CROSSTOWN LRT Construction Liaison Committee Brentcliffe Victoria Park June 1, 2017

Upload: crosstown-to

Post on 22-Jan-2018

2.192 views

Category:

Government & Nonprofit


0 download

TRANSCRIPT

Page 1: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

CROSSTOWN LRTConstruction Liaison CommitteeBrentcliffe – Victoria ParkJune 1, 2017

Page 2: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

2

Agenda

• West At-Grade (East Portal to Victoria Park Stop) Update

• Science Centre Station Update

Page 3: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

3

What Are We Building

• 15 underground stations and 10 surface stops – 9 km below ground and 10 km above ground

• A maintenance and storage facility

• A 19-kilometre route separated from regular traffic

• Transit communications system

• Links to 54 bus routes, three subway stations, GO Transit, and a new UP Express station

Page 4: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

4

Safety First – Our #1 Priority

We train and direct staff to:

• Always have a site specific safety plan and site specific emergency plan.

• Ensure pre-work hazard assessments are complete and understood.

• Ensure job hazards analyses are complete and understood.

• Do everything possible to protect themselves, co-workers, and members of the public.

• Stop work if the safety of themselves, co-workers and members of the public cannot be assured.

• Identify and report unsafe behaviour and coach each other to make improvements.

• Be prepared and equipped to work safely.

Page 5: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

5

Crosstown Design Approach

Street Level – Contextual and Inviting

An International Signature for Toronto

Entrance – Bright & Secure

Concourse – Simple & Pristine Concourse – Transparent & Open Platform – Spacious & Animated

Page 6: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

6

Accessibility

Station and Stops are designed to be universally accessible, including satisfaction of the AODA, applicable City of Toronto Guidelines, the OBC, and CSA Standards.

Some of those features include:

• Barrier‐free paths from the entrance level to the station platform level

• Tactile warning strips and tactile walking surface indicators

• Signage systems with tactile indicators

• Passenger Assistance Intercoms (PAI)

• Low floor Light Rail Vehicles (LRV) with designated wheelchair locations

• Nominal gaps from platform edges to LRV entries

• Automated visual and audible stop announcements

• On-street and off-street paratransit passenger pick-ups and drop-offs

Page 7: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

7

Environment & Sustainability

During Construction

• Programs to minimize impact on wildlife, their habitats, watercourses and trees

• Reduce impact on our community neighbours through the management of dust,

noise and vibration

• Sustainable construction practices, including active management of construction

and demolition generated wastes, targeting 75% waste diversion from landfills;

and off-site beneficial reuse of excess soil.

Project Design Sustainability

• Project wide application of Toronto Green Standard

• LEED Certification at EMSF

• Bike parking for short- and long-term users

• Dedicated pedestrian routes

• High Solar Reflectance Index paving

• Green roofs

• Water use conservation/efficiency

• Fritted glazing (minimize bird collisions)

• Shielded exterior lighting (prevent off-site light trespass)

• Sheltered waiting areas

• Energy efficiency – LED lighting, heat recovery systems

• Landscaping – use of native, drought-tolerant plants and large trees

Page 8: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

8

How We’re Building the Crosstown: Construction Overview

Page 9: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

9

The Crosstown: 2016 in Review

9

• Tunnels complete

• Construction activities at all 15 underground stations

• Utility relocations & support in place, underway or complete

• Shoring work underway or nearing completion at several stations

• All design through 60% completion

• Transit system definition for underground segments 60% complete

• Full Building Permit application packages being finalized for submission Q1-Q3

Page 10: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

10

The Crosstown: 2017 Construction Milestones

• Year of the Dig – 1 million tons to be excavated in 2017

• Start excavating main station boxes

• Shoring & utility relocations at interchange stations – Cedarvale, Eglinton, Kennedy

• Utilities Relocation

• Road Widening

• Start Guideway Install

• Track work – pour concrete base and first track installation

• Maintenance & Storage Facility buildings enclosed

10

Page 11: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

11

How we’re building the Crosstown:

Construction Overview

Distinct phases of construction:

• Preliminary works

• Utility relocations

• Handover of tunnel sections

• Support of excavation (shoring)

• Excavation & mining works

• Structural and architectural works

• Track work and systems installation

• Traction power system

• Signalling system

• Testing and commissioning

• Restoration works

Page 12: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

12

West At-Grade (Brentcliffe Portal to Victoria Park Stop)

Update

Brentcliffe Portal• Preparatory works are underway or complete

– Geotechnical Investigations

– Subsurface Utility Investigations

– Tree Protection and Removals

• Piling, the first stage for Support of Excavation (Shoring) almost complete

West At-Grade • Preparatory works are underway or complete

– Geotechnical Investigations

– Subsurface Utility Investigations

– Tree Protection and Removals

• Median Removals across Eglinton Avenue East scheduled to begin

Page 13: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

13

Brentcliffe Portal Aerial View (60% Rendering)

Page 14: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

14

Sunnybrook Park Stop Aerial View (60% Rendering)

Page 15: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

15

Aga Khan Park & Museum Stop Aerial View (60%

Rendering)

Page 16: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

16

Wynford Stop Aerial View (60% Rendering)

Page 17: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

17

Sloane Stop Aerial View (60% Rendering)

Page 18: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

18

O’Connor Stop Aerial View (60% Rendering)

Page 19: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

19

Science Centre Station Update

• Preparatory works are underway or complete

• Utility Relocation work continues

• Piling, the first step for Support of Excavation (Shoring), almost complete for Bus Depot, Pedestrian Entrance, Station Box and Portals. Main Entrance works scheduled to get underway as early as June 2017.

• Existing traffic set up installed in early May and expected to be in place for approximately three months. Traffic set up supports piling, utility works and road widening

• Next stage of work will include piling at the Main Entrance located at the southwest corner of Eglinton Ave. East and Don Mills Road and excavation in the centre of Eglinton Avenue to begin underground works: shoring, portals, station box, and track work

Page 20: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

20

Current Traffic Staging at Don Mills & Eglinton

Began early May. Scheduled to be in place for approximately 3 months.

Page 21: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

21

How we’re building Science Centre Station

Cut and Cover Methodology at Science Centre Station

Page 22: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

22

Science Centre Aerial View (90%)

Secondary Entrance

Main Entrance

Bus Terminal

Page 23: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

23

Science Centre Main Entrance Plaza (90%)

Page 24: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

24

Science Centre Main Entrance Dusk (90%)

Page 25: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

25

Science Centre West Portal (60%)

Page 26: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

26

Science Centre East Portal (60%)

Page 27: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

27

Science Centre Bus Terminal (60%)

Page 28: Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017

28

Science Centre Bus Depot (60%)