appendixb final report - welcome to the town of … - culture recreation... · oakville harbour...

122

Upload: nguyenthuy

Post on 11-Aug-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 2: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 3: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

All Rights Reserved, John George Associates, Inc. © 2008

The following document is the property of the Town of Oakville. The process, ideas and material contained herein are the property of John George Associates, Inc. and Visionscapes Landscape Architects Inc. Copyright 2008. Copying for use outside of the Town of Oakville must have written permission from John George Associates, Inc.

For further information, contact:

John George, OALA John George Associates, Inc. 327 Pine Cove Road

Burlington, Ontario, Canada L7N 1W4

Tel: (905) 632-3473 Fax: (905) 692-2407 [email protected]

OAKVILLE HARBOURWest Shore Master Plan

Page 1

Page 4: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 5: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

OAKVILLE HARBOURWest Shore Master Plan

Table of Contents

OAKVILLE HARBOURWest Shore Master Plan

Page 2

Part One: Executive Summary and Introduction

Part Two: Inventory and Analysis Detailed Photographic Analysis

Part Three: Mission and Concept Statement Detailed Concept Descriptions Final Concept Plan and Sections

Part Four: Next Steps and Conclusions

Appendix 1: Tree Inventory

Appendix 2: Preliminary Shoreline Report

Appendix 3: Cost Estimates

Page 3

Page 7Page 10

Page 26Page 30Page 47

Page 50

Page 6: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 7: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Executive Summary

The Oakville Harbour West Shore Master Plan presented the opportunity to enhance the ‘green necklace’ that connects the greater waterfront system along Lake Ontario. To date, each parcel (Shipyard Park, Tannery Park, Walker Street Promenade and Waterworks Park) has been developed for its own distinct purposes. The relationship of these parks is disjointed and as an overall open space system has great potential.

Mission and Goals

To create a multi-functional, diversified and fully accessible all season waterfront park which cel-ebrates the Harbour and the water’s edge, and encapsulates the heritage and evolution of Oakville Harbour and the downtown.

The guiding principles are to:

• Develop a Waterfront Park with a sense of permanence and importance.

• Improve visual access to the water’s edge, and create spaces that celebrate the creek and Lake Ontario.

• Develop creative and innovative detail design solutions which pay homage to the spirit of Oakville Harbour’s past, present and future.

• Use design detailing which respects the ambience and roots of Oakville Harbour, and use innovative interpretive elements which ‘tell the story’ of the Harbour.

• Strengthen the connection and accessibility between the various member parks, and public access to the water’s edge.

• Develop a truly ‘multi-use’ park which is adaptable, can accommodate change, and projected future programming; including festival and community events.

• Create a more dynamic waterfront edge, and link Tannery, Walker Promenade and Waterworks along the shoreline.

OAKVILLE HARBOURWest Shore Master Plan

OAKVILLE HARBOURWest Shore Master Plan

Page 3

Page 8: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

• Develop effective signage appropriate for the park - way-finding and interpretive, and develop common furnishing systems.

• Design with CPTED principles to ensure a safe site.

• Improve the environmental characteristics and natural qualities of the site - including water quality (surface and sub-surface), and drainage, improve the shoreline, enhance aquatic habitat, and protect the physical resources of the site.

• Use a variety of plant materials that will provide diversity, and will be reminiscent of native plant material found along the water’s edge where appropriate.

• Create a more functional marina and boating center which fully accessible to the public.

Concept Statement

A simple approach was used to develop a unified creative solution for the Oakville Harbour West Shore Master Plan:

• To create a distinct and unified identity to the area.

• To visually and functionally simplify and unify the area

• To eliminate redundant elements. • To develop each park in the system to have a more of an individual character and identity while maintaining the intention of a whole system that is linked and related. This will be accomplished by making:

•Shipyard Park more of a marina and boating friendly facility

• Tannery Park more of an accessible urban waterfront park

• Walker St. Promenade actually be a promenade

• Waterworks Park more of what it currently is – a terrific naturalised neighbourhood park

OAKVILLE HARBOURWest Shore Master Plan

Page 4

Page 9: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

OAKVILLE HARBOURWest Shore Master Plan

Introduction

In September 2007, the Town of Oakville identified that the west shore of Oakville Harbour and adjacent park areas needed to be updated. It was recognized that the call to prepare an Oakville Harbour West Shore Master Plan was an opportunity to have a creative solution developed for the community that would provide unity and identity to what was presently four disparate parks. This report outlines the significant findings in the review and analysis of the existing parklands, sets out a landscape for the future and outlines ‘next steps’ towards an implementation strategy to be taken for the enhancement of Oakville Harbour. Thereby, ensuring this will be an important recreational and community resource as well as a significant tourist destination.

The Oakville Harbour West Shore Master Plan presented the opportunity to enhance the ‘green necklace’ that connects the greater waterfront system along Lake Ontario. To date, each parcel (Shipyard Park, Tannery Park, Walker Street Promenade and Waterworks Park) has been developed for its own distinct purposes. The relationship of these parks is disjointed and inharmonious; there is no particular identity to each park area apart from its name. The overall open space system has great potential however it is disorganized.

The design philosophy directing the master plan was to identify and highlight the opportunities that can be experienced along the west shore of Oakville Harbour and the Lake Ontario waterfront (from Tannery to Walker Street Promenade and Waterworks Park). This direction has provided outcomes which will serve as a guide to meaningful development of these parks. To achieve the best results, multiple meetings with staff and stakeholders were used to direct project development and decisions.

Analysis of the project site revealed that simple pedestrian linkages to the multiple adjacent neighbourhoods as well as much needed routes from the Oakville core along Lakeshore Road are underdeveloped. The recreational resource for the casual visitor is immense and underdeveloped for those who prefer to meander, sit and contemplate one of the most spectacular views along 16-Mile Creek/ Oakville Harbour and Lake Ontario. Some park spaces need relatively simple upgrades to pathways, lighting and way finding. Overall, the park system needs to be more flexible, with greater offerings for a quiet neighbourhood park under preserved mature trees, shady places for dog walking and picnicking, locations to fish, launch/haul out, store and dock boats and provide identity to Oakville’s recreation system.

OAKVILLE HARBOURWest Shore Master Plan

Page 5

OAKVILLE HARBOUR West Shore Master Plan

Page 10: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

To date a variety of marina facilities, water recreation opportunities, passive recreational opportunities with pathways and displays have been developed, drawing the community and visitors to the waterfront. The intensity of use at the docking facilities needs to be addressed as these areas are tired. They need a significant re-design that better reflects the safety needs of dock users, boats and the general public wanting access to the area; in addition there is a need for the creation of more efficient spaces for autumn haul out and spring launch. Both the casual pedestrian and the avid boater need to be welcomed and provided with updated facilities and clear direction to allow for the most enjoyable experience by all.

Review of the 1994 Master Plan was also undertaken. The following items are identified as being applicable at this date:

� General mooring configuration support � Program to upgrade dock and facilities � Tenants to be surveyed to find out what services and willingness to pay � Upgrade Walker Street building � Launch ramp facility � West pier parking upgraded � Harbour Entrance tour boat stopover � Landscape improvements � lighthouse replica on pier � No fishing fleet expansion � No expansion of OHDA moorings in upstream wetlands

A critical review of the organization of marina facilities, site services, and landscape resources, as well as technical and user data and community input has provided the design team with additional programmatic direction and an ability to define needs, wants and opportunities of these parks. As a result the new master plan for the west shore of the Harbour has character related to both harbour and community. Within the scope of the four parks, the shoreline of Lake Ontario is highlighted to provide the best opportunity to get close to the waters edge allowing for opportunities to create habitat, and diversity in edge character and amenities.

Overall the West Shore Master Plan reflects the benefits of working closely with staff and stakeholders; and excellence in waterfront design and development – the resulting master plan enhances the harbour and the local and greater Oakville community.

OAKVILLE HARBOURWest Shore Master Plan

Page 6

Page 11: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 12: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 13: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 14: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 15: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

OAKVILLE HARBOUR West Shore Master Plan

Inventory and Analysis

At present the four parks that make up the harbour are a jumble of functionality and visual quality. The overall impression is a lack of – or at minimum, a confusing identity. Relationships of the indi-vidual parts are unclear, as often are the differentiations between public and private space.

Visually, as well as functionally, the atmosphere and materials are somewhat tired and worn. This is not unusual for a park system of this age. Many municipalities in the GTA and Golden Horseshoe have been - or are in the process of rejuvenating their urban waterfront parks for these very reasons.

Shipyard, Tannery and Walker Street Promenade are particularly not functioning to their full potential. For example, Shipyard Park is a marina based facility but many of the important marina functions are compromised. There is a log cabin in disrepair, compound like fences, lack of parking, confusing orientation for visitors - and little room to effectively manoeuvre cranes for lift out, store masts etc. Tannery Park, is a nice park in some areas and visually appealing especially in some of the areas up top - but areas such as the bottom and the water’s edge are unappealing. The most important part of any waterfront is the water’s edge. The lower waterfront area is cramped for space functionally and visually.

Walker Street Promenade and Waterworks Park are disconnected from Tannery Park along the shore-line. At present barrier free access between these parks does not exist at the lower level. A connective set of steps exist that do not meet current safety standards.

Following is a photographic analysis as well as an Analysis and Inventory Plan showing the various existing elements and aspects of the existing area.

OAKVILLE HARBOURWest Shore Master Plan

Page 8

Page 16: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 17: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

LAK

ES

HO

RE

RO

AD

L A

K E

O

N T

A R

I O

1 6 M I L E C R E E K

Forsythe St

And

erso

n S

t

Bur

net S

t

Wal

ker S

t

Wilson St

Chisholm St

Oak

ville

Har

bour

Wat

er T

reat

men

t Pla

nt

Wal

ker S

t. P

rom

enad

e

Shi

pyar

d P

ark

Wat

erw

orks

Par

k

Tann

ery

Par

k

Bur

net P

ark

AP

PR

OV

ED

SC

ALE

:

DA

TE

CH

EC

KE

D

DR

AW

N

DR

AW

ING

NO

.P

RO

JEC

T N

O.

PR

OJE

CT

JG JG 1:50

0m

LOC

ATI

ON

Oak

ville

, Ont

ario

Janu

ary

2008

Oak

ville

Har

bour

Maste

r P

lan

JOH

N G

EOR

GE

ASS

OC

IATE

S IN

C32

7 P

ine

Cov

e R

oad

Bur

lingt

on, O

N, L

7N 1

W4

905-

632-

3473

FA

X 9

05-6

32-2

407

CO

NS

ULT

AN

T

Land

scap

e A

rchi

tect

sV

isio

nsca

pes

Urb

an F

ores

try

Urb

an F

ores

t Inn

ovat

ions

Inc.

CLI

EN

T Tow

n O

f Oak

ville

1225

Tra

falg

ar R

oad

OA

KV

ILLE

ON

L6J

5A

6

Park

and

Pla

nnin

gD

evel

opm

ent

NO

RTH

TAICOSSA OI RATNO

STCE

TIHC

RA

EPACSDNALFO

NOI

ME

MB

ER

JOH

N G

EO

RG

E

05m

10m

20m

50m

Met

ric B

ar S

cale

L1

LEG

EN

D

Spe

cial

Site

Fea

ture

Maj

or In

ters

ectin

g N

ode

Min

or In

ters

ectin

g N

ode

Min

or F

eatu

re

Veh

icul

ar E

ntra

nce

Veh

icul

ar R

oad

Par

king

Lot

Pav

ed P

edes

train

Wal

kway

Woo

d S

tairc

ase

Uni

t Pav

er B

oard

wal

k

Ope

n S

pace

Law

n A

rea

Ste

ep S

lope

, Law

n/P

lant

ing

Arm

our S

tone

Sho

relin

e

Foot

Pat

h

Wat

erfro

nt T

rail

Ana

lysi

s an

d In

vent

ory

Pla

n

Page 18: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 19: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 20: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 21: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

OAKVILLE HARBOURWest Shore Master Plan

Page 12

Page 22: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

OAKVILLE HARBOURWest Shore Master Plan

Page 13

Page 23: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

OAKVILLE HARBOURWest Shore Master Plan

Page 14

Page 24: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

OAKVILLE HARBOURWest Shore Master Plan

Page 15

Page 25: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

OAKVILLE HARBOURWest Shore Master Plan

Page 16

Page 26: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

OAKVILLE HARBOURWest Shore Master Plan

Page 17

Page 27: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

OAKVILLE HARBOURWest Shore Master Plan

Page 18

Page 28: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

OAKVILLE HARBOURWest Shore Master Plan

Page 19

Page 29: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

OAKVILLE HARBOURWest Shore Master Plan

Page 20

Page 30: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

OAKVILLE HARBOURWest Shore Master Plan

Page 21

Page 31: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

OAKVILLE HARBOURWest Shore Master Plan

Page 22

Page 32: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

OAKVILLE HARBOURWest Shore Master Plan

Page 23

Page 33: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

OAKVILLE HARBOURWest Shore Master Plan

Page 24

Page 34: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

OAKVILLE HARBOURWest Shore Master Plan

Page 25

Page 35: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 36: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 37: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 38: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 39: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

To create a multi-functional, diversified and fully accessible all season waterfront park which celebrates the Harbour and the water’s edge, and encapsulates the heritage and evolution of Oakville Harbour and the downtown.

The guiding principles are to:

� Develop a Waterfront Park with a sense of permanence and importance.

� Improve visual access to the water's edge, and create spaces that celebrate the 16 Mile Creek & Lake Ontario.

� Develop creative and innovative detail design solutions which pay homage to the spirit of Oakville Harbour's past, present and future.

� Use design detailing which respects the ambience and roots of Oakville Harbour, and use innovative interpretive elements which 'tell the story' of the Harbour.

� Strengthen the connection and accessibility between the various member parks, and public access to the water’sedge.

� Develop a truly 'multi-use' park which is adaptable, can accommodate change, and projected future programming; including festival and community events.

� Create a more dynamic waterfront edge, and link Tannery, Walker Street Promenade and Waterworks along the shoreline

� Develop effective signage appropriate for the park - way-finding and interpretive, and develop common furnishing systems.

� Design with CPTED principles to ensure a safe site.

� Improve the environmental characteristics and natural qualities of the site - including water quality (surface and sub-surface), and drainage, improve the shoreline, enhance aquatic habitat, and protect the physical resources of the site.

� Use a variety of plant materials that will provide diversity, and will be reminiscent of native plant material found alongthe water’s edge where appropriate.

� Create a more functional marina and boating center which fully accessible to the public.

OAKVILLE HARBOUR West Shore Master Plan

Mission and Goals

OAKVILLE HARBOURWest Shore Master Plan

Page 27

Page 40: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 41: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

A simple approach was used to develop a unified creative solution for the Oakville Harbour MasterPlan:

� To create a distinct and unified identity to the area.

� To visually and functionally simplify and unify the area

� To eliminate redundant elements.

� To develop each park in the system to have a more of an individual character and identity while maintaining the intention of a whole system that is linked and related. This will be accomplished by making:

� Shipyard Park more of a marina and boating friendly facility

� Tannery Park more of an accessible urban waterfront park

� Walker St. Promenade actually be a promenade

� Waterworks Park more of what it currently is – a terrific naturalised

neighbourhood park

Concept Statement

OAKVILLE HARBOURWest Shore Master Plan

Page 28

A simple approach was used to develop a unified creative solution for the Oakville Harbour West Shore Master Plan:

Page 42: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 43: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

1

2

345

6

7 89

10 1011

1213

14

1615

17

1819

2021

22

23

24

25

26

27

28

293031

32

333434

3435

3436

3437

3438

3439 3440

34413442

3443

34443445

3446

3447

Key

Pla

n fo

r D

eta

iled

Co

ncep

t D

escrip

tio

ns

OAKVILLE HARBOURWest Shore Master Plan

Page 29

Page 44: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 45: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

OAKVILLE HARBOUR West Shore Master Plan

Detailed Concept Descriptions

The following numbers correspond with the reference numbers shown on the attached initial concept sketch plan and the Final Concept Plan.

1.0 Park Entrance at Walker and Wilson Streets• Extend sidewalk partially up Wilson Street, in order to create a landing area for the park path.• Provide park entrance and wayfinding sign.• Provide highlight planting to frame the entrance and improve its visual appeal from the street.• Reinforce edges of mature trees, with younger trees intended to replace the older trees in time.

