TENDER FOR SUPPLY
OF MDPE PIPES (ARC) P.012213 Sabrmati Gas-Serv.of Proc Asst-MDPE pipe SGL
TENDER DOCUMENT NO.: P.012213 R10750 001
GANDHINAGAR | INDIA
SABARMATI GAS LIMITED
PUBLIC
16 February 2018
Tender
VOLUME II OF II, REV. NO.: 0
S.No. Document / Drawing No. Rev. No. Pages
IA VOLUME I OF II
1 P.012213 R11050 001 0 2 2 - 3
2 SECTION I P.012213 R11064 001 0 10 4 - 13
3 SECTION II P.012213 R11064 002 0 20 14 - 33
4 SECTION III P.012213 R11065 001 0 20 34 - 53
5 SECTION IV P.012213 R11066 001 0 8 54 - 61
6 SECTION V P.012213 R11068 001 0 26 62 - 87
7 P.012213 R11069 001 0 2 88 - 89
II VOLUME II OF II
1P.012213 G00050 001
1 2 2 - 3
2 P.012213 R11071 001 1 6 4 - 9
3 PTSP.012213 M11097 001
1 10 10 - 19
4 QCT P.012213 M11098 001 1 2 20 - 21
SCHEDULE OF RATES
TECHNICAL
INTRODUCTION
MATERIAL REQUISITION (MR)
MDPE PIPES
MDPE PIPES
COMMERCIAL TENDER WITH INDEX
INVITATION FOR BID ( IFB )
INSTRUCTIONS TO BIDDERS ( ITB )
GENERAL CONDITION OF CONTRACTS ( GCC )
SPECIAL CONDITION OF CONTRACT ( SCC )
FORMS AND FORMATS
MAIN TABLE OF CONTENTS
TENDER FOR SUPPLY OF MDPE PIPES (ARC)
OF SGL
P.012213
R11050
001
Description Page No.
COMMERCIAL
Tender For Supply Of MDPE Pipes (ARC) Page 1 of 1
INTRODUCTION
P.012213
G00050
001
Page 1 of 2
SABARMATI GAS LIMITED
TENDER FOR SUPPLY OF MDPE PIPES (ARC)
INTRODUCTION
1 16.02.2018 Issued for RFP BP AS PP
0 14.02.2018 Draft issued for comment BP AS PP
Rev. Date Description Prepared by Checked by Approved by
INTRODUCTION
P.012213
G00050
001
Rev.1 _16.02.2018 Tender For Supply Of MDPE Pipes (ARC) Page 2 of 2
1.0 INTRODUCTION
Sabarmati Gas Limited is promoted by BPCL & GSPC for developing City Gas Distribution Network in the
4 Gas /districts of North Gujarat i.e. Gandhinagar, Mehsana, Sabarkantha & Patan.
Sabarmati Gas Limited (SGL) (hereinafter referred as Owner), is a system driven, procedure oriented,
customer centric organization progressively enhancing volume of business, sales turnover, profits and
market share year after year.
SGL predominately serves 4 segments in its whole spectrum of retailing of Natural Gas. These four
segments are Domestic, Industrial and Commercial/Non Commercial customers through PNG and
automobiles through its CNG outlets through its CGD and CNG networks
PNG is a mixture of hydrocarbon gases and vapours consisting of principally methane in gaseous form. The
PNG network consist of receiving natural gas from suppliers at city gate station (CGS), steel mains,
pressure regulating installations (PRI), poly ethylene (PE) mains and supply system to end users.
SGL intends to develop its CGD and CNG network in Gandhinagar, Mehsana, Sabarkantha and Patan in
Gujarat to supply Natural gas to Domestic, Commercial consumers through MDPE network and to new
CNG stations through Steel pipeline network by setting up new facilities.
Natural Gas (NG) is today increasingly gaining popularity over as alternate auto fuel primarily because it is
environment friendly, economical and more efficient as compared to other conventional auto & kitchen
fuels. Emission of harmful oxide and other polluting particulates is minimal in case of CNG.
SGL intends to appoint supplier/s for the supply of PE 100 MDPE pipes of 32mm, 63mm, 90mm & 125mm
pipes.
SGL is now inviting tenders on Competitive Bidding basis for procurement of Medium Density
Polyethylene Pipes for this project.
The present document covers the technical specifications for the enquiry.
2.0 TECHNICAL SPECIFICATIONS
The technical specifications for this present tender enquiry are as listed in Material Requisition (No.
P.012213 R11071 001).
