hillsborough county aviation authority traffic control sequence authority project number: 8110 14...

14
Hillsborough County Aviation Bridge Replacement at Tampa International Airport Traffic Control Sequence Authority Project Number: 8110 14 Date: October 17, 2014

Upload: egbert-gilbert-dixon

Post on 18-Jan-2018

222 views

Category:

Documents


0 download

DESCRIPTION

HillsboroughCountyAviationAuthorityOUTBOUNDPARKWAY INBOUNDPARKWAY BESSIE COLEMAN BOULEVARD TAXIWAY J  Close Taxiway J  Demolition of Taxiway J Embankment  Build Relocated Bessie Coleman Boulevard

TRANSCRIPT

Page 1: Hillsborough County Aviation Authority Traffic Control Sequence Authority Project Number: 8110 14 Date: October 17, 2014

Hillsborough CountyAviation Authority

Taxiway J Bridge Replacement

at Tampa International

AirportTraffic Control Sequence

Authority Project Number: 8110 14Date: October 17, 2014

Page 2: Hillsborough County Aviation Authority Traffic Control Sequence Authority Project Number: 8110 14 Date: October 17, 2014

HillsboroughCountyAviationAuthority

Stage 1-Typical Section

INBOUNDPARKWAY

OUTBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

WORK ZONE

Close Taxiway J Demolition of Taxiway J Embankment Build Relocated Bessie Coleman Boulevard

Early February 2015 through Early April 2015

Page 3: Hillsborough County Aviation Authority Traffic Control Sequence Authority Project Number: 8110 14 Date: October 17, 2014

HillsboroughCountyAviationAuthorityStage 1

OUTBOUNDPARKWAY

INBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

TAXIWAY J

Close Taxiway J Demolition of Taxiway J Embankment Build Relocated Bessie Coleman Boulevard

Page 4: Hillsborough County Aviation Authority Traffic Control Sequence Authority Project Number: 8110 14 Date: October 17, 2014

HillsboroughCountyAviationAuthority

Stage 2-Typical Section

BESSIE COLEMANBOULEVARD

WORK ZONE

INBOUNDPARKWAY

OUTBOUNDPARKWAY

Shift Bessie Coleman Traffic; Change to 1-lane Operations

Demolition East Span of Taxiway J Bridge Build Relocated Inbound George Bean Parkway

Early April 2015 through Early May 2015

Page 5: Hillsborough County Aviation Authority Traffic Control Sequence Authority Project Number: 8110 14 Date: October 17, 2014

HillsboroughCountyAviationAuthorityStage 2

TAXIWAY J

OUTBOUNDPARKWAY

INBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

Shift Bessie Coleman Traffic; Change to 1-lane Operations

Demolition - East Span of Taxiway J Bridge Build Relocated Inbound George Bean Parkway

Page 6: Hillsborough County Aviation Authority Traffic Control Sequence Authority Project Number: 8110 14 Date: October 17, 2014

HillsboroughCountyAviationAuthority

Stage 3-Typical Section

INBOUNDPARKWAY

OUTBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

WORK ZONE

Shift Inbound George Bean Parkway Traffic Remove Existing Pier 3 & Span over Existing Inbound Parkway Build Outbound George Bean Parkway and Pier 3

Early May 2015 through Late June 2015

Page 7: Hillsborough County Aviation Authority Traffic Control Sequence Authority Project Number: 8110 14 Date: October 17, 2014

HillsboroughCountyAviationAuthorityStage 3

TAXIWAY J

OUTBOUNDPARKWAY

INBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

Shift Inbound George Bean Parkway Traffic Remove Existing Pier 3 & Span over Existing Inbound Parkway Build Outbound George Bean Parkway and Pier 3

Page 8: Hillsborough County Aviation Authority Traffic Control Sequence Authority Project Number: 8110 14 Date: October 17, 2014

HillsboroughCountyAviationAuthority

Stage 4-Typical Section

INBOUNDPARKWAY

OUTBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

WORK ZONE

Shift Outbound George Bean Parkway Traffic; Reduce to 2-lanes

Demolish Remaining Spans of Taxiway J Bridge Build New Spans for George Bean Parkway

Late June 2015 through Late January 2016

Page 9: Hillsborough County Aviation Authority Traffic Control Sequence Authority Project Number: 8110 14 Date: October 17, 2014

HillsboroughCountyAviationAuthorityStage 4

TAXIWAY J

OUTBOUNDPARKWAY

INBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

Shift Outbound George Bean Parkway Traffic; Reduce to 2-lanes

Demolish Remaining Spans of Taxiway J Bridge Build New Spans for George Bean Parkway

Page 10: Hillsborough County Aviation Authority Traffic Control Sequence Authority Project Number: 8110 14 Date: October 17, 2014

HillsboroughCountyAviationAuthority

Stage 5-Typical Section

OUTBOUNDPARKWAY

INBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

Shift Outbound George Bean Parkway Traffic & Reopen 3rd Lane Shift Inbound George Bean Parkway Traffic Shift Bessie Coleman Boulevard Traffic

Late January 2016 through Mid February 2016

Page 11: Hillsborough County Aviation Authority Traffic Control Sequence Authority Project Number: 8110 14 Date: October 17, 2014

HillsboroughCountyAviationAuthorityStage 5

TAXIWAY J

OUTBOUNDPARKWAY

INBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

Shift Outbound George Bean Parkway Traffic & Reopen 3rd Lane Shift Inbound George Bean Parkway Traffic Shift Bessie Coleman Boulevard Traffic

Page 12: Hillsborough County Aviation Authority Traffic Control Sequence Authority Project Number: 8110 14 Date: October 17, 2014

HillsboroughCountyAviationAuthority

Stage 6-Typical Section

INBOUNDPARKWAY

OUTBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

WORK ZONE

Traffic in Interim Configuration Construct APM Piers & Bessie Coleman Boulevard

(By Others) Complete Taxiway J Bridge and East Approach

Late Mid February 2016 through Mid December 2016

Page 13: Hillsborough County Aviation Authority Traffic Control Sequence Authority Project Number: 8110 14 Date: October 17, 2014

HillsboroughCountyAviationAuthorityStage 6

TAXIWAY J

OUTBOUNDPARKWAY

INBOUNDPARKWAY

BESSIE COLEMANBOULEVARD

Traffic in Interim Configuration Construct APM Piers & Bessie Coleman Boulevard

(By Others) Complete Taxiway J Bridge and East Approach

Page 14: Hillsborough County Aviation Authority Traffic Control Sequence Authority Project Number: 8110 14 Date: October 17, 2014

Hillsborough CountyAviation Authority

Taxiway J Bridge Replacement

at Tampa International

AirportTraffic Control Sequence

Authority Project Number: 8110 14Date: October 17, 2014

Questions