August 13-14, 2007TPTF Meeting
Texas Nodal Program Update
Jerry Sullivan
![Page 2: August 13-14, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan](https://reader036.vdocuments.site/reader036/viewer/2022072006/56649d165503460f949eb9d0/html5/thumbnails/2.jpg)
2Texas Nodal Program UpdateAugust 13-14, 2007 2
Agenda
Item Purpose Page
Program Status For Information 3
Schedule performance For Information 4
Changes since the last Market Readiness Seminar
For Information 8
![Page 3: August 13-14, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan](https://reader036.vdocuments.site/reader036/viewer/2022072006/56649d165503460f949eb9d0/html5/thumbnails/3.jpg)
3Texas Nodal Program UpdateAugust 13-14, 2007 3
CostScheduleScope / Quality
Legend
Summary
Overall program status remains amber
Green
The program is spending to budget through July’s actuals.
Cost at complete dependent on achieving quality and schedule
targets.
Amber Amber
Baseline 1 & 2 were approved by the BoD on
July 17 and changes are now being
incorporated.
Red
Amber
Green Estimate at Complete = < $263m
Estimate at Complete < $263m + 10%
Estimate at Complete >$263m + 10%
Go-live = 12/1/08
Go-live = <30 days+
Go-live = >30 days+
Program is aligned with current protocols
Program is aligned to previous protocol version
Program is not aligned to protocols
Confirming ability of key vendors to incorporate Baseline 1 & 2 within
original schedule.
Evaluating downstream lead/cycle time and productivity for
improvements.
Scope/Quality
Nodal
Cost
ScheduleScope/Quality
Schedule
Cost
Nodal Delivery
Nodal Delivery
Amber
Current product quality is not sufficient for Nodal launch
Most Nodal products currently achieve quality standards
All Nodal products currently achieve quality standards
Testing Czar being appointed to provide overall
testing focus.
Increasing End User engagement in User Interface
reviews.
![Page 4: August 13-14, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan](https://reader036.vdocuments.site/reader036/viewer/2022072006/56649d165503460f949eb9d0/html5/thumbnails/4.jpg)
4Texas Nodal Program UpdateAugust 13-14, 2007 4
Schedule Performance – Critical Path
http://nodal.ercot.com/about/po/tim/kd/timeline_0803.pdf
Paper copy distributed at meeting
![Page 5: August 13-14, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan](https://reader036.vdocuments.site/reader036/viewer/2022072006/56649d165503460f949eb9d0/html5/thumbnails/5.jpg)
5Texas Nodal Program UpdateAugust 13-14, 2007 5
Schedule Performance – key recent milestones completed
Milestone Planned Date
Actual Date Comments
Start the Point to Point (PtP) Checkout
Jun 01, 2007 Jun 01, 2007 We have completed 68% of PtP testing with an error rate of 4%. 20 out of 39 MPs (51%) have completed PtP. 46,802 points out of 68,476 (projected) points have been tested. 11,547 points remaining.
Start ICCP Validation Jun 01, 2007 Jun 01, 2007 Testing on schedule.
MMS Security Constrained Economic Dispatch (SCED) Factory Acceptance Testing (FAT) Complete
Jun 15, 2007 Jun 15, 2007 SCED FAT completed by ERCOT MMS teamSCED FAT details (e.g., scenarios, use cases, results) to be reviewed with TPTF tomorrow.
Priority 1 Web Services Test Site - “Sandbox”
Jun 30, 2007 Jul 16, 2007 Delay in obtaining design documents from ABB (MMS Vendor).
Within 30 days of planned milestone dateOn schedule
More than 30 days from planned milestone
√√
√√
√√
√√
√√Milestone Complete
![Page 6: August 13-14, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan](https://reader036.vdocuments.site/reader036/viewer/2022072006/56649d165503460f949eb9d0/html5/thumbnails/6.jpg)
6Texas Nodal Program UpdateAugust 13-14, 2007 6
Schedule Performance – key Future milestones
Within 30 days of planned milestone dateOn schedule
More than 30 days from planned milestone
Milestone Planned Date
Forecast Date
Comments
Early EDS 3 SCED Validation Oct 1, 2007 revised to Jul 30, 2007
Aug 24, 2007 Delay in migrating and configuring application across environments.
