bridge preservation classification
TRANSCRIPT
4/19/2013
1
Nebraska Statewide Bridge Conference
April 16, 2013
Anwar S. Ahmad, P.E.
Bridge Preservation Engineer
Federal Highway Administration
Office of Bridges and Structures
Topics Bridge Preservation Overview
Bridge Preservation Program Implementation Strategies
Examples of Deck Preservation Techniques
What is Bridge Preservation?Actions or strategies that prevent, delay or reduce deterioration of bridges or bridge elements, restore the function of existing bridges, keep bridges in good condition and extend their useful life. Preservation actions may be preventive or condition‐driven.
This Definition was adopted by AASHTO SCOH in Sep. 2011
Bridge Preservation
Preventive Maintenance
Cyclical (Non‐Condition Based)
Activities
Condition Based Activities
Rehabilitation
Bridge Replacement
Bridge Preservation Classification
Why Bridge Preservation?
Public safety
Cost effective
Minimum traffic disruption
Lower user cost
Reduce the need to replace
Preventive Maintenance
Preventive maintenance (PM) is considered a component of preservation
PM includes cyclical and condition based activities
Bridge Preservation
Preventive Maintenance
Cyclical (Non‐Condition Based)
Activities
Condition Based Activities
4/19/2013
2
Preventive Maintenance
Examples of condition based PM activities include:
• Sealing or replacing leaking joints
• Sealing concrete cracks
• Complete, spot, or zone painting of steel elements
• Scour countermeasures installation
Preventive Maintenance
Cyclical PM Activity ExamplesCommonly
Used Frequencies
Clean/Flush bridge decks or entire bridge Annual
Seal decks with waterproofing penetrating sealant 3 to 5 Years
Lubricate bearing devices 2 to 4 Years
Clean/flush drainage system Annual
Clean/flush culverts 1 to 2 Years
Coat timber elements with wood preserver 1 to 2 Years
Rehabilitation Examples of Rehabilitation activities include:
• Deck repairs and installation of overlay
• Repairs and restorations of superstructure, substructure, and culverts
• Functional improvements such as adding a travel lane or raising vertical underclearance are not considered preservation.
Bridge Preservation
Preventive Maintenance
Rehabilitation
Replacement
Bridge replacement is an important activity, but not considered a preservation activity.
Examples of Preservation Activities
Seal or replace leaking joints or elimination of deck joints
Deck overlays
Examples of Preservation Activities
4/19/2013
3
Spot, zone, and complete coating of structural steel elements.
Examples of Preservation Activities
Installation of Cathodic Protection (CP) Systems.
Examples of Preservation Activities
Installation of scour countermeasures.
Removing large debris from channels.
Examples of Preservation Activities
Application of concrete sealants, coatings.
Bridge cleaning and/or washing service.
Examples of Preservation Activities
CopiescanmayorderedfromtheFHWAReportCenterEmail:[email protected]:(814)239‐1160OrContactAnwarAhmadEmail:[email protected]:(202)366‐ 8501
Copiesmaybedownloadedfromhttp://www.fhwa.dot.gov/bridge/preservation/guide/guide.pdf
Bridge Preservation Guide
Implementation Strategies for Bridge Preservation Program
4/19/2013
4
Program Goal
Example: Implement timely preservation treatments on structurally sound bridges, thereby extending their useful life.
Objectives & Measures
Example: Maintain 90 percent of bridges in a state of good repair.
Measure: Percent of bridges with element condition state ≤ 2.
Measure: Percent of bridges with NBI general condition rating ≥ 6.
Condition Assessments
Safety Inspection (NBIS)
Element Level Inspections
Work Activities
Identify Feasible and Cost Effective Activities & Treatments, and
Classify Activities Under Major Programs For Ease of Management.
For example, work activities can be classified under three programs: Preventive Maintenance, Rehabilitation, and Replacement/Improvement
PreservationImprovement
Preventive Maintenance RehabilitationBridge Cleaning/Washing Deck Repairs and Installation of Thin Bonded Overlay Bridge Replacement
Deck Joint Maintenance/Repairs Deck Repairs and Installation of Rigid Bonded Overlay Bridge Widening/Raising
Deck Joint Replacement Deck Repairs and Installation of Thin Bonded Overlay, and Cathodic Protection
Bridge Relocation
Deck Surface Repairs Deck Repairs and Installation of Rigid Bonded Overlay and Cathodic Protection
Culvert Replacement
Rail Maintenance/Repairs Superstructure Rehabilitation Culvert ExtensionCrack Sealing Superstructure Repairs and Painting
Deck Sealing Retrofitting Fatigue Prone Details/Fracture Critical Members
Installation of Thin Bonded Deck Overlay Substructure Rehabilitation
Installation of Rigid Bonded Deck Overlay Culvert Rehabilitation
Superstructure Maintenance/ Surface Repairs Culvert Lining/Sleeving
Superstructure Spot/Zone Painting Substructure Repairs and installation of Pile Jacketing
Complete Superstructure Painting
Substructure Maintenance/ Surface Repairs
Culvert CleaningChannel Debris Removal
Installation of Scour Countermeasures
Pile Jacketing
Work Activities Examples
FundingDetermine needs and funding levels
Identify unmet needs
Determine funding and resource needs for meeting your program goal and objectives
Compare the unmet needs and targeted needs with allocated funds (authorized budget)
Develop short and long‐term plans
Seek or make adjustments to budget
4/19/2013
5
Work Plan Select and rank candidate projects
Classify projects based on work groups as discussed earlier (PM, Rehab, Improvement)
Conduct LCCA
Update your projects estimates
Group projects based on type and location (Site specific, Multiple sites, Corridor, Region‐wide, etc.)
