Line Fault 302 499
4.6.2 Triple Line Fault 304 502
4.6.3 Line to Ground Fault 299 501
4.6.4 Double Line to Ground
Fault
301 498
4.6.5 Triple Line to Ground
Fault
302 503
Table 4.6.6 shows the distance to fault indicated by the DNDR
![Page 20: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/20.jpg)
20
4.7 DISCUSSIONS AND CONCLUSIONS
The Power System Model designed here simulates 400 kV, 500 km High Voltage
Transmission Line. The following experiments were performed using this model:
1. Simulating Faults clearing in the two sections (300 km and 200 km) of the
simulated
transmission line.
2. Obtaining distance to fault.
3. Power flow in Interconnected Grid network.
4. Data Acquisition and Supervisory Control using the SCADA architecture
provided on the model.
The experiments conducted on the Power System Model was to study DNDR which
provides protection to the transmission line by tripping the circuit and indicating
distances of different types of faults (L-G, L-L, LL-G, LLL, LLL-G) common in
overhead transmission lines.
These experiments indicate satisfactory performance of the DNDR. The results
obtained were within the accuracy of + 1% i.e. the transmission line of 500 km
showed result of 503 km in one experiment and 505 km in other experiment. Further
accuracy can be increased if the per kilometer inductance and resistance value of the
transmission line is correctly measured and fed in the DNDR.
This has resulted in to a portable overhead transmission line ‘test set’ to find the
distance to fault in 11 kV and 33 kV distribution lines. As in the most cases these
lines are not provided with the arrangement of DNDR due to the cost factor.
The SCADA automation was implemented on the model to understand the
architecture and its performance on a grid network of power system. The software
screen indicate the layout of facilities for data acquisition from the MFM and remote
![Page 21: CHAPTER 4 - Information and Library Network Centreshodhganga.inflibnet.ac.in/bitstream/10603/90408/5/05_chapter 4.pdf · 1 chapter 4 a power system model – to study scada automation](https://reader030.vdocuments.site/reader030/viewer/2022041219/5e089d034f8e552bf842eddd/html5/thumbnails/21.jpg)
21
supervisory control command that is used to control operational function of the
model image shown in 4.6A and 4.6B.
List of operations performed by using SCADA application:
The SCADA architecture implemented on the power system model comprised
Siemens PLC, relays, software and software program. The SCADA tested on the
model works smoothly and accurately. The precautions were taken for providing
good earthing and using co-axial connecting leads.