Hillsborough CountyAviation Authority

Taxiway J Bridge Replacement

at Tampa International

AirportTraffic Control Sequence

Authority Project Number: 8110 14Date: October 17, 2014

HillsboroughCountyAviationAuthority

Stage 1-Typical Section

INBOUNDPARKWAY

OUTBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

WORK ZONE

Close Taxiway J Demolition of Taxiway J Embankment Build Relocated Bessie Coleman Boulevard

Early February 2015 through Early April 2015

HillsboroughCountyAviationAuthorityStage 1

OUTBOUNDPARKWAY

INBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

TAXIWAY J

Close Taxiway J Demolition of Taxiway J Embankment Build Relocated Bessie Coleman Boulevard

HillsboroughCountyAviationAuthority

Stage 2-Typical Section

BESSIE COLEMANBOULEVARD

WORK ZONE

INBOUNDPARKWAY

OUTBOUNDPARKWAY

Shift Bessie Coleman Traffic; Change to 1-lane Operations

Demolition East Span of Taxiway J Bridge Build Relocated Inbound George Bean Parkway

Early April 2015 through Early May 2015

HillsboroughCountyAviationAuthorityStage 2

TAXIWAY J

OUTBOUNDPARKWAY

INBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

Shift Bessie Coleman Traffic; Change to 1-lane Operations

Demolition - East Span of Taxiway J Bridge Build Relocated Inbound George Bean Parkway

HillsboroughCountyAviationAuthority

Stage 3-Typical Section

INBOUNDPARKWAY

OUTBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

WORK ZONE

Shift Inbound George Bean Parkway Traffic Remove Existing Pier 3 & Span over Existing Inbound Parkway Build Outbound George Bean Parkway and Pier 3

Early May 2015 through Late June 2015

HillsboroughCountyAviationAuthorityStage 3

TAXIWAY J

OUTBOUNDPARKWAY

INBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

Shift Inbound George Bean Parkway Traffic Remove Existing Pier 3 & Span over Existing Inbound Parkway Build Outbound George Bean Parkway and Pier 3

HillsboroughCountyAviationAuthority

Stage 4-Typical Section

INBOUNDPARKWAY

OUTBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

WORK ZONE

Shift Outbound George Bean Parkway Traffic; Reduce to 2-lanes

Demolish Remaining Spans of Taxiway J Bridge Build New Spans for George Bean Parkway

Late June 2015 through Late January 2016

HillsboroughCountyAviationAuthorityStage 4

TAXIWAY J

OUTBOUNDPARKWAY

INBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

Shift Outbound George Bean Parkway Traffic; Reduce to 2-lanes

Demolish Remaining Spans of Taxiway J Bridge Build New Spans for George Bean Parkway

HillsboroughCountyAviationAuthority

Stage 5-Typical Section

OUTBOUNDPARKWAY

INBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

Shift Outbound George Bean Parkway Traffic & Reopen 3rd Lane Shift Inbound George Bean Parkway Traffic Shift Bessie Coleman Boulevard Traffic

Late January 2016 through Mid February 2016

HillsboroughCountyAviationAuthorityStage 5

TAXIWAY J

OUTBOUNDPARKWAY

INBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

Shift Outbound George Bean Parkway Traffic & Reopen 3rd Lane Shift Inbound George Bean Parkway Traffic Shift Bessie Coleman Boulevard Traffic

HillsboroughCountyAviationAuthority

Stage 6-Typical Section

INBOUNDPARKWAY

OUTBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

WORK ZONE

Traffic in Interim Configuration Construct APM Piers & Bessie Coleman Boulevard

(By Others) Complete Taxiway J Bridge and East Approach

Late Mid February 2016 through Mid December 2016

HillsboroughCountyAviationAuthorityStage 6

TAXIWAY J

OUTBOUNDPARKWAY

INBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

Traffic in Interim Configuration Construct APM Piers & Bessie Coleman Boulevard

(By Others) Complete Taxiway J Bridge and East Approach

Hillsborough CountyAviation Authority

Taxiway J Bridge Replacement

at Tampa International

AirportTraffic Control Sequence

Authority Project Number: 8110 14Date: October 17, 2014