MATERIAL REQUISITION
P.012213
R11071
001
Page 1 of 6
SABARMATI GAS LIMITED
TENDER FOR SUPPLY OF MDPE PIPES (ARC)
MATERIAL REQUISITION - MDPE PIPES
1 16.02.2018 Issued for RFP BP AS PP
0 14.02.2018 Draft issued for comment BP AS PP
Rev. Date Description Prepared by Checked by Approved by
MATERIAL REQUISITION
P.012213
R11071
001
Rev. 1 -16.02.2018 Tender For Supply Of MDPE Pipes (ARC) Page 2 of 6
Subject : Supply of PE 100 Medium Density Polyethylene Pipes
1.1 Mehsana, Sabarkantha, Gandhinagar and Patan in state of Gujarat as per the tender terms & conditions :
A. DESCRIPTION OF GOODS AND/OR SERVICES
Item
No. Description
Total
Quantity
(Mtrs.)
Designated
Store at
Mehsana
(Mtrs.)
Designated
Store at
Gandhinaga
r (Mtrs.)
Designated
Store at
Sabarkanth
a (Mtrs.)
Designate
d Store at
Patan
(Mtrs.)
End
Conn.
SGL’s
Item code
1.0
32 mm OD x
SDR 11, PE
100
Polyethylene
Pipes
5,94,000.00 * * * *
Electro
-Fusion
Weld 100000547
2.0
63 mm OD x
SDR 11, PE
100
Polyethylene
Pipes
4,47,000.00 * * * *
Electro
-Fusion
Weld 100000546
3.0
90 mm OD x
SDR 17.6, PE
100
Polyethylene
Pipes
3,30,000.00 * * * *
Electro
-Fusion
Weld 100000545
4.0
125 mm OD x
SDR 17.6, PE
100
Polyethylene
Pipes
1,70,000.00 * * * *
Electro
-Fusion
Weld 100000544
5.0
125 mm OD x
SDR 17.6, PE
100
Polyethylene
Pipes ( In 50 M
coil)
7,000.00 * * * *
Electro
-Fusion
Weld 100000460
WILL BE INTIMATED AT THE TIME OF DESPATCH OF PE PIPES
Notes:
1 . The above quantities are indicative only and are subjected to change
2 . Tolerances on total length shall be as per PTS - P.012213 M11097 001
MATERIAL REQUISITION
P.012213
R11071
001
Rev. 1 -16.02.2018 Tender For Supply Of MDPE Pipes (ARC) Page 3 of 6
B. REMARKS / COMMENTS
1. GENERAL NOTES
VENDOR's compliance
Vendor shall submit his bid offer in compliance with the requirement of this MR and attachments.
Compliance with this material requisition in any instance shall not relieve the Vendor of his responsibility to
meet the specified performance.
2. COMPLIANCE WITH SPECIFICATION
The vendor shall be completely responsible for the design, materials, manufacture, supply, testing,
inspection, preparation for shipment, loading at your works, unloading at Owner’s stores of the above item
strictly in accordance with PTS, Material Requisition and all other applicable codes.
Any exception must be highlighted by the vendor at bidding stage and will be considered accepted only
after written approval from Owner / TE.
3. VENDOR’S SCOPE
Vendor’s scope of work includes the design, materials, manufacture, supply, testing, inspection, loading /
unloading according to present specification and applicable codes and standards and all other works
necessary for completion of works.
All material shall be delivered at Purchaser’s designated storage yard located at Gandhinagar, Mehsana,
Sabarkantha & Patan in the state of Gujarat.
4. INSPECTION
Inspection shall be performed by SGL’s nominated Third party Inspection Agency or SGL delegate, as set
out and specified in codes and particular documents forming this Material requisition at vendor works as per
approved ITP/QAP/QCT and Technical specifications . Vendor to comply with all the related inspection
documents. Inspection charges of TPIA shall be borne by the purchaser.
5. APPLICABLE DOCUMENTS
General prescriptions, requirements and information are listed in annexure C of this Material requisition.
6. BIDDER / SUPPLIER/ VENDOR'S DOCUMENTS
Vendor shall supply the documentation as listed under point D of this Material Requisition.
All documents shall be supplied in English language.
Vendor shall strictly follow the document numbering procedure in their document as illustrated below:
Document numbering shall consist of Maximum 20 Characters
MATERIAL REQUISITION
P.012213
R11071
001
Rev. 1 -16.02.2018 Tender For Supply Of MDPE Pipes (ARC) Page 4 of 6
Document No. :
Project No. Item Document Index No. Serial No. Revision No.
Where,
Project No. is P.012213;
Item is MDPE PIPES;
Document Index No. will be of three characters as indicated under point D of this MR;
Serial No. shall be 4 digit no. ranging from 0001 to 9999
Revision No. is Revision of the document starting with R0, R1 …..;
Example: For QCT program, the document no. will be
P.012213 PE PIPES QCT 0001 R0
MATERIAL REQUISITION
P.012213
R11071
001
Rev. 1 -16.02.2018 Tender For Supply Of MDPE Pipes (ARC) Page 5 of 6
C. LIST OF ATTACHMENTS
The table herebelow lists the documents which are integral part of
this Material Requisition. The applicable revision index of each
document is mentioned in the column below the current Material
Requisition revision index.
