april, 2003

39
DESC CHALLENGES ASSOCIATED WITH CHALLENGES ASSOCIATED WITH HORIZONTAL DIRECTIONAL DRILLING AND HORIZONTAL DIRECTIONAL DRILLING AND PIPING INSTALLATION UNDER A MAJOR PIPING INSTALLATION UNDER A MAJOR HIGHWAY FOR THE REMEDIATION OF A HIGHWAY FOR THE REMEDIATION OF A PETROLEUM PLUME PETROLEUM PLUME By: By: Michael Heffron, P.G., Tetra Tech FW, Michael Heffron, P.G., Tetra Tech FW, Inc. Inc. April, 2003

Upload: magee

Post on 19-Jan-2016

24 views

Category:

Documents


0 download

DESCRIPTION

CHALLENGES ASSOCIATED WITH HORIZONTAL DIRECTIONAL DRILLING AND PIPING INSTALLATION UNDER A MAJOR HIGHWAY FOR THE REMEDIATION OF A PETROLEUM PLUME By: Michael Heffron, P.G., Tetra Tech FW, Inc. April, 2003. Site Background. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: April, 2003

DESC

CHALLENGES ASSOCIATED WITH CHALLENGES ASSOCIATED WITH HORIZONTAL DIRECTIONAL DRILLING AND HORIZONTAL DIRECTIONAL DRILLING AND

PIPING INSTALLATION UNDER A MAJOR PIPING INSTALLATION UNDER A MAJOR HIGHWAY FOR THE REMEDIATION OF A HIGHWAY FOR THE REMEDIATION OF A

PETROLEUM PLUMEPETROLEUM PLUME

By:By:Michael Heffron, P.G., Tetra Tech FW, Inc.Michael Heffron, P.G., Tetra Tech FW, Inc.

April, 2003

Page 2: April, 2003

DESC

Site BackgroundSite Background

A large free-phase refined petroleum plume (1-1.5 million gallons) underlies the former Defense Supply Center Philadelphia property, a major highway and a former housing development to the south.

An existing remediation system has removed over 850,000-gallons of product (which does not include the 1 to 1.5 million gallons remaining).

Page 3: April, 2003

DESC

SU

NO

CO

PR

OP

ER

TY

SU

NO

CO

PR

OP

ER

TY

PROPERTYPROPERTY

PACKER AVEPACKER AVE

DSCPDSCP

RY

DE

R P

RO

PE

RT

YR

YD

ER

PR

OP

ER

TY

SEPTA PROPERTYSEPTA PROPERTY

STEENSTEEN

PASSYUNK HOMES

PASSYUNK HOMES

PACKER AVENUE SEWERPACKER AVENUE SEWER

HOTELHOTELPENROSE DINERPENROSE DINER

PACKER PARK

PACKER PARK

SCHUYLKILL EXPRESSWAYSCHUYLKILL EXPRESSWAY

EXTENT OF FREE PHASE PLUME (9/8/03)EXTENT OF FREE PHASE PLUME (9/8/03)

Major Highway bisecting the petroleum plume

Page 4: April, 2003

DESC

PRODUCT RECOVERY OPERATIONSPRODUCT RECOVERY OPERATIONS

A Phase II Remediation vacuum enhanced skimming system is being installed to expedite the remediation efforts.

Since the plume and recovery wells are transected by a major highway, the options included the installation of two separate remediation systems on two separate properties or a way to connect the wells on either side of the highway to one system.

Page 5: April, 2003

DESC

Proposed Remediation SystemProposed Remediation System

If two systems were to be installed, it would have required the installation of two buildings.

It would also have required the installation of a thermal oxidizer on both sides of the highway.

Page 6: April, 2003

DESC

Highway Bisecting the Petroleum PlumeHighway Bisecting the Petroleum Plume

The highway that bisects the plume is the Walt Whitman Bridge Approach off the Schuylkill Expressway.

This approach to the bridge is one of the main arteries in Philadelphia used by over 100,000 vehicles a day.

Page 7: April, 2003

DESC

To Directionally Drill or Not to DrillTo Directionally Drill or Not to Drill

The risk of using horizontal directional drilling to install piping under the highway were weighed against the costs of having to install two separate remediation systems.

It was determined that a cost savings of up to $300,00 to $400,000 would be realized if the recovery wells on both sides of the highway were connected up with piping to one system versus the installation of two systems on both sides of the highway.

Page 8: April, 2003

DESC

Geological Evaluation for Risk Geological Evaluation for Risk MitigationMitigation

Borehole path selection and a review of the geology are very important for ensuring a successful drilling operation.