EDS 2 State Estimator (SE) Tuning and Verification
Sep 01, 2007 Sep 01, 2007 PI Consultant was not available on time, but effort is on track. (State Estimator reports delivery mechanism to be determined).
Priority 2 Web Services Test Site - “Sandbox”
Aug 31, 2007 Aug 31, 2007 6 SCED interfaces will be delivered on Aug 31.
The rest of the interfaces will be incrementally delivered by Sep 26.
Enlist all QSEs with Resources in EDS
Oct 01, 2007 Oct 01, 2007
Sep 26, 2007
![Page 7: August 13-14, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan](https://reader036.vdocuments.site/reader036/viewer/2022072006/56649d165503460f949eb9d0/html5/thumbnails/7.jpg)
7Texas Nodal Program UpdateAugust 21, 2007 7
The real business of testing and integrating exposes challenges in downstream projects, however we are making major strides
FAT
Integration Project
Projects
EMS, MMS etc
iDev iFAT
Integration Testing
ITEST
EDS EDSeEDS Sandbox
RM
RM
RM RM
RM RM RM
Improvements in Dev cycle time 1st Sandbox - 0.5 interface / week 2nd Sandbox - 1 interface / week 3rd Sandbox – 10 interface / week
Issues being addressed: Establishing reusable components Stabilizing design for NMMS integration Communicating upstream dependencies
Improvements in Testing cycle time 1st Sandbox - 0.25 services / day 2nd Sandbox - 0.84 services / day
Issues being addressed: Involvement of ITEST team in upstream
activities Access to stable env to begin test scripts Testing Czar has been appointed
Improvements in migration and configuration MMS migration time – reduced from 5 weeks to 3 days Web Services migration time – 14 days to 3 hours
Issues being addressed: Implementation of automation tools for configuration and
release Communicating upstream dependencies for architecture
and migration
SCED FAT – Completed on schedule NMMS FAT – Failed with Sev 1 defects and
sent back to vendor for evaluation
(Factory Acceptance Test)
(Development and Unit Test of Integration) (Integration Factory Acceptance Test)
(Integration Testing)
(Pre Early Delivery System) (Early Delivery System)
LegendRM Release Management (Manages the migration of applications
across hardware)ERCOT Testing Phases
Gains in productivity and challenges being addressed
![Page 8: August 13-14, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan](https://reader036.vdocuments.site/reader036/viewer/2022072006/56649d165503460f949eb9d0/html5/thumbnails/8.jpg)
8Texas Nodal Program UpdateAugust 13-14, 2007 8
Market Readiness Update – Metric Map Progress
C1 thru C9
C1 thru C9
R1
E5
E1-4
R1
E5
E1-4CRR2CRR2
MP7
MP8
MP9
MP12-2
MP13-2
CO1
CO2
EMO4
MP7
MP8
MP9
MP12-2
MP13-2
CO1
CO2
EMO4
EMO9-2MP6-2E9 EMO9-2MP6-2E9
MP1MP1
E1-3E1-3
MO2MO2 MP17-1MP17-1 MP16MP16
E6E6
E4
R2
E4
R2
CRR4
E13
CRR4
E13
EMO3
EMO2
EMO3
EMO2
EMO7
E8
EMO7
E8
CO3CO3 MP10MP10
CO7
CO6
CO5
CO4
CO7
CO6
CO5
CO4 E15
E14
E2
E15
E14
E2
MO6
MO3
MO1
MO6
MO3
MO1
MP17-3
CO10
MP17-3
CO10
MP13-1
EMO8
MP13-1
EMO8
MP17-2MP17-2
CRR1
CRR5
CO8
CRR1
CRR5
CO8MO5-5MO5-5
EMO6EMO6EMO5EMO5
N1N1
MP5
N2
MP5
N2
E1-1E1-1
MP14MP14
EMO1EMO1
CRR1CRR1
E12E12
E1-2E1-2 MP12MP12
MP11
CO9
MP11
CO9
N3
MP6-1
EMO9-1
N3
MP6-1
EMO9-1
MP4
MP2
MP3
MP4
MP2
MP3 CRR3CRR3
MP12-1MP12-1
MO5-2MO5-2 MO5-3MO5-3
MO5-4MO5-4
MO4
MO5-1
MO4
MO5-1
E11
E10
E7
E3
E11
E10
E7
E3
MO5-T1MO5-T1MO5-T2MO5-T2
