Change over process Check List
Check points Visual Action Remarks
3.Verify the weld wire used for carbon steel returned to production store
4. Verify the forming tools shall be cleaned thoroughly by solvent
5.Verify the weld tacks over the bed has been ground off
6.Verify the work area cleaned to remove the dust containing iron
. Verify the distance between cable tie!wire on net
". #nsure $ork lift forks are protected with stainless sheet
Quality : DATE:
1. Verify the grinding% cut off & flap wheel used for carbon steel returned toproduction store
'.Verify the hand tools (chisel% wire brush and )* clamps+ used for carbon steelreturned to production store
,.Verify the carbon steel work*platforms must be covered with stainless sheets orred o-ide paint to prevent any contact with carbon steel