brief analysis of variable renewable energy contribution during … · 2019-04-24 · 1 brief...
TRANSCRIPT
1
Brief analysis of variable renewable energy contribution during loadshedding (Q1-2019)CSIR Energy Centre
CSIR Energy CentrePretoria. 15 April 2019v1.1
JARRAD [email protected]
JOANNE [email protected]
2
Key takeaways
A constrained power system meant South Africa had to loadshed again in Q1-2019
• The RSA power system again became constrained in Q1-2019 with Eskom needing to loadshed (Stage 4 at times)
• Causes of loadshedding have been cited as high unplanned plant failures on the thermal coal fleet, the loss ofCahora Bassa import from Mozambique followed by intensive use of diesel (at OCGTs) and water (at pumpedstorage schemes) which eventually depleted1
• This has been the most intensive loadshedding experienced in RSA with 595 GWh of load shed just in March 2019of the total 769 GWh in Q1-2019 (there was 1325 GWh of loadshedding throughout 2015)
The utility-scale VRE fleet notably contributed to limit the extent of loadshedding in Q1-2019
• The utility-scale VRE fleet2 contributed 2 975 GWh (5.3%) to the RSA power system in Q1-2019 with monthlycontributions ranging from 4.9-6.0%, weekly contributions from 4.1-7.0% and daily contributions from 2.9-7.7%
• During loadshedding periods, the utility-scale VRE fleet contributed 357 GWh of the total 2975 GWh from VREduring Q1-2019 i.e. loadshedding could have increased from 769 GWh to 1126 GWh (a 46% increase)
• Instantaneous contributions from the VRE fleet during loadshedding periods was up to 2.3 GW i.e. without the VREfleet, loadshedding stage 5 & 6 could have been envoked
1 Department of Public Enterprises, UPDATE : ESKOM ELECTRICITY SUPPLY, 03 April 2019; 2 1.5 GW solar PV, 2.0 GW wind and 0.5 GW CSP (CSP is marginally dispatchable considering coupling with thermal storage)
RSA = Republic of South Africa; VRE = variable renewable energy
3
100
600
200
300
400
250
0
450
50
550
150
350
500
Apr-18
21
6
6
Jul-18
39
GWh of load shedding
306
164122
5
42
Jan-15
Feb-19
200
Nov-15
71
Feb-15
36
36
Mar-15
60
Nov-18
122
156
77
Aug-15
56
May-15
Jul-15
40
260
Jun-15
84
19
Oct-15
Dec-15
Jan-18
Aug-18
384
Feb-18
Mar-18
May-18
Sep-18
15
Oct-18
24
Jun-18
106
32
Dec-18
Jan-19
36
54
190
Sep-15
Mar-19
63
283
Apr-15
233
178
49
3
43
138
174
595
184
27
12
63
Stage 4 Stage 1Stage 3 Stage 2
First 3 months of 2019 – most intensive loadshedding in March with 595 GWh of 769 GWh in 2019... 1325 GWh throughout 2015
Year
2015
2016
2017
2018
2019
Energy (GWh)
1325
-
-
192
769
Duration (hours)
858
-
-
127
272
Notes: Load shedding assumed to have taken place for the full hours in which it was implemented. Practically, load shedding (and the Stage) may occassionally
change/end during a particular hour; Total GWh calculated assuming Stage 1 = 1 000 MW, Stage 2 = 2 000 MW, Stage 3 = 3 000 MW, Stage 4 = 4 000 MW
Sources: Eskom Twitter account; Eskom se Push (mobile app); CSIR analysis
4
Loadshedding in 2015 predominantly during high demand periods (day and evening peaks)… most recently in 2019 this has been day/night
Hour of the day -->
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Total
Jan 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Feb 0 0 0 0 0 0 0 0 8 10 10 10 10 14 14 14 14 14 14 14 14 14 0 0 174
Mar 13 13 13 13 13 13 13 13 19 30 31 32 33 33 33 34 34 34 34 34 34 34 29 13 595
No load shedding
No load shedding
2015
2016
