Wickersham Elementary School –Renovation / Addition Initial Presentation

Wickersham Elementary SchoolSchool Board Presentation

October 8, 2019

2

Wickersham Elementary School - Site Plan Concept

3

Wickersham Elementary SchoolOption A – Gym Addition

4

Wickersham Elementary School – Option A 3D View

5

Wickersham Elementary SchoolOption B – Classroom Addition

6

Wickersham Elementary School – Option B 3D View

7

Wickersham Elementary School – Draft Schedule

8

Wickersham Elementary School – Cost Estimate

PHASE III CONSTRUCTION PROJECTS – WICKERSHAM ELEMENTARY SCHOOL - Renovations / Additions

Renovated Square Footage

Cost per SF New Construction

Square Footage

Cost per SF Final Build-Out Square Footage

Construction Costs

Project Cost

Multiplier

Project Cost

51,450 SF $192.00 15,900 SF $290.50 67,350 SF $14,497,350 116% $16,816,926

9

Questions / Discussion

10

Wickersham Elementary School – Phasing Option

Phasing Options1. Occupied renovation / addition.2. Modular Classrooms on site, use common spaces.3. Investigate possible use of existing Buchanan ES.

11

Wickersham Elementary SchoolExisting Floor Plans