No. RW/G-23012/1/2019-W&A(Pt.1)
Government of India
Ministry of Road Transport & Highways Transport Bhawan, 1, Parliament Street, New Delhi - 110001
Dated: 14‘" September, 2021
OFFICE MEMORANDUM
Sub: - Revised Sanction Ceiling for PR/IRQP works during FY 2021-22 for Annual Renewal Programme (ARP) under NH(Q) Head-Reg.
Ref: - Planning O.M of even no. dated 30.03.2021 & 29.07.2021.
Competent Authority has approved the additional Sanction Ceiling for PR/IRQP works during FY 2021-22 for Annual Renewal Programme (ARP) under NH(O) head for the State of Tripura and UT of Puducherry.
2. The details of approved Sanction Ceiling are as under: -
Sanction Ceiling in Rs. Crore Existin Additional (+)/ Revised
Be ace: Sanction Gelling action! Sanction Ceiling | 1 Andhra Pradesh 116.87 0.00 116.87
2 | Arunachal Pradesh 53.90 0.00 53.90
3 | Assam 254.76 0.00 254.76
4 _| Bihar 77.66 0.00 77.66
5 | Chhattisgarh 11.82 0.00 11.82
6 Gujarat 187.69 0.00 187.69
7 | Haryana 7.00 0.00 7.00
8 | Himachal Pradesh 51.47 0.00 51.47
9 | Jharkhand 169.89 0.00 169.89
10 | Madhya Pradesh 45.00 0.00 45.00
11 | Manipur 24.14 0.00 24.14
12 | Meghalaya 79.86 0.00 79.86
13 | Mizoram 107.71 0.00 107.71
14__| Nagaland 22.00 0.00 22.00
15 | Punjab 54.35 0.00 54.35
16 | Tamil Nadu 105.45 0.00 105.45
17 | Tripura 0.00 30.00 30.00
18 | Uttar Pradesh 236.50 0.00 236.50
19 | Uttarakhand 43.89 0.00 43.89
20 | West Bengal 25.14 0.00 25.14
21 =| Puducherry 0.00 19.00 19.00
Total 1,675.10 49.00 1,724.10
3. Further, in continuation of the above it is to mention that -
(i) The projects/works whose sanction ceiling are approved under ARP for PR/IRQP
during FY 2019-20 and 2020-21 but sanction could not be accorded within 31.03.2021, may
be considered for sanction in FY 2021-22 also.
(ii) From FY 2021-22 on-wards the funding for the PR/IRQP works are considered
under NH(O) in three categories viz. PR/IRQP [NH(O)-General], PR/IRQP [NH(O)-NE] and
PR/IRQP [NH(O)-TSP]. The sanction ceiling could not be provided in these three different
No.RW/G-23012/1/2019-W&A(Pt. |) Government of India
Ministry of Road Transport & Highways Transport Bhawan, 1, Parliament Street, New Delhi - 110001
categories at this stage, therefore, ROs are requested to sanction the PR/IRQP works under the appropriate category/ head i.e. (i) for North Eastern States sanction should be under PR/IRQP [NH(O)-NE] head, (ii) for the works confined within one or more adjoining tribal districts sanction should be under PR/IRQP [NH(O)-TSP] head and (iii) for remaining, works sanction should be under PR/IRQP [NH(O)-General] head.
4, This issues with the concurrence of the Finance Wing vide Note #385 dated 10.09.2021 and approval of the Secretary (RT&H).
Encl.: As Above
(Saurav Shivhare) Asst. Executive Engineer (Planning)
. E-mail-planningmorth@gmail.com oO,
1. All Project zone CEs 2. All CE-ROs / SE-ROs 3. AFA, MoRT&H
Copy for information to: -
1. Sr. PPS to Secretary (RT&H) 2. Sr. PPS to DG (RD)&SS 3. PPS to AS & FA 4. Sr. PPS/ PPS to all ADGs
Copy to: - NIC with a request to upload on MoRTH website
No. RW/G-2301 2/1/2019-W&A(Pt. 1)
Government of India
Ministry of Road Transport & Highways Transport Bhawan, 1, Parliament Street, New Delhi - 110001
Dated: 29°" July, 2021
OFFICE MEMORANDUM
Sub: - Sanction Ceiling for PR/IRQP works during FY 2021-22 for Annual Renewal
Programme (ARP) under NH(O) Head-Reg.
Ref: - Planning O.M of even no. dated 30.03.2021.
Competent Authority has approved the Sanction Ceiling for PR/IRQP works during
FY 2021-22 for Annual Renewal Programme (ARP) under NH(O) head for the States/UTs.
2. The details of approved Sanction Ceiling are as under: -
Sanction Ceiling in Rs. Crore
Approved Sanction Ceiling S.No. State/UT EY 24-29
1 Andhra Pradesh 116.87
2 Arunachal Pradesh 53.90
3 Assam 204.76
4 | Bihar 77.66
5 Chhattisgarh 11.82
6 Gujarat 187.69
7 Haryana 7.00
8 Himachal Pradesh 51.47
9 Jharkhand 169.89
10 | Madhya Pradesh 45.00
11 | Manipur 24.14
12 | Meghalaya 79.86
13 | Mizoram 107.71
14__| Nagaland 22.00
15 | Punjab 54.35
16 | Tamil Nadu 105.45
17 __| Uttar Pradesh 236.50
18 | Uttarakhand 43.89
19 | West Bengal 20.14
Total 1,675.11
3. Further, in continuation of the above it is to mention that -
(i) The projects/works whose sanction ceiling are approved under ARP for PR/IRQP during
FY 2019-20 and 2020-21 but sanction could not be accorded within 31.03.2021, may be
considered for sanction in FY 2021-22 also.