2.0 Reinforcement of Mature Tree Planting• In this area, the park contains mature trees, with no understory. Intent in this area is to reinforce the mature trees with younger trees, intended to augment this feature and to provide a long-term viability with different ages of trees.• The main pathway is intended to stay in the same location as exists at present.• Some screening can occur against the north and east faces of the municipal water plant.• The screening vegetation should be native.• Some native plants were completed by volunteers, previously; these plants will be protected.

3.0 Water Plant Southern Boundary• Native species planting is proposed to occur along the southern boundary of the water plant.• The intent is to provide a green backdrop to the northern section of the park.

4.0 Existing West Parking Lot and Park Entrance• The existing parking lot will remain largely the same with minor changes to line painting and addition of bollards or barriers to prevent vehicular access.• Accessible spaces will be located on the southeast corner, and the southeast corner will be made accessible by inclusion of a ramp.• The park entrance and wayfinding sign should be located at this park entrance.• Some planting against the western border of the park, and the adjoining private property can also occur in this area.

5.0 Outfall• Some repairs are required to control erosion at the existing outfall.

OAKVILLE HARBOURWest Shore Master Plan

Page 30

Page 46: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

6.0 Natural Play Feature• The basic theme for Waterworks Park, is green. It serves primarily as a neighborhood park. However, it will see intensified use with the connecting of the shoreline along Walker Street Promenade to Tannery Park.• Our feeling is that a traditional piece of play equipment would be out of place in this green environment. There is a more traditional play equipment located relatively close by in Burnet Park.• By Natural Play, we mean using natural forms and materials and interpretation to provide opportunity for play and interaction.• This type of play area, more or less can contain different themes and forms which are tied into the overall theme of this zone of the park.• By locating the play area in the convergence of the pathway system, we begin to introduce a more abstract interpretation of nature, in this green zone of the park.• The hill, mentioned above, is used for tobogganing and skiing by children in the winter so location is proposed on west side of convergence.

OAKVILLE HARBOURWest Shore Master Plan

Page 31

Page 47: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

7.0 Shoreline Abstraction• The entire shoreline from the western boundary of the park to approximately where the townhouses start 200m east; currently exists as a partially grassed area with random shoreline protection in the form of rocks and stones.• In keeping with the green theme for this area of the park, we are proposing to introduce natural materials such as stone, wood, etc. to create visual ‘green’ art along the shoreline.• This could include using different types of boulders or stones, set in an architectural or man-made pattern that would provide interest to the waterfront edge.• These materials can also be functional, and provide places to sit, as well as being visually appealing. They can help create interesting effects from wave action along the shoreline.• This is a man-made shoreline, so our feeling is that we can enhance the ‘natural’ qualities of this zone by using abstract design to play around with, and have fun with the materials that make up the shoreline.• We propose that all soft areas on the lake side of the pathway in this zone be mass planted with ground covers and or grasses to contribute to the overall look and feel.• This abstraction of the shoreline would continue in different ways from Waterworks Park, to Tannery Park. Giving the park user a unique and original and interesting walk along the shoreline.

OAKVILLE HARBOURWest Shore Master Plan

Page 32

Page 48: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

8.0 Natural Found Feature• Continuing the natural theme in this zone, this location would be perfect for an art object, possibly made of found or natural materials from the site.• The basic content along this entire section of shoreline is to create a visual effect, as if an artist was doing the job of a coastal engineer• This allows the shoreline to become something very unique artistic and interesting, while at the same time fulfilling basic erosion control from a functional standpoint.

9.0 Path Seating and Path Lighting• We propose that the pathway stays in the same basic location as exists now.• Seating areas would be added on the north side of the path to provide resting areas, and overviews of the lake.• This would consist of asphalt or concrete pads set back from the main path and containing bench furniture, which would be consistent with the overall furnishing theme for the entire park.• The pad would be wide enough to allow wheelchair access, adjacent to the bench.• We also propose, dark sky initiative style lighting of the entire pathway from the parking lot and Walker St. entrances.• All furnishings such as benches, trash receptacles, recycling bins, lighting standards, signings and interpretive panels – should be of one overall language unique to Oakville Harbour.• All park paths should have a minimum width of 3.5 m. This width is suitable for Parks vehicle use, small boom truck for light changing, and is a safe width for combined pedestrians and cyclists.

OAKVILLE HARBOURWest Shore Master Plan

Page 33

Page 49: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

10.0 Savanna• We propose a reinforced savanna style planting area in this zone of the steep slope rear yard residences of Walker Street.• The same treatment would occur on both the east and western edges of these rear yard areas.

11.0 Steep Slope, Visual Improvement, Greening• This area is the narrowest section of shoreline.• The existing slope had vegetation removed by, and will be subject to severe erosion.• We propose green this area with low vegetation cover along this zone. In keeping with the abstraction of nature theme, this green slope could take form resulting from some alternate and innovative approaches.• There are some examples from around the world that deal with steep slope areas such as this, in a nontraditional manner.

OAKVILLE HARBOURWest Shore Master Plan

Page 34

Page 50: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

12.0 Path Convergence, Overlook Staircase, Feature Zone• This area, the park is an important one, because it is the convergence of the new widened shoreline leading to Tannery Park, the redevelopment of the staircase, and the proposed development of a feature overlook.• We propose to move the walkway closer to the waterfront edge in this zone, to create more of a buffer between the steep slope at the rear yards of the Walker Street residences.• This area provides lots of opportunity to create interest with grade and elevation variations.• It is an area that makes the transition from neighborhood park to the larger waterfront Park.• The existing staircase, should be redeveloped with more appropriate materials such as steel railings platforms, and safety treads.

Overlook Staircase• The staircase could be developed in such a way that overlook opportunities are provided, and even places to sit, incorporated into the design.• Using steel type structures allows a much lighter setting of the structure into the landscape.• It provides opportunities to almost have a see-through structure that allows the user to be more in the landscape than ‘on’ the landscape. The current heavy timber design no longer meets current safety standards, the materials can be slippery when wet, and the overall effect is dark and uninviting.• Our feeling is, not to finish the material with methods such as powder coated paint, but rather more ‘natural’ and raw effect, such a plain galvanized steel.

Feature Zone• An overlook feature is proposed to be located in this area, to provide an interesting and visually appealing feature that anchors the western boundary of the main waterfront park.• It could begin on grade plaza, with different shoreline treatments jutting slightly out into the lake, where users could look down upon the water. Stacked armor stone or some other type of vertical edge would add interest and change, which fits in with the overall theme of the waterfront edge.• It could be a slightly raised platform on stilts that would allow the user to literally feel as if they were in the water, waves lapping below and underneath the structure.• The elevations of the overlook can add interest to the multiple levels of this zone of the park.• The overlook being slightly set into the lake provides linear vistas to both the east and west shoreline edges.• The pathways in this area would converge to connect all the different elevations and levels and staircase and overlook features.

13.0 Woodlot Improvements• We are proposing to largely leave this area, the way it currently exists. • The forestry report will address any thinning or clean up or enhancements, recommendations for this and other similar areas.• There is a natural path connection between the staircase, and the street that runs through this zone, and that should be a mulched path, and not more formal materials such as asphalt or screenings.

OAKVILLE HARBOURWest Shore Master Plan

Page 35

Page 51: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

14.0 Park Entrance• Small improvements can be made to this park entrance, including information and wayfinding signings and extension of the concrete walkway along the north side of the road.• The exact extent of other improvements will depend on a final layout of the new park buildings and parking lot in this area.

15.0 Tableland and Region Building• We are proposing to screen the regional service building in this location, and to reinforce tree planting on both sides of the pathway leading to the pedestrian staircase.

16.0 New Shoreline Connecting Waterworks to Tannery• We propose a minimum cross-section along this zone of the park, which would include: • Approximately 5m for sure protection. • 2- 3m for a green edge adjacent to the shoreline. • 3.5 m wide walkway. • 4-5m wide green zone to the base of the steep slope • The approximate total width of the shore protection is 10 to 12 m.• Continuing the abstraction of the shoreline theme, the shore protection material could be totally different in this zone, such as a red granite compared to a white limestone or rounded armor compared to angular armor.• The green zone immediately above the shore protection would consist of hardy low species, including grasses and ground covers.• In selected areas the pathway would widen to contain seating platforms.• The steep vegetative slope which exists now, will be reinforced in order to maintain its thick vegetation profile and erosion control abilities.

17.0 Widening of Shoreline, and Transition Between Upper and Lower Path Systems.• In this area, the shoreline is a transition between the relatively narrow section with a steep slope back drop to the wider head land section located adjacent to the existing pier.• In this area, transitions will be made to connect the upper walkways leading to the future pavilion location, and the lower shoreline walkway, as well as connections to the revised parking lot.• The intent in this area will be to provide 6% or less slopes, for accessibility.

OAKVILLE HARBOURWest Shore Master Plan

Page 36

Page 52: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

• The basic section in this area would be the following; • 5-10 m shore protection • 4-5m green space • 3.5m walkway • 5-10m green space • Edge of overlook parking • The total width required would be in the 18-30m range.• It is important that the headland extend to the limits shown on our sketch plan. This will allow an adequate amount of room to provide ample space for pedestrians, people and cars, and to eliminate the effect and character of all hard surfaces, which currently exists.• An additional feature of this area is the connection of the path systems to the existing concrete pier.• The design of this area should occur with subtle elevation changes from the highest point in the parking lot, and the lowest elevation at the shore protection.• The addition of the headland and shoreline fill to make a connection between Tannery Park and Waterworks Park, will create a whole new identity for this section of the Oakville Harbor waterfront.• In its existing form the shoreline edge varies from, a park like setting in the west, to an uninviting hard surface zone in the east, adjacent to the pier.• The new shoreline access will combine hard surfaces and green surfaces to create a much more inviting atmosphere and character, in addition to providing full access for the public to the waters edge.• In keeping with the abstract interpretation of nature, with respect to the shoreline, this zone of shoreline should contain different characteristics than those from the shoreline sections to the west. This would typically include a change of materials, colors and textures, and to become intricate elements in the diversity of the shoreline along Lake Ontario.• Creating this headland is one of the most important aspects of the revitalization of the harbour.

18.0 Headland Section• The intent in this area is to create more public access, and better public access; in addition to creating the opportunity to design an improved fishery habitat.• It was generally agreed that the extent of landfill would be to the approximate end of the existing pier, and the landform shape would gradually narrow to the existing steep shoreline section identified in item 16.

OAKVILLE HARBOURWest Shore Master Plan

Page 37

Page 53: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

19.0 Relocated Lighthouse• We recommend that the existing lighthouse or a new structure be located at this juncture of the pier.• If a lighthouse were to be built, in keeping with the abstract nature of the shoreline, a sculptural form could potentially be developed, that in essence, showed the outline of a lighthouse in a sculptural form.• By outline we mean almost a wireframe structure, possibly with lighting built-in, that captured the essence of the lighthouse as it would have existed in a previous era.• We also think that this location of the park would be very suitable for an abstract metal sculpture, such as the examples we will show you today (see example of a framed window to the lake).• Upon visiting the site, with the city, we saw a very unique scene unfolding below us on the pier, when standing on top of the mound structure. There were 8 to 10 mothers pushing their baby carriages in single file along the hard surface of the pier. They were clearly undertaking exercise for themselves, in addition to walking their children. It immediately struck us that this was a very architectural and artistic scene that might be re-created in a sculptural form using silicon bronze or some other type of environmental metal. The intent would be to introduce a more structural form of art in this more structural area of the waterfront and harbor as another abstraction of the shoreline.

20.0 Revised Parking Lot• One of the most popular potential features of any waterfront park is having the ability to be able to drive up to the edge of the water, sit there and overlook the lake.• We propose that this area be much more organized than exists at present. We propose to provide car parking at a higher elevation overlooking the lake and pier. • We propose a center turnaround, designing the radius for emergency vehicles and fire trucks to reduce the impact of hard surface on this area. The center turnaround could contain vegetative or structural features.• We recommend a green separation space between the parking area and turnaround and the existing concrete pier.• In addition, a pedestrian crossing area leading to the spiral walkway up to the pavilion would define the north border of this zone.• This area would be one area that would remain open (without boat storage) for the entire year.• This area would also contain access to the linear shoreline walkway system.• The forms and design from a geometrical standpoint, in this area, combined with the headland area would continue the circular and curvilinear character of this zone of the park.

OAKVILLE HARBOURWest Shore Master Plan

Page 38

Page 54: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

21.0 Serpentine Walkway System Transition to Pavilion• Intention in this area is to maintain the Oakville annual perennial display on the hillside, in addition to creating a serpentine pathway system that winds itself up the slope to eventually reach the pavilion zone at the highest elevation.• In essence, we are carving a circuit or terrace into the mound and hillside that will allow park users a unique set of perspectives, in terms of overviews of the lake and harbor and the various levels and elevations of the park.• The walkway could contain notched out seating areas to provide interesting viewpoints back into the harbor and boating areas, as well as the lake.• Because the mound, is there (and is basically a large area of land fill), we feel creating a serpentine walkway, provides an opportunity to make this mound look more like it is integrated into the park as an environmentally sculptural feature.• When viewed from the lower elevations in serpentine walkway will increase the dimensional quality of the mound and the elevation changes and perspective.

22.0 Garden Development on the Mound• Discovery gardens and other features could be developed along the path of the serpentine walkway to add additional interest to this feature.• The intent would be to create personal types of gardens, along this discovery, serpentine route.

OAKVILLE HARBOURWest Shore Master Plan

Page 39

Page 55: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

23.0 Pavilion and Plaza• At the high point of the mound, we propose a shelter pavilion zone with an associated plaza.• The pavilion could take many forms, from a modern steel type structure to a traditional masonry with roof structure in the arts and crafts style.• The plaza area would be an expansion of the space directly below and adjacent to the pavilion. This would provide opportunities for gatherings and special events.• The plaza could contain various interpretive and educational panels that reflected upon and described those different parts of the harbor, that can be directly viewed from this excellent vantage point on the waterfront.

• The plaza would include seating areas, electrical connections for heating, special equipment, sound equipment, speakers, and specialized lighting.• The design of the pavilion should be closely tied into the design of the new washroom building and maintenance structure for the park.• Our initial feelings are that the structures should not be too modern, but rather should be modern interpretations of classic structures.• There are other opportunities in this area for sculpture gardens or special theme gardens tied into the interpretation and history of Oakville Harbour.• We would intend to keep ample open-space grassed areas to the west of the pavilion, to allow the creation of a ‘throw about’ space where various activities such as kite flying, kicking around a ball, having a picnic, and other such miscellaneous activities could occur.• The pavilion area could also provide an opportunity for windows into the lake sculptures or abstract forms that pointed out to the users, historical or cultural aspects of the waterfront.

OAKVILLE HARBOURWest Shore Master Plan

Page 40

Page 56: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

24.0 Pathway Nodal Area• This area, the park will remain largely as it exists now. We would propose that the central node, which connects the pathways coming from the entrance road, to the stairs, to the pavilion, and to the lower walkway areas, be developed in a little more detail; and to include wayfinding and directional information for park users.

25.0 Parking Expansion• We propose that parking be expanded in this area to the south side to mimic that which exists on the North Side.

26.0 Park Maintenance Washroom Building Zone• The washroom building is located at the approximate south east corner of the existing park maintenance building.• The building will have accessible washrooms.• Pathways will lead from the building to the corner of Forsythe and Anderson. The existing stairs will be removed.• The remaining area of this block which is the existing maintenance building roof will be turned into parkland.• The existing stairs located south of the proposed new washroom building will be widened and brought up to current standards.• New connections will be made to existing parking lot.

27.0 Parking and Boat Storage Space• This area will be widened slightly to contain parking on both sides with a wider road• We propose that the waterfront edge walkway be widened to the minimum 3.5 m.• We propose to also create a small green space on the north side to make the transition between the hard surface area and the waterfront edge walkway.• This area will continue to be used for boat storage.

28.0 Public Shoreline Access• The intent in this area is to widen the public access pathway, adjacent to the waterfront edge to 3.5 m.• In addition to the widening of the pathway, we propose to add seating areas overlooking the water.

OAKVILLE HARBOURWest Shore Master Plan

Page 41

Page 57: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

29.0 Transitional Node From Lower Level Walkway to Public Washroom Building• This area may change depending on the final layout of the public washroom building and maintenance operations building.• It is an important node, as a transition between the marina operations zone, the public washroom zone, and the linear waterfront pathway.

