biomass plants and biomass district heating networks€¦ · for biomass plants and biomass...
TRANSCRIPT
Biomass plants and biomass district heating networks
DI Hubert SteinerLandesEnergieVerein Steiermark+43 316 877 - [email protected]://www.lev.at
Source: qm Project database
LandesEnergieVerein Steiermark
Goals:▫ Increase in energy efficiency▫ Use of regional renewable sources in the interest
of regional development, environmental protection and sustainability
Many years of experience in the field of biomass▫ Regional operator meetings▫ Maps of biomass plants▫ Research projects▫ Some years funding authority
EU Energy Policy
EU climate strategy▫ Max. 2°C increase of the earth’s temperature▫ Reduction of 30% of CO2 emissions until 2020▫ Increase of Energy efficiency by 20% until 2020▫ Increase of renewable Energy from 6,5% to 20%
by 2020 (Austria: 34%)
Reduction goals for global warming gases
World Energy Outlook
©OECD/IEA
5
The future is renewable!
Energy from▫ Biomass▫ Solar▫ Hydro▫ Wind
Heat from biomassWood energy contracting▫ Small scale district heating▫ Single building heating▫ Contracting into large district
heating networks Small and medium size
biomass boilers▫ Small businesses▫ Multi family homes
Source: Agricultural Chamber Styria
Map of plants in styria in 1993
Styria:16.400 km2
1.2 Mio Inh.74 Inh/km2
34 cities508 communities
Map of plants in styria in 2001
Map of plants in styria in 2008
Map of austria - > 1.000 plants (size > 150 kW)
Amount and total power installed for federal state:
Austrian biomass support scheme
for biomass plants and biomass district heating networks from 400 kW biomass boiler power approx. 25% of total invest cost
including: ▫ Boiler house▫ Components▫ Piping and electricity▫ District heating network
Source: qm Project database
Development of support schemes
Biomasse Nahwärme: 80; Förderung Bund gesamt: 12,8 Mio. Wärmeverteilung: 64; Förderung Bund gesamt: 6,9 Mio. Biomasse KWK: 4; Förderung Bund gesamt: 1,2 Mio.
Development of national and international Austrian environmental support schemes from 1990 to 2009
Mio
€ Num
ber
Invest cost Subsidies state Number
Source: Kommunalkredit Public Consulting
Environment MinistryMinister of Environment
Application form
Formal and substance check
Preparation of funding Proposal
Compilation of an agreement
Monitoring, Controlling while in realization (qm heizwerke)
Closing statement
Payment of subsidies
Debate in the Commission andSuggestion to the Minister
Approbation by the Minister
Assignment of the capital and transfer to an account in trust at
Kommunalkredit Public Consulting
Kommunalkredit Public Consulting GmbH
Commission (Advisory service of the Minister)Representatives of different concerned ministries, political parties, chambers, …
Support scheme process
qm heat plants (qm heizwerke)
Nationwide quality and efficiency improvement programme For biomass plants and biomass district heating networks▫ supports operating companies during the plant set up
phase▫ provides independent quality delegates▫ supports during grant application ▫ manages the project data
online in a comprehensive web - database
▫ Offers a cost efficient monitoring system.
Source: Biowärme Hatzendorf GmbH
Optimized design engineering process
Know-How exchange
More efficient biomass district heating plants
CO2 – Reduction
International co-operations for more dissemination of biomass district heating plants
Feedback for subsidising authorities.
qm heizwerke - goals
qm strategy
Easy access to project data
Feedback to the subsidising authority
Efficient work of the quality managers
Controlled by the programme manager (LEV).
subs
idy
programmemanager
design dataoperation data
heat plant
qm database
subsidisingauthority
qa - manager
Ver
ifyin
g +
guid
ing
Milestone 1 - preliminary studyResults: reasonable project model
Milestone 2 – design engineeringResults: Detailed planning, grant application data
Milestone 3 – tender procedureResults: Fixed project design, service contracts
Milestone 4 – plant realization and acceptance inspectionResults: Acceptance certificates
Milestone 5 – Monitoring and OptimizationResults: Optimized plant and district heating network
qm heizwerke - Milestones
qm project database Detailed project documentation 900 projects within the first 3
years More than 39.000 PDF-
documents 1.800 photos
qm project database technology
Part of the funding process Technical and economical data Standard forms are composed
automatically
Source: Bioenergie PongauSource: Nahwärmeversorgung Fusch an der GlocknerstrasseSource: Biomasse Heizwerk Wald im Pinzgau
qm project database images
Stake holders
Operator
Heat customers Neighbourhood
Grant giving authorities
Componentdevelopers
Project developer
Bio fuel suppliers
Community
Some key figures
Source: Nahwärmeversorgung Wiesmath
Source: Bio Wärme Hatlerdorf
Source: nahwaerme.at
Source: Nahwärme Gleinstätten GmbH
Source: nahwaerme.at
share of fossil fuels in heat plants
District heating - prices
Private customers up to 50 kW
Energy price: 0,045 – 0,087 [€/kWh]Basic price: 13,00 – 26,00 [(€/kW)/a]Meter charge: 90,00 – 130,00 [€/a]
Net prices + 20% taxSource: qm Project database
Energy input of heat plants
3.038 GWh in total76 GWh fossil fuels2,5% fossil share
Benchmarking qm heat plants
Feedback for allplant operators Includes design and
operation data For energy and
economic parameters Tool included in the
web-interface.
QQC - Quick Quality Check –a one day check for a heat plant Delivers information for operators,
investors and subsidising authorities Optimization potential is shown,
needed improvements are demonstrated Very short pay back periods of the
suggested measures Cost effective and independent.
Thank you!