brazilian nuclear operator’s · 2013-08-29 · iaea technical meeting on evaluation of npp design...
TRANSCRIPT
IAEA Technical Meeting on EVALUATION OF NPP DESIGN SAFETY IN THE AFTERMATH OF THE FUKUSHIMA DAIICHI ACCIDENT 26–29 August 2013 Vienna International Centre
Brazilian Nuclear Operator’s Response to Fukushima Accident ELETRONUCLEAR – Paulo Carneiro
Contents
1. Angra Nuclear Power Station
2. Brazilian Operator’s Approach to Fukushima
Accident
3. Reevaluation of Hazard Events
4. Reinforcement of Cooling Capacity
5. Mitigation of Accident Consequences
(updated and complementary information to the paper
submitted for the Technical Meeting)
3
1. Angra Nuclear Power Station
ANGRA 1 PWR
Power: 640 MW
Technology: Westinghouse
Operation start: Jan. 1985
ANGRA 2 PWR
Power: 1,350 MW
Technology: KWU/ Siemens
Operation start: Jan. 2001
ANGRA 3 PWR
Power: 1,405 MW
Technology: KWU/ Siemens/ Areva
Under construction
Planned start of operation: May 2018
(illustrative view)
ANGRA 1
ANGRA 2
RADIOACTIVE
WASTE STORAGE
CENTER 500kV Switchyard
2. Brazilian Operator’s Approach to Fukushima
Working groups of specialists under guidance of a
Fukushima Response Management Committee;
o gathering and evaluation of information about the accident
onset, development and consequences;
o identification of lessons learned applicable to Brazilian
NPPs;
o safety assessments;
o establishment and management of an execution plan
(studies and projects consolidated in the
ELETRONUCLEAR Fukushima Response Plan);
o participation in national and international discussion forums
about the lessons learned and safety initiatives.
Full Integration with Nuclear Industry Initiatives Brazilian Nuclear Authority
2. Brazilian Operator’s Approach to Fukushima
1st Document - Preliminary Report: submitted to CNEN in August, 2011
• Plant Comparison Angra x Fukushima;
• Design Criteria for Protection Against External Events;
• Preliminary Evaluation of Plant Behavior for SBO and LUHS;
• Measures for Mitigation of Consequences from Severe Accidents
2nd Document – Fukushima Response Plan: submitted to CNEN in Dec, 2011
• 58 initiatives (studies and projects, including performance of Stress Tests)
• Protection Against Hazard Events, Reinforcement of Cooling Capacity and
Mitigation of Accident Consequences
• Budget estimation: around US$ 150 million to be applied from 2012 to 2016
3rd Document – Stress Test Report: submitted to CNEN in April, 2012
• According to specification issued by Iberoamerican Forum of Regulatory
Bodies, Nuclear and Radiological (request from CNEN in January 2012)
• Compliance with WENRA Specification for Stress Tests
• Same cross-checking procedure by different regulators as WENRA.
3. Reevaluation of Hazard Events
Earthquakes
Low seismicity site
Largest earthquake 5.2 mb at
250 km (PGA 0.002g at site)
Design PGA 0.10g (p< 10-4/yr)
Slopes very steep around the site
Residual and colluvial soils
High rainfall rates
Station protected by slope stabilization
works and slope monitoring system
Rainfalls
3. Reevaluation of Hazard Events
Ilha Grande Bay
Angra NP
Station
Bay area, natural protection
from Atlantic Ocean
Tidal Waves
Favorable
geological
characteristics
of the South
Atlantic coast
to
3. Reevaluation of Hazard Events
Verification and enlargement of safety margins
Seismic hazard
• updating of geological and seismological database already
started; probabilistic seismic spectra expected for 2016
(preliminary spectrum already available);
• methodology for evaluation of the seismic design margin
under discussion; preliminary results expected for 2014;
Landslides
• reevaluation of slope stabilization works and slope
movement monitoring system concluded, taking earthquakes
in consideration;
• recommendation of reinforcement of some slopes, additional
measures for proper soil drainage and extension of the slope
monitoring system; implementation until 2015;
3. Reevaluation of Hazard Events
Verification and enlargement of safety margins
Tidal waves
• reevaluation of jetty stability, considering severe
meteorological conditions, to be concluded until end of 2013;
• expected indication of reinforcement measures;
implementation until 2016;
Site flooding
• reevaluation of flooding level under more severe conditions
concluded (rainfall rate higher than 10,000 years rainfall,
blockage of site drainage channels and circulating water
discharge tunnel due to landslides and continued operation of
circulating pumps);
• current design flooding level includes sufficient safety margin;
no plant changes necessary.
3. Reevaluation of Hazard Events
Verification and enlargement of safety margins
Tornadoes
• tornadoes were not originally considered for Angra 1 and 2
(few data for defining a design basis for tornadoes);
• tornado hazard study developed for Angra 3 (10-7/yr);
•impact on Angra 1 and 2 under evaluation; affected
components and recommended protective measures until the
end of 2013; implementation until 2016;
Conclusions:
Design basis for external events confirmed;
Opportunity for enlarging safety margins;
Additional protective measures under definition for
implementation in 2 to 3 years.