Material Requisition revision
When the Material Requisition revision index is "A" or "1", all
listed documents are attached. For other Material Requisition
revision index, only modified or new documents are attached.
0 1 2
Documents Revision of documents
Particular Technical Specification for MDPE Pipes
P.012213 M11097 001
0 1
QCT for MDPE Pipes
P.012213 M11098 001
0 1
MATERIAL REQUISITION
P.012213
R11071
001
Rev. 1 -16.02.2018 Tender For Supply Of MDPE Pipes (ARC) Page 6 of 6
D. DOCUMENTS & DATA REQUIREMENTS
The table hereunder specifies the quantities and the nature of the documents to be submitted by the
VENDOR/CONTRACTOR/BIDDER to the ENGINEER-IN-CHARGE (EIC)
The documents required at the inquiry stage and to be included in the bid are listed under column A.
The documents required after award of the AGREEMENT and subject to the written approval of the EIC are listed under
column B. The final and certified documents are listed under column C.
Any document, even when preliminary, shall be binding and therefore duly identified and signed by the CONTRACTOR.
It shall bear the EIC's Project reference, the Material Requisition number and the identification number.
THE DOCUMENTS ARE FULLY PART OF THE SUPPLY WHICH SHALL BE COMPLETE ONLY IF AND WHEN
THE DOCUMENTS COMPLYING FULLY WITH THE MATERIAL REQUISITION REQUIREMENTS ARE
RECEIVED BY THE ENGINEER – IN -CHARGE
Item Documents and Data
A B C
Number
of copies
Number
of copies Required
date
Number
of copies Required date
1. Type Test or Compliance or BIS
Certificate as per IS-14885: 2001
2 - - 2 Along with
despatch/Shipment
2. Compliance to Raw Material
Manufacturer
2 2 2 weeks 2 Along with
despatch/Shipment
3. Compliance to Tender QCT 2 2 2 weeks 2 Along with
despatch/Shipment
4. Manufacturer’s Test certificates - - 2 Along with
despatch/Shipment
5. Material certificate
- - 2 Along with
despatch/Shipment
6. Final technical file - - 2 Before Claim of
final payment
NOTES:
1) Documents listed in column A is required to be submitted during bid time (1 original+ 2 copies). Durations in
column B (Required date) are weeks after Purchase order / LOA date or as indicated in Table. Durations in
column C (Required date) are weeks after document approval or as indicated in Table. Due date of each
document may be proposed.
2) Latest submittal time for:
Test procedure : 2 weeks before test
Test report : 2 weeks after test
3) Final technical file shall be supplied in hard copy as indicated, and in electronic format
(.pdf Acrobat files) on 3 (three) CD-ROMs to SGL.
PTS - POLYETHYLENE PIPES
P.012213
M11097
001
Page 1 of 10
SABARMATI GAS LIMITED
TENDER FOR SUPPLY OF MDPE PIPES (ARC)
PTS – MEDIUM DENSITY POLYETHYLENE PIPES
1 16.02.2018 Issued for RFP BP AS PP
0 14.02.2018 Draft issued for comment BP AS PP
Rev. Date Description Prepared by Checked by Approved by
PTS - POLYETHYLENE PIPES
P.012213
M11097
001
Rev. 1_16.02.2018 Tender For Supply Of MDPE Pipes (ARC) Page 2 of 10
TABLE OF CONTENTS
1.0 INTRODUCTION & SCOPE ..................................................................................................... 3
2.0 DEFINITIONS ........................................................................................................................ 3
3.0 TERMINOLOGY ...................................................................................................................... 3
4.0 DESIGN CODES/ STANDARDS/REFERENCES ......................................................................... 4
5.0 RAW MATERIAL GRADE AND PROPERTIES ........................................................................... 5
6.0 APPROVED MANUFACTURER FOR RAW MATERIAL (PE-100) ................................................ 6
7.0 PIPE SIZE/ DIMENSION......................................................................................................... 6
8.0 METHOD OF MEASUREMENT ................................................................................................ 6
9.0 TOLERANCE .......................................................................................................................... 6
10.0 COLOUR ................................................................................................................................ 7
11.0 MARKING .............................................................................................................................. 7
12.0 INSPECTION AND TEST PROCEDURE (ITP)........................................................................... 7
13.0 TYPE TEST CERTIFICATE ...................................................................................................... 8
14.0 FINISH / DEFECT LIABILITY ................................................................................................. 8
15.0 SUPPLY, PACKAGING, HANDLING TRANSPORTATION AND STORAGE OF PE-100 PIPES ....... 8
16.0 DOCUMENTS OF PRECEDENCE ............................................................................................. 8
17.0 DOCUMENTS TO BE SUBMITTED ALONG WITH BID ............................................................. 8
AMENDMENTS TO THE CLAUSES OF IS 14885:2001 ........................................................................ 8
PTS - POLYETHYLENE PIPES
P.012213
M11097
001
Rev. 1_16.02.2018 Tender For Supply Of MDPE Pipes (ARC) Page 3 of 10
1.0 INTRODUCTION & SCOPE
SABARMATI GAS LIMITED (SGL) plans to augment the PE Network. It supplies natural gas to domestic
& commercial consumers in the cities of Gandhinagar, Mehsana, Sabarkantha & Patan in the state of
Gujarat.
