EGLINTON CROSSTOWN Cedarvale-Forest Hill Construction Liaison Committee February 28, 2018

2

Agenda

• Cedarvale Station Update • Forest Hill Station Update

3

Cedarvale Station Updates

Ongoing • Shoring and traffic deck installation on the south side of Eglinton • Backfill of crossover section

Upcoming • Water main relocation on Eglinton Avenue West at Allen Road North • Water main relocation on Marlee Avenue and laneway north of Eglinton

Avenue between Marlee and Fairleigh – 8-10 weeks; 5-6 weeks occupying a lane on Marlee

• Allen Road South utility relocation – New sewer main – Confirmed weekend closure (midnight Friday – 5am Monday) of the Allen for March 17/18

• Stage 2 shoring on the north side of Eglinton Ave – South Allen Road realignment – Planning a weekend closure (midnight Friday – 5am Monday) of the Allen planned for March

24/25, April 7/8, or April 14/15

4

Cedarvale Station Shoring Stage 2 – 2018

5

Marlee Water Main Works

6

Construction Progress Picture Final pour at east

entrance

7

Construction Progress Picture

Shoring at Everden Road

8

Construction Progress Picture

Backfill at the crossover

Forest Hill Construction Updates

Forest Hill Station Update

ACTIVITY LOCATION APPROXIMATE DURATION

WINTER & SPRING 2018

Support of Excavation – SW Station Box Eglinton Ave W, west of Bathurst St Ongoing through June 2018

Support of Excavation – SE Station Box Eglinton Ave W, east of Bathurst St Ongoing through fall 2018

Wet Utilities Relocation Bathurst St and Eglinton Ave W Ongoing through 2018

Support of Excavation – Main Entrance Northwest corner of Bathurst St and Eglinton Ave W Week of Feb 5 through May 2018

Roof Slab Pour – SW Station Box

Eglinton Ave W, west of Bathurst St Southbound curb lane on Bathurst St, south of Eglinton Ave W

March 3, 2018

Traffic Change – Temporary Bridge Works See map March 8, 2018 (overnight)

Traffic Change – Support of Excavation See map Late April 2018

Road Reinstatement Works – SW Station Box: Eglinton Ave W, west of Bathurst St April through June 2018

Roof Slab Pour – March 3

• Saturday March 3, 2018

beginning at 7:00 a.m.

• Southbound curb lane

south of Eglinton Ave W will

be occupied for concrete

truck staging

• Concrete trucks will exit site

from Peveril Hill

TRUCK EGRESS

Current Construction Staging

Week of February 5 to March 8, 2018

Upcoming Traffic Staging March 8, 2018 through Late April 2018 Activities: Support of Excavation, Temporary Bridge Works & Wet Utilities

Upcoming Traffic Staging Late April 2018 to June 2018 Activities: Support of Excavation, Road Reinstatement & Wet Utilities

15

Forest Hill Station Construction Progress

15

SOUTHWEST STATION BOX AREA

16

Forest Hill Station Construction Progress

16

MAIN ENTRANCE PILING

17

Forest Hill Station Construction Progress

17

SHORING BOX FOR WET UTILITIES

18

Forest Hill Station Construction Progress

SHORING BOX FOR WET UTILITIES

19

Forest Hill Station Concept Aerial View

Main Entrance

Secondary Entrance

*60% rendering