building construction 2 project 1 report

12
INDEX Exploration -Design 1 -Design 2 1 2 Mock up model -Structural Analysis -Failure Analysis 3 4 Final Model - Construction Process - Structural Analysis - Model Testing 1 -Timelapse -Model Testing 2- Timelapse -Success & Failure Analysis 5 6 7 8-9 10 Conclusion 11 1

Upload: hiewyennee

Post on 06-May-2015

439 views

Category:

Design


1 download

DESCRIPTION

Project 1: Understanding Forces in Skeletal Structure

TRANSCRIPT

Page 1: Building Construction 2 Project 1 Report

INDEX

Exploration -Design 1 -Design 2

1 2

Mock up model -Structural Analysis -Failure Analysis

3 4

Final Model - Construction Process - Structural Analysis - Model Testing 1 -Timelapse -Model Testing 2- Timelapse -Success & Failure Analysis

5 6 7

8-9 10

Conclusion 11

1

Page 2: Building Construction 2 Project 1 Report

Exploration –DESIGN 1

100mm away from the tip of the popsicle stick, a 2mm x 50mm slit is cut to enable interlocking of popsicles sticks to form a interlocked square as horizontal component of the tower.

Using the same method above, the slit is cut in the middle of the popsicle sticks. Cross bracing is created in order to transfer force diagonally.

Cross bracing is slot into the vertical and horizontal components and will be tied to the connecting point.

Advantages

•Cross bracing helps to spread the load evenly to the both sides. •A total number of eight vertical components help to strengthen the load carry capacity of the structure.

Disadvantages •High shearing force between the components as the cross bracings are not tie together with the vertical and horizontal components. •Middle part of the horizontal component breaks easily when a load applies to it as it only supported by the vertical component.

1

Page 3: Building Construction 2 Project 1 Report

Exploration - DESIGN 2

• A slit is cut on diagonal structure to connect to the vertical

and horizontal component.

• String is then used to tie all three components together to

overcome shear stress.

• Vertical and horizontal component are connected

with toothpick and string to create one surface.

• A slit is cut 5mm away from the hole on the horizontal

component.

• Two surfaces are connected by interlocking the

horizontal components.

Advantages •Toothpick acts as a support to the whole structure. •High friction between the components and the toothpick gives a small shearing force to the components. •A total number of eight vertical components help to strengthen the load carry capacity of the structure.

Disadvantages •Horizontal component cracks easily when the slit is cut too near to the hole which as a result weakens the load carry capacity of it. •The popsicle stick cracks easily when a force applies to the pin is press directly into it. •A big slit is cut in the narrow area of the diagonal component which as a result causing it to crack.

2

Page 4: Building Construction 2 Project 1 Report

From design 1 and 2, a problem that we found was the joining part of the vertical component as we have no idea how to connect the upper part of the vertical component to the lower part. Before that, we planned to join the upper part of vertical component by overlapping it end to end to the lower part of vertical component. However, we found that force is not transmit vertically from part to the other part. So, we couldn’t use the overlapping method in these designs.

Force can’t transmit vertically to the lower part of the vertical component

Force transmit vertically to the lower part of the vertical component

In order to make the force transmits vertically downward, we decided to join them by connecting them end to end to each other. In order to make them more stable, we cut out the rounded part of the vertical components and crafted a inverted ‘V’. To increase their strength, we doubled them by joining them with toothpick.

For the horizontal components, we cut a slit from 1cm away in the end of them and then joined them by interlocking them to each other to create a surface. After that, we connect it to the vertical component with toothpick and string like the method of Design 1.

For the bracing, initially, we planned to use cross bracing. However, we found that we had overused the popsicle stick as we only allow to use maximum 100 sticks. So, we decided to diagonal bracing only.

The reasons that we added bracing was to avoid the whole structure from shearing and also it helps to transfer force diagonally to the next component. Besides, we also added bracing at the bottom of the structure to reduce force of the vertical component and to make the whole structure stable.

MOCK UP MODEL’s STRUCTURAL ANALYSIS

3

Page 5: Building Construction 2 Project 1 Report

Inappropriate installation of the bracings When the uneven force exerted on the tower, compression occurred at one side of the bracings, however bracings of opposite side will experience tension. Due to the uneven spreading of load, the tower will tend to fall on the side where compression occurred.

Uneven Contact point with the load and floor Due to the uneven length of vertical members, not every members contact to the floor and the load above. This will directly affect the stability of the tower which is also the main cause for the falling of tower when carrying load

Incompatible vertical members The connection of the vertical members are not consistent due to the lack of accuracy. The inverted “V” of the vertical members were not crafted accurately.T he contact points of the vertical members had gaps after the tying stage. Due to the lack of efficiency, the vertical members are crooked.

Slot to slot horizontal bracings The cut slots weaken the load carrying capacity of the popsicle sticks.This is due to the narrow surface area of the lock and key joints. This had result in an uneven surface of the square.

