Page 1: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

Update on FCPS

Construction/Renovation Projects

July 2015

Page 2: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

Jessie Clark Middle -- Renovation

Architect: Tate Hill Jacobs Architects

General Contractor: Alliance Corporation

GC Contract Sum: $18,041,500

Total Project Cost: $22,377,666

Change Orders to Date (18): $97,325

Scheduled Contract Completion Date: July 2015

% of Contract Completed: 85.41%

Revised Completion Date per GC: August 2015

July 2015

Page 3: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

Jessie Clark Middle -- Renovation

Rendering of Final Façade

July 2015

Page 4: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

Jessie Clark Middle -- Renovation

Work Completed to Date:

Installed roof top equipment curbs and set roof top units.

Installed quarry tile in the kitchen.

Constructed masonry portion of the building sign.

Poured concrete curb at parent/student drop off area.

Vitrification of the F2 corridor terrazzo.

Current Work Effort (July):

Begin sidewalks and loading dock area.

Grade for paver installation at student drop off.

Hang ceiling clouds in the Cafeteria.

Finish terrazzo floors.

Continue with room finishes.

July 2015

Page 5: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

Jessie Clark Middle -- Renovation

July 2015

Site Work at Plaza Plaza Seating Bench

Phase 3 Roof Installation Cafeteria

Page 6: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

Jessie Clark Middle -- Renovation

July 2015

Cafeteria Fam-Con Casework

Robotics Room

Terrazzo Installation

Page 7: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

Squires Elementary -- Renovation

Architect: JRA Architects

General Contractor: D.W. Wilburn, Inc.

GC Contract Sum: $12,166,000

Total Project Cost: $15,207,000

Change Orders to Date (4): $32,409

Scheduled Contract Completion Date: July 2016

% of Contract Completed: 41.0%

Revised Completion Date per GC: No Change

July 2015

Page 8: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

Squires Elementary -- Renovation

Rendering of Final Façade

July 2015

Page 9: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

Squires Elementary -- Renovation

Work Completed to Date:

Metal stud soffits and walls are complete in Area “A” (Phase 1).

Drywall finishing and paint continued in Area “A” (Phase 1).

VCT, carpet and terrazzo floors have begun in Area “A” (Phase 1).

Site grading, parking lot, and curbs have begun (Phase 1).

Area “B” building pad and caissons are complete (Phase 2).

Current Work Effort (July):

Windows and storefronts to complete in Area “A” (Phase 1).

Installation of VCT, carpet and terrazzo floors to complete in Area “A” (Phase 1).

Casework installation to complete in Area “A” (Phase 1).

Elevator shaft to complete (Phase 1).

Area “B” grade beams and footings to begin (Phase 2).

July 2015

Page 10: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

Squires Elementary -- Renovation

July 2015

Site Grading / Parking Lot Carpet in Admin. Area

Stained Concrete Floors VCT Flooring in Classrooms

Page 11: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

Squires Elementary -- Renovation

July 2015

Rotunda Light Fixtures

Restroom Terrazzo Floors

Page 12: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

New Elementary at Passage Mound

Architect: Moody-Nolan Architects

General Contractor: Griggs Enterprises, Inc.

GC Contract Sum: $14,980,350

Total Project Cost: $19,478,511

Change Orders to Date (2): $74,859

Scheduled Contract Completion Date: July 2016

% of Contract Completed: 6.98%

Revised Completion Date per GC: No Change

July 2015

Page 13: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

New Elementary at Passage Mound

Rendering of Final Façade

July 2015

Page 14: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

New Elementary at Passage Mound

Work Completed to Date:

Continue grading outside of building area.

Area A -- Complete footings and foundation walls.

Area A -- Complete plumbing and electrical underground.

Area A -- Install first course of CMU.

Complete site electrical underground.

Area B -- Start footings, foundation walls and underground plumbing.

Current Work Effort (July):

Areas A and B -- Pour slab, set door frames, start masonry walls.

Area B -- Complete plumbing and electrical underground.

Area B -- Install first course of CMU.

Set fire vault and install site fire and water lines.

Area C -- Start footings and foundations, plumbing and electrical underground.

Continue installing storm.

July 2015

Page 15: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

New Elementary at Passage Mound

July 2015

Site – Towards Area B Lower Curb Cut

Bus Drop Off – Area B Rain Garden – Area A

Page 16: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

New Elementary at Passage Mound

July 2015

Area A Slab Storm Structure

Street View Utility Trench Fill

Page 17: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

New Elementary at Georgetown Road

Architect: Clotfelter-Samokar Architects

General Contractor: D.W. Wilburn, Inc.

GC Contract Sum: $14,874,000

Total Project Cost: $19,848,291

Change Orders to Date (3): $18,871

Scheduled Contract Completion Date: July 2016

% of Contract Completed: 17.0%

Revised Completion Date per GC: No Change

July 2015

Page 18: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

New Elementary at Georgetown Road

Rendering of Final Façade

July 2015

Page 19: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

New Elementary at Georgetown Road

Work Completed to Date:

Site contractor completed the storm line to the building and around the site.

Contractor to continue installation of concrete footings and foundation walls.

Under-slab plumbing and sanitary piping on-going.

Installation of storm collection system completed.

Below slab masonry started.

Current Work Effort (July):

Contractor to continue installation of concrete footings and foundation walls.

Underground plumbing and sanitary piping to begin.

Begin erecting structural steel.

Below slab masonry on-going.

Begin installation of building slab at Area C

July 2015

Page 20: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

New Elementary at Georgetown Road

July 2015

Parking Lot Subgrade Area C Ready for Concrete Pour

Water Being Removed Rebar Being Installed

Page 21: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

New Elementary at Georgetown Road

July 2015

Floors Ready for Concrete Temp. Gravel Drive

Storm Water Retention System Dewatering Trench

Page 22: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

New High at Winchester Road

Architect: Tate Hill Jacobs: Architects

General Contractor: D.W. Wilburn, Inc.

GC Contract Sum: $62,044,000

Total Project Cost: $81,511,696

Change Orders to Date (1): $0

Scheduled Contract Completion Date: July 2017

% of Contract Completed: 3.31%

Revised Completion Date per GC: No Change

July 2015

Page 23: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

New High at Winchester Road

Rendering of Final Façade

July 2015

Page 24: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

New High at Winchester Road

Work Completed to Date:

Removal of vegetation & trees in upper area of site, related to academic building.

Continue site grading to establish a Building Pad.

Begin blasting in area of solid rock.

Submittal & review of construction materials.

Progress meeting on June 26.

Current Work Effort (July):

Continue site grading to establish a Building Pad.

Blasting at Building Pad to be completed, blasting to continue in areas of solid

rock at parking lot.

Foundations for Area E4 to be completed (pending weather).

Submittal & review of construction materials.

July 24 scheduled meetings: Progress Meeting, Pre-installation Meetings for

Commissioning and ICF, concrete/under-slab vapor barrier & piping.

July 2015

Page 25: Update on FCPS Construction/Renovation ProjectsNew High at Winchester Road Work Completed to Date: Removal of vegetation & trees in upper area of site, related to academic building

New High at Winchester Road

July 2015

Silt Fence (Looking North) Building Site & Pad

Setting Blasting Charge North Portion of Site