2017
2019
2018
Notes: Load shedding assumed to have taken place for the full hours in which it was implemented. Practically, load shedding (and the Stage) may occassionally
change/end during a particular hour; Total GWh calculated assuming Stage 1 = 1 000 MW, Stage 2 = 2 000 MW, Stage 3 = 3 000 MW, Stage 4 = 4 000 MW
Sources: Eskom Twitter account; Eskom se Push (mobile app); CSIR analysis
No Loadshedding
Intensive loadshedding
Loadshedding intensity (per year)
5
450100
100
BW 2 BW 4BW 1 BW 3
100
BW 3.5 BW 4Expedited
15050
200200 450
649 559
676 650
686
BW 2 BW 3 BW 3.5BW 1 BW 4 BW 4Expedited
787
1 362
650
415591
398
BW 3.5BW 3BW 1 BW 2 BW 4 BW 4Expedited
627417 435
813591
Supply Sources
Notes: RSA = Republic of South Africa. Wind excludes Eskom’s Sere wind farm (100 MW). BW = Bid Window. PPA = Power Purchase Agreement. BW 4 includes BW 4 additional.Sources: Eskom; DoE IPP Office
Procured and operational capacity under RSA’s RE IPP Procurement Programme (REIPPPP) with only 100 MW of CSP added in Q1-2019
2078 MW 1479 MW
Capacity operational(1 January 2019)
400 MW 2078 MW 1479 MW 500 MW
435
415
398
BW 4BW 3BW 2BW 1 BW 3.5 BW 4Expedited
627417
813591
649 559787
676 650
686
BW 4Expedited
BW 2BW 1 BW 3 BW 3.5
650
1 362
BW 4
200450
100
100
BW 2
50
BW 4BW 1 BW 3 BW 3.5 BW 4Expedited
150 200200 450
Capacity operational(31 March 2019)
Solar PV procured,PPAs not signed yet
Solar PV procured,PPAs signed
Solar PV operational
Wind procured,PPAs not signed yet
Wind operational
Wind procured,PPAs signed
CSP procured,PPAs not signed yet
CSP procured,PPAs signed
CSP operational
6
257560
1 075
300 400 500210
960
965
1 460
2 078 2 078 2 078
1 479
1 479 1 479 1 479
467
2018
3 857
2013 2015
3 139
2014 2016
200
2020
2 040
2017
3 957 4 057
2019(Q1)
1 520
+1 053
+520
+1 094
+718 +100 +100
Wind
Solar PV
CSP
Supply Sources
Notes: RSA = Republic of South Africa. Solar PV capacity = capacity at point of common coupling. Wind includes Eskom’s Sere wind farm (100 MW). Sources: Eskom; DoE IPP Office
From 1 November 2013 to 31 March 2019, 2 078 MW of wind, 1 479 MW of large-scale solar PV and 500 MW of CSP became operational in RSA
Capacity operational [MW]
7
Notes: Wind includes Eskom’s Sere wind farm (100 MW). CSP energy measured from date when more than two CSP plant were commissioned. Wind and solar PV energy excludes curtailment and is thus lower than actual wind and solar PV generation
Sources: Eskom; DoE IPP Office
In Q1-2019 - 3.0 TWh of wind, solar PV and CSP energy was produced in RSA with estimates of over 12 TWh for 2019 expected
Supply Sources
Annual energy produced [TWh] 12.4
4.7
5.0
0.05
2013
6.5
1.1
2014
1.1
2.2
1.62.5
2015
2.6
3.7
0.01
9.0
2.2
0.5
2016
3.3
0.7
2017
3.3
6.9
1.0
9.4
2018
0.9
0.4
2019 2020
0.1
10.8
Wind
Estimate for rest of 2019
Solar PV
CSP
8
176 121 137
649
485 503
337
273294
0
100
200
300
400
500
600
700
800
900
1 000
1 100
1 200
1 300
1 400
Monthly electricity production in GWh
1 161
880933
5.0%
6.0%
4.9%
Monthly electricity production of SA’s wind, solar PV and CSP fleet ranging from 4.9-6.0% (similar to previous year)
Solar PV
Wind
CSP
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Supply Sources
Note: Wind generation includes Eskom’s 100 MW Sere wind farm. CSP energy only measured from date when more than two CSP plant were commissioned.Wind and solar PV energy excludes curtailment and is thus lower than actual wind and solar PV generation.
