hillsborough county aviation authority traffic control sequence authority project number: 8110 14...
DESCRIPTION
HillsboroughCountyAviationAuthorityOUTBOUNDPARKWAY INBOUNDPARKWAY BESSIE COLEMAN BOULEVARD TAXIWAY J Close Taxiway J Demolition of Taxiway J Embankment Build Relocated Bessie Coleman BoulevardTRANSCRIPT
Hillsborough CountyAviation Authority
Taxiway J Bridge Replacement
at Tampa International
AirportTraffic Control Sequence
Authority Project Number: 8110 14Date: October 17, 2014
HillsboroughCountyAviationAuthority
Stage 1-Typical Section
INBOUNDPARKWAY
OUTBOUNDPARKWAY
BESSIE COLEMANBOULEVARD
WORK ZONE
Close Taxiway J Demolition of Taxiway J Embankment Build Relocated Bessie Coleman Boulevard
Early February 2015 through Early April 2015
HillsboroughCountyAviationAuthorityStage 1
OUTBOUNDPARKWAY
INBOUNDPARKWAY
BESSIE COLEMANBOULEVARD
TAXIWAY J
Close Taxiway J Demolition of Taxiway J Embankment Build Relocated Bessie Coleman Boulevard
HillsboroughCountyAviationAuthority
Stage 2-Typical Section
BESSIE COLEMANBOULEVARD
WORK ZONE
INBOUNDPARKWAY
OUTBOUNDPARKWAY
Shift Bessie Coleman Traffic; Change to 1-lane Operations
Demolition East Span of Taxiway J Bridge Build Relocated Inbound George Bean Parkway
Early April 2015 through Early May 2015
HillsboroughCountyAviationAuthorityStage 2
TAXIWAY J
OUTBOUNDPARKWAY
INBOUNDPARKWAY
BESSIE COLEMANBOULEVARD
Shift Bessie Coleman Traffic; Change to 1-lane Operations
Demolition - East Span of Taxiway J Bridge Build Relocated Inbound George Bean Parkway
HillsboroughCountyAviationAuthority
Stage 3-Typical Section
INBOUNDPARKWAY
OUTBOUNDPARKWAY
BESSIE COLEMANBOULEVARD
WORK ZONE
Shift Inbound George Bean Parkway Traffic Remove Existing Pier 3 & Span over Existing Inbound Parkway Build Outbound George Bean Parkway and Pier 3
Early May 2015 through Late June 2015
HillsboroughCountyAviationAuthorityStage 3
TAXIWAY J
OUTBOUNDPARKWAY
INBOUNDPARKWAY
BESSIE COLEMANBOULEVARD
Shift Inbound George Bean Parkway Traffic Remove Existing Pier 3 & Span over Existing Inbound Parkway Build Outbound George Bean Parkway and Pier 3
HillsboroughCountyAviationAuthority
Stage 4-Typical Section
INBOUNDPARKWAY
OUTBOUNDPARKWAY
BESSIE COLEMANBOULEVARD
WORK ZONE
Shift Outbound George Bean Parkway Traffic; Reduce to 2-lanes
Demolish Remaining Spans of Taxiway J Bridge Build New Spans for George Bean Parkway
Late June 2015 through Late January 2016
HillsboroughCountyAviationAuthorityStage 4
TAXIWAY J
OUTBOUNDPARKWAY
INBOUNDPARKWAY
BESSIE COLEMANBOULEVARD
Shift Outbound George Bean Parkway Traffic; Reduce to 2-lanes
Demolish Remaining Spans of Taxiway J Bridge Build New Spans for George Bean Parkway
HillsboroughCountyAviationAuthority
Stage 5-Typical Section
OUTBOUNDPARKWAY
INBOUNDPARKWAY
BESSIE COLEMANBOULEVARD
Shift Outbound George Bean Parkway Traffic & Reopen 3rd Lane Shift Inbound George Bean Parkway Traffic Shift Bessie Coleman Boulevard Traffic
Late January 2016 through Mid February 2016
HillsboroughCountyAviationAuthorityStage 5
TAXIWAY J
OUTBOUNDPARKWAY
INBOUNDPARKWAY
BESSIE COLEMANBOULEVARD
Shift Outbound George Bean Parkway Traffic & Reopen 3rd Lane Shift Inbound George Bean Parkway Traffic Shift Bessie Coleman Boulevard Traffic
HillsboroughCountyAviationAuthority
Stage 6-Typical Section
INBOUNDPARKWAY
OUTBOUNDPARKWAY
BESSIE COLEMANBOULEVARD
WORK ZONE
Traffic in Interim Configuration Construct APM Piers & Bessie Coleman Boulevard
(By Others) Complete Taxiway J Bridge and East Approach
Late Mid February 2016 through Mid December 2016
HillsboroughCountyAviationAuthorityStage 6
TAXIWAY J
OUTBOUNDPARKWAY
INBOUNDPARKWAY
BESSIE COLEMANBOULEVARD
Traffic in Interim Configuration Construct APM Piers & Bessie Coleman Boulevard
(By Others) Complete Taxiway J Bridge and East Approach
Hillsborough CountyAviation Authority
Taxiway J Bridge Replacement
at Tampa International
AirportTraffic Control Sequence
Authority Project Number: 8110 14Date: October 17, 2014
Questions