30.0 Linear Public Access to Previously Private Waterfront Edge• We propose to provide public access to the waterfront along this edge leading toward the existing Marina building.• Currently this area is fenced off and non-accessible to the public.• We propose a combination of waterfront edge plus green space plus a 3.5 m walkway, which continues around the previously private area to the launch ramp zone.

OAKVILLE HARBOURWest Shore Master Plan

Page 42

Page 58: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

31.0 Existing Stairway Deleted• We propose that the existing stairway, be eliminated.• We propose to keep the stairway further to the north.

32.0 Existing Steep Vegetated Slope• Our recommendations for this area are to reinforce and enhance the existing slope with the primary view towards erosion control and visual improvement.• At the base of the slope we propose to create a new 3.5 m walkway, complete with a low decorative railing, which separates the walkway from the marina parking lot.• This new 3.5 m wide walkway will also contain pedestrian level lighting. In order to improve safety and visibility factors.

33.0 Waterfront Edge Treatment at Marina Building• The concept for this area is to create public access to the full length of waterfront around the Marina Building.• This includes the addition of green space and to separate access walkways.• The walkway immediately adjacent to the docks, is for the private use of boaters to gain access to their boats.• That access is through a series of gates.• The gates are part of a low decorative railing which would have a height of 1.2 m.• A small green space would separate the railing from the private walkway.• Interior to the new fence would be a 3.5 m wide public walkway system with full visual access to the waterfront.• In the future, if the boat club was changed from private to public, the gates could be maintained in an open position.

34.0. Marina Building• The Marina Building is proposed to be better defined by the addition of green space around the exterior, and elimination of asphalt paving and boat storage on the south.• The displaced boat storage for five to eight boats is being made up elsewhere on site.• The waterfront side of the building would contain a private patio, which would be fenced off and accessible from the interior of the building.• Exterior to the private patio is the public access walkway, and the private boater access to the docks.

35.0 Linear Walkway, and Vegetation Buffer• The linear edge along this zone will be the same as occurs around the Marina Building to the walkway connecting the public system to Tannery Park is a combination of private and public walkways.• In the current location of the lighthouse play area and cabin building, we are proposing a green buffer space to separate the parking lot from the waterfront edge.• The northern culmination of this space ends up at the access point to launch ramp.

OAKVILLE HARBOURWest Shore Master Plan

Page 43

Page 59: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

36.0 Parking Lot and Boat Storage• It has been determined that the utility of the marina and boating area at present is at a minimal standard.• We propose to expand the boating utility area to allow an approximate 25 to 30% increase in hard surface areas for parking and boat storage.• In addition, this enlarged area will provide a better space for maneuvering cranes and other maintenance equipment used for marina purposes.• The parking lot will be well defined on all borders by curbs and green space. • The west border will be contained by a decorative fence which protects the widened pedestrian access along base of the steep slope bank.• We propose to use a change in material from concrete asphalt to define road and circulation areas within the parking lot. These are not curbs, but rather concrete bands that define the internal roads and access to the launch ramp.• All existing chain-link fencing will be removed so that access is open to both private boaters and the public.• The main future expansion of the parking lot is north of the launch ramps, included with improvements to the entrance road; this area would also provide for a larger turning radius into the north boating utility and storage area.• The north expansion area would provide ample room for storage of trailers used at the launch ramp.• In summary, the intent is to have a much cleaner and well-defined edge area to major pedestrian access, the first being along the waterfront and the second alone the bottom bank of the slope; and to expand the hard surface area used for boating activity, storage and parking.

37.0 Launch Ramp Zone• The launch ramp would remain in its existing location.• The area round launch ramp would be widened to provide more hard surface area for pedestrians and boaters.• The top zone would connect the boater to the north, and public to the south pedestrian pathway systems.• Both pedestrian path entrance systems would contain wayfinding and interpretive information features.• It is recommended that the existing cabin be relocated to another more appropriate site, or in a less conspicuous location on this site.

38.0 Pedestrian Node at Existing Staircase• We propose to keep and improve the existing staircase at this location.• At the bottom of the staircase we propose to develop a pedestrian node which connects a 3.5 m wide walkway south to Tannery Park. A connection across the parking lot to the waterfront pedestrian path, and a connection north to the boater area.• Staircase would be developed in a similar fashion to the staircase at the main waterfront Park, using steel structures and hand rails and safety treads.• We also propose to create a little wider green space around this node to help define the entrance road more clearly, and to create a clearly defined pedestrian crosswalk across the main road into the boater area.• This wider green space, will provide an opportunity to create a larger buffer against the pulling out boats.

OAKVILLE HARBOURWest Shore Master Plan

Page 44

Page 60: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

39.0 Parking Lot Expansion Area• As indicated previously the intent in this area is to increase the usable hard surface footprint for boating purposes.• The entrance road to the north will be wider and more direct. Approximately located at the western boundary of the existing parking and mast storage.• This widened area will provide much greater room for crane and other vehicles maintaining or pulling out boats.• This expanded hard surface should allow for an additional 10 to 20 boats to be stored during winter.

40.0 Boater Utility Area and Linear Edge Improvements• We propose to simplify and widen the pedestrian access edge from this location north to the limits of the property.• The widened walkway would be wide enough to accommodate a parks vehicle• The widened walkway would also accommodate, electrical plug-ins and other utilities built into the section.• The edge would be designed with a safety edge rail and tie-ups.• The entire waterfront edge from this point north would be accessible to the public.• The intent is to have a simple, functional, wide access edge, with lighting and utility built in, and incorporated into the overall furnishing system design of the project.

41.0 Pedestrian Access and Green Zones• The area surrounding the rectangular inlet, is intended to be simplified by providing a green buffer strip between the widened walkway edge and the widened crane and vehicle access road. Possible picnic table area.• There will also be a pedestrian crossing at this location for users entering the park along the main entrance road and from the new condominium developments north of the park.• The widened access roads will provide easier access to the inlet and the northerly boat removal area.

42.0 Crane Lift Out Area• We propose to expand this area and simplify the edges. In addition, we propose a widened radius to connect this zone to the wider access road.

43.0 Below Bridge Mast Storage Zone• The easterly half of the hard surface area below the existing Lakeshore Road bridge will be fenced with a removable fencing system for storage of masts.• The removable fencing system will allow for this zone to be used for parking or other purposes during the summer season.• Vertical boat storage racks would be incorporated into this zone.

OAKVILLE HARBOURWest Shore Master Plan

Page 45

Page 61: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

44.0 Existing Slope Zone, and Staircase• The concept in this area is to improve the visual appeal of the sloped area from Lakeshore Road down into the park.• This includes removal of the existing staircase, which is rarely used.• The information kiosk currently located in this area would be relocated to the area around the launch ramp.• Proposed treatments would include tree planting and simplification of shrub and ground covers with the intent of minimizing maintenance and maximizing visual impact.

45.0 Redefined Entrance Road• It is intended to more clearly define the bottom of the main entrance road and it’s transition into the parking lot area.• This would include containment of the pedestrian pathway systems with defined crosswalks and concrete curb edges.• A larger buffer area at the base of the existing stacked armor stone wall, is also proposed.

46.0 Refined Entrance Road and Pedestrian Sidewalk• We propose a minimum 1.5 m wide concrete sidewalk be placed on the east side of the main entrance road.• This sidewalk will provide a new public access separated from the road surface from the Lakeshore Road area, and upper neighborhoods in the north park district.

47.0 Improved Entrance Road• We propose to simplify the existing entrance road by eliminating the current island and orienting the entrance road to more of a 90° angle to the main street.• Improvements to the entrance would include full radius to allow for large machines such as cranes to easily enter the park, and to meet current emergency and fire vehicle turning radii.• Improvements would also include a park entrance sign and wayfinding sign along with a pedestrian sidewalk located along the south edge of the road.• Planting lighting and other improvements are recommended to improve the visual appeal of this important entrance to the park.

48.0 Pedestrian Connection to New Steps North of Lakeshore• A small green space and stairway is being constructed on the North side of Lakeshore Road adjacent to the condominium development under construction.• This will provide safer more up to date access from Lakeshore Road down to the park and replaces the steps currently existing on the south side.

OAKVILLE HARBOURWest Shore Master Plan

Page 46

Page 62: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 63: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 64: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 65: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

AP

PR

OV

ED

SC

ALE

:

DA

TE

CH

EC

KE

D

DR

AW

N

DR

AW

ING

NO

.P

RO

JEC

T N

O.

PR

OJE

CT

JG JG 1:50

0m

LOC

ATI

ON

Oak

ville

, Ont

ario

July

200

8

Oak

ville

Har

bour

Maste

r P

lan

West

Sh

ore

JOH

N G

EOR

GE

ASS

OC

IATE

S IN

C32

7 P

ine

Cov

e R

oad

Bur

lingt

on, O

N, L

7N 1

W4

905-

632-

3473

FA

X 9

05-6

32-2

407

CO

NS

ULT

AN

T

Land

scap

e A

rchi

tect

sV

isio

nsca

pes

Urb

an F

ores

try

Urb

an F

ores

t Inn

ovat

ions

Inc.

CLI

EN

T Tow

n O

f Oak

ville

1225

Tra

falg

ar R

oad

OA

KV

ILLE

ON

L6J

5A

6

Park

and

Pla

nnin

gD

evel

opm

ent

NO

RTH

TAICOSSA OI RATNO

STCE

TIHC

RA

EPACSDNALFO

NOI

ME

MB

ER

JOH

N G

EO

RG

E

05m

10m

20m

50m

Met

ric B

ar S

cale

Was

hroo

mB

uild

ing

1

2

3

4 5

6

7

8

7

9

1011

12

14 13

15

16

17

18

2022

21

23

24

26

LAK

ES

HO

RE

RO

AD

L A

K E

O

N T

A R

I O

1 6 M I L E C R E E K

Forsythe St

And

erso

n S

t

Bur

net S

t

Wal

ker S

t

Wilson St

Chisholm St

Oak

ville

Har

bour

Wat

er T

reat

men

t Pla

nt

27

28

29

32

3130

1

35

34

38

37

36

1

40

42

41

43

44

47

45

Prop

osed

Pub

lic A

cces

s N

orth

Lak

esho

re R

d.

77.0

0

9 9

R=1

5000

R=1

5000

R=1

5000

13

12

11

9

9

7

10

10

Par

king

89

Spa

ces

8

Ligh

thou

se

Par

king

Ove

rlook

Sea

ting

Pro

men

ade

5m W

ide

Mas

s Lo

w P

lant

ing

5m W

ide

Ram

p D

own

to L

ower

Lev

el

Low

Pla

ntin

g - H

igh

Bran

ch T

rees

6.5

m W

ide

Sea

ting

Sho

re P

rote

ctio

n 8.

5m W

ide

Har

d S

urfa

ce C

rane

2m P

rivat

e W

alkw

ay

2m L

ow P

lant

ing

1.2m

Rai

ling

1.2m

Rai

ling

3.5m

Pub

lic W

alkw

ay

Gat

e A

cces

s V

ario

us L

ocat

ion

Exis

ting

Bui

ldin

gP

rivat

e P

atio

s

68

1515

1819

1313

1313

1619

44

Alte

rnat

e6

Trai

lers

17

31

5

Lift

Out

Are

a

16

11

55

98 P

arki

ng S

pace

sN

orth

of L

aunc

h R

amp

(47

dash

ed s

pace

s on

wes

t sid

eop

tiona

l or f

utur

e)

168

Par

king

Spa

ces

Sou

th o

f Lau

nch

Ram

p

Tota

l Par

king

Mar

ina

Are

as 2

66 S

pace

s

R=1

2500

Rev

ised

Ent

ranc

e90

Deg

rees

to S

treet P

edes

trian

Sid

ewal

k

Upd

ated

Sta

irs

3.5m

Lig

hted

W

alkw

ay W

ithLo

w D

ecor

ativ

eFe

nce

Mas

t S

tora

geFe

nced

Pat

hway

Bel

ow

Brid

ge to

Con

nect

sto

New

Nor

th

Par

kette

Acc

ess

Pav

ilion

and

Sta

ge S

eatin

g

Pro

men

ade

3.5m

Wid

e

Mas

s Lo

w P

lant

ing

3m W

ide

Sho

re P

rote

ctio

n 8.

5m W

ide

Ove

rlook

Fe

atur

e Con

nect

ion

Poi

ntB

ewte

en N

ew a

ndE

xist

ing

Shor

elin

es

New

Sta

ircas

e

Rev

ised

Ent

ranc

e

Laun

ch R

amp

OAKVILLE

Nat

ural

Pla

y Ar

ea

10

10

19

25

3339

46

48

A

BC

D

E

F

G

Con

cept

Pla

n

Wal

ker S

treet

Pro

men

ade

Wat

erw

orks

Par

k

Tann

ery

Par

k

Shi

pyar

dP

ark

Opt

iona

lR

eloc

atio

n of

Log

Cab

in

Page 66: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 67: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

AP

PR

OV

ED

SC

ALE

:

DA

TE

CH

EC

KE

D

DR

AW

N

DR

AW

ING

NO

.P

RO

JEC

T N

O.

PR

OJE

CT

JG JG NTS

LOC

ATI

ON

Oak

ville

, Ont

ario

June

200

8

Oak

ville

Har

bour

Maste

r P

lan

JOH

N G

EOR

GE

ASS

OC

IATE

S IN

C32

7 P

ine

Cov

e R

oad

Bur

lingt

on, O

N, L

7N 1

W4

905-

632-

3473

FA

X 9

05-6

32-2

407

CO

NS

ULT

AN

T

Land

scap

e A

rchi

tect

sV

isio

nsca

pes

Urb

an F

ores

try

Urb

an F

ores

t Inn

ovat

ions

Inc.

CLI

EN

T Tow

n O

f Oak

ville

1225

Tra

falg

ar R

oad

OA

KV

ILLE

ON

L6J

5A

6

Park

and

Pla

nnin

gD

evel

opm

ent

NO

RTH

TAICOSSA OI RATNO

STCE

TIHC

RA

EPACSDNALFO

NOI

ME

MB

ER

JOH

N G

EO

RG

E

Sec

tions

Sectio

n A

A -

Walk

er

Str

eet

Pro

men

ad

e a

nd

Ste

ps

Sectio

n B

B -

Walk

er

Str

eet

Pro

men

ad

e t

o

Tan

nery

Park

Co

nn

ectio

nS

ectio

n C

C -

Walk

er

Str

eet

Pro

men

ad

e t

o

Tan

nery

Park

Co

nn

ectio

n (

narr

ow

er)

Sectio

n D

D -

Ta

nn

ery

Park

Lo

wer

Park

ing

Lo

t to

Lake

Sectio

n F

F -

S

hip

yard

Park

Park

ing

Lo

t

Sectio

n D

D -

Sh

ipyard

Park

at

Sq

uad

ron

Sectio

n G

G -

S

hip

yard

Park

at

Flo

atin

g D

ocks

Page 68: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 69: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 70: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 71: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

OAKVILLE HARBOURWest Shore Master Plan

Next Steps and Conclusions

Next Steps

Outlined below as an implementation strategy are “Next Steps” to be taken for the enhancement of the west shore of Oakville Harbour (in no particular order):

� Identify distinct projects based on immediate need (i.e. failing shoreline protection along west shore of 16 Mile Creek and Lake Ontario shorelines);

� Prioritize distinct projects in relation to improvements for projects all ready in motion (i.e. new washroom building being designed in conjunction with new site development in immediate area);

� Initiate applications with various approval bodies to address improvements to west shoreline, filling, fish habitat;

� Complete approval process to adopt this document as a guideline for future development;

� Address current lease negotiations to ensure a more functional and publicly accessible shoreline and marina facility;

� Identify shared improvement projects such the outfall from the Region of Halton’s waterworks plant;

� Identify partnering opportunities with local businesses and business improvement area in the downtown core;

� Identify and apply for federal and provincial funding opportunities for infrastructure replacements and shoreline improvements;

� Initiate project phasing in conjunction with projected and identified park improvement budgets in coming years;

� Identify and initiate process to take landscape maintenance budgets to a higher level than those currently applied;

OAKVILLE HARBOUR West Shore Master Plan

OAKVILLE HARBOURWest Shore Master Plan

Page 51

Page 72: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

During the public open house, two items related to adjacent areas outside the scope of work were identified for improvements and are recommend as projects in conjunction with Works Department of the Town of Oakville:

� Sidewalk deck improvements to the existing Lakeshore Road bridge; and � Improved pedestrian connection from Waterworks Park along Kerr Street

Operational maintenance issues including geese, snow removal and security will be addressed outside of the scope of this master plan.