Existing soil boring logs were used to evaluate the geology in the vicinity of the proposed piping run.

Page 9: April, 2003

DESC

Geological Evaluation for Risk Geological Evaluation for Risk MitigationMitigation

A dense silt layer was identified at an average depth of 9-feet below grade and 5 to 9 feet thick.

The distribution and geotechnical characteristics of this silt layer were extensively studied during a prior risk assessment.

Page 10: April, 2003

DESC

Determination of Directional Drilling Determination of Directional Drilling Borehole DepthBorehole Depth

The proposed depth of the borehole was determined to be 12-feet below grade.

This would place the borehole just below the silt, but above the free-phase petroleum plume.

The proposed depth would also be at least 3 feet below the sanitary sewer line under the highway.

Page 11: April, 2003

DESC

Contingencies and Traffic ControlContingencies and Traffic Control

Several meetings were held involving engineers, geologists, and the owners of the highway to discuss the methodologies, potential traffic problems and contingencies.

A Contingency and Traffic Control Plan was prepared and submitted.

Page 12: April, 2003

DESC

Contingencies and Traffic ControlContingencies and Traffic Control

Contingencies were established for: Partial or complete highway collapse; “Frac-out” or drilling mud being pushed to

the surface of the highway; Partial highway or full-highway shut-down

procedures. Detour routes were established and agreed

upon by all responsible parties.

Page 13: April, 2003

DESC

Directional Crossing Contractor’s Association, July 10, 2002, www.dcca.org

HORIZONTAL DIRECTIONAL DRILLING METHOD

Page 14: April, 2003

DESC

DIRECTIONAL DRILLING OPERATIONS DIRECTIONAL DRILLING OPERATIONS FACING SOUTHEASTFACING SOUTHEAST

Page 15: April, 2003

DESC

DIRECTIONAL DRILLING RIGDIRECTIONAL DRILLING RIG

Page 16: April, 2003

DESC

Pilot Hole Drill BitPilot Hole Drill Bit

Page 17: April, 2003

DESC

DRILLING BITS USED FOR DRILLING BITS USED FOR DIRECTIONAL DRILLINGDIRECTIONAL DRILLING

Page 18: April, 2003

DESC

TANKS USED TO MANAGED THE DRILLING MUD DURING THE TANKS USED TO MANAGED THE DRILLING MUD DURING THE DRILLING OPERATIONSDRILLING OPERATIONS

Page 19: April, 2003

DESC

TANKS (BLUE) USED TO STORE DRILLING MUDS PRIOR TO TANKS (BLUE) USED TO STORE DRILLING MUDS PRIOR TO OFF-SITE DISPOSALOFF-SITE DISPOSAL

Page 20: April, 2003

DESC

PILOT HOLE BEING DIRECTIONALLY DRILLEDPILOT HOLE BEING DIRECTIONALLY DRILLED

Page 21: April, 2003

DESC

ABOVE-GRADE LOCATOR USED TO LOCATE THE DEPTH AND ABOVE-GRADE LOCATOR USED TO LOCATE THE DEPTH AND ORIENTATION OF THE DRILLING BITORIENTATION OF THE DRILLING BIT

LOCATOR

Page 22: April, 2003

DESC

EXCAVATION THROUGH THE PATH OF THE DIRECTIONAL EXCAVATION THROUGH THE PATH OF THE DIRECTIONAL DRILLING TO SHOW DRILLING BIT BEING ADVANCED DRILLING TO SHOW DRILLING BIT BEING ADVANCED UNDERGROUNDUNDERGROUND

Page 23: April, 2003

DESC

PIPING THAT WAS FUSED AND INSTALLED UNDER THE HIGHWAYPIPING THAT WAS FUSED AND INSTALLED UNDER THE HIGHWAY

Page 24: April, 2003

DESC

FUSION MACHINE BEING USED TO FUSE OR “WELD” THE PIPE FUSION MACHINE BEING USED TO FUSE OR “WELD” THE PIPE TOGETHERTOGETHER

Page 25: April, 2003

DESC

LARGE SECTIONS OF THE PIPE BEING FUSED TOGETHERLARGE SECTIONS OF THE PIPE BEING FUSED TOGETHER

Page 26: April, 2003

DESC

EXCAVATION ON PASSYUNK HOMES TO ACCESS DRILLING BITS EXCAVATION ON PASSYUNK HOMES TO ACCESS DRILLING BITS AND INSTALL THE PIPINGAND INSTALL THE PIPING