The present document covers the technical specifications for the procurement of “Medium Density
Polyethylene Pipes" The Polyethylene Pipes shall be manufactured, supplied in accordance with Pr EN:
1555-1 Plastic Piping System for the Supply of Gaseous Fuels, IS 14885:2001 Polyethylene Pipes for
Supply of Gaseous Fuels and ISO-4437 Buried Polyethylene (MDPE) for the supply of gaseous fuels metric
series specifications.
2.0 DEFINITIONS
Owner Means Sabarmati Gas Limited., SGL
Vendor /Manufacturer Means the Vendor / Manufacturer of the MDPE pipe.
PTS Means the present <<Particular Technical Specification>>and all
its appendix, if any.
TPIA
Means Third Party Inspection Agency
3.0 TERMINOLOGY
Maximum Allowable Operating Pressure (MAOP): The maximum effective pressure of gas in a
piping system, expressed in bars, which is allowed in continuous use. It takes in account physical &
mechanical characteristics of the components of piping system.
The equation for MAOP = (20 x MRS) /[C X (SDR - 1)]
Minimum Required Strength (MRS): The value of lower confidence limit rounded down to next
value as defined in ISO 3:1973 MRS is expressed as a hoop stress in mega-Pascal. Standardised class
of component for which the Lower Confidence Limit (LCL) is equal to 10.
PE 100 : Standard designation for PE compound in class MRS 10.
For such PE compounds, the long term hydrostatic strength- calculated and classified according to
the standardised method (ISO 9080 and ISO 12162) for a temperature of 20 degree centigrade, a
period of 50 years and a reliability of 97.5% - must be at least 10 Mpa.
Co-efficient (C): C is an overall co-efficient with a value greater than 1 which takes into
consideration service condition as well as properties of the components of a piping system other than
those represented in the lower confidence limit. For this specification the minimum of C is 2.0
Nominal Outside Diameter(dn): A convenient round number (in millimetres) for reference purposes
which is common to all components in all thermoplastic systems ,except for flanges and components
which are designated by thread size.
PTS - POLYETHYLENE PIPES
P.012213
M11097
001
Rev. 1_16.02.2018 Tender For Supply Of MDPE Pipes (ARC) Page 4 of 10
Out of roundness (Ovality): The absolute out of roundness is the difference between the measured
maximum outside diameter and the measured minimum outside diameter in the cross – section of
pipe.
Nominal Wall Thickness (en): The wall thickness in millimetres corresponding to minimum wall
thickness at any point around circumference of the pipe.
Resin: A material (solid or semi-solid) which has a high molecular weight and is a product of
polymerization.
Metal Flow Rate (MFR): is a value relating to the viscosity of the molten material at a specified
temperature and a rate of shear.
Standard Dimension Ratio (SDR). The ratio of nominal outside diameter of a pipe to its nominal
thickness.
SDR= dn/en
For any other terminology, IS-14885-2001 (latest) and / or other applicable National & International codes /
Standards can be referred.
4.0 DESIGN CODES/ STANDARDS/REFERENCES
The following National & International codes / standards / references (Latest edition) shall be applicable for
PE-100 material as well as Polyethylene pipe.
Pr EN 1555 -1 Plastic Piping System for the Supply of Gaseous Fuels.
Pr EN 1555-2 Standard PE Pipes and Fitting, Suitable for Gas Transportation System Solutions
IS-14885 Polyethylene pipes for supply of Gaseous Fuels.
ISO-4437 Buried Polyethylene pipe for supply of gaseous fuels – metric series - specification
IS-2530 Methods of test for PE moulding materials and PE compound
ISO-1183:1987 Plastic: Methods for determining the density of non-cellular plastics.
ISO-1872- 2B Plastic: polyethylene (PE) moulding and extrusion material.
ISO- 527 Plastics: Determination of tensile properties.
EN 728 Plastic Piping and Ducting System – Determination of oxidation Induction time.