Conclusions

The Oakville Harbour West Shore Master Plan presents the opportunity to enhance the ‘green necklace’ that connects the greater waterfront system along Lake Ontario.

The design philosophy has identified and highlighted the experiential opportunities along Oakville Harbour and the Lake Ontario waterfront (from Tannery to Walker Street Promenade and Waterworks Park). Multiple meetings with staff and stakeholders were used to direct project development and decisions – the outcomes will guide meaningful development of these parks.

The proposed recreational resource is provided for those who prefer to meander, sit and contemplate one of the most spectacular views along 16-Mile Creek/ Oakville Harbour and Lake Ontario. Overall, the park system is proposed to be flexible, with greater offerings for a quiet neighbourhood park under preserved mature trees, shady places for dog walking and picnicking, locations to fish, launch/haul out, store and dock boats and improve cohesion and identity to Oakville’s recreation system as well as improve Lake Ontario’s waterfront.

Proposed marina facilities improvements will better reflect safety and security needs of dock users, boats and the general public wanting access to the area. Both the casual pedestrian and the avid boater will be welcomed with updated facilities and clear direction to allow for the most enjoyable experience by all.

As a result the proposed master plan for the west shore of the Harbour has character related to both harbour and community. Within the scope of the four parks, the shoreline of Lake Ontario is highlighted to provide the best opportunity to get close to the waters edge allowing for opportunities to create habitat, and diversity in edge character and amenities.

Overall the West Shore Master Plan reflects the benefits of working closely with staff and stakeholders; and excellence in waterfront design and development – the resulting master plan enhances the overall harbour and the local and greater Oakville community. Thereby, ensuring this will be an important recreational and community resource as well as a significant tourist destination.

OAKVILLE HARBOURWest Shore Master Plan

Page 52

Page 73: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 74: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 75: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 76: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 77: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

ARBORIST REPORT FOR LANDSCAPE MASTER PLAN FOR OAKVILLE HARBOUR, OAKVILLE, ONTARIO

Prepared for:

John George Associates Inc.327 Pine Cove Road

Burlington ONL7N 1W4

Prepared By:

Philip van Wassenaer, B.Sc., MFCUrban Forest Innovations Inc.

1253 Crossfield BendMississauga, Ontario

L5G 3P5

July 14, 2008

Appendix 1 Page 1OAKVILLE HARBOURWest Shore Master Plan

Page 78: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 79: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Oakville Harbour Tree Inventory, Oakville, Ontario, 2008

Urban Forest Innovations Inc., 14/07/08

2

Table of Contents

Introduction ...................................................................................................3

Field Observations.........................................................................................3

Discussion.......................................................................................................3

Conclusions ....................................................................................................4

Recommendations .........................................................................................5

Appendix 1 – Tree Inventory .......................................................................7

Limitations of Assessment ..........................................................................20

Appendix 1 Page 2

Page 80: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 81: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Oakville Harbour Tree Inventory, Oakville, Ontario, 2008

Urban Forest Innovations Inc., 14/07/08

3

Introduction

John George Associates Inc. are developing a park master plan for Oakville Harbour and the associated park areas. John George Associates Inc. has requested that Urban Forest Innovations Inc. prepare the tree preservation report as required by the Town of Oakville.

This report provides an inventory of the trees on the site. The report outlines the current condition and preservation recommendations for all inventoried trees. Trees recommended for removal will also be identified.

Field Observations

The initial site and field observations were made on March 31P

th, and revisited on June 10th, 2008. There was no construction activity on the site. Trees on the site were measured for diameter at 1.3 meters above grade, assessed for health, structure and risk. All of the specimens were individually tagged and referenced on a site map provided by John George Associates Inc. Four hundred and fifty four trees are included in the tree inventory.

Discussion

The tree inventory is provided in Table 1, Appendix 1. A brief explanation of the assessment categories follows:

Tree Number- this number refers to the number on the site plan and on the tree.

Species- the common and botanical name for each tree is provided.

DBH- this refers to diameter (in centimetres) at breast height and is measured at 1.3 m above the ground for each tree.

Trunk Integrity (T.I.) - this is an assessment of the trunk for any defects or weaknesses. It is measured on a scale of poor, fair, good.

Canopy Structure (C.S) - this is an assessment of the scaffold branches and the canopy of the tree.This is also measured on a scale of poor, fair, good.

Canopy Vigour (C.V.) - this is an assessment of the health of the tree and assesses the amount of deadwood and live growth in the crown as compared to a 100% healthy tree. The size, colour and amount of foliage are also considered in this category.

Crown Width (C.W.) – this is width of the tree’s crown in meters.

Appendix 1 Page 3

Page 82: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Oakville Harbour Tree Inventory, Oakville, Ontario, 2008

Urban Forest Innovations Inc., 14/07/08

4

Tree Removals

Trees 17159, 17162, 17223, 17757, 17816, 17824, 17846, 17871, 17874, 17877, 17892, 25926, 25971, 25974, and 26028 are dead or beyond the point of preservation and are recommended for immediate removal.

Tree Preservation

The recommendations section provides guidelines for the protection of the trees from any proposed construction activity and the activities that will be unacceptable within tree preservation areas.

The following recommendations pertain to particular trees on the site:

1. Trees found in the inventory with deadwood present should be pruned. The pruning should be prioritized on the size and location of the deadwood. Large deadwood and deadwood observed over or near to the paths and roads should be the top priority.

2. Several Austrian pine trees have been with observed with Spheropsis (formerly known as Diploda Tip Blight). This disease can be remedied by pruning out small infected areas within the tree and thinning to allow for better wind penetration through the crown. Trees found with over 50% of the crown infected are recommended for removal and replacement.

3. Cables have been recommended for trees found with tightly included stems.

4. Trees found with fences, ivy, movable obstacles or other trees that impede their natural growth have been observed and recorded. We recommend that the obstacles be removed to allow for the trees unobstructed development.

Conclusions

There are four hundred and fifty four trees associated with this project. Most of the inventoried treeswere found to be in good health and condition. Fifteen trees are recommended for immediate removal. Tree preservation recommendations have been provided for trees that may be affected by construction activities in their rooting zones.

Appendix 1 Page 4

Page 83: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Oakville Harbour Tree Inventory, Oakville, Ontario, 2008

Urban Forest Innovations Inc., 14/07/08

5

Recommendations

The following is a list of practical considerations for the construction phase of the project that applies to all trees that may be impacted by the construction.

1. No groundbreaking activities or demolition should occur until all tree preservation requirements have been met. Of primary concern is the erection of proper hoarding to establish the tree preservation zones (TPZ).

2. A consulting arborist should be consulted for all work that impacts the tree preservation zone.

3. The location of the tree preservation zone should be clearly indicated on the site plan. Fencing shall remain in place until all site work has been completed, and may not be removed, relocated, or otherwise altered without the written permission of the consulting arborist. The hoarding should be constructed of four-foot high solid sheets of plywood fastened to posts.

4. A qualified arborist will undertake proper root pruning when and if roots of retained trees are to be exposed by construction activities. Exposed roots will be covered with soil or mulch as soon as possible to prevent further damage and desiccation. Root pruning prior to excavation will help prevent unnecessary damage to tree roots and is highly recommended.

5. The tree preservation zone should be posted with signs. Within the tree preservation zonethere will be no:

� Grade changes� Dumping or storage of any materials� Use of any machinery without prior approval� Landscaping with heavy machinery� Activity of any kind without permission of the arborist

6. Efforts should be made to route all underground utilities around the tree preservation zones. If this is not possible, they should be bored or tunneled under the root zone of the trees (minimum 1.6 m depth). Using traditional trenching methods, there will be significant root damage to the trees that are being preserved. Where possible it is strongly recommended that any installation of underground utilities (water, sewage or hydro) should utilize a non-destructive methodology such as directional boring, Airspade technology or hydrovac removal of soil.

7. If injury should occur to retained trees during construction, the consulting arborist should evaluate them so that appropriate treatments can be recommended and performed.

Appendix 1 Page 5

Page 84: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Oakville Harbour Tree Inventory, Oakville, Ontario, 2008

Urban Forest Innovations Inc., 14/07/08

6

8. All contractors should be informed of the tree preservation measures and guidelines at a pre-construction meeting.

9. Monitoring of the trees and the tree preservation zones should be conducted by a consulting arborist throughout the duration of the project.

Appendix 1 Page 6

Page 85: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

App

endi

x 1

–T

ree

Inve

ntor

y

Tab

le 1

: Tre

e in

vent

ory

for

Oak

ville

Har

bour

, Oak

ville

, Ont

ario

.

Tag

#C

om

mo

n N

ame

Bo

tan

ical

Nam

eD

BH

TI

CS

CV

CW

Co

mm

ents

fro

m 3

/31/

08 v

isit

Co

mm

ents

fro

m 6

/10/

08 v

isit

1715

0B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia20

GG

G4

1715

1B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia17

GF

G4

1715

2B

lack

Wal

nut

Jugl

ans

nigr

a16

GG

G4

1715

3B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia29

FG

G6

1715

4B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia16

GG

G3

1715

5B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia20

GF

G5

1715

6W

hite

Will

owS

alix

alb

a75

GG

G12

Med

ium

siz

ed d

eadw

ood

1715

7B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia78

GF

F9

1715

8B

lack

Wal

nut

Jugl

ans

nigr

a30

,44

GF

G10

Cab

le r

ecom

men

ded

1715

9B

lack

Wal

nut

Jugl

ans

nigr

a52

PP

F9

Med

ium

siz

ed d

eadw

ood

Sho

win

g di

e-ba

ck, d

ecay

in t

runk

, rem

ove

tree

1716

0M

anito

ba M

aple

Ace

r ne

gund

o30

FG

G8

1716

1M

anito

ba M

aple

Ace

r ne

gund

o22

FG

G4

1716

2B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia43

PP

G10

Rec

omm

end

rem

oval

1716

3T

amar

ack

Larix

laric

ina

28G

GG

5

1716

4T

amar

ack

Larix

laric

ina

32G

FG

4T

oppe

d

1716

5B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia42

GG

G9

1716

6T

amar

ack

Larix

laric

ina

36G

FG

7

1716

7M

anito

ba M

aple

Ace

r ne

gund

o45

GF

G12

1716

8M

anito

ba M

aple

Ace

r ne

gund

o36

FF

G8

1716

9H

oney

Loc

ust

Gle

dits

ia tr

iaca

ntho

s14

FG

G6

1717

0H

oney

Loc

ust

Gle

dits

ia tr

iaca

ntho

s14

GG

G6

1717

1H

oney

Loc

ust

Gle

dits

ia tr

iaca

ntho

s12

GG

G5

1717

2H

oney

Loc

ust

Gle

dits

ia tr

iaca

ntho

s30

GG

G15

1717

3H

oney

Loc

ust

Gle

dits

ia tr

iaca

ntho

s31

GG

G15

1717

4H

oney

Loc

ust

Gle

dits

ia tr

iaca

ntho

s28

GF

G14

1717

5S

ilver

Map

leA

cer

sacc

harin

um38

GF

G13

1717

6A

pple

Mal

us s

p.34

GG

G7

1717

7S

ilver

Map

leA

cer

sacc

harin

um63

GG

G18

Ivy

on t

runk

tha

t cou

ld b

e re

mov

edC

row

n is

ver

y th

in

1717

8F

alse

Ced

arC

ham

aecy

paris

sp.

6,4,

3G

GG

3

1717

9F

alse

Ced

arC

ham

aecy

paris

sp.

10,8

,5G

GG

4

1718

0R

ed O

akQ

uerc

us r

ubra

29G

FG

8

Appendix 1 Page 7OAKVILLE HARBOURWest Shore Master Plan

Page 86: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Oak

ville

Har

bour

Tre

e In

vent

ory,

Oak

ville

, Ont

ario

, 200

8

Urb

an F

ores

t Inn

ovat

ions

Inc

., 14

/07/

08

8

1718

1C

orks

crew

Will

owS

alix

mat

suda

na

12G

GG

2.5

1718

2C

orks

crew

Will

owS

alix

mat

suda

na

8,7

GG

G3

1718

3C

orks

crew

Will

owS

alix

mat

suda

na

11G

GG

3

1718

4C

orks

crew

Will

owS

alix

mat

suda

na

11,1

0G

GG

2.5

1718

5C

orks

crew

Will

owS

alix

mat

suda

na

12,8

GG

G3

1718

6C

orks

crew

Will

owS

alix

mat

suda

na

12G

GG

3

1718

7C

orks

crew

Will

owS

alix

mat

suda

na

14G

GG

2.5

1718

8C

orks

crew

Will

owS

alix

mat

suda

na

19G

GG

4

1718

9W

illow

sp.

Sal

ix s

p.17

GG

G6.

5

1719

0A

pple

sp.

Mal

us s

p.20

GG

G7

1719

1B

eech

sp.

Fag

us s

p.14

GG

G5

1719

2B

eech

sp.

Fag

us s

p.12

,10,

8G

FG

3

1719

3B

eech

sp.

Fag

us s

p.8

FG

G2

1719

4B

eech

sp.

Fag

us s

p.9

FG

G2

1719

5W

hite

Ash

Fra

xinu

s am

eric

ana

26G

GG

8

1719

6S

ilver

Map

leA

cer

sacc

harin

um32

GG

G10

1719

7S

ilver

Map

leA

cer

sacc

harin

um29

GG

G10

1719

8C

arol

ina

Pop

lar

Pop

ulus

x c

anad

ensi

s49

,45,

44F

FG

19

1719

9S

ilver

Map

leA

cer

sacc

harin

um29

GG

G8

1720

0H

oney

Loc

ust

Gle

dits

ia tr

iaca

ntho

s22

GG

G6

1720

1R

ed B

udC

erci

s ca

nade

nsis

17G

FG

6C

row

n is

slig

htly

thi

n

1720

2H

oney

Loc

ust

Gle

dits

ia tr

iaca

ntho

s24

GG

G8

1720

3A

pple

sp.