![Page 9: August 13-14, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan](https://reader036.vdocuments.site/reader036/viewer/2022072006/56649d165503460f949eb9d0/html5/thumbnails/9.jpg)
9Texas Nodal Program UpdateAugust 13-14, 2007 9
Market Readiness Update – Metric Map Progress
Market Participant MetricsQSE with Resources Connectivity to EDS Environment (MP2)QSE with Resources Upload of SCED Offers to EDS (MP3)ICCP Point to Point Telemetry Test (MP5)MP Registration Activities (MP11)MP EDS-2 Trials Participation (MP14)
ERCOT Internal MetricsERCOT Staff Completes Training (E1) Develop Nodal Operating Guides (E6)ERCOT Staffed for Texas Nodal Operations (E8)Develop TN Procedures (E9)
Network Model management MetricsERCOT Telemetry Alarm Processing (N1)
The Metric Inventory Document has complete Metric to Date cross-reference.
The Readiness Metrics Dashboard will provide details on when metrics will begin to be measured
Release Metrics TPTF ReviewTPTF
Approval TAC ApprovalDashboard Production
ReleaseERCOT BoD
ReportIteration 1 MP Engagement 23-Jul 23-Jul 2-Aug 27-Aug 18-Sep
Iteration 2MP2, MP3, MP5, MP11,
MP13, E1, E6, E8, E9, N1 13-Aug 27-Aug 6-Sep End of September, 2007 16-Oct
Iteration 3 TBD 10-Sep 24-Sep 5-Oct TBD ~ End of November 13-Nov
![Page 10: August 13-14, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan](https://reader036.vdocuments.site/reader036/viewer/2022072006/56649d165503460f949eb9d0/html5/thumbnails/10.jpg)
10Texas Nodal Program UpdateAugust 13-14, 2007 10
Hall of Fame / Wall of Shame*
The following QSEs with Resources secured an EDS3 testing Slot by the August 8 deadline (MP2 / MP3):
Austin Energy American Electric Power ANP Funding Brazos Electric Coop BP Energy Calpine Power Management Coral Power City Public Services Direct Energy Eagle Energy Partners Exelon FPL
2/3rd signed up in first three days of scheduling
* Experience in other countries has proven the Terminology based on Hall of Fame / Wall of Shame to be effective. Current as of Friday 08.10.2007
The following QSEs with Resources failed to secure an EDS3 testing Slot by the August 8 deadline (MP2 / MP3):
Constellation Energy BTU - Bryan Texas Utilities (APX Client) Fulcrum (APX Client) IPA Marketing (APX Client) Scurry Wind (APX Client) Topaz (APX Client)
Formosa Garland Power and Light LCRA - Lower Colorado River NRG Occidental Power Svcs Reliant Rio Nogales Suez Energy Marketing South Texas Electric Coop Tenaska Power Services Texas Utilities Westar
Hall of Fame
Wall of Shame
![Page 11: August 13-14, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan](https://reader036.vdocuments.site/reader036/viewer/2022072006/56649d165503460f949eb9d0/html5/thumbnails/11.jpg)
11Texas Nodal Program UpdateAugust 13-14, 2007 11
Market Readiness Update – Hall of Fame*
The following QSEs and TSPs have Completed 100 percent Point to Point (PtP) Testing As of August 10 (MP5):
AEN - Austin Energy AEP - American Electric Power APX BP Energy Calpine Power Management Constellation Energy CPE - CenterPoint Energy Exelon Garland Power and Light GEUS - Greenville NRG OXY - Occidental Power Svcs Reliant STEC - South Texas Electric Coop Suez Energy Marketing TMPA - Texas Muni Power Auth OnCor TXU - Texas Utilities
* Experience in other countries has proven the Terminology based on Hall of Fame / Wall of Shame to be effective. Current as of Friday 08.10.2007