EN 12099 Polyethylene piping system - Determination of Volatile Content
ISO 13949:1997 Method of assessment of the degree of pigment dispersion in polyolefin pipes,
fittings and compounds
EN 12118 Plastic Piping system – Determination of moisture content in thermoplastic by
coulometer
ISO-1133 Plastics – determination of the melt-mass flow rate (MFR) and melt volume flow
rate (MVR) of thermoplastic.
EN 1555-7 Gaseous fuels supply polyethylene (PE)
PTS - POLYETHYLENE PIPES
P.012213
M11097
001
Rev. 1_16.02.2018 Tender For Supply Of MDPE Pipes (ARC) Page 5 of 10
5.0 RAW MATERIAL GRADE AND PROPERTIES
5.1. Raw material grade / classification shall conform to Cl.4.2 of IS-14885: 2001. i.e. PE 100
5.2. The raw material of polyethylene pipes shall be PE 100. The properties of PE-100 compound shall conform
to the table 2 of IS-14885: 2001.
Other materials / additives such as anti oxidant, UV stabilizer, pigment dispersion etc. shall conform to IS-
14885: 2001.
Raw material of polyethylene pipes shall be virgin quality. PE compound shall be Cadmium free pigment
compound.
Anti oxidant & UV stabilised used in PE resin shall not exceed 0.3 and 0.5 % by mass of finished resin
respectively.
Raw material supplier to submit the certificate for percentage use of U.V. stabilizer in the raw materials (PE
compound)
5.3. Characteristic of PE-100 Compound
Sr. Characteristic
Unit
Requirement
Test Method
1 Conventional Density Kg/m3 > 928.4 at 23°C (Base
Polymer)
> 930 at 27°C (Base
Polymer)
IS-14885 /ISO IS 7328
2 Tensile Yield Point
MPa Min. 15 MPa IS-14885 : 2001
3 Elongation at break
% Min 350 IS-14885 : 2001
4 Melt-mass Flow Rate g/10 min. + 20% of value nominated
by compound producer @
190°C / 5.0 kg. (load)
IS-14885 /IS 2530
5 Thermal stability
(Oxidation Induction
time)
Minute
>20@200°C
Annex. D of
IS-14885 : 2001
6 Volatile Matter Content
(mg/kg) <350 IS-14885 : 2001/
EN 12099
7 Pigment Dispersion
<3 Annex. E of
IS-14885 : 2001
8 Resistance to gas
constituents
H >20 @ 100°C Clause 5.5 of
IS-14885 : 2001
9 Resistance to Slow
crack growth
H 165h at 80°C,0.92 MPa ISO 13479
Table – 1
The above requirements are also same for the final product.
PTS - POLYETHYLENE PIPES
P.012213
M11097
001
Rev. 1_16.02.2018 Tender For Supply Of MDPE Pipes (ARC) Page 6 of 10
5.4. PE compound quality evaluation
PE compound quality evaluation shall be as per IS-14885: 2001
6.0 APPROVED MANUFACTURER FOR RAW MATERIAL (PE-100)
1. INEOS
2. BOROUGE (Part of BOREALIS & ADNOC group)
3. TOTAL PETROCHEMICALS
4. DOW
5. BASELL
7.0 PIPE SIZE/ DIMENSION
7.1. Wall Thickness
7.2. Length of Pipes
The required minimum length of straight pipes and coils / reels shall be as Follows:
8.0 METHOD OF MEASUREMENT
The method of measurement of outside diameter, wall thickness, length, ovality etc. of pipe shall conform
to IS-14885: 2001 or equivalent code/standards.
9.0 TOLERANCE
9.1. Tolerances for Random Length of Pipes
Tolerances for each rolled pipes - 0 / +0.5m
Sl.no. Nominal
diameter (mm)
Minimum wall thickness (e) ,
mm SDR
OVALITY as per
1 32 3.0 11 IS-14885 : 2001
2 63 5.8 11 IS-14885 : 2001
3 90 5.2 17.6 IS-14885 : 2001
4 125 7.1 17.6 IS-14885 : 2001
Nominal Diameter Packing Length (m) Coil / Reel /Straight
32
63
90
125
125 50 Coil
PTS - POLYETHYLENE PIPES
P.012213
M11097
001
Rev. 1_16.02.2018 Tender For Supply Of MDPE Pipes (ARC) Page 7 of 10
Tolerances for each straight pipes - 0 / +0.05m
9.2. Tolerances on Nominal wall thickness at any points of pipe shall be in accordance with IS-14885: 2001 or
equivalent codes / standards.
10.0 COLOUR
The pipe shall be of ORANGE color, when the pipe shall be manufactured from PE-100 grade of raw
material.