Mal

us s

p.42

GG

G7

1720

4S

ilver

Map

leA

cer

sacc

harin

um49

GG

F10

Cro

wn

is th

in, i

vy o

n ba

se s

houl

d be

rem

oved

1720

5W

hite

Will

owS

alix

alb

a81

GF

G11

1720

6W

hite

Will

owS

alix

alb

a10

4G

FG

15S

torm

bre

ak s

tub

on lo

wer

nor

th s

tem

to

be

prun

ed

1720

7M

anito

ba M

aple

Ace

r ne

gund

o10

0G

FG

21C

able

fou

nd in

Tre

e

1720

8S

iber

ian

Elm

Ulm

us p

umila

48G

FG

11

1720

9C

arol

ina

Pop

lar

Pop

ulus

x c

anad

ensi

s10

4F

GG

15G

row

ing

in t

o fe

nce

1721

0C

arol

ina

Pop

lar

Pop

ulus

x c

anad

ensi

s74

GG

G12

1721

0aA

ustr

ian

Pin

eP

inus

nig

ra30

GG

G7

1721

0bLi

nden

Tili

a co

rdat

a28

GG

G5

Rec

omm

end

rem

ovin

g de

ckin

g ar

ound

ba

se o

f tre

e

1721

0cLi

nden

Tili

a co

rdat

a25

GG

G6

1721

1R

ed O

akQ

uerc

us r

ubra

26G

GG

10

1721

2N

orw

ay M

aple

Ace

r pl

atan

oide

s18

GG

G6

1721

3B

lack

Wal

nut

Jugl

ans

nigr

a31

GG

G8

Appendix 1 Page 8OAKVILLE HARBOURWest Shore Master Plan

Page 87: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Oak

ville

Har

bour

Tre

e In

vent

ory,

Oak

ville

, Ont

ario

, 200

8

Urb

an F

ores

t Inn

ovat

ions

Inc

., 14

/07/

08

10

1724

9A

ustr

ian

Pin

eP

inus

nig

ra31

GG

G6

1725

0A

ustr

ian

Pin

eP

inus

nig

ra24

GG

G6

1725

1N

orw

ay M

aple

Ace

r pl

atan

oide

s34

GG

G11

Slig

htly

gird

led

root

s at

bas

e

1725

2N

orw

ay M

aple

Ace

r pl

atan

oide

s32

GG

G10

Slig

htly

gird

led

root

s at

bas

e

1725

3N

orw

ay M

aple

Ace

r pl

atan

oide

s38

GG

F10

Gird

led

root

s at

bas

e

1725

4N

orw

ay M

aple

Ace

r pl

atan

oide

s29

GG

G9

1725

5W

hite

Birc

hB

etul

a pa

pyrif

era

34,2

8,18

GF

G11

1725

6W

hite

Birc

hB

etul

a pa

pyrif

era

30G

GG

8

1725

7B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia50

FF

G7

1725

8W

hite

Pin

eP

inus

str

obus

34G

GF

10

1725

9W

hite

Birc

hB

etul

a pa

pyrif

era

20,1

5,18

GF

G11

1726

0W

hite

Birc

hB

etul

a pa

pyrif

era

22,2

1G

GG

7

1726

1S

cots

Pin

eP

inus

syl

vest

ris22

GP

F6

1726

2W

hite

Birc

hB

etul

a pa

pyrif

era

18G

GG

6

1726

3S

cots

Pin

eP

inus

syl

vest

ris24

GF

F7

1726

4W

hite

Ash

Fra

xinu

s am

eric

ana

43G

GG

16

1726

5W

hite

Ash

Fra

xinu

s am

eric

ana

44G

GG

16

1726

6S

cots

Pin

eP

inus

syl

vest

ris26

GG

G5

1726

7A

mer

ican

Bee

chF

agus

gra

ndifo

lia34

GG

G10

1726

8W

hite

Pin

eP

inus

str

obus

33G

GG

7

1726

9W

hite

Pin

eP

inus

str

obus

34G

GG

7

1727

0W

hite

Ash

Fra

xinu

s am

eric

ana

62G

GG

12

1727

1W

hite

Ash

Fra

xinu

s am

eric

ana

55G

GG

16

1727

2S

cots

Pin

eP

inus

syl

vest

ris28

GG

F7

Cro

wn

die-

back

1727

3S

cots

Pin

eP

inus

syl

vest

ris32

GG

G6

1727

4W

hite

Ced

arT

huja

occ

iden

talis

10G

GG

1.5

1727

5W

hite

Ced

arT

huja

occ

iden

talis

8G

GG

1.5

1727

6W

hite

Ced

arT

huja

occ

iden

talis

10G

GG

1.5

1727

7P

ine

sp.

Pin

us s

p.2

Clu

mps

GG

G7

1727

8B

lack

Che

rry

Pru

nus

sero

tina

42G

GG

12

1727

9B

lack

Wal

nut

Jugl

ans

nigr

a38

GG

G11

1728

0B

lack

Wal

nut

Jugl

ans

nigr

a40

GG

G12

1728

1B

lack

Wal

nut

Jugl

ans

nigr

a58

GG

G16

1728

2M

anito

ba M

aple

Ace

r ne

gund

o34

,39,

44F

FG

12

1728

3D

awn

Red

woo

dM

etas

equo

ia

glyp

tost

robo

ides

18G

GG

3.5

1728

4M

anito

ba M

aple

Ace

r ne

gund

o29

GF

G7

Appendix 1 Page 9OAKVILLE HARBOURWest Shore Master Plan

Page 88: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Oak

ville

Har

bour

Tre

e In

vent

ory,

Oak

ville

, Ont

ario

, 200

8

Urb

an F

ores

t Inn

ovat

ions

Inc

., 14

/07/

08

11

1728

5B

lack

Wal

nut

Jugl

ans

nigr

a39

GG

G10

1728

6B

lack

Wal

nut

Jugl

ans

nigr

a35

GG

G7

1728

7B

lack

Wal

nut

Jugl

ans

nigr

a32

GG

G10

1728

8Ju

nipe

rJu

nipe

rus

virg

inia

na10

GG

G1.

5

1728

9Ju

nipe

rJu

nipe

rus

virg

inia

na9

GG

G1.

5

1729

0Ju

nipe

rJu

nipe

rus

virg

inia

na10

GG

G1.

5

1729

1H

oney

Loc

ust

Gle

dits

ia tr

iaca

ntho

s25

GG

G7

1729

2H

oney

Loc

ust

Gle

dits

ia tr

iaca

ntho

s27

GG

G9

1729

3S

ervi

cebe

rry

sp.

Am

elan

chie

r sp

.12

GG

G3.

5

1729

4A

ustr

ian

Pin

eP

inus

nig

ra47

GG

G8

1729

5A

ustr

ian

Pin

eP

inus

nig

ra34

GF

G7

1729

6A

ustr

ian

Pin

eP

inus

nig

ra43

GG

G9

1729

7A

ustr

ian

Pin

eP

inus

nig

ra34

GG

G7

1729

8A

ustr

ian

Pin

eP

inus

nig

ra38

GG

G9

1729

9A

ustr

ian

Pin

eP

inus

nig

ra38

,22,

27G

FG

11La

rge

scaf

fold

limb

torn

out

1773

9A

ustr

ian

Pin

eP

inus

nig

ra28

GG

F7

Dip

lodi

a

1774

0H

orse

ches

tnut

Aes

culu

s hi

ppoc

asta

num

10P

FG

2.5

1774

1W

hite

Ash

Fra

xinu

s am

eric

ana

44G

GG

9

1774

2W

hite

Ash

Fra

xinu

s am

eric

ana

32G

GG

7.5

1774

3W

hite

Ash

Fra

xinu

s am

eric

ana

20G

GG

7

1774

4R

ed O

akQ

uerc

us r

ubra

10G

GG

4

1774

5R

ed O

akQ

uerc

us r

ubra

12G

GG

4

1774

6R

ed O

akQ

uerc

us r

ubra

26G

GG

9

1774

7R

ed O

akQ

uerc

us r

ubra

27G

GG

8

1774

8R

ed O

akQ

uerc

us r

ubra

27G

GG

9

1774

9R

ed O

akQ

uerc

us r

ubra

10G

GG

4

1775

0R

ed O

akQ

uerc

us r

ubra

16G

GG

5

1775

1R

ed O

akQ

uerc

us r

ubra

13F

GG

3.5

Dec

ay a

t ba

se

1775

2S

ilver

Map

leA

cer

sacc

harin

um8

GG

G1.

5

1775

3N

orw

ay M

aple

Ace

r pl

atan

oide

s13

FG

G3

1775

4S

ugar

Map

leA

cer

sacc

haru

m

12G

GG

5

1775

5W

hite

Ash

Fra

xinu

s am

eric

ana

12F

GG

3

1775

6B

lack

Wal

nut

Jugl

ans

nigr

a20

GF

G6.

5

1775

7R

ed O

akQ

uerc

us r

ubra

7P

PF

1.5

Rec

omm

ende

d re

mov

al

1775

8H

oney

Loc

ust

Gle

dits

ia tr

iaca

ntho

s9

GG

G4.

5

1775

9S

ilver

Map

leA

cer

sacc

harin

um16

PG

G4

1776

0W

hite

Ash

Fra

xinu

s am

eric

ana

20G

GG

6.5

Appendix 1 Page 10OAKVILLE HARBOURWest Shore Master Plan

Page 89: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Oak

ville

Har

bour

Tre

e In

vent

ory,

Oak

ville

, Ont

ario

, 200

8

Urb

an F

ores

t Inn

ovat

ions

Inc

., 14

/07/

08

13

1779

9W

hite

Ash

Fra

xinu

s am

eric

ana

24G

GG

8

1780

0W

hite

Ash

Fra

xinu

s am

eric

ana

21G

GG

7

1780

1W

hite

Ash

Fra

xinu

s am

eric

ana

21G

GG

7

1780

2C

arol

ina

Pop

lar

Pop

ulus

x c

anad

ensi

s18

PF

F3.

5

1780

3B

lack

Wal

nut

Jugl

ans

nigr

a13

GG

G4.

5

1780

4W

hite

Ash

Fra

xinu

s am

eric

ana

17G

GG

4

1780

5M

anito

ba M

aple

Ace

r ne

gund

o29

,30

FP

G12

1780

6B

lack

Wal

nut

Jugl

ans

nigr

a28

GG

G8

1780

7W

hite

Ash

Fra

xinu

s am

eric

ana

13G

GG

4

1780

8W

hite

Ash

Fra

xinu

s am

eric

ana

10G

GG

3.5

1780

9M

anito

ba M

aple

Ace

r ne

gund

o34

,24,

30G

FG

10

1781

0M

anito

ba M

aple

Ace

r ne

gund

o14

,24

GG

G8

1781

1B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia32

,27

GF

G8

1781

2M

anito

ba M

aple

Ace

r ne

gund

o12

PP

P3

1781

3M

anito

ba M

aple

Ace

r ne

gund

o10

GG

G2

1781

4B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia42

GG

G8

1781

5B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia32

GF

G6

1781

6B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia14

PP

P2

Dea

dD

ead,

rem

ove

1781

7B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia26

,26

GP

G7

Cab

le r

ecom

men

ded

1781

8B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia34

GG

G7

1781

9M

anito

ba M

aple

Ace

r ne

gund

o15

,10

GG

G4.

5

1782

0M

anito

ba M

aple

Ace

r ne

gund

o16

,14

GG

G8

1782

1B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia40

GF

G9

1782

2B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia32

GG

G7

Low

er

smal

l dea

dwoo

d ov

er p

ath

1782

3B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia36

GG

G6

1782

4B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia19

GG

P3.

5R

ecom

men

ded

rem

oval

1782

5B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia23

GG

G6

1782

6N

orw

ay M

aple

Ace

r pl

atan

oide

s14

GG

G4

1782

7B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia30

GG

G5.

5

1782

8B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia25

GG

G5

Low

er

med

ium

siz

ed d

eadw

ood

over

pat

h

1782

9B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia21

GG

G4

1783

0B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia26

GG

G5

1783

1B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia29

GG

G5.

5

1783

2M

anito

ba M

aple

Ace

r ne

gund

o18

FG

G5

1783

3B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia22

GF

F4

1783

4M

anito

ba M

aple

Ace

r ne

gund

o15

GG

G4

1783

5B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia26

GG

G5

Low

er

med

ium

siz

ed d

eadw

ood

over

pat

h

Appendix 1 Page 11OAKVILLE HARBOURWest Shore Master Plan

Page 90: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Oak

ville

Har

bour

Tre

e In

vent

ory,

Oak

ville

, Ont

ario

, 200

8

Urb

an F

ores

t Inn

ovat

ions

Inc

., 14

/07/

08

14

1783

6B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia28

GG

G6

Low

er

med

ium

siz

ed d

eadw

ood

over

pat

h

1783

7B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia32

,24

GP

G6

Cab

le r

ecom

men

ded

1783

8M

anito

ba M

aple

Ace

r ne

gund

o13

GF

G3

1783

9B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia19

GG

G4

1784

0B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia29

GG

G6

1784

1B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia26

GG

G5

1784

2B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia23

,25

GG

G6

1784

3B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia29

GG

G5

1784

4B

lack

Wal

nut

Jugl

ans

nigr

a19

GF

G6

1784

5B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia24

GF

G6

1784

6B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia15

GG

P4

80%

dea

d -

Rec

omm

ende

d re

mov

al

1784

7B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia29

FP

F5

1784

8B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia26

FP

G6

Fru

iting

bod

ies

ate

base

-in

clud

ed a

t 5f

t.

1784

9M

anito

ba M

aple

Ace

r ne

gund

o14

FF

G7

1785

0M

anito

ba M

aple

Ace

r ne

gund

o17

GF

G7

1785

1M

anito

ba M

aple

Ace

r ne

gund

o10

,14

GP

F7

1785

2M

anito

ba M

aple

Ace

r ne

gund

o24

,10

GF

F8

1785

3B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia17

GF

G3.

5

1785

4M

anito

ba M

aple

Ace

r ne

gund

o10

,8G

GG

4.5

1785

5M

anito

ba M

aple

Ace

r ne

gund

o10

GG

G3.

5

1785

6B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia31

GF

G6

Med

ium

size

d de

adw

ood

-in

clud

ed a

t 6f

t.Lo

we

rm

ediu

m s

ized

dea

dwoo

d ov

er p

ath

1785

7B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia18

GF

F5

Low

er

med

ium

siz

ed d

eadw

ood

over

pat

h

1785

8B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia28

,13

GG

G6

Med

ium

size

d de

adw

ood

Low

er

med

ium

siz

ed to

larg

e de

adw

ood

ove

r pa

th

1785

9B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia19

GG

G4.

5Lo

we

rsm

all s

ized

dea

dwoo

d ov

er p

ath

1786

0B

lack

Wal

nut

Jugl

ans

nigr

a29

GG

G7

1786

1B

lack

Wal

nut

Jugl

ans

nigr

a47

GG

G10

Med

ium

size

d de

adw

ood

1786

2B

lack

Wal

nut

Jugl

ans

nigr

a20

GG

G4

1786

3B

lack

Wal

nut

Jugl

ans

nigr

a37

GG

G10

Sm

all s

ized

dea

dwoo

d

1786

4B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia30

GF

G4.

5

1786

5B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia43

GF

G6.

5

1786

6S

iber

ian

Elm

Ulm

us p

umila

21G

GG

6

1786

7M

anito

ba M

aple

Ace

r ne

gund

o11

,11,

12G

PG

5.5

1786

8B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia23

GF

F3

1786

9M

anito

ba M

aple

Ace

r ne

gund

o12

,12

GP

G6

Sm

all s

ized

dea

dwoo

d

1787

0B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia36

GG

G8

Med

ium

size

d de

adw

ood

Low

er

med

ium

siz

ed d

eadw

ood

over

pat

h

1787

1B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia13

GP

P2.

580

% d

ead

-re

com

men

ded

rem

oval

1787

2B

lack

Wal

nut

Jugl

ans

nigr

a13

GG

G3.

5

Appendix 1 Page 12OAKVILLE HARBOURWest Shore Master Plan

Page 91: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Oak

ville

Har

bour

Tre

e In

vent

ory,

Oak

ville

, Ont

ario

, 200

8

Urb

an F

ores

t Inn

ovat

ions

Inc

., 14

/07/

08

15

1787

3B

lack

Wal

nut

Jugl

ans

nigr

a15

GG

G3.

5

1787

4B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia31

FP

F6

Rec

omm

ende

d re

mov

al

1787

5B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia36

GF

F9

Mai

n st

em d

ead

1787

6B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia16

FP

G6

1787

7B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia34

FF

G10

Wou

nd o

n tr

unk

-co

uld

be r

emov

edS

how

ing

die-

back

, cro

wn

is v

ery

thin

,S/E

ste

m is

de

ad,

rem

ove

tree

1787

8B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia42

,22

GF

G11

1787

9W

hite

Mul

berr

yM

orus

alb

a37

,27,

37G

FG

19M

ediu

msi

zed

dead

woo

dC

row

n is

ver

y th

in

1788

0R

ed P

ine

Pin

us r

esin

osa

10G

GG

3T

oppe

d at

one

poi

nt

1788

1R

ed P

ine

Pin

us r

esin

osa

16G

GG

4

1788

2B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia70

GF

G14

Med

ium

size

d de

adw

ood

-ca

ble

reco

mm

ende

dM

ediu

m to

larg

e si

zed

dead

woo

d ov

er p

ark

road

1788

3R

ed O

akQ

uerc

us r

ubra

38G

GG

10M

ediu

m s

ized

dea

dwoo

d ov

er p

ark

road

1788

4B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia50

GF

G11

Incl

uded

-ca

ble

reco

mm

ende

d -

cont

act

with

#17

883

1788

5B

lack

Wal

nut

Jugl

ans

nigr

a19

GF

G4.

5

1788

6B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia29

FF

G4.