Sources: Eskom; CSIR Energy Centre analysis
Capacity operational
(1 Jan-31 Mar)
2078 MW
1479 MW
500 MW
% of totalsystem load
9
Monthly electricity production from wind, solar PV, CSP, residual loadand loadshedding impact in Q1-2019
0
18
2
10
20
4
6
8
12
14
16
22
19.3
Monthly electricity production in TWh
18.216.8
18.2
17.9
19.8
Loadshedding
Solar PV
ResidualLoad
CSP
Wind
Notes: Pumping load excluded. Wind generation includes Eskom’s 100 MW Sere wind farm. Sources: Eskom; CSIR Energy Centre analysis
Supply Sources
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Capacity operational
(1 Jan-31 Mar)
2078 MW
1479 MW
500 MW
10
0
50
100
150
200
250
300
350
400
450
13 4037 4322
Electricity productionin GWh/week
1 4 7 10 16 19 25 28 31 34 46 49 52
5.9%
5.7%
6.9%
6.1%
4.5%
5.6%
4.5%
5.2%4.9%
5.8%
4.8%
4.1%
Weekly contribution from utility-scale RE in first 3 months of 2019 ranges from 4.1-6.9% of total system demand
Note: Design as per Fraunhofer ISE. Sources: Eskom; CSIR Energy Centre analysis
% of totalsystem load
CSP
Solar PV
Wind
Supply Sources
2078 MW
1479 MW
Capacityoperational
500 MW
11
Weekly electricity production wind, solar PV, CSP, residual load and loadshedding in Q1-2019
0
500
1 000
1 500
2 000
2 500
3 000
3 500
4 000
4 500
5 000
1 40
Electricity production in GWh/week
4 7 10 13 16 19 433122 25 5228 34 37 46 49
Supply Sources
Note: Week 1 only 6 of 7 days; Design as per Fraunhofer ISE. Pumping load excluded. Sources: Eskom; CSIR Energy Centre analysis
Loadshedding
Wind
CSP
Solar PV
ResidualLoad
2078 MW
1479 MW
Capacityoperational
500 MW
12
For Jan-Mar 2019, electricity production from wind, solar PV and CSP was above 25 GWh/d 90% of the time with maximum of 48 GWh/d
0
5
10
15
20
25
30
35
40
45
50
Electricity productionin GWh/day
Supply Sources
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Note: Design as per Fraunhofer ISE.Wind includes Eskom‘s Sere wind plant. Sources: Eskom; CSIR Energy Centre analysis
Wind
Solar PV
CSP
2078 MW
1479 MW
Capacity operational
(end of month)
400 MW
13
Daily electricity production of between 543-666 GWh in Jan 2019 with VRE contributing 5-8%
0
100
200
300
400
500
600
700
800
21
GWh/day
73 171541 2 285 6 261311 149 16 18 198 292010 22 2423 25 30 312712
CSP
Solar PV
Wind
ResidualLoad
Loadshedding
Supply Sources
2078 MW
1479 MW
Capacity operational
(end of month)
Note: Design as per Fraunhofer ISE. Daily production excludes pumping load. Wind includes Sere. Sources: Eskom; CSIR Energy Centre analysis
400 MW
14
Daily electricity production of between 593-672 GWh/d in Feb 2019, VRE supplied 3-6% of system demand and up to 7% of load was shed
0
100
200
300
400
500
600
700
800
2 30
GWh/day
24 2815131 3 4 6 297 8 9 10 2011 1812 1714 16 19 21 22 23 25 26 27 315
ResidualLoad
Loadshedding
Solar PV
CSP
Wind
Supply Sources
Capacity operational
(end of month)
Note: Design as per Fraunhofer ISE. Daily production excludes pumping load. Wind includes Sere. Sources: Eskom; CSIR Energy Centre analysis
2078 MW
1479 MW
500 MW
15
Daily electricity production of 538-658 GWh/d in Mar 2019, VRE contributed 3-7% everyday and up to 14% of load was shed
0
100
200
300
400
500
600
700
800
28 3127
GWh/day
21 4 6 239 10 3012 1513 14 16 18 20 21 22 2924 25 26753 8 17 1911
Solar PV
CSP
Wind
Loadshedding
ResidualLoad
Supply Sources
Capacity operational
(end of month)
Note: Design as per Fraunhofer ISE. Daily production excludes pumping load. Wind includes Sere. Sources: Eskom; CSIR Energy Centre analysis
2078 MW
1479 MW
500 MW
16
0.0
2.0
0.5
1.0
1.5
2.5
3.0
3.5
4.0
GW
CSP
Solar PV
Wind
Hourly VRE production in Jan 2019 shows periodic solar PV and CSP; wind varies but contributes notably during evening peaks
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
SupplySources
Note: Design as per Fraunhofer ISE. Pumping load excluded.Sources: Eskom; CSIR Energy Centre analysis
2078 MW
1479 MW