11.0 MARKING
11.1. Owner’s name as SGL to be marked on each pipe.
All pipes shall be permanently and legibly marked along their length with a legend, which shall be
impressed to a depth of not more than 0.15 mm.
Marking details shall be formed in such a way that marking does not initiate cracks or other type of
failure and in such away that with normal storage weathering and processing and permissible method of
installation use legibility shall be maintained for the pipe.
11.2. The embossing for orange pipe shall have black base. Height of character shall be uniform and at least as
given below:
a) 3mm for pipe not greater than 90mm nominal size.
b) 5mm for pipe greater than 90mm nominal size.
11.3. Legend shall be repeated at intervals of 1 m and shall consist of following
Information:
a) Manufacturer’s identity name or trade name,
b) Material and designation
c) Batch no. or lot no.
d) Internal fluid
e) SDR
f) Reference of standard
12.0 INSPECTION AND TEST PROCEDURE (ITP)
Vendor to submit ITP, in line with tender QCT for Purchaser / Consultant’s approval after award of work.
Inspection shall be carried out as per approved ITP.
PTS - POLYETHYLENE PIPES
P.012213
M11097
001
Rev. 1_16.02.2018 Tender For Supply Of MDPE Pipes (ARC) Page 8 of 10
13.0 TYPE TEST CERTIFICATE
Vendor to submit Type Test or Compliance Certificate as per IS-14885: 2001along with the offer.
14.0 FINISH / DEFECT LIABILITY
The internal and external surfaces of the pipes shall generally be smooth, clean and free from cavities and
other surface defects, which may affect pipe performance. The pipe ends shall be cut cleanly and square to
the axis of the pipe and shall be within the tolerances of ends. Defect liability period shall be 24 months
from last date of delivery of pipes at site.
15.0 SUPPLY, PACKAGING, HANDLING TRANSPORTATION AND STORAGE OF PE-100 PIPES
Packaging shall be done in Hessian cloth (Jute) with polyethylene sheet wrapped around the pipe of 100
micron to avoid direct sunlight and facilitate out-door storage and both ends of pipe shall be protected with
proper end caps.
Packing size to be mentioned to ensure uniformity in delivery conditions of the pipe being procured. Bidder
shall submit the packaging details during offer and also complied with at the time of delivery.
Manufacturer shall make an arrangement for unloading of pipes at Owner’s premises.
16.0 DOCUMENTS OF PRECEDENCE
Where any portion of the documents is repugnant or variance with any provisions of the PTS, unless a
different intention appears, the provision(s) of PTS shall be deemed to govern the provision(s) of documents
of contract. If there is no variance or repugnance between documents and PTS both clauses shall be
applicable.
In case of conflict between the requirements of this specification and that of the referred codes, standards
and specifications, the stringent requirements of the referred codes, standards and specifications shall
govern.
17.0 DOCUMENTS TO BE SUBMITTED ALONG WITH BID
All relevant documents like BIS Certification, Catalogue etc to be submitted along with the bid.
AMENDMENTS TO THE CLAUSES OF IS 14885:2001
3. TERMINOLOGY
ADD
3.14 Lot of Batch of Compound
By lot of batch of compound is meant a homogeneous quantity of PE compound of same origin of particular
brand.
The lot must be registered under a single identification number (lot No.) which leaves no doubt as to the
origin, identity & date of manufacture of the compound.
PTS - POLYETHYLENE PIPES
P.012213
M11097
001
Rev. 1_16.02.2018 Tender For Supply Of MDPE Pipes (ARC) Page 9 of 10
5. MATERIAL
5.1 Polyethylene Compound
ADD
Polyethylene compound used in manufacture of pipes shall not contain following:-
Recycled Materials
Mixture of different material
5.7 Other Materials
ADD
Addition of complementary materials and / or mixture of different materials by the pipe manufacturer are
forbidden.
8. PERFORMANCE REQUIREMENTS
8.5 THERMAL STABILITY TO OXIDATION
ADD
The Maximum admissible decrease in the oxidation induction time measured on a pipe sample compared to
that measured on the raw material shall not exceed 20% of the latter.
9. SAMPLING, FREQUENCY OF TEST AND CRITERIA FOR CONFORMITY
9.2 Acceptance Tests
9.2.2 LOT
ADD
All pipes of the same size, same pressure rating and also manufactured essentially under similar conditions
of manufacture i.e. made in a continuous process by the same extrusion machine and from the same Lot of
batch of compound shall constitute a lot.
11.0 ANNEXURE K (CLAUSE 11) - SUPPLY, PACKAGING, HANDLING AND TRANSPORTATION OF
POLYETHYLENE PIPES FOR GAS TRANSMISSION
K.1 SUPPLY
ADD
Prior to execution of the order, the manufacturer must submit to the company the seals which it intends to
use for all the types of pipes ordered. The seals shall preferably be made of PE or material which does not
adulterate polyethylene. Metal and PVC seals are not permitted. The seals must be able to withstand storage
terms as guaranteed in K.6 STORING of this Annexure, and also to withstand handling during installation.