5

1788

7B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia32

,30

GP

G6

Incl

uded

-ca

ble

reco

mm

ende

d

1788

8B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia46

GG

G10

1788

9B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia47

GG

G13

Med

ium

size

d de

adw

ood

Med

ium

siz

ed d

eadw

ood

over

par

k ro

ad

1789

0P

urpl

e S

andc

herr

yP

runu

s ci

sten

a10

GF

G2

1789

1R

ed M

aple

Ace

r ru

brum

26F

FG

7C

able

rec

omm

ende

d

1789

2R

ussi

an O

live

Ela

eagn

us a

ngus

tifol

ia

26,2

4F

FG

9S

how

ing

die-

back

, cro

wn

is t

hin,

dec

ayin

sou

th

stem

, re

mov

e tr

ee

1789

3B

lack

Wal

nut

Jugl

ans

nigr

a53

GG

G11

1789

4R

ussi

an O

live

Ela

eagn

us a

ngus

tifol

ia

44G

FG

10

1789

5N

orw

ay M

aple

Ace

r pl

atan

oide

s31

GG

G10

1789

6A

ustr

ian

Pin

eP

inus

nig

ra41

GG

G7

Dip

lodi

a

1789

7A

ustr

ian

Pin

eP

inus

nig

ra42

GG

G7

Dip

lodi

a

1789

8A

ustr

ian

Pin

eP

inus

nig

ra40

GG

G7

Dip

lodi

a

1789

9N

orw

ay M

aple

Ace

r pl

atan

oide

s13

GG

G3

2590

0R

ed M

aple

Ace

r ru

brum

20G

GG

6

2590

1B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia49

,50

GG

G12

Med

ium

siz

ed d

eadw

ood

2590

2B

lue

Spr

uce

Pic

ea p

unge

ns33

GG

G6

2590

3S

ilver

Map

leA

cer

sacc

harin

um10

GG

G2.

5

2590

4A

mer

ican

Bee

chF

agus

gra

ndifo

lia39

GG

G8

2590

5W

hite

Will

owS

alix

alb

a41

,36

GF

G9

2590

5aW

hite

Will

owS

alix

alb

a33

,27

GF

G9

2590

6B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia27

GF

G4.

5

Appendix 1 Page 13OAKVILLE HARBOURWest Shore Master Plan

Page 92: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Oak

ville

Har

bour

Tre

e In

vent

ory,

Oak

ville

, Ont

ario

, 200

8

Urb

an F

ores

t Inn

ovat

ions

Inc

., 14

/07/

08

16

2590

7M

anito

ba M

aple

Ace

r ne

gund

o26

GG

G6

2590

8B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia49

GG

G7

2590

9B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia43

GG

G7

Med

ium

size

d de

adw

ood

2591

0M

anito

ba M

aple

Ace

r ne

gund

o22

,30,

21F

GG

11

2591

1M

anito

ba M

aple

Ace

r ne

gund

o35

FP

G5

2591

2M

anito

ba M

aple

Ace

r ne

gund

o24

FG

G4.

5

2591

3M

anito

ba M

aple

Ace

r ne

gund

o24

FP

G6

2591

4M

anito

ba M

aple

Ace

r ne

gund

o17

FG

G3

2591

5B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia29

,37

GF

G8

Tre

e in

con

tact

with

#91

6 cr

own

2591

6B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia34

GF

G6

2591

7B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia33

GF

G5

2591

8B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia27

FF

G4

Ope

n de

cay

at 2

ft.

2591

9B

lack

Wal

nut

Jugl

ans

nigr

a22

GF

G6

Tre

e ru

bbin

g #2

5918

tru

nk

2592

0B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia10

GG

G3

2592

1B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia30

GP

G6

Gro

win

g ou

t of

slo

pe -

Med

ium

size

d de

adw

ood

2592

2B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia42

GF

G7.

5G

row

ing

out

of s

lope

-S

mal

l siz

ed

dead

woo

d

2592

3M

anito

ba M

aple

Ace

r ne

gund

o28

,21

GP

F6.

5In

clud

ed a

t 2.

5ft.

2592

4M

anito

ba M

aple

Ace

r ne

gund

o18

GG

F4.

5

2592

5B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia22

GG

G4

2592

6C

arol

ina

Pop

lar

Pop

ulus

x c

anad

ensi

s12

PP

P1.

5D

ead

2592

7W

hite

Birc

hB

etul

a pa

pyrif

era

8,7

GF

G3

2592

8B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia20

GF

G4.

5In

clud

ed a

t 2f

t.

2592

9B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia15

,15

GF

G6.

5

2593

0B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia19

GG

G4.

5

2593

1B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia26

GG

G6

2593

2S

cots

Pin

eP

inus

syl

vest

ris23

GF

G4.

5

2593

3B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia17

GG

G3.

5

2593

4B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia19

GP

G5

Incl

uded

at

5ft -

coul

d re

mov

e tr

ee

2593

5B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia15

GG

G4.

5

2593

6W

hite

Birc

hB

etul

a pa

pyrif

era

13,1

6G

FG

5

2593

7W

hite

Birc

hB

etul

a pa

pyrif

era

6,15

,20

GF

G7

2593

8W

hite

Birc

hB

etul

a pa

pyrif

era

10,1

2,9

GF

G8

2593

9S

iber

ian

Elm

Ulm

us p

umila

22,2

3G

FG

5.5

2594

0A

mur

Map

leA

cer

ginn

ala

11@

<10

GF

F9.

5

2594

1W

hite

Birc

hB

etul

a pa

pyrif

era

10,8

GP

G3

2594

2W

hite

Birc

hB

etul

a pa

pyrif

era

11G

FG

4

Appendix 1 Page 14OAKVILLE HARBOURWest Shore Master Plan

Page 93: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Oak

ville

Har

bour

Tre

e In

vent

ory,

Oak

ville

, Ont

ario

, 200

8

Urb

an F

ores

t Inn

ovat

ions

Inc

., 14

/07/

08

18

2598

0S

ilver

Map

leA

cer

sacc

harin

um16

,10,

8P

PG

3

2598

1C

arol

ina

Pop

lar

Pop

ulus

x c

anad

ensi

s18

GG

G6

2598

2G

reen

Ash

Fra

xinu

s pe

nnsy

lvan

ica

14F

GG

4.5

2598

3W

hite

Will

owS

alix

alb

a22

GF

G4

2598

4M

anito

ba M

aple

Ace

r ne

gund

o21

GF

G6

2598

5W

hite

Mul

berr

yM

orus

alb

a20

GF

G3.

5

2598

6W

hite

Will

owS

alix

alb

a42

,30

GF

G11

2598

7N

orw

ay M

aple

Ace

r pl

atan

oide

s16

GG

G5

2598

8W

hite

Will

owS

alix

alb

a26

,14,

12G

FG

6.5

2598

9S

iber

ian

Elm

Ulm

us p

umila

18G

FG

3

2599

0W

hite

Will

owS

alix

alb

a24

,20

GG

G6

2599

1S

ilver

Map

leA

cer

sacc

harin

um17

FG

G4

2599

2W

hite

Will

owS

alix

alb

a18

GF

P2

2599

3W

hite

Will

owS

alix

alb

a22

GG

G3

2599

4C

arol

ina

Pop

lar

Pop

ulus

x c

anad

ensi

s11

GG

G1.

5

2599

5W

eepi

ng W

illow

Sal

ix a

lba

52G

FG

7

2599

6S

ilver

Map

leA

cer

sacc

harin

um6@

<36

GF

G12

2599

7P

ussy

Will

owS

alix

dis

colo

r18

PG

F2

2599

8P

urpl

e S

andc

herr

yP

runu

s ci

sten

a14

GF

G3

2599

9P

urpl

e S

andc

herr

yP

runu

s ci

sten

a10

,12

GF

G3

2600

0W

hite

Will

owS

alix

alb

a26

,21,

16G

FG

10

2600

1B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia39

,20

GF

G6.

5

2600

2W

hite

Will

owS

alix

alb

a12

3G

FG

16

2600

3S

ilver

Map

leA

cer

sacc

harin

um14

GF

G3.

5

2600

4A

pple

sp.

Mal

us s

p.21

GG

G7

2600

5S

ilver

Map

leA

cer

sacc

harin

um33

GG

G6.

5

2600

6S

ilver

Map

leA

cer

sacc

harin

um26

GG

G6

2600

7S

ilver

Map

leA

cer

sacc

harin

um30

GG

G6

2600

8S

ilver

Map

leA

cer

sacc

harin

um28

GG

G5.

5

2601

9A

pple

sp.

Mal

us s

p.14

GG

G2.

5

2602

0W

hite

Mul

berr

yM

orus

alb

a18

GG

G5.

5

2602

1R

ed O

akQ

uerc

us r

ubra

15G

GG

5

2602

2M

anito

ba M

aple

Ace

r ne

gund

o17

GG

G5.

5

2602

3R

ed O

akQ

uerc

us r

ubra

127

GF

F18

2602

4R

ed O

akQ

uerc

us r

ubra

20G

GG

15

2602

5R

ed O

akQ

uerc

us r

ubra

90G

FG

16

Appendix 1 Page 15OAKVILLE HARBOURWest Shore Master Plan

Page 94: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Oak

ville

Har

bour

Tre

e In

vent

ory,

Oak

ville

, Ont

ario

, 200

8

Urb

an F

ores

t Inn

ovat

ions

Inc

., 14

/07/

08

17

2594

3W

hite

Birc

hB

etul

a pa

pyrif

era

11,8

GF

G6

2594

4W

hite

Birc

hB

etul

a pa

pyrif

era

11,1

1G

FG

6

2594

5R

ed O

akQ

uerc

us r

ubra

30,3

4G

FG

7

2594

6B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia51

GG

G10

2594

7B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia47

GG

G8

2594

8B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia46

GG

G9

2594

9B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia72

GG

G12

2595

0B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia70

GG

G11

2595

1R

ed O

akQ

uerc

us r

ubra

66,4

0G

FG

162

Cab

les

Rec

omm

ende

d

2595

2B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia64

,56

FF

G14

Cab

le a

nd b

race

foun

d in

tree

2595

3B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia52

GG

G11

2595

4A

ustr

ian

Pin

eP

inus

nig

ra60

GF

G15

Slig

ht D

iplo

dia

2595

5B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia48

FF

G6.

5C

able

rec

omm

ende

d

2595

6R

ed O

akQ

uerc

us r

ubra

56G

FG

11M

ediu

mS

ized

dea

dwoo

d

2595

7R

ed O

akQ

uerc

us r

ubra

89G

GG

18

2595

8G

reen

Ash

Fra

xinu

s pe

nnsy

lvan

ica

47G

GG

6.5

2595

9G

reen

Ash

Fra

xinu

s pe

nnsy

lvan

ica

32G

GG

5.5

2596

0B

lack

Wal

nut

Jugl

ans

nigr

a22

FG

G5

2596

1B

lack

Wal

nut

Jugl

ans

nigr

a54

GG

G13

2596

2R

ed O

akQ

uerc

us r

ubra

10G

GG

3

2596

3M

anito

ba M

aple

Ace

r ne

gund

o12

GF

G3.

5

2596

4B

lack

Wal

nut

Jugl

ans

nigr

a62

GG

G13

2596

5E

lm s

p.U

lmus

sp.

22P

FF

4

2596

6S

umac

hT

oxic

oden

dron

10G

GF

2

2596

7B

lack

Wal

nut

Jugl

ans

nigr

a62

GG

G13

2596

8M

anito

ba M

aple

Ace

r ne

gund

o18

FP

F5

2596

9C

arol

ina

Pop

lar

Pop

ulus

x c

anad

ensi

s13

GP

F3

2597

0B

lack

Wal

nut

Jugl

ans

nigr

a18

GF

G4.

5

2597

1R

ed M

aple

Ace

r ru

brum

18P

PG

3.5

Rec

omm

ende

d re

mov

al

2597

2B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia28

GG

G8

2597

3W

eepi

ng W

illow

Sal

ix a

lba

26F

GG

5

2597

4H

oney

Loc

ust

Gle

dits

ia tr

iaca

ntho

s16

,11,

14P

PP

5R

ecom

men

ded

rem

oval

2597

5W

hite

Will

owS

alix

alb

a26

,20

FP

G8

2597

6W

hite

Will

owS

alix

alb

a28

FG

G9

2597

7W

hite

Ash

Fra

xinu

s am

eric

ana

19G

GG

4.5

2597

8W

hite

Ash

Fra

xinu

s am

eric

ana

24G

GG

5.5

2597

9W

hite

Ash

Fra

xinu

s am

eric

ana

10P

GF

1.5

Appendix 1 Page 16OAKVILLE HARBOURWest Shore Master Plan

Page 95: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Oak

ville

Har

bour

Tre

e In

vent

ory,

Oak

ville

, Ont

ario

, 200

8

Urb

an F

ores

t Inn

ovat

ions

Inc

., 14

/07/

08

18

2598

0S

ilver

Map

leA

cer

sacc

harin

um16

,10,

8P

PG

3

2598

1C

arol

ina

Pop

lar

Pop

ulus

x c

anad

ensi

s18

GG

G6

2598

2G

reen

Ash

Fra

xinu

s pe

nnsy

lvan

ica

14F

GG

4.5

2598

3W

hite

Will

owS

alix

alb

a22

GF

G4

2598

4M

anito

ba M

aple

Ace

r ne

gund

o21

GF

G6

2598

5W

hite

Mul

berr

yM

orus

alb

a20

GF

G3.

5

2598

6W

hite

Will

owS

alix

alb

a42

,30

GF

G11

2598

7N

orw

ay M

aple

Ace

r pl

atan

oide

s16

GG

G5

2598

8W

hite

Will

owS

alix

alb

a26

,14,

12G

FG

6.5

2598

9S

iber

ian

Elm

Ulm

us p

umila

18G

FG

3

2599

0W

hite

Will

owS

alix

alb

a24

,20

GG

G6

2599

1S

ilver

Map

leA

cer

sacc

harin

um17

FG

G4

2599

2W

hite

Will

owS

alix

alb

a18

GF

P2

2599

3W

hite

Will

owS

alix

alb

a22

GG

G3

2599

4C

arol

ina

Pop

lar

Pop

ulus

x c

anad

ensi

s11

GG

G1.

5

2599

5W

eepi

ng W

illow

Sal

ix a

lba

52G

FG

7

2599

6S

ilver

Map

leA

cer

sacc

harin

um6@

<36

GF

G12

2599

7P

ussy

Will

owS

alix

dis

colo

r18

PG

F2

2599

8P

urpl

e S

andc

herr

yP

runu

s ci

sten

a14

GF

G3

2599

9P

urpl

e S

andc

herr

yP

runu

s ci

sten

a10

,12

GF

G3

2600

0W

hite

Will

owS

alix

alb

a26

,21,

16G

FG

10

2600

1B

lack

Loc

ust

Rob

inia

pse

udo-

acac

ia39

,20

GF

G6.

5

2600

2W

hite

Will

owS

alix

alb

a12

3G

FG

16

2600

3S

ilver

Map

leA

cer

sacc

harin

um14

GF

G3.

5

2600

4A

pple

sp.

Mal

us s

p.21

GG

G7

2600

5S

ilver

Map

leA

cer

sacc

harin

um33

GG

G6.

5

2600

6S

ilver

Map

leA

cer

sacc

harin

um26

GG

G6

2600

7S

ilver

Map

leA

cer

sacc

harin

um30

GG

G6

2600

8S

ilver

Map

leA

cer

sacc

harin

um28

GG

G5.

5

2601

9A

pple

sp.

Mal

us s

p.14

GG

G2.

5

2602

0W

hite

Mul

berr

yM

orus

alb

a18

GG

G5.

5

2602

1R

ed O

akQ

uerc

us r

ubra

15G

GG

5

2602

2M

anito

ba M

aple

Ace

r ne

gund

o17

GG

G5.