(ii) From FY 2021-22 on-wards the funding for the PR/IRQP works are considered under
NH(O) in three categories viz. PR/IRQP [NH(O)-General], PR/IRQP [NH(O)-NE] and PR/IRQP
[NH(O)-TSP]. The sanction ceiling could not be provided in these three different categories
at this stage, therefore, ROs are requested to sanction the PR/IRQP works under the
appropriate category/ head i.e. (i) for North Eastern States sanction should be under
PR/IRQP [NH(O)-NE] head, (ii) for the works confined within one or more adjoining tribal
districts sanction should be under PR/IRQP [NH(O)-TSP] head and (iii) for remaining, works
sanction should be under PR/IRQP [NH(O)-General] head.
No. RW/G-2301 2/1/2019-W&A(Pt. 1)
Government of India
Ministry of Road Transport & Highways Transport Bhawan, 1, Parliament Street, New Delhi - 110001
4. This issues with the concurrence of the Finance Wing vide Note #367 dated
28.07.2021 and approval of the Secretary (RT&H).
Encl.: As Above
(Saurav Shivhare)
Asst. Executive Engineer (Planning)
E-mail-planningmorth@gmail.com
To,
1. All Project zone CEs
2. All CE-ROs / SE-ROs 3. AFA, MoRT&H
Copy for information to: -
1. Sr. PPS to Secretary (RT&H)
2. Sr. PPS to DG (RD)&SS 3. PPS to AS & FA 4. Sr. PPS/ PPS to all ADGs
Copy to: - NIC with a request to upload on MoRTH website
No.G-23012/1/2019-W&A(Pt.1) Government of India
Ministry of Road Transport & Highways (Planning Zone)
Transport Bhawan, 1, Parliament Street, New Delhi - 110001
Dated: 30" March, 2021
OFFICE MEMORANDUM
Sub: - Revised Sanction Ceiling for PR/ IRQP works during FY 2019-20 and 2020- 21 for Annual Renewal Programme (ARP) under M&R Head-Reg.
Ref: - Ministry’s even no. OM dated 18.12.2020, 30.12.2020 & 04.03.2021.
Competent Authority has approved the revised Sanction Ceiling for PR/IRQP works during FY 2019-20 and 2020-21 for Annual Renewal Programme (ARP) under
M&R head for the States/ UTs.
2. The detail of revised approved sanction ceiling for PR/IRQP works during FY 2019-20 and 2020-21 for Annual Renewal Programme (ARP) under M&R head for the States/ UTs is as under,
(Rs. in crore) Sl. Existin Additional : No. ecitee Ts Senedon (+) SP
Ceiling Reduction(-) anetion Geling
(1) (2) (3) (4) (5) 1 | Andhra Pradesh 233.50 0.00 233.50 2 | Arunachal Pradesh 59.00 0.00 59.00 3 | Assam 86.50 0.00 86.50 4 | Bihar 141.76 0.00 141.76 5 | Chhattisgarh 80,82 10.00 90.82 6 | Goa 38.50 0.00 38.50 7 | Gujarat 174.00 0.00 174.00 8 | Himachal Pradesh 50.00 0.00 50.00 9 | Jharkhand 50.00 0.00 50.00 10 | Karnataka 350.50 0.00 350.50
11 | Kerala 225.00 0.00 225.00
12__| Madhya Pradesh 52.04 0.00 52.04 13_| Maharashtra 379.00 0.00 379.00
14 | Manipur 30.00 0.00 30.00
15 | Meghalaya 99.50 0.00 99.50 16 | Mizoram 45.00 0.00 45.00
17 __| Nagaland 22.00 0.00 22.00 18 | Odisha 151.00 0.00 151.00
19 | Punjab 30.50 0.00 30.50 20 | Rajasthan 92.00 0.00 92.00
21 | Sikkim 2.00 0.00 2.00
22 | Tamil Nadu 105.00 0.00 105.00
23 | Telangana 266.00 0.00 266.00
(Rs. in crore) Sl. States/ UTs Existing Additional Ravised
Nei Sanction (+)/ Sanction Ceiling Ceiling Reduction(-)
(1) (2) (3) (4) (5) 24 | Tripura 15.50 0.00 15.50 25 | Uttar Pradesh 203.91 0.00 203.91 26 | Uttarakhand 30.00 0.00 30.00 27_| West Bengal 41.00 0.00 41.00 28 | Chandigarh 11.00 0.00 11.00
Dadra & Nagar Haveli and 29 Daman& Bid 3.00 0.00 3.00
30 | Jammu & Kashmir 8.09 0.00 8.09
31__| Ladakh 4.33 0.00 4.33 Total 3,080.45 10,00 3,090.45
3; It is to mention that, projects/works whose sanction ceiling are approved under ARP for PR/IRQP during FY 2019-20 and 2020-21 but sanction could not be
accorded within 31.03.2021, may be considered for sanction in FY 2021-22 also.
4, It is pertinent to mention here that, from FY 2021-22 onward, booking of expenditure for PR/IRQP works is to be made under NH(Q). Therefore, there is no issue of funds for PR/IRQP works.
5. This issues with the concurrence of Finance Wing vide Note # 348 dated
30.03.2021 and approval of the Secretary (RT&H).
e (L. Behera)
SE (PL) - Il E-mail-planningmorth@gmail.com
To,
1. All Project Zone Chief Engineer 2. All CE-RO/ All SE-RO 3. Director Finance, MoRT&H
Copy for information to: -
1. Sr.PPS to Secretary (RT&H) 2. Sr. PPS to DG(RD)&SS 3. Sr. PPS to AS&FA 4. Sr. PPS/ PPS to all ADGs
Copy to: - NIC with a request to upload on MoRTH website.
top related