Update on FCPS
Construction/Renovation Projects
July 2015
Jessie Clark Middle -- Renovation
Architect: Tate Hill Jacobs Architects
General Contractor: Alliance Corporation
GC Contract Sum: $18,041,500
Total Project Cost: $22,377,666
Change Orders to Date (18): $97,325
Scheduled Contract Completion Date: July 2015
% of Contract Completed: 85.41%
Revised Completion Date per GC: August 2015
July 2015
Jessie Clark Middle -- Renovation
Rendering of Final Façade
July 2015
Jessie Clark Middle -- Renovation
Work Completed to Date:
Installed roof top equipment curbs and set roof top units.
Installed quarry tile in the kitchen.
Constructed masonry portion of the building sign.
Poured concrete curb at parent/student drop off area.
Vitrification of the F2 corridor terrazzo.
Current Work Effort (July):
Begin sidewalks and loading dock area.
Grade for paver installation at student drop off.
Hang ceiling clouds in the Cafeteria.
Finish terrazzo floors.
Continue with room finishes.
July 2015
Jessie Clark Middle -- Renovation
July 2015
Site Work at Plaza Plaza Seating Bench
Phase 3 Roof Installation Cafeteria
Jessie Clark Middle -- Renovation
July 2015
Cafeteria Fam-Con Casework
Robotics Room
Terrazzo Installation
Squires Elementary -- Renovation
Architect: JRA Architects
General Contractor: D.W. Wilburn, Inc.
GC Contract Sum: $12,166,000
Total Project Cost: $15,207,000
Change Orders to Date (4): $32,409
Scheduled Contract Completion Date: July 2016
% of Contract Completed: 41.0%
Revised Completion Date per GC: No Change
July 2015
Squires Elementary -- Renovation
Rendering of Final Façade
July 2015
Squires Elementary -- Renovation
Work Completed to Date:
Metal stud soffits and walls are complete in Area “A” (Phase 1).
Drywall finishing and paint continued in Area “A” (Phase 1).
VCT, carpet and terrazzo floors have begun in Area “A” (Phase 1).
Site grading, parking lot, and curbs have begun (Phase 1).
Area “B” building pad and caissons are complete (Phase 2).
Current Work Effort (July):
Windows and storefronts to complete in Area “A” (Phase 1).
Installation of VCT, carpet and terrazzo floors to complete in Area “A” (Phase 1).
Casework installation to complete in Area “A” (Phase 1).
Elevator shaft to complete (Phase 1).
Area “B” grade beams and footings to begin (Phase 2).
July 2015
Squires Elementary -- Renovation
July 2015
Site Grading / Parking Lot Carpet in Admin. Area
Stained Concrete Floors VCT Flooring in Classrooms
Squires Elementary -- Renovation
July 2015
Rotunda Light Fixtures
Restroom Terrazzo Floors
New Elementary at Passage Mound
Architect: Moody-Nolan Architects
General Contractor: Griggs Enterprises, Inc.
GC Contract Sum: $14,980,350
Total Project Cost: $19,478,511
Change Orders to Date (2): $74,859
Scheduled Contract Completion Date: July 2016
% of Contract Completed: 6.98%
Revised Completion Date per GC: No Change
July 2015
New Elementary at Passage Mound
Rendering of Final Façade
July 2015
New Elementary at Passage Mound
Work Completed to Date:
Continue grading outside of building area.
Area A -- Complete footings and foundation walls.
Area A -- Complete plumbing and electrical underground.
Area A -- Install first course of CMU.
Complete site electrical underground.
Area B -- Start footings, foundation walls and underground plumbing.
Current Work Effort (July):
Areas A and B -- Pour slab, set door frames, start masonry walls.
Area B -- Complete plumbing and electrical underground.
Area B -- Install first course of CMU.
Set fire vault and install site fire and water lines.
Area C -- Start footings and foundations, plumbing and electrical underground.
Continue installing storm.
July 2015
New Elementary at Passage Mound
July 2015
Site – Towards Area B Lower Curb Cut
Bus Drop Off – Area B Rain Garden – Area A
New Elementary at Passage Mound
July 2015
Area A Slab Storm Structure
Street View Utility Trench Fill
New Elementary at Georgetown Road
Architect: Clotfelter-Samokar Architects
General Contractor: D.W. Wilburn, Inc.
GC Contract Sum: $14,874,000
Total Project Cost: $19,848,291
Change Orders to Date (3): $18,871
Scheduled Contract Completion Date: July 2016
% of Contract Completed: 17.0%
Revised Completion Date per GC: No Change
July 2015
New Elementary at Georgetown Road
Rendering of Final Façade
July 2015
New Elementary at Georgetown Road
Work Completed to Date:
Site contractor completed the storm line to the building and around the site.
Contractor to continue installation of concrete footings and foundation walls.
Under-slab plumbing and sanitary piping on-going.
Installation of storm collection system completed.
Below slab masonry started.
Current Work Effort (July):
Contractor to continue installation of concrete footings and foundation walls.
Underground plumbing and sanitary piping to begin.
Begin erecting structural steel.
Below slab masonry on-going.
Begin installation of building slab at Area C
July 2015
New Elementary at Georgetown Road
July 2015
Parking Lot Subgrade Area C Ready for Concrete Pour
Water Being Removed Rebar Being Installed
New Elementary at Georgetown Road
July 2015
Floors Ready for Concrete Temp. Gravel Drive
Storm Water Retention System Dewatering Trench
New High at Winchester Road
Architect: Tate Hill Jacobs: Architects
General Contractor: D.W. Wilburn, Inc.
GC Contract Sum: $62,044,000
Total Project Cost: $81,511,696
Change Orders to Date (1): $0
Scheduled Contract Completion Date: July 2017
% of Contract Completed: 3.31%
Revised Completion Date per GC: No Change
July 2015
New High at Winchester Road
Rendering of Final Façade
July 2015
New High at Winchester Road
Work Completed to Date:
Removal of vegetation & trees in upper area of site, related to academic building.
Continue site grading to establish a Building Pad.
Begin blasting in area of solid rock.
Submittal & review of construction materials.
Progress meeting on June 26.
Current Work Effort (July):
Continue site grading to establish a Building Pad.
Blasting at Building Pad to be completed, blasting to continue in areas of solid
rock at parking lot.
Foundations for Area E4 to be completed (pending weather).
Submittal & review of construction materials.
July 24 scheduled meetings: Progress Meeting, Pre-installation Meetings for
Commissioning and ICF, concrete/under-slab vapor barrier & piping.
July 2015
New High at Winchester Road
July 2015
Silt Fence (Looking North) Building Site & Pad
Setting Blasting Charge North Portion of Site