alternative project delivery

18
Alternative project delivery Gastonia’s experience with CMAR Presented by: Rusty Bost, City of Gastonia Keith Garbrick, LaBella Associates

Upload: others

Post on 24-Apr-2022

10 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Alternative project delivery

Alternative project deliveryGastonia’s experience with CMAR

Presented by:Rusty Bost, City of Gastonia

Keith Garbrick, LaBella Associates

Page 2: Alternative project delivery

When we Last met…

Page 3: Alternative project delivery

presentation preview:

• Review of the basics for how CMAR works, governing statutes and legal requirements.

• The City of Gastonia’s Water Treatment Plant, basics of the project into lessons learned

• Up Next: FUSE (Franklin Urban Sports and Entertainment) project.

Page 4: Alternative project delivery

Construction manager

at risk (cmar)

• Construction Manager is chosen by qualifications

• CMAR becomes part of the design team and provides Value Engineering input and estimates based on progress drawings (30%, 60% and 90%).

• CMAR provides owners with a Guaranteed Maximum Price (GMP)

• CMAR cannot self perform work*

Page 5: Alternative project delivery

Governing statutes

• NC General Statute §143-128, October 1, 2014• Allows Construction Manager At Risk• Municipality has to have “concluded that Construction

Management at Risk service is in the best interest of the project” and have to have compared to other delivery methods.

• NC General Statute §143-135.8, October 1, 2014 • Allows prequalification of subcontractors

Page 6: Alternative project delivery

Selecting a construction manager at risk

• Qualifications Based Selection – Standard RFQ process for Professional Services

• RFQ Suggestions:• Litigation History• GMP vs Actual cost history (possible payback)• Bonding Capacity and grade of Bonding Agency• Page limits are a must

• Short List Interview Suggestions:• Time Limit• Bring the Superintendent• Limit number of representatives from applicant

Page 7: Alternative project delivery

Construction manager

At risk contract

• Single contract for pre-construction services, with GMP added later.

• Separate contracts for Preconstruction Services and Construction.

Page 8: Alternative project delivery

Construction manager

At risk fees

• Preconstruction Services• 0.25% per pricing exercise or 1% of the cost of work

• General Conditions• Includes costs associated with the project team - (Senior Project

Manager, Superintendent, etc.)• Includes items required to administer the project -(job trailer,

storage trailer, etc.)• Typically 8% of the cost of work

Page 9: Alternative project delivery

Construction manager

At risk fees

• Construction Fee• Typically in the range of 2.5% to 3%• Includes profit and home office overhead (including the Project

Executive, Accounting, etc.)

• Contingencies• Preconstruction: Team Decision• Construction Contingency: 3%

• Bonds and Insurance• Typically 2% of the cost of work (P&P Bond/GL Insurance/Builders

Risk)

Page 10: Alternative project delivery

pre-Construction

services

• Value Engineering • CMAR Provides estimates at 30%, 60%

and 90%• Constructability review/input• Materials/equipment reviews, field trips

to other facilities• Possible early bid package for long lead

items

Page 11: Alternative project delivery

Construction

• CMAR cannot self perform

• All work is still competitively bid to “1st Tier Subcontractors”

• The CMAR has to prequalify all 1st Tier Subs • Minimum score method,

with points awarded for experience, bonding capacity, references, staffing, etc.

• Changes in work – Two separate contingencies• Contractors contingency –

carried by CMAR in the GMP • Owners contingency – can

be carried separately• A CMAR is still a contractor • At close out, CMAR carries the

warranty. The subs may have to come back to repair/finish items; however, it is the CMAR’s responsibility.

Page 12: Alternative project delivery

Close out

• Water Treatment Plant: Was under operation during the entire project, and was a phased approach with Temporary CO’s being issued for parts throughout the project.

• CMAR may help with “Soft Openings”

Page 13: Alternative project delivery

Gastonia case

studies

• Water Treatment Plant Renovations• New 5 m.g. clearwell• Membrane treatment of

surface water• $56 million dollar upgrade• Very limited site (in

downtown)

Page 14: Alternative project delivery

Gastonia case

studies

• FUSE (Franklin Urban Sport & Entertainment) District• $15 Million economic

development investment• Surrounding private

redevelopment• Lots of public attention

Page 15: Alternative project delivery

Contingency funds

• Gastonia (WTP) elected to not encumber an owners contingency within the GMP. Funds were held within existing enterprise fund accounts

• Contractors Contingency was established within the GMP for “Scope Gap”, used by the contractor with our advise, but not consent

• Split savings as motivator

Page 16: Alternative project delivery

Expect the unexpected

• Union issues with 3rd tier subcontractor (you never know what will make the news)

• Claims from subcontractors –City’s risk (or CMAR)?

• Quality of Work – how do issues get resolved?

• Responsiveness to schedule, and total cost to municipality

Page 17: Alternative project delivery

Would we use cmar again?

• Team building and buy in

• Off ramp – if GMP negotiations aren’t working out, you still have options.

• Certainty of pricing – open book.

• Pre construction services.

Page 18: Alternative project delivery

The future of cmar

• Owners going to design build, time = money, time savings (due to current market, general conditions cost)

• Changes to statutes – self performing (where subs works needs correcting)