They must not be brittle or sharp and the materials, shapes and dimensions thereof most are such that they
cannot fully penetrate inside the pipes. They are of the internal plug type for all pipes supplied in straight
lengths, and or pipes rolled in coils, the seals may be caps.
PTS - POLYETHYLENE PIPES
P.012213
M11097
001
Rev. 1_16.02.2018 Tender For Supply Of MDPE Pipes (ARC) Page 10 of 10
All seals shall be placed on the pipes immediately after completion of manufacturing & testing. Their
removal on site should not require the use of special tools.
PE can be delivered in straight length or coils, transported and stored. Care should be taken to maintain the
coil diameter at or above the specified minimum to prevent deformation. The pipe should be wrapped with
non transparent PE films of 100 mm gauge to protect from ultra violet rays.
K.4 Handling
ADD
PE pipe is relatively light and flexible however, it is susceptible to damage from sharp objects and stones. It
should not be dragged, dropped or subjected to rough handling during loading or unloading, transport,
storage or actual installation.
K.5 Transportation
ADD
When being transported, care should be taken to ensure pipes are not restrained in such a manner as to cause
damage to them. Sharp sections bearing against the pipes should be avoided so as to minimize the chance of
indentation or scoring of the pipe wall.
Pipes with end treatment should be stacked or supported in such a way that the ends are free from loading.
Pipe ends, particularly ends cut for jointing, should be given special attention at all times to ensure they are
free from damage.
K.6 Storage
ADD
Pipes should be stored in such a manner as to prevent damage from elevated temperatures, direct sunlight
and contact with chemicals.
QCT No.
Date
Prepared : BP
Checked : AS
Approved
S.NO. Activity Quantum of Check
Acceptance Criteria /Norms
(PrEN 1555-1:2001 /PTS _ P.012213 M11097 001
for Raw Material and IS 14885:2001 for PE Pipe)
Format of Record VendorCA/TPIA
Remarks
1 RAW MATERIAL INSPECTION - Test result of PE compound
1.1 Test result of PE compoundPer Lot of Batch of
CompoundISO 1183:1987 & PTS MTC of Manufacturer R R
Witness may be done by
CA to ensure use of
compound material
2
APPROVAL OF TYPE TEST FOR
LONG TERM HYDROSTATIC
STRENGTH & OTHERS
-
@ 80º C for 1000 hours
@ 20 º C for more than100 hours, As per Table 7 of IS
14885
TPIA approved
certificateR R /W
3
3.1Raw Material Identification at the time of
pouring the bags in Hopper.Each Bag PE100 Cl. No. 5 of IS & PTS Consumption Report P H
TPI to verify MTC of
each batch for
consumption .
4
Visual Appearance
a) Smoothness & Cleanliness Smooth & clean or as specified in CL no. 7 of IS 14885 -- P W
b) Surface DefectsFree from grooves, scoring etc. or as specified in CL no. 7
of IS 14885-- P W
c) CuttingsCleanly cut ends & square to axis or as specified in CL no.
7 of IS 14885-- P W
Dimension
a) Outside diameter Cl no. 6 /Table 4 of IS 14885 Inspection Report P W
b) Wall Thickness Cl no. 6 /Table 4 of IS 14885 Inspection Report P W
c) Ovality Cl no. 6 /Table 3 of IS 14885 Inspection Report P W
d) Length Cl. No. 7.2 & 8 of PTS Inspection Report P W
Hydraulic Characteristics
a) 80OC for 165 hrs Table 9 Cl 8.1, Annexure A & B & Table 7 of IS 14885 Hydrotest Report P W
4.4 Heat reversion test CL 8.2, Annexure C of IS 14885 / Not more than 3% Inspection Report P W
4.5 Density (matl. from pipe) @ 23 º C > 928.4 kg/m3 & '@ 27 º C > 930 kg/m3 Inspection Report P W
4.6 Melt Flow Rate - Pipe Cl 5.3 of PTS Inspection Report P W
4.7 Thermal Stability to Oxidation Cl 8.5, Annexure D of IS 14885 / OIT > 20 minutes Inspection Report P W
One out of 10 Pipes
FINAL INSPECTION
: 16.02.2018
: PP
: P.012213 M11098 001 Rev 1
4.1
4.2
4.3
One out of 10 Pipes
IN-PROCESS INSPECTION
QUALITY CONTROL TABLE
MEDIUM DENSITY POLYETHYLENE PIPES (MDPE)
Table 11
Rev-0 _14.02.2018 Tender For Supply Of MDPE Pipes (ARC) Page 1 of 2
QCT No.