Unattached joints Load cannot transfer straight down through the unattached “V” joints. In contrast, toothpicks withstand the load

FAILURE ANALYSIS OF MOCK UP MODEL

4

Page 6: Building Construction 2 Project 1 Report

FINAL MODEL‘s CONSTRUCTION PROCESS

5

Page 7: Building Construction 2 Project 1 Report

Zig Zag Pattern of Bracing Installation Due to the uneven load distribution of the single diagonal bracing arrange in parallel way, we change the arrangement of bracing to zigzag pattern. This is because if one side of the tower experience greater force than the other side ,the compressive force will be offsetting by the tensile force exerting on the opposite bracing. This will increase the strength of the tower. Other than that ,compressive force will not only concentrate on one side if uneven force exerted

Horizontal Bracing at the Bottom Instead of allowing only four contacting point to the floor, we improved our design by adding one more horizontal bracing to the bottom of tower ,to increase the surface area contacting to the floor. This will further enhance the stability of the tower and compensate the minor unequal length of vertical members due to human error.

Changing V joints to flat joints Due to the technical difficulty, we replaced V join by using flat join , The straight cut surface allowed full contact with the adjoining members. When load was applied, load can transfer straight down through the well joined vertical members .

Using Vertical Core as Formwork The eight vertical members are temporary attach to a vertical wooden block which function as a guideline which result having a straight structure. BY using this mechanism , less error will be occurred as different parts were able to collaborate well during assembly process .As a result, the structure was firm even before the tying process. This vertical block was also increase the accuracy and efficiency for the construction of tower

Increased layers of thread on the joins Bracings, vertical and horizontal members are tied as one so they are not likely to slide or shear off. It will hold and fix the members to prevent movement of members in pressure.

STRUCTURE ANALYSIS OF FINAL MODEL

6

Page 8: Building Construction 2 Project 1 Report

Four 10kg load was put on the

model Six 5kg load was added on

Total : 40 + 30 = 70kg

Six 2.5kg load was added on

Total :70+ 15 = 85 kg

Ten 1.25kg load was added on

Total: 85+12.5= 97.5kg

Four 5kg and four 2.5kg was added on

Total : 97.5 +30 = 127.5 One 10kg load was added was added

Total = 127.5 + 10 = 137.5

Model Testing 1 -Timelapse

7

Page 9: Building Construction 2 Project 1 Report

Model testing 2 time-lapse

20kg was put on the

model.

20kg was added on

to the model.

Total: 40kg

(15+15+15kg)=

45kg was added on

to the model.

Total: 85kg (10+10+10kg)=

30kg was added on

to the model.

Total: 115kg

10kg was added on

to the model.

Total: 125kg

8

Page 10: Building Construction 2 Project 1 Report

(2.5+2.5+2.5kg)=

7.5kg was added on

to the model.

Total: 162.5kg

(15+10+10+10kg)=

30kg was added on

to the model.

Total: 155kg

(2.5+2.5+2.5+1.25+

1.25kg+)= 10kg was

added on to the

model.

Total: 172.5kg

(1.25+1.25+1.25kg)

= 3.75kg was added

on to the model.

Total: 176.25kg

The upper part of

the model was

bended toward the

right.

The model

collapsed at the load

of 176.25kg.

9

Page 11: Building Construction 2 Project 1 Report

ANALYSIS OF FINAL MODEL (AFTER TESTING)

After the testing, we have noticed that the breaking points are at the connections of the vertical component. This is because when the vertical component is under compression, the vertical component tend to bend. When the vertical components are bent, it becomes weaker as only one stick is holding the weight of the load. This problem can be overcome by reinforcing the connections with more thread.

Before After

Efficiency = Load Held (Kg) / Mass of Tower (Grams) x Height of Tower (cm)

= 176.25kg / 108g x 30cm

= 48.96 Success The efficiency of our model is relatively high. This is due to the success of our design and our design process. At the breaking point of our model, it can be seen that the load fell quite vertically compared to our mock up model. This is due to the more even base of the final model and also the stacking of the loads. In our final testing, we have ensured that the weights are put in such a way that load is distributed evenly to the ground. The double layer vertical component had made the model successful. We have estimated that the load will be transferred vertically downward, hence, we reinforced the vertical components by putting double layer. The horizontal and diagonal components have successfully held and braced the vertical component to avoid shearing and compression.

Failure compression

compression

compression

compression

Strength of popsicle sticks do not weaken when bent

Strength decreased as only one popsicle stick is holding the load transmitted through it.

10

Page 12: Building Construction 2 Project 1 Report

Conclusion

From project 1, we have a better understanding of skeletal structure, its relevant structural components, understand how a skeletal structure reacts under loading, understanding of how it works and even be able to manipulate it to solve an oblique design problem. Therefore, we can apply the technique into construction system design by considering the issues of strength, stiffness and stability of structures including modes of structural systems, forces, stress and strain and laws of static.

11