Event Initial Conditions
• Loss of Offsite Power - LOOP;
• failure to switchover to supply by plant main generator;
• no possibility of external support within 72h after the accident
onset;
Plant in Power Operation
• 100% reactor power;
• reactor and turbine trip after LOOP;
Plant Refueling (worst condition for fuel pool temperature)
• full core transferred to fuel pool;
• full utilization of fuel pool storage racks;
Basic Assumptions for Safety Evaluation
4. Reinforcement of Cooling Capacity
4 x 50% 2 x 100%
M G
2x
M G
2x
M G
4x
M G
4x
EDE – 3/4
EAS – 1A/1B ULB – D2
UBP – D1
SE
500kV
SE
138kV
A2 A1 A2 A1
Cachoeira
Paulista
São
Jos é
Zona
Oeste
Santa
Cruz
2,5h 4,0h
“ Off - Site
Power ”
M G
2x
M G M G M G
2x
2x
M G M G M G
2x
M G
4x
M G M G M G
4x
M G
4x
M G M G M G
4x
EDE – 3/4
EAS – 1A/1B ULB – D2
UBP – D1
Angra 2 Angra 1
SE
500kV
SE
138kV
A2 A1 A2 A1
Cachoeira
Paulista
São
Jos é
Zona
Oeste
Santa
Cruz
2,5h 4,0h
“ Off - Site
Power ”
4 x 50% 2 x 100%
Evaluation of Station Blackout Scenarios (SBO)
special design conditions for
Angra 1 and 2 (12 diesel
groups for 2 reactors !!!)
normal design condition
(2 diesel groups per
reactor)
1st Emergency
Power System
2nd Emergency
Power System
Favorable power supply
conditions in
Angra 1 and Angra 2
both meet NRC
requirements for
exclusion of SBO
Very conservative approach of
considering loss of all AC power
Evaluation of Station Blackout Scenarios (SBO)
• possibility of SG feeding through mechanically driven
pumps (Auxiliary Feedwater Turbine Pump AF-2 in Angra 1
and Diesel Driven Emergency Feedwater Pumps LAS in
Angra 2);
• at least 20 hours in Angra 1 and 33 hours in Angra 2 of
feeding from, respectively, Auxiliary Feedwater Tank - AFT
and Demineralized Water Pools - DWP;
• possibility of AFT and DWP refilling from Fire Fighting
Water Supply System - FFWS (5,000 m3 reservoir, located
on an elevation 110 m above the site grade);
• possibility of full passive secondary B&F from the FFWS
reservoir (connection before SG becomes empty, in case
AF-2 or LAS pump fails, about 50 minutes).
Very conservative approach:
• water intake structures in an area of protected sea water (Ilha
Grande Bay);
• water intake structures protected by jetty 8.0 m high above
average seawater level;
• very low probability of water intake blockage to the extent of
impairing minimum flow for residual heat removal;
Main implications for the plants:
• failure of both Emergency Supply Diesel Generator Systems
in Angra 1 (bunkered Emergency Feedwater Diesels in Angra
2 not dependent on Service Water);
• impossibility of operating the RHR chain.
Evaluation of Loss of Heat Sink Condition
Loss of Fuel Pool Cooling
Unit Plant condition Time until start
boiling
Time until fuel
element
exposure
Angra 1
Power
Operation
18 h 190 h
Refueling (*) 9 h 63 h
Angra 2
Power
Operation
23 h 155 h
Refueling (*) 5 h 35 h
(*) limit condition, full core unloaded and full occupation of pool racks
Fuel Pool Temperature Increase after Loss of Cooling
Improvements in Design / Implementation Phase
Conditions for restoring AC power supply:
• possibility of manual inter-train connection in Angra 1;
• possibility of EPSS1 feeding EPSS2 consumers in Angra 2;
• possibility of manual connection of emergency power busbars
of Angra 1 and Angra 2 (use of large installed DG reserve
capacity);
• alternative for cooling Emergency Power System Diesels of
Angra 1 in case of failure of service water;
• mobile diesel generators for emergency supply of essential
systems and components (1,800 kVA in Angra 1 and 1,000 kVA
in Angra 2);
• mobile diesel generators for recharging batteries (250 kVA for
Angra 1 and for Angra 2)
2014 / 2015
Improvements in Design / Implementation Phase
Conditions for Reactor and Fuel Pool Cooling:
• mobile compressor for operating Angra 1 MS-valves;
• mobile diesel engine driven pumps for feeding SGs (27 kg/s and
75 m head, two pumps for each plant);
• mobile diesel engine driven pumps for refilling AF Tank in Angra 1
and DW Pools in Angra 2 (20 kg/s and 20 m head, two pumps for
each plant);
• additional 4,000 m3 seismic reservoir, located on the elevation
70m above site grade, connected to the plant by seismic designed
piping;
• autonomous mobile cooling unit for fuel pool cooling in Angra 1;
• possibility of fuel pool cooling and residual heat removal
connecting FFWS to the RHR heat exchanger in Angra 2
2014 / 2016
5. Mitigation of Accident Consequences
Containment Protection:
• passive H2 catalytic recombiners already purchased for
Angra 1 and Angra 2 (until 2015)
• filtered venting under technical evaluation for Angra 1 and
commercial clarification for Angra 2 (until 2016);
Severe Accident Management Guidelines:
• pre-Fukushima SAMGs are being implemented in Angra 1
(planned for the middle of 2014);
• post-Fukushima SAMGs are in preparation for Angra 2
(planned for the end of 2014);
Other improvements in the infrastructure for emergency
planning are being planned and performed.
Focus of the 2nd Semester of 2013
• conclude all hazard external event studies and define
additional protective measures (exception: earthquakes);
• define methodology and start seismic margin evaluation;
• finish detailed design for plant modifications related to the
control of SBO and LUHS;
• technical and commercial definitions for purchasing filtered
containment venting;
• finalize safety design concept for BDBA systems and
equipment (plants with different safety design concepts);
• start preparation of procedures for utilization of mobile
equipment (equipment already purchased).