5

2602

3R

ed O

akQ

uerc

us r

ubra

127

GF

F18

2602

4R

ed O

akQ

uerc

us r

ubra

20G

GG

15

2602

5R

ed O

akQ

uerc

us r

ubra

90G

FG

16

Appendix 1 Page 17OAKVILLE HARBOURWest Shore Master Plan

Page 96: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Oak

ville

Har

bour

Tre

e In

vent

ory,

Oak

ville

, Ont

ario

, 200

8

Urb

an F

ores

t Inn

ovat

ions

Inc

., 14

/07/

08

19

2602

6W

hite

Oak

Que

rcus

alb

a10

6G

GG

16M

ediu

m s

ized

dea

dwoo

d in

cro

wn

2602

7R

ed O

akQ

uerc

us r

ubra

106

GF

F14

2602

8R

ed O

akQ

uerc

us r

ubra

14G

PG

5W

ound

s on

trun

k an

d in

cro

wn

-re

com

men

ded

rem

oval

2602

9R

ed O

akQ

uerc

us r

ubra

32G

GG

7

2603

0R

ed O

akQ

uerc

us r

ubra

24G

GG

6

2603

1R

ed O

akQ

uerc

us r

ubra

24G

GG

5.5

2603

2R

ed O

akQ

uerc

us r

ubra

20G

FG

4.5

2603

3S

ugar

Map

leA

cer

sacc

haru

m

127

GG

G20

Dec

ay in

cen

ter

stem

, 1 c

able

in t

ree,

rec

omm

end

Pic

us a

sses

smen

t

2603

4B

lue

Spr

uce

Pic

ea p

unge

ns42

GF

G5

2603

5B

lue

Spr

uce

Pic

ea p

unge

ns44

GF

G5

2603

6B

lue

Spr

uce

Pic

ea p

unge

ns62

GF

G5

2603

7N

orw

ay S

pruc

eP

icea

abi

es22

GG

G5

2603

8R

ed M

aple

Ace

r ru

brum

74G

FF

8D

ie-b

ack

on n

orth

ste

m, t

ree

shou

ld b

e m

onito

red,

co

uld

rem

ove

stem

2603

9S

ugar

Map

leA

cer

sacc

haru

m

37F

GG

8G

row

ing

out

of f

ence

-fa

ir

2604

0S

ugar

Map

leA

cer

sacc

haru

m

45F

GG

8G

row

ing

out

of f

ence

-sl

ight

ly w

orse

than

#2

6040

2604

1S

ugar

Map

leA

cer

sacc

haru

m

38G

GG

7

2604

2R

ed O

akQ

uerc

us r

ubra

33G

GG

8

2604

3M

anito

ba M

aple

Ace

r ne

gund

o10

GF

G2

2604

4M

anito

ba M

aple

Ace

r ne

gund

o12

GF

G2.

5

2604

5W

hite

Mul

berr

yM

orus

alb

a58

GG

G8

2604

6R

ed O

akQ

uerc

us r

ubra

26G

GG

6

2604

7Iv

ory

Silk

Lila

cS

yrin

ga r

etic

ulat

a17

GG

G2.

5

2604

8Iv

ory

Silk

Lila

cS

yrin

ga r

etic

ulat

a13

GG

G2.

5

2604

9Iv

ory

Silk

Lila

cS

yrin

ga r

etic

ulat

a16

GG

G2.

5

Appendix 1 Page 18OAKVILLE HARBOURWest Shore Master Plan

Page 97: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Oakville Harbour Tree Inventory, Oakville, Ontario, 2008 20

Limitations of Assessment

It is my policy to attach the following clause regarding limitations. I do this to ensure that the client is aware of what is technically and professionally realistic in retaining trees.

The assessment of the trees presented in this report has been made using accepted arboricultural techniques. These include a visual examination of all the above ground parts of the tree for structural defects, scars, external indications of decay such as fungal fruiting bodies, evidence of attack by insects, discoloured foliage, the condition of any visible root structures, the degree and direction of lean (if any), the general condition of the trees and the surrounding site, and the proximity of property and people. Except where specifically noted, the trees were not cored, probed or climbed and there was no detailed inspection of the root crowns involving excavations.

Notwithstanding the recommendations and conclusions made in this report, it must be recognized that trees are living organisms, and their health and vigour constantly change over time. They are not immune to changes in site conditions or seasonal variations in the weather conditions.

While reasonable efforts have been made to ensure that the subject trees are healthy, no guarantees are offered, or implied, that these trees or any of their parts will remain standing. It is both professionally and practically impossible to predict with absolute certainty the behaviour of any single tree or its component parts under all circumstances. Inevitably, a standing tree will always pose some level of risk. Most trees have the potential for failure under adverse weather conditions, and the risk can only be eliminated if the tree is removed.

Although every effort has been made to ensure that this assessment is reasonably accurate, the trees should be re-assessed periodically. The assessment presented in this report is valid at the time of inspection.

Respectfully submitted by:

Philip van Wassenaer, B. Sc., MFCConsulting Arborist, ASCAISA Certified Arborist, ON - 0361ATel: (905) 274-1022Fax: (905) 274 2170e-mail: [email protected]

Appendix 1 Page 19OAKVILLE HARBOURWest Shore Master Plan

Page 98: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 99: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

LAK

ES

HO

RE

RO

AD

L A

K E

O

N T

A R

I O

1 6 M I L E C R E E K

Forsythe St

And

erso

n S

t

Bur

net S

t

Wal

ker S

t

Wilson St

Chisholm St

Oak

ville

Har

bour

Wat

er T

reat

men

t Pla

nt

0.20

ØD

EC

.

0.20

ØD

EC

.

0.40

ØD

EC

.

GA

RD

EN

GA

RD

EN

0.40

ØD

EC

.

0.50

ØD

EC

.

0.50

ØD

EC

.0.10

ØM

AP

LE

0.10

ØD

EC

.

0.60

ØD

EC

.

0.60

ØD

EC

.

0.30

ØD

EC

.

0.30

ØM

AP

LE

0.50

ØP

INE

0.50

ØP

INE

0.60

ØP

INE

0.60

ØP

INE

0.60

ØP

INE

0.15

ØD

EC

.

0.45

ØP

INE

0.45

ØP

INE

0.65

ØP

INE

0.70

ØP

INE

0.60

ØP

INE

0.70

ØD

EC

.

0.20

ØD

EC

.

0.35

ØD

EC

.

0.20

ØD

EC

.

0.25

ØD

EC

.

0.40

ØD

EC

.

0.40

ØD

EC

.

0.30

ØD

EC

.

0.20

ØD

EC

.0.

20Ø

DE

C.

0.20

ØD

EC

.

0.20

ØD

EC

.

0.40

ØD

EC

.

0.45

ØD

EC

.

0.35

ØD

EC

.

0.15

ØD

EC

.

0.15

ØD

EC

.

0.15

ØD

EC

.

0.15

ØD

EC

.

0.10

ØD

EC

.0.

20Ø

DE

C.

0.50

ØM

AP

LE

0.50

ØD

EC

.0.

60Ø

DE

C.

0.80

ØD

EC

.

0.75

ØD

EC

.0.60

ØD

EC

.0.70

ØD

EC

.

0.45

ØP

INE

BIR

CH

ES

x4

0.25

ØP

INE

0.35

ØD

EC

.

0.50

ØD

EC

.

0.45

ØM

AP

LE0.

45Ø

MA

PLE

0.45

ØM

AP

LE0.

35Ø

MA

PLE

0.05

ØD

EC

.

0.08

ØM

AP

LE

0.45

ØD

EC

.0.

40Ø

DE

C.

0.40

ØD

EC

.

0.30

ØD

EC

.

0.30

ØD

EC

.

0.30

ØD

EC

.

0.30

ØD

EC

.

0.30

ØD

EC

.

0.70

ØD

EC

.

0.70

ØD

EC

.0.

25Ø

DE

C.

0.25

ØD

EC

.

0.95

ØD

EC

. 0.60

ØD

EC

.0.

45Ø

DE

C.

0.30

ØD

EC

.

0.70

ØD

EC

.

0.20

ØD

EC

.

0.30

ØD

EC

.

0.80

ØD

EC

.x3

0.50

ØD

EC

.

0.50

ØD

EC

. 0.50

ØD

EC

.

0.30

ØD

EC

.

0.50

ØD

EC

.

0.35

ØD

EC

.0.

80Ø

DE

C.

0.50

ØD

EC

.

0.10

ØD

EC

.0.

10Ø

DE

C.

RO

W O

F 0.

20Ø

-0.3

0Ø C

ED

AR

S

F O

R E

S T

E D

A R

E A

0.95

ØM

AP

LE

0.40

ØP

INE

0.30

ØP

INE

0.55

ØD

EC

.

0.60

ØM

AP

LE

0.60

ØM

AP

LE0.

30Ø

MA

PLE

0.25

ØB

IRC

H

0.35

ØP

INE

0.90

ØD

EC

.0.

90Ø

DE

C.

0.40

ØP

INE

0.60

ØB

IRC

H

0.25

ØB

IRC

HE

S

1.0Ø

DE

C.

0.50

ØD

EC

.

0.80

ØD

EC

.

0.85

ØD

EC

.0.

80Ø

DE

C.

1.20

ØD

EC

.

0.25

ØD

EC

.

0.20

ØP

INE

x2

0.20

ØP

INE

0.25

ØC

ED

AR

x4

0.15

ØD

EC

.

0.35

ØD

EC

.

0.40

ØD

EC

.

0.50

ØD

EC

.

0.75

ØD

EC

.

0.50

ØD

EC

.

0.50

ØD

EC

.

0.65

ØD

EC

.

0.40

ØB

IRC

H

0.25

ØC

ED

AR

0.40

ØP

INE

0.55

ØM

AP

LE

0.90

ØO

AK

0.90

ØO

AK

x2

0.50

ØD

EC

.

0.30

ØD

EC

.

0.35

ØD

EC

.

0.85

ØD

EC

.

1.2Ø

DE

C.

0.45

ØD

EC

.x20.

40Ø

DE

C.

0.50

ØD

EC

.

0.60

ØD

EC

.x2

0.20

ØD

EC

.

0.35

ØD

EC

.

0.30

ØD

EC

.

0.12

ØP

INE 0.

12Ø

DE

C.x

3

1.1Ø

DE

C.

1.0Ø

DE

C.

0.85

ØD

EC

.

0.55

ØM

AP

LE

0.65

ØM

AP

LE

0.30

ØD

EC

.0.55

ØP

INE0.

60Ø

PIN

E0.40

ØD

EC

.

0.50

ØD

EC

.

BU

SH

AR

EA

0.60

ØD

EC

.

0.50

ØD

EC

.

0.60

ØD

EC

.

0.30

ØD

EC

.

0.45

ØD

EC

.0.

75Ø

DE

C.x

4

0.25

ØD

EC

.x3

0.45

ØD

EC

.

0.20

ØD

EC

.x3

0.15

ØD

EC

.x2

0.95

ØD

EC

.

1.0Ø

DE

C.

0.50

ØD

EC

.

0.60

ØD

EC

.

0.50

ØD

EC

.

0.30

ØD

EC

.0.35

ØD

EC

.0.

50Ø

DE

C.

0.55

ØD

EC

.

0.50

ØD

EC

.

0.55

ØM

AP

LE0.

55Ø

MA

PLE

0.2Ø

SPR

UC

E 0.50

ØP

INE

0.45

ØD

EC

.0.

40Ø

DE

C.

0.45

ØD

EC

.

0.45

ØP

INE

0.45

ØP

INE

0.85

ØD

EC

.

0.30

ØD

EC

.0.

12Ø

DE

C.

0.60

ØD

EC

.0.45

ØD

EC

.

AP

PR

OV

ED

SC

ALE

:

DA

TE

CH

EC

KE

D

DR

AW

N

DR

AW

ING

NO

.P

RO

JEC

T N

O.

PR

OJE

CT

JG JG 1:50

0m

LOC

ATI

ON

Oak

ville

, Ont

ario

Janu

ary

2008

Oak

ville

Har

bour

Maste

r P

lan

West

Sh

ore

JOH

N G

EOR

GE

ASS

OC

IATE

S IN

C32

7 P

ine

Cov

e R

oad

Bur

lingt

on, O

N, L

7N 1

W4

905-

632-

3473

FA

X 9

05-6

32-2

407

CO

NS

ULT

AN

T

Land

scap

e A

rchi

tect

sV

isio

nsca

pes

Urb

an F

ores

try

Urb

an F

ores

t Inn

ovat

ions

Inc.

CLI

EN

T Tow

n O

f Oak

ville

1225

Tra

falg

ar R

oad

OA

KV

ILLE

ON

L6J

5A

6

Park

and

Pla

nnin

gD

evel

opm

ent

NO

RTH

TAICOSSA OI RATNO

STCE

TIHC

RA

EPACSDNALFO

NOI

ME

MB

ER

JOH

N G

EO

RG

E

05m

10m

20m

50m

Met

ric B

ar S

cale

L2

Tree

Inve

ntor

y P

lan

Page 100: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 101: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 102: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 103: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

B a i r d & A s s o c i a t e s

6 2 7 L yo n s L a n e , S u i t e 2 0 0

Oakville, Ontario Canada L6J 5Z7

T . 9 0 5 8 4 5 5 3 8 5

F . 9 0 5 8 4 5 0 6 9 8Baird

o c e a n s

e n g i n e e r i n g

l a k e s

d e s i g n

r i v e r s

s c i e n c e

w a t e r s h e d s

c o n s t r u c t i o n

21 May 2008

John George Associates Inc. Mr. John George 327 Pine Cove Burlington, Ontario, L7N 1W4

Re: Oakville Harbour – Coastal Processes

Dear Mr. George:

This letter report provides preliminary comment on the potential impacts on coastal processes, of proposed changes to the shoreline immediately west of the 16 Mile Creek in Oakville. These changes are proposed in the master plan for Oakville Harbour, under development by John George Associates Inc. The preliminary concept is to extend the shoreline lakeward to meet the existing west pier as shown in Figure 1. Our comments are based on a site visit undertaken on 9 April 2008 and our understanding of coastal processes in this region.

This section presents a description of the shoreline and the proposed changes, followed by a discussion of potential impacts of the changes on coastal processes.

Shoreline Description and Type

The project site is located on the north shore of Lake Ontario, west of the 16 Mile Creek in Oakville.There are two concrete-capped steel sheet pile piers at the mouth of the 16 Mile Creek. Figure 2 shows an oblique aerial view of the site. The harbour is heavily used by recreational boats, and includes docking facilities for sailboats. A check water was constructed on the inner side of the west pier in the 1990’s, to reduce wave activity inside the harbour. There is a shingle beach on the east side of the harbour, retained by the east pier and an armourstone groyne. The beach was also constructed in the 1990’s. Historical photos indicate that this shoreline was historically a shingle beach. A sediment plume from the 16 Mile Creek is visible in the photo. Plumes occur with every significant rainfall event.

Till bluffs and banks typically dominate the western Lake Ontario shoreline, except at river mouths where the shoreline dips down. The shoreline immediately west of the harbour appears to have been artificially filled at some time in the past. It is a low bank, rising approximately 2 m above water level, protected with scrap concrete and armourstone. The backshore is currently occupied by a gravel parking lot (see Figure 3).

Further west, the shoreline is also a low bank, protected by an armourstone revetment (see Figure 4). The shoreline rises gradually, then more steeply to a high bank. No beach was observed along this shoreline during the site visit, though there might be a small beach at some locations during lower water levels.

OAKVILLE HARBOURWest Shore Master Plan

Appendix 2 Page 1

Page 104: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Mr. John George 21 May 2008 Page 2 of 8

W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

Baird Cohesive Shorelines

The shoreline in the area is classified as a “cohesive shoreline”. It is our experience that the lakebed at this location is predominantly shale and siltstone. Therefore the lakebed erosion process is very slow. The historical and natural shingle beaches along this shore were (and are in some areas) evidence of the natural process of lakebed erosion. This lakebed erosion is referred to as “downcutting”. Figure 5 shows that the process for erosion of cohesive shores consists of a translational retreat of the nearshore and backshore profile. However, at this location the process will be relatively slow given the erosion resistance associated with the sedimentary rock lakebed material.

Bathymetry

Bathymetry data were collected by the Town of Oakville 13 May 2008. The data are shown in Figure 6. The depths at the end of the pier, where the proposed lakefilling will occur, are in the range of 2 m below datum. Chart Datum for Lake Ontario is 74.2 m IGLD. Depths in the channel between the piers are greater.

Proposed Changes and Potential Impacts

The proposed changes to the shoreline include extending the shoreline lakeward to meet the existing west pier as shown in Figure 1. At the pier, this means moving the shoreline approximately 30 m lakeward of its current position. It is our understanding that the shoreline would be protected with armourstone, in the form of a revetment or stepped armourstone wall.

There are a number of coastal issues that will require investigation during the preliminary and final design stages of this project including:

�� Impact on sediment processes �� Impact on river plume and the Oakville Water Treatment Plant intake �� Impact on waves at harbour entrance �� Impact on fish habitat

A brief discussion follows.