Date
Prepared : BP
Checked : AS
Approved
S.NO. Activity Quantum of Check
Acceptance Criteria /Norms
(PrEN 1555-1:2001 /PTS _ P.012213 M11097 001
for Raw Material and IS 14885:2001 for PE Pipe)
Format of Record VendorCA/TPIA
Remarks
: 16.02.2018
: PP
: P.012213 M11098 001 Rev 1
QUALITY CONTROL TABLE
MEDIUM DENSITY POLYETHYLENE PIPES (MDPE)
4.8 Volatile Matter Content Test - Cl 8.6, Annexure H of IS 14885 / < 350 mg/kg Inspection Report P W
4.9 Tensile Test & Elongation at break Table 11Cl 8.7& Annexure J of IS 14885 / Tensile Yield Strength
= 15 Mpa (min.), Elongation = 350% (Min.)Inspection Report P R/W*
4.10 Resistance to weathering - Cl 8.8 & Annexure F of IS 14885 Inspection Report P R/W*
4.11 Squeeze Off Test - Cl 8.9 & Annexure G of IS 14885 Inspection Report P W
5 MARKING INFORMATION
5.1 Legibility Table 10 Visual / Should be legible Inspection Report P R
5.2 Depth Table 10 As per Cl 10.1 of PTS, Depth < 0.15 mm Inspection Report P RW
5.3 Marking Strip Table 10
Cl 10.3 of IS 14885, Single Strip for Pipes with Nominal
Size <=32mm & two strips on opposite side of pipe for
other pipes.
Inspection Report P RW
5.4 Colour or Marking Table 10 As per Cl 9 & 10 of PTS/ IS 14885 Inspection Report P RW
5.5 Height of Character Table 10As per Cl 10.2 of PTS, Min.3 mm for < 90mm pipe sizes
& Min. 5 mm for > 90mm pipe sizes.Inspection Report P RW
5.6 Legends Table 10As per Cl 10.3 of PTS, At interval of 1 mtr. And should
contain information as specified in PTSInspection Report P RW
6 FINAL DOCUMENTATION - P.O. / PTS Compliance Certificate p H
1
2
3
4
5
6
7
8
Contractor shall in coordination with Supplier/Sub vendor issue detailed Production and Inspection schedule indicating the dates and the locations to facilitate Owner/Owner's representative and TPIA to
organize Inspection.
Special manufacturing procedures have to be specially approved or only previously approved procedures have to be used. In case of conflict between specifications, more stringent condition shall be
applicable.
Owner / Owner's representative including TPIA will have the right to inspect any activity of manufacturing at any time.
All reference Codes/ Standards, Documents, P.O. Copies shall be arranged by vendor / supplier for reference of TPIA/SGL at the time of Inspection
Notes: -
The Above Testing and acceptance criteria are minimum requirements. However, manufacturer shall ensure that the product shall also comply to the additional requirements as per Particular Technical
specifications(PTS)
At the time of delivery of material in stores, vendor will submit copy of all related document of inspection along with release note & MTC.
Owner/Owner representative shall review/approve all the documents related to QAP/Quality manuals/Drawings etc.submitted by supplier.
The supplier shall submit their own detailed ITP prepared on the basis of above / Technical specification for approval of Owner/Owner's representative.
*Witness shall be done
in case valid Type Test
Report is not available
LEGENDS: R - Review, W - Witness, A - Approval, RW - Random Witness, H - Hold, P - Perform, TPIA - Third Party Inspection Agency , CA - Control Authority ( Owner / owner's representative ) ,
P.O. - Purchase order
Rev-0 _14.02.2018 Tender For Supply Of MDPE Pipes (ARC) Page 2 of 2
At the helm of the Energy Transition, Tractebel provides a full range of engineering and consulting services throughout the
life cycle of its clients’ projects, including design and project management. As one of the world’s largest engineering consultancy
companies and with more than 150 years of experience, it's our mission to actively shape the world of tomorrow. With about 4,400
experts and offices in 33 countries, we are able to offer our customers multidisciplinary solutions in energy, water and
infrastructure.
TRACTEBEL ENGINEERING PVT. LTD. Intec House 37
Institutional Area, Sector 44
122 002 - Gurgaon - INDIA
tractebel-engie.com
Pintukumar Chandubhai PATEL tel.
+91 11 47012200 pintu.patel@tractebel.engie.com
TRACTEBEL ENGINEERING PVT. LTD. GUJARAT OFFICE 409-A, Meghmalhar Complex, Sector-11 Gandhinagar
382011 - Gujarat - INDIA
tractebel-engie.com
Pintukumar Chandubhai PATEL tel.
+91 79 23243982
pintu.patel@tractebel.engie.com
top related