Capacity operational
(end of month)
400 MW
17
2.0
4.0
0.0
1.0
2.5
0.5
1.5
3.0
3.5
GW
Wind
Solar PV
CSP
Hourly VRE electricity production in Feb 2019 shows how loadsheddingcould have increased to Stage 5-6 without VRE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
SupplySources
Note: Design as per Fraunhofer ISE. Pumping load excluded.Sources: Eskom; CSIR Energy Centre analysis
2078 MW
1479 MW
Capacity operational
(end of month)
500 MW
3 124
Loadshedding stage
18
0.0
2.0
1.5
1.0
0.5
2.5
3.0
3.5
4.0
GW
Solar PV
Wind
CSP
Hourly VRE electricity production in Mar 2019 shows again how loadshedding could have increased to Stage 5-6 without VRE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
SupplySources
Note: Design as per Fraunhofer ISE. Pumping load excluded.Sources: Eskom; CSIR Energy Centre analysis
2078 MW
1479 MW
Capacity operational
(end of month)
500 MW
4 3 2 1
Loadshedding stage
19
0
5
15
20
10
25
30
35
40
GW
SupplySources
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Hourly electricity production in Jan 2019 highlighting role of VRE fleet
Note: Design as per Fraunhofer ISE. Pumping load excluded.Sources: Eskom; CSIR Energy Centre analysis
2078 MW
1479 MW
Capacity operational
(end of month)
400 MW
ResidualLoad
Loadshedding
CSP
Solar PV
Wind
20
0
5
30
15
10
20
25
35
40
GW
Loadshedding
ResidualLoad
Solar PV
Wind
CSP
Hourly electricity production in Feb 2019 with 5 days of loadshedding
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
SupplySources
Note: Design as per Fraunhofer ISE. Pumping load excluded.Sources: Eskom; CSIR Energy Centre analysis
2078 MW
1479 MW
Capacity operational
(end of month)
500 MW
5 days of loadshedding
21
15
0
5
10
20
40
25
30
35
GW
Loadshedding
Wind
CSP
Solar PV
ResidualLoad
Hourly electricity production in Mar 2019 with 10 days of loadshedding
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
SupplySources
Note: Design as per Fraunhofer ISE. Pumping load excluded.Sources: Eskom; CSIR Energy Centre analysis
2078 MW
1479 MW
Capacity operational
(end of month)
500 MW
10 days of loadshedding
22
0
20
30
2
14
16
4
6
28
8
12
26
22
24
32
34
18
36
10
Power in GW
Loadshedding
Wind
PV
CSP
Residual (Eskom)
Sources: Eskom; CSIR Energy Centre analysis
Significant contribution from VRE during loadshedding in Feb 2019 –103 GWh and a maximum inst. contribution of 2.0 GW
2078 MW
1479 MW
Capacity operational
(end of month)
500 MW
System demand
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Week of 11-17 February 2019
Supply Sources
23
10
14
18
22
26
34
0
28
20
32
30
36
16
2
4
6
8
12
24
Power in GW
Loadshedding
PV
Residual (Eskom)
Wind
CSP
Supply Sources
Sources: Eskom; CSIR Energy Centre analysis
Similarly, VRE provided valuable capacity during loadshedding in March 2019 – 254 GWh and a maximum inst. contribution of 2.3 GW
System demand
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Week of 18-24 March 2019
2078 MW
1479 MW
Capacity operational
(end of month)
500 MW
24
LDC = Load Duration Curve; 1 When demand is >90% of peak demand; VRE = variable renewable energy (solar PV, wind and CSP)Sources: Eskom; CSIR Energy Centre analysis
0 200 400 600 800 1000 1200 1400 1600 1800 2000 2200
10
0
2
18
16
22
20
34
14
12
26
8
38
6
30
4
32
24
28
36
40
Hours of the year (sorted)
Power in GW
-1.1 GW
System demand (before loadshedding)
Residual demand (after VRE & loadshedding)
System demand (after loadshedding)
VRE reduced peak by 1.1 GW & high demand hours notably; loadshedding could have increased by as much as 46% without VRE
LDC (1 Jan – 31 Mar 2019)
With VRE fleet, peak demand wasreduced by 1.1 GW.
1But more importantly, high demandhours1 were reduced from 730 hrs to144 hrs.
2
2
1
2
357 GWh of 2975 GWh from VRE was during loadshedding between Jan-Mar 2019.
Without VRE, loadshedding would have been more severe, it could have increased by 46% from769 GWh to 1126 GWh.
25
Thank you