Page 27: April, 2003

DESC

END OF PIPE TO BE PULLED UNDER THE HIGHWAY WITH THE END OF PIPE TO BE PULLED UNDER THE HIGHWAY WITH THE DRILLING RODSDRILLING RODS

PIPEPOINT FUSED ONTO PIPE TO PULL THROUGH THE

HOLE

DRILLING RODS

Page 28: April, 2003

DESC

PIPING BEING PULLED FROM PASSYUNK HOMES, UNDER THE HIGHWAY, PIPING BEING PULLED FROM PASSYUNK HOMES, UNDER THE HIGHWAY, ONTO DSCPONTO DSCP

Page 29: April, 2003

DESC

18-INCH DIAMETER PIPING ABOUT TO BE PULLED UNDER THE 18-INCH DIAMETER PIPING ABOUT TO BE PULLED UNDER THE HIGHWAYHIGHWAY

Page 30: April, 2003

DESC

Lessons Learned-Upfront PlanningLessons Learned-Upfront Planning

It is extremely helpful to prepare a presentation to the stakeholders on exactly what you are proposing for the drilling operations.

This approach saves time and money by allowing questions to be raised and addressed prior to the submittal of any plans

Page 31: April, 2003

DESC

Lessons Learned-3Lessons Learned-3rdrd Party Backup on Party Backup on Borehole StabilityBorehole Stability

A Study on the annular space around pipes installed by horizontal directional was submitted with the Work Plan.

This provided third-party evidence that there was no concern over the collapse of the annular space around the pipe and the highway. (Source: Arianratum, 2001)

Page 32: April, 2003

DESC

Lessons Learned-Proper Geological Lessons Learned-Proper Geological InformationInformation

It is important to have good and accurate geological data in the area of the proposed directional drilling pathway.

If this data is not available, then the appropriate drilling operations should be conducted to obtain the data.

Page 33: April, 2003

DESC

Lessons Learned-Traffic ControlLessons Learned-Traffic Control

It is necessary to prepare a comprehensive Traffic Control Plan to address any expected and unexpected problems.

It was agreed to set-up detour routes with all the signs in place prior to the work beginning.

The detour routes required the hiring of specialized subcontractors.

Page 34: April, 2003

DESC

Lessons Learned-Preparation for Frac-Lessons Learned-Preparation for Frac-OutOut

“Frac-Out” is the inadvertent return of drilling fluid being forced up to the ground surface.

The drilling fluid is pumped into the directional drilling borehole at 1,000 psi, which could force the drilling fluid into preferential pathways (natural and manmade).

The geological analyses plays an important role evaluating the potential for frac-out to occur.

Page 35: April, 2003

DESC

Lessons Learned-Preparation for Frac-Lessons Learned-Preparation for Frac-OutOut

It is important to ensure that there is proper drilling fluid circulation. If the drilling fluid circulation is restricted, it could cause extreme pressures resulting in a frac out.

It is important to have a direct line of communication (cell phone, walkie-talkie) between the driller and the spotter at the exit pit to establish that there is circulation and relay any problems.

Page 36: April, 2003

DESC

Lessons Learned-Preparation for Frac-Lessons Learned-Preparation for Frac-OutsOuts

While every upfront precaution should be taken to ensure frac-out does not occur, there should be contingencies in place in the event it occurs.

Drilling mud is comprised of bentonite and polymers, which are extremely slippery. The drilling mud creates a severe slip hazard if it is spilled.

The depths in which frac-out may occur should be determined based upon the geology and then the rig and borehole angle should be situated in a position that would result in the frac-out occurring in the least dangerous location.

Page 37: April, 2003

DESC

Lessons Learned-Preparation for Frac-Lessons Learned-Preparation for Frac-OutsOuts Where possible, the

overland portion of the drilling route should be roped off.

This area should be patrolled to look for surface expressions of any frac-outs.

Hay bails should be available in order to help contain the drilling fluid in the event of a frac-out.

A vacuum truck should be made available to vacuum any spilled drilling fluid as well as handle the drilling fluid itself.

Page 38: April, 2003

DESC

Lessons Learned-Unexpected CostsLessons Learned-Unexpected Costs

The owners of the highway or the stakeholders may require additional work as part of the access agreement.

We had to agree to survey the elevation of the highway before the drilling and quarterly thereafter to ensure there was no subsidence.

We were also responsible for paying the costs for the highway owner’s consultant to oversee the work.

Page 39: April, 2003

DESC

In Conclusion, when properly managed and planned, directional drilling can be an effective and cost effective method for the installation of piping.