The net direction of sediment transport along this shoreline is from east to west. As stated previously, the shoreline is characterized by narrow shingle beaches. The shingle is a product of erosion of the shale lakebed. The east pier and the mostly submerged groynes associated with Lakeside Park beach act as a barrier, trapping any alongshore drift. No beach was visible along the shoreline on the west side of the harbour during the site visit, however, there may be some loose shale on the lakebed. If the shoreline is moved lakeward, there may be some impacts on the sediment transport processes. This may result in increased deposition at the harbour entrance. However, the sediment in this area is relatively coarse (shingle size) and the changes are proposed along the downdrift shoreline. More significant impacts would be likely if the shoreline were sandy and the changes were along the updrift

OAKVILLE HARBOURWest Shore Master Plan

Appendix 2 Page 2

Page 105: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Mr. John George 21 May 2008 Page 3 of 8

W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

Baird shoreline. Nevertheless, sediment transport processes should be considered in the design. If an alternative shoreline treatment such as a shingle beach is considered for the site, the beach may require some retaining structures to ensure that the shingle is not transported into the harbour entrance. This could be addressed during the design phase of the project.

The intakes for the Oakville Water Treatment Plant are located less than 1 km west of 16 Mile Creek. During spring runoff and storm events, there is a significant plume, often extending several kilometers offshore and alongshore. During the design phase of the work, it will be important to evaluate potential impacts of the shoreline changes on the plume advection and dispersion. Although these impacts are not expected to be significant, due to the close proximity of the WTP and the importance of the municipal water supply, it will be important to undertake this assessment. The project shoreline is located within the Source Water Intake Protection Zone.

There is potential for the proposed changes to modify the wave climate at the entrance to the harbour. Although this is not anticipated to be significant, potential changes should be assessed. There is a significant amount of boat traffic using the harbour that could be affected. The proposed changes will result in a net loss of fish habitat. This will trigger the Canadian Environmental Assessment Act. Authorization will be required under the Fisheries Act and a fish habitat compensation plan will be required. It is recommended that Fisheries and Oceans Canada and Conservation Halton be contacted early in the design process to discuss the project, alternatives and to obtain their input.

Should you have any questions or wish to discuss this letter further, please give me a call.

Sincerely, Baird & Associates

Fiona Duckett, M.Sc., P.Eng. Associate

OAKVILLE HARBOURWest Shore Master Plan

Appendix 2 Page 3

Page 106: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 107: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Mr. John George 21 May 2008 Page 4 of 8

W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

Baird

Figure 1 Plan showing Proposed Changes to Shoreline West of 16 Mile Creek

OAKVILLE HARBOURWest Shore Master Plan

Appendix 2 Page 4

Page 108: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Mr. John George 21 May 2008 Page 5 of 8

W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

Baird

Figure 2 Oakville Harbour with Project Shoreline on the Left (Photo: Baird, 2003)

OAKVILLE HARBOURWest Shore Master Plan

Appendix 2 Page 5

Page 109: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Mr. John George 21 May 2008 Page 6 of 8

W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

Baird

Figure 3 View North from West Pier Toward Project Shoreline

Figure 4 View West with Armourstone Revetment in Background

OAKVILLE HARBOURWest Shore Master Plan

Appendix 2 Page 6

Page 110: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Mr. John George 21 May 2008 Page 7 of 8

W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

Baird

Figure 5 Erosion Process for Cohesive Shoreline

Irreversible downcuttingof nearshore profile

Bluff Recession

Cohesivematerial

Downcutting of Cohesive Nearshore Profile

OAKVILLE HARBOURWest Shore Master Plan

Appendix 2 Page 7

Page 111: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Mr. John George 21 May 2008 Page 8 of 8

W . F . B a i r d & A s s o c i a t e s C o a s t a l E n g i n e e r s L t d . w w w . b a i r d . c o m

Baird

Figure 6 Bathymetry at 16 Mile Creek (collected 13 May 2008, elevations in m below 75.6 m IGLD 1985)

OAKVILLE HARBOURWest Shore Master Plan

Appendix 2 Page 8

Page 112: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 113: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 114: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 115: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Oakville Harbour Master Plan - West Shore Cost Estimate June, 2008

Shipyard Park

No Item Qty Unit Unit Price Total

1.0 Demolition, Removals, Site Protection1 Demolition and Removals 20000 m2 5.00$ 100,000.00$ 2 Silt Control Fence 600 m 18.00$ 10,800.00$ 3 Safety Fence 300 m 5.00$ 1,500.00$

sub total 112,300.00$

2.0 Roads and Parking Lots4 Asphalt Paving 8915 m2 60.00$ 534,900.00$ 5 Concrete Curb 910 m 68.00$ 61,880.00$ 6 Line Painting Parking 1 LS 15,000.00$ 15,000.00$

sub total 611,780.00$

3.0 Paving Surfaces and Concrete Slabs7 Asphalt Paving Path 0 m2 40.00$ -$ 8 Concrete Paving and Paths 3200 m2 115.00$ 368,000.00$

sub total 368,000.00$

4.0 Earthworks and Planting9 Cut and Fill, Rough Grading 20000 m2 2.25$ 45,067.07$

10 Fine Grading 20000 m2 0.50$ 10,000.00$ 11 Sod 8100 m2 3.50$ 28,350.00$ 12 Imported Topsoil 1215 m3 31.00$ 37,665.00$ 13 Imported Topsoil Mix for Planting Beds (600mm) 1020 m3 42.00$ 42,840.00$ 14 Tree Planting 70 Ea 600.00$ 42,000.00$ 15 Shrub Planting 1700 m2 40.00$ 51,000.00$

sub total 256,922.07$

5.0 Walls, Steps and Edges16 Seat Wall 0 m 700.00$ -$ 17 Concrete Edge Waterfront Walkway 120 m 110.00$ 13,200.00$ 18 Steel Steps 1 LS 25,000.00$ 25,000.00$

sub total 38,200.00$

6.0 Furnishings and Miscellaneous19 Benches 15 Ea 2,500.00$ 37,500.00$ 20 Trash Receptacles Toronto Fabricating c/w Concrete Base D 20 Ea 2,000.00$ 40,000.00$ 21 Park Signs and Wayfinding 1 LS 15,000.00$ 15,000.00$ 22 Picnic Tables 10 Ea 800.00$ 8,000.00$ 23 Steel Fence 250 m 250.00$ 62,500.00$ 24 Security System Gates 1 LS 10,000.00$ 10,000.00$

sub total 173,000.00$

7.0 Electrical and Park Lighting25 Wiring & Conduit Park Path Lighting 600 m 42.00$ 25,200.00$ 26 Camera Conduit, Security and IT 1 LS 8,000.00$ 8,000.00$ 27 Lighting Standards 18 Ea 4,000.00$ 72,000.00$ 28 Electrical Switches/Panels Connect to Hydro 1 LS 15,000.00$ 15,000.00$

sub total 120,200.00$

OAKVILLE HARBOURWest Shore Master Plan

Appendix 3 Page 1

Page 116: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

No Item Qty Unit Unit Price Total

8.0 Site Services29 Catch Basins 10 Ea 2,300.00$ 23,000.00$ 30 Catch Basin Manholes 2 Ea 4,100.00$ 8,200.00$ 31 Area Drains 2 Ea 1,200.00$ 2,400.00$ 32 Storm 250 Dia. 400 m 160.00$ 64,000.00$ 33 Water Connections, Reducers, Bends and Tees 1 LS 5,000.00$ 5,000.00$ 34 Backflow Preventer and Pump 1 LS 7,000.00$ 7,000.00$ 35 Valve and Boxes 3 Ea 900.00$ 2,700.00$ 36 Irrigation System and Turf Valves 1 LS 25,000.00$ 25,000.00$

sub total 137,300.00$

Administrative and Holdbacks37 Inspection and Testing 1 LS 15,000.00$ 15,000.00$ 38 Bonds and Insurance 2% 1 LS 36,654.04$ 36,654.04$ 39 Contingency 10% 1 LS 183,270.21$ 183,270.21$

sub total 234,924.25$

Total Base Construction 2,052,626.31$ GST 5% 102,631.32$

Total Project Cost 2009 2,155,257.63$

Tannery Park

No Item Qty Unit Unit Price Total

1.0 Demolition, Removals, Site Protection1 Demolition and Removals 26000 m2 5.00$ 130,000.00$ 2 Silt Control Fence 600 m 18.00$ 10,800.00$ 3 Safety Fence 500 m 5.00$ 2,500.00$

sub total 143,300.00$

2.0 Roads and Parking Lots4 Asphalt Paving 4600 m2 60.00$ 276,000.00$ 5 Concrete Curb 800 m 68.00$ 54,400.00$ 6 Line Painting Parking 1 LS 8,000.00$ 8,000.00$

sub total 338,400.00$

3.0 Paving Surfaces and Concrete Slabs7 Asphalt Paving Path 1700 m2 40.00$ 68,000.00$ 8 Concrete Paving and Paths 3150 m2 115.00$ 362,250.00$

sub total 430,250.00$

4.0 Earthworks and Planting9 Cut and Fill, Rough Grading 26000 m2 2.25$ 58,587.19$

10 Fine Grading 26000 m2 0.50$ 13,000.00$ 11 Sod 21000 m2 3.50$ 73,500.00$ 12 Imported Topsoil 3150 m3 31.00$ 97,650.00$ 13 Imported Topsoil Mix for Planting Beds (600mm) 2340 m3 42.00$ 98,280.00$ 14 Tree Planting 105 Ea 600.00$ 63,000.00$ 15 Shrub Planting 3900 m2 40.00$ 117,000.00$

sub total 521,017.19$

OAKVILLE HARBOURWest Shore Master Plan

Appendix 3 Page 2

Page 117: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

No Item Qty Unit Unit Price Total

5.0 Walls, Steps and Edges16 Seat Wall 98 m 700.00$ 68,600.00$ 17 Stone Edge Waterfront Walkway 250 m 300.00$ 75,000.00$ 18 Steel Steps 1 LS 60,000.00$ 60,000.00$

sub total 203,600.00$

6.0 Furnishings and Miscellaneous19 Benches 25 Ea 2,500.00$ 62,500.00$ 20 Trash Receptacles Toronto Fabricating c/w Concrete Base D 30 Ea 2,000.00$ 60,000.00$ 21 Park Signs and Wayfinding 1 LS 40,000.00$ 40,000.00$ 22 Overlook Platforn at Steps Base 1 LS 60,000.00$ 60,000.00$ 23 Pavilion and Lighthouse Frame 1 LS 300,000.00$ 300,000.00$ 24 Plazas and Special Paving 1 LS 100,000.00$ 100,000.00$

sub total 622,500.00$

7.0 Electrical and Park Lighting25 Wiring & Conduit Park Path Lighting 1050 m 42.00$ 44,100.00$ 26 Camera Conduit, Security and IT 1 LS 16,000.00$ 16,000.00$ 27 Lighting Standards 27 Ea 4,000.00$ 108,000.00$ 28 Electrical Switches/Panels Connect to Hydro 1 LS 15,000.00$ 15,000.00$

sub total 183,100.00$

8.0 Site Services29 Catch Basins 12 Ea 2,300.00$ 27,600.00$ 30 Catch Basin Manholes 2 Ea 4,100.00$ 8,200.00$ 31 Area Drains 6 Ea 1,200.00$ 7,200.00$ 32 Storm 250 Dia. 325 m 160.00$ 52,000.00$ 33 Water Connections, Reducers, Bends and Tees 1 LS 5,000.00$ 5,000.00$ 34 Backflow Preventer and Pump 1 LS 7,000.00$ 7,000.00$ 35 Valve and Boxes 3 Ea 900.00$ 2,700.00$ 36 Irrigation System and Turf Valves 1 LS 40,000.00$ 40,000.00$

sub total 149,700.00$

Administrative and Holdbacks37 Inspection and Testing 1 LS 15,000.00$ 15,000.00$ 38 Bonds and Insurance 2% 1 LS 52,137.34$ 52,137.34$ 39 Contingency 10% 1 LS 260,686.72$ 260,686.72$

sub total 327,824.06$

Total Base Construction 2,919,691.25$ GST 5% 145,984.56$

Total Project Cost 2009 3,065,675.81$

Walker Street Promenade and Waterworks Park

No Item Qty Unit Unit Price Total

1.0 Demolition, Removals, Site Protection1 Demolition and Removals 4000 m2 5.00$ 20,000.00$ 2 Silt Control Fence 200 m 18.00$ 3,600.00$ 3 Safety Fence 100 m 5.00$ 500.00$

sub total 24,100.00$

OAKVILLE HARBOURWest Shore Master Plan

Appendix 3 Page 3

Page 118: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

No Item Qty Unit Unit Price Total

2.0 Roads and Parking Lots4 Asphalt Paving 600 m2 60.00$ 36,000.00$ 5 Concrete Curb 102 m 68.00$ 6,936.00$ 6 Line Painting Parking 1 LS 1,500.00$ 1,500.00$

sub total 44,436.00$

3.0 Paving Surfaces and Concrete Slabs7 Asphalt Paving Path 1500 m2 40.00$ 60,000.00$ 8 Concrete Paving and Paths 65 m2 115.00$ 7,475.00$

sub total 67,475.00$

4.0 Earthworks and Planting9 Cut and Fill, Rough Grading 6500 m2 2.25$ 14,646.80$

10 Fine Grading 6500 m2 0.50$ 3,250.00$ 11 Sod 10700 m2 3.50$ 37,450.00$ 12 Imported Topsoil 1605 m3 31.00$ 49,755.00$ 13 Imported Topsoil Mix for Planting Beds (600mm) 240 m3 42.00$ 10,080.00$ 14 Tree Planting 40 Ea 600.00$ 24,000.00$ 15 Shrub Planting 400 m2 40.00$ 12,000.00$

sub total 151,181.80$

5.0 Furnishings and Miscellaneous16 Benches 6 Ea 2,500.00$ 15,000.00$ 17 Playground Natural 1 LS 15,000.00$ 15,000.00$ 18 Trash Receptacles Toronto Fabricating c/w Concrete Base D 8 Ea 2,000.00$ 16,000.00$ 19 Park Signs and Wayfinding 1 LS 5,000.00$ 5,000.00$

sub total 51,000.00$

7.0 Electrical and Park Lighting20 Wiring & Conduit Park Path Lighting 300 m 42.00$ 12,600.00$ 21 Camera Conduit, Security and IT 1 LS 8,000.00$ 8,000.00$ 22 Lighting Standards 8 Ea 4,000.00$ 32,000.00$ 23 Electrical Switches/Panels Connect to Hydro 1 LS 5,000.00$ 5,000.00$

sub total 57,600.00$

8.0 Site Services24 Catch Basins 2 Ea 2,500.00$ 5,000.00$ 25 Storm 250 Dia. 50 m 160.00$ 8,000.00$

sub total 13,000.00$

Administrative and Holdbacks26 Inspection and Testing 1 LS 15,000.00$ 15,000.00$ 27 Bonds and Insurance 2% 1 LS 8,475.86$ 8,475.86$ 28 Contingency 10% 1 LS 42,379.28$ 42,379.28$

sub total 65,855.14$

Total Base Construction 474,647.93$ GST 5% 23,732.40$

Total Project Cost 2009 498,380.33$

OAKVILLE HARBOURWest Shore Master Plan

Appendix 3 Page 4

Page 119: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates

Summary all Parks

Total Base Construction 2009 Dollars 5,446,965.49$ GST 5% 272,348.27$

A Total Project Cost 2009 Dollars 5,719,313.77$

B Consulting Fee, Studies, Approvals and Envronmental Assesment Fee Allowance 15% 857,897.07$

Total Project Costs (A+B) Consuling and Construction 6,577,210.83$

Anualized Costs Allowing for 5% Inflation Costs 2010 6,906,071.37$ 2011 7,251,374.94$ 2012 7,613,943.69$ 2013 7,994,640.88$ 2014 8,394,372.92$ 2015 8,814,091.57$ 2016 9,254,796.14$ 2017 9,717,535.95$ 2018 10,203,412.75$

Notes:

These costs are estimates developed without detailed design or final working drawings. The unit prices are generated using industry costs of recently built projects to assist the Town in determining the magnitude of proposed improvements. Quantities are based upon the current concept plan as presented.

OAKVILLE HARBOURWest Shore Master Plan

Appendix 3 Page 5

Page 120: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 121: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates
Page 122: AppendixB Final Report - Welcome to the Town of … - culture recreation... · OAKVILLE HARBOUR West Shore Master Plan ... Preliminary Shoreline Report Appendix 3: Cost Estimates