case study number one for energy efficiency · 2010. 6. 21. · phone operator cellnet, it became...
TRANSCRIPT
![Page 1: CASE STUDY NUMBER ONE FOR ENERGY EFFICIENCY · 2010. 6. 21. · phone operator Cellnet, it became immediately apparent that this would not meet their needs – largely because the](https://reader034.vdocuments.site/reader034/viewer/2022051808/60090e68d2806b15025e7382/html5/thumbnails/1.jpg)
CASE STUDY NUMBER ONE FOR ENERGY EFFICIENCY
The energy required to heat, cool, ventilate and light Cellnet’s new Service Provision Division HQ
at No1 Leeds City Office Park is only 25% of that needed by a typical prestige office building –
and this despite it being fully air conditioned. A Trend building management system has made a
vital contribution to this high level of energy efficiency. As well as controlling all the HVAC
services – which include chilled ceilings – it has enabled remote monitoring of their performance,
and this has led to problems being quickly identified and put right. Most of the system was
supplied, engineered and commissioned by AES Control Systems of Northampton – to Oscar
Faber’s detailed design and specification.
No 1 Leeds Office Park was developed
by British Gas Properties and provides
6500m2 of office space. The subject of
an EU grant (under the Thermie
scheme), it is one of eight ‘Energy
Comfort 2000’ projects, whose
purpose has been to develop
concepts for commercial and public
building which significantly reduce
energy consumption.
The building combines a range of
features designed to limit energy
usage, such as a high thermal mass,
high levels of insulation, high utilisation
of natural light and solar shading.
Originally, it was intended that the
offices would be cooled partly by
natural ventilation and partly by a low
velocity mechanical system, with
occasional use of forced night
ventilation in the summer. However,
when the premises were let to mobile
phone operator Cellnet, it became
immediately apparent that this would
not meet their needs – largely because
the building was to be used 24 hours a
day. Some form of air conditioning was
unavoidable.
Oscar Faber – who Cellnet had
appointed as the building services,
structural and IT consultants for the fit-
out – developed a novel solution.
Based on an initial concept devised by
Sonofoss Design Services Ltd, it
involved the installation of large chilled
ceiling panels throughout most of the
three-storey building. It was also
necessary to upgrade the existing H&V
plant. This included installing an extra
boiler and adding cooling and
humidification to the main air handling
unit, which delivers air, at floor level, to
the whole building. Yet, though the
services have been substantially
uprated, energy consumption is in fact
slightly less than the level originally
predicted for the building.
Because they have a large surface
area and the ‘coolth’ they provide is
over 50% radiant, the ceiling panels
can be supplied with water at relatively
high temperature (14-18ºC). This is
primarily supplied (via a heat
exchanger, secondary circuit and zone
valves), by a cooling tower circuit.
Should this be unable to maintain the
temperature setpoint then chilled
water is directly injected into the
secondary, the source being a pair of
200kW chillers (with heat recovery)
whose main function is to serve
computer room air conditioning plant.
In practice the cooling tower circuit
First published: IQ News June 1999
Cellnet 2pp 2/11/06 09:53 Page 1
![Page 2: CASE STUDY NUMBER ONE FOR ENERGY EFFICIENCY · 2010. 6. 21. · phone operator Cellnet, it became immediately apparent that this would not meet their needs – largely because the](https://reader034.vdocuments.site/reader034/viewer/2022051808/60090e68d2806b15025e7382/html5/thumbnails/2.jpg)
Trend Control Systems LimitedP.O. Box 34, Horsham, West Sussex, RH12 2YF, UK. Tel: +44 (0)1403 211888 Fax: +44 (0)1403 241608 www.trend-controls.com
copes unaided virtually all of the time.
Indeed, the chilled water valve has
gone months without opening at all.
All of the cooling/chilled water plant is
automatically controlled and monitored
by the Trend BMS, as is the air
handling plant, boilers and heating/hot
water circuits. Many of the strategies it
implements are designed to save
energy by avoiding unnecessary plant
operation. For instance, on the cooling
tower circuit it closely regulates pump
and tower fan speeds (via inverter
drives) in strict accordance with
demand. In operating the main AHU, it
constantly monitors air quality
throughout the space and controls the
recirculation damper and fan speeds
accordingly, one effect of which is to
prevent energy wastage when building
occupancy levels fall. Among its many
other tasks, the BMS also controls the
AHU’s heat recovery system to achieve
maximum savings.
The BMS comprises nine Trend IQ
intelligent controllers of various sizes.
Two were installed when the original
plant went in and AES has had to
modify and expand the control
strategies these implement. Owing to
the IQ’s ease of configuration this did
not present problems. The system’s
main operator interface is a graphics-
based Trend 945 supervisor, which is
used by the building’s facilities
manager and maintenance team.
Northampton-based Sonofoss also
has a 945, through which they can
remotely monitor the building (via
modem) – a facility that has proved
extremely valuable. For example it
allowed Sonofoss to spot that the
AHU’s heat recovery dampers were
working incorrectly – just the sort of
fault which could have gone unnoticed
for months and cost thousands of
pounds in wasted energy. It has also
revealed ways in which the control
strategies can be enhanced.
The system has also been monitoring
the site’s gas and electricity
consumption and the figures have
been used in a report on the building
produced by consultants ECD. Data
collected during a four month
monitoring period showed a total
energy usage equating to carbon
dioxide emissions of just 37kg/m2/yr.
Though excellent energy efficiency has
already been achieved there is still
scope for further savings through
measures such as fine tuning of certain
control settings and modifying some
aspects of how plant is operated.
AES Control Systems can be
contacted on 01604 790606.
Current issue: Oct 2006
Cellnet 2pp 2/11/06 09:53 Page 2