Examples of Deck Preservation Techniques
Cyclical cleaning
Cyclical sealing and waterproofing
Installation of overlay
Deck Cleaning Sweeping
Pressure washing
Sealing and Waterproofing
Penetrating Sealers: These sealers include silanes which are absorbed into the concrete and react with it to form a hydrophobic (water repellant) surface
Surface Preparation
Follow the manufacturer's cleaning instructions
Power sweeping should be used to remove dirt and debris.
Shot blasting, sand blasting, or power washing must be used to remove grease, oil, and surface contaminants.
Surface Preparation: Shot‐blasting
30
4/19/2013
6
Application
Sealer is applied by spray or pour application in accordance with manufacturer‘s recommendations.
Sealer is applied at the appropriate coverage and number of coats according to the manufacturer’s recommendations.
Sealer is allowed to cure for a sufficient time prior to opening to traffic (2 to 6 hours)
Crack Sealer: Non‐moving Crack Being Filled
The resin poured into the crack and distributed by brush
Sealing Application
Material is poured out on concrete and moved along the deck using solvent resistant rollers on extension polls.
33
Deck Overlay
Hydraulic cement overlays include:
Latex modified with Type I/II cement (LMC)
Latex modified with very early strength cement (LMC‐VE)
Silica Fume with Type I/II cement (SF)
Thin Epoxy Polymer Overlay
Hydraulic cement overlays Surface Preparation
Remove deteriorated concrete (milling, or hydrodemolityon, or saw cut and jackhammer)
Clean surface with shot blasting
Complete a final cleaning within 24 hours prior to overlay.
An hour before overlay, water‐soak the surface and cover with plastic
Leave surface wet and covered until overlay is placed
Prepared Surface
4/19/2013
7
Broom overlay mortar over surface, screed consolidates and strikes‐off overlay
Mobile mixer discharges concrete.Fogging increases relative humidity
Curing: wet burlap is placed on overlay as soon as practical
Curing: polyethylene is placed on wet burlap as soon as practical
Finished Product
Polymer overlays are placed on bridge decks to reduce infiltration of water and chloride ions and to improve skid resistance and surface appearance.
2 layers of epoxy and broadcasted aggregate placed on a dry, shot blasted surface.
Test patches done to verify materials, surface preparation, mixing and placing of materials are acceptable.
Overlay is 1/4 to 3/8 in thick.
Polymer overlay resins are typically epoxy, methyl methacrylate or polyester based
Thin Epoxy Polymer Overlay
4/19/2013
8
Ensure that the surface is clean and dry prior to application.
Pour polymer on the deck surface.
Work polymer into deck with a regular squeegee.
Cast aggregate over polymer.
After a couple hours, remove the unbounded aggregate.
Apply a second layer of polymer and aggregate.
Properly dispose contaminated material.
Procedure
Surface Preparation by Shot Blasting
drywall mud mixer
Mixing must be complete so that 1 or 2 parts A and 1 part B make contact and cure properly.
50‐ml gel sample is taken from each batch
Test Patch
• Shot blasted surface, duct tape, epoxy layer one, and broadcast aggregate
• The next day the overlay is cored at 3 locations for bond testing
Test Patch
4/19/2013
9
Spreading Epoxy
• 2 layers of epoxy & broadcasted aggregate 0.25‐in thick
Broadcasting Aggregate
51
Spreading 2nd Layer of Epoxy and aggregates
Bridge preservation should be integrated in all core phases of bridge’s life…….. “cradle to grave”
Building an effective bridge preservation program entails a proactive and balanced approach
Implementing an effective bridge preservation program calls for appropriate tools and resources
Achieving optimum results is accomplished by applying the appropriate treatments/strategies at the right time
Summary
Anwar S. Ahmad, P.E.Bridge Preservation Engineer
Federal Highway AdministrationTelephone: (202) 366‐8501
Email: [email protected]
Thank You