albert bridge presentation hyder consulting
DESCRIPTION
Bridge DesignTRANSCRIPT
© Hyder Consulting (UK) Limited
Hyder Involvement
• Review of original assessment methodology
• Ascertain and confirm as built details
• Determine the likely construction sequence and
the impact this might have on built in stresses
• Carry out a 3D Non-Linear Analysis
• Carry out local checks of the deck elements
• Develop strengthening options to bring the bridge
up to 7.5T
• Identify essential maintenance requirements.
© Hyder Consulting (UK) Limited
Albert Bridge Construction
• As new neighbourhoods evolved, desire to get to Battersea Park.
• Idea originated by Prince Albert – hence the Name. Albert Bridge Company formed in 1864.
• Mr R M Ordish prepared a design based on a similar award winning bridge over the river Moldan in Prague.
• Nothing happened for a few years, as opposition from the Chelsea Bridge operators as they feared they would loose toll revenue.
• A Captain Roberts subsequently came up with a new alternative design, which was light and cheap. This was initially accepted by the directors.
• The Bill proposed in 1870, but there were major shortcomings in Roberts design.
• Bill was finally accepted with the unusual procedure of naming Mr Ordish to be designer. The Bridge was completed in 1877.
© Hyder Consulting (UK) Limited
Albert Bridge Construction
• Unfortunately The directors had previously
purchased Rope for the Captain Roberts
design, which Ordish despite his objection had
to use.
• Furthermore – the rope was made of parallel
wires, and banded at 7ft centres, but not
wrapped – as ‘was an expensive operation’.
© Hyder Consulting (UK) Limited
Albert Bridge Construction
• Consequently corrosion took place soon after construction, and in 1885 tenders were sought to replace the cable with chain links as Ordish had initially requested during the construction.
• Replacement of the wire rope with steel chain system was under the instruction of Sir Joseph Bazalgette
© Hyder Consulting (UK) Limited
History
• From 1906 to 1970 various committees and reports suggested the Bridge suffered from excessive movement and further works were required.
• Restricted to 2 tonne vehicles since 1960’s.
• 1972 remedial works were undertaken includingthe addition of a central pier
• Only bridge in central London not to have beenreplaced
© Hyder Consulting (UK) Limited
Suspension Saddle Bearings
• The Saddle Bearings were designed to equalise stresses in the
catenary and radial bars either side of the towers.
© Hyder Consulting (UK) Limited
Pre-Assessment Investigation
• Archive drawings discovered in the basement of
the ICE
• Publications and Engineering articles from the day
including sketches illustrating the temporary
works
• Historical records including previous inspection
and assessment reports
• Site Inspections and surveys
© Hyder Consulting (UK) Limited
Rocker Bearing Restraints
• Rocker provides
negligible longitudinal
restraint.
• Horizontal forces in the
catenary chain are
resisted directly by the
longitudinal deck
girders.
• Live loading of the
central span results in
siginificant axial loads
in the deck.
© Hyder Consulting (UK) Limited
3D Analysis Objectives
• Estimate the likely development of built in
stresses during construction sequence.
• Determine whether the structure was sensitive
to geometric non-linearities.
• Carry out sensitivity analysis on New Central
Pier.
• Investigate Transfer of forces through hybrid
suspension system.
© Hyder Consulting (UK) Limited
Construction Loads
• Superstructure was fully supported on temporary props.
• Suspension bars were also supported in order to maintain a straight profile.
• Dead loads were released following connection of the suspension elements.
• The substantial radial bars provided a direct support to the deck.
• Deck deflections following the removal of the temporary props are kept to a minimum.
© Hyder Consulting (UK) Limited
Typical Deck Section
Douglas Fir
Jarrah Boarding
Douglas Fir
Timber Decking
© Hyder Consulting (UK) Limited
Strengthening Requirements
• Corroded Cross Girder elements to be replaced in
order to restore adequate capacity
© Hyder Consulting (UK) Limited
Strengthening Requirements
• Longitudinal Girders to receive localised
strengthening/ repairs where necessary in the form of
additional plates on the top and bottom flanges
© Hyder Consulting (UK) Limited
Deck Timbers
• Footway Timbers to be strengthened with an additional support in order to resist Accidental Wheel Loading.
© Hyder Consulting (UK) Limited
Refurbishment Works
• Rotting Deck Timbers to be replaced where necessary
• Waterproofing and Drainage System to be renovated and improved in order to prevent further deterioration of the under deck elements
• Repainting Structure
• Bearings deck supports to be renovated
• New Lighting System
© Hyder Consulting (UK) Limited
Conclusion
• We have found during our analysis that due to the construction and form of the Albert Bridge it is not sensitive to geometric non linearities.
• A rigorous review and analysis has meant that strengthening requirements have been minimised and better placed.
• Refined analysis of the U-Frame behaviour was key in identifying residual capacity.
• We are presently finalising our analysis to identify areas that require strengthening.
• Contract to strengthen and refurbish the bridge to be let at the end of the year.
• Completion by Olympics 2012