albert bridge presentation hyder consulting

36
© Hyder Consulting (UK) Limited Albert Bridge Phil Bailey and Adam Smith

Upload: jessica-lee

Post on 06-Dec-2015

221 views

Category:

Documents


1 download

DESCRIPTION

Bridge Design

TRANSCRIPT

© Hyder Consulting (UK) Limited

Albert Bridge

Phil Bailey and Adam Smith

© Hyder Consulting (UK) Limited

Albert Bridge

© Hyder Consulting (UK) Limited

Hyder Involvement

• Review of original assessment methodology

• Ascertain and confirm as built details

• Determine the likely construction sequence and

the impact this might have on built in stresses

• Carry out a 3D Non-Linear Analysis

• Carry out local checks of the deck elements

• Develop strengthening options to bring the bridge

up to 7.5T

• Identify essential maintenance requirements.

© Hyder Consulting (UK) Limited

Albert Bridge Construction

• As new neighbourhoods evolved, desire to get to Battersea Park.

• Idea originated by Prince Albert – hence the Name. Albert Bridge Company formed in 1864.

• Mr R M Ordish prepared a design based on a similar award winning bridge over the river Moldan in Prague.

• Nothing happened for a few years, as opposition from the Chelsea Bridge operators as they feared they would loose toll revenue.

• A Captain Roberts subsequently came up with a new alternative design, which was light and cheap. This was initially accepted by the directors.

• The Bill proposed in 1870, but there were major shortcomings in Roberts design.

• Bill was finally accepted with the unusual procedure of naming Mr Ordish to be designer. The Bridge was completed in 1877.

© Hyder Consulting (UK) Limited

Albert Bridge Construction

• Unfortunately The directors had previously

purchased Rope for the Captain Roberts

design, which Ordish despite his objection had

to use.

• Furthermore – the rope was made of parallel

wires, and banded at 7ft centres, but not

wrapped – as ‘was an expensive operation’.

© Hyder Consulting (UK) Limited

Franz Joseph Bridge - Prague

© Hyder Consulting (UK) Limited

Temporary Works

being erected

© Hyder Consulting (UK) Limited

Illustration of Temporary Works

© Hyder Consulting (UK) Limited

Albert Bridge Construction

• Consequently corrosion took place soon after construction, and in 1885 tenders were sought to replace the cable with chain links as Ordish had initially requested during the construction.

• Replacement of the wire rope with steel chain system was under the instruction of Sir Joseph Bazalgette

© Hyder Consulting (UK) Limited

Albert Bridge Construction

© Hyder Consulting (UK) Limited

History

• From 1906 to 1970 various committees and reports suggested the Bridge suffered from excessive movement and further works were required.

• Restricted to 2 tonne vehicles since 1960’s.

• 1972 remedial works were undertaken includingthe addition of a central pier

• Only bridge in central London not to have beenreplaced

© Hyder Consulting (UK) Limited

Albert Bridge Today

© Hyder Consulting (UK) Limited

© Hyder Consulting (UK) Limited

New Central Pier

© Hyder Consulting (UK) Limited

Suspension Saddle Bearings

• The Saddle Bearings were designed to equalise stresses in the

catenary and radial bars either side of the towers.

© Hyder Consulting (UK) Limited

Pre-Assessment Investigation

• Archive drawings discovered in the basement of

the ICE

• Publications and Engineering articles from the day

including sketches illustrating the temporary

works

• Historical records including previous inspection

and assessment reports

• Site Inspections and surveys

© Hyder Consulting (UK) Limited

Comparisson of Historical As-Built

and Recent Survey

© Hyder Consulting (UK) Limited

Rocker Bearing Restraints

• Rocker provides

negligible longitudinal

restraint.

• Horizontal forces in the

catenary chain are

resisted directly by the

longitudinal deck

girders.

• Live loading of the

central span results in

siginificant axial loads

in the deck.

© Hyder Consulting (UK) Limited

3D Analysis Objectives

• Estimate the likely development of built in

stresses during construction sequence.

• Determine whether the structure was sensitive

to geometric non-linearities.

• Carry out sensitivity analysis on New Central

Pier.

• Investigate Transfer of forces through hybrid

suspension system.

© Hyder Consulting (UK) Limited

MIDAS Model

© Hyder Consulting (UK) Limited

Model Detail

© Hyder Consulting (UK) Limited

Construction Loads

• Superstructure was fully supported on temporary props.

• Suspension bars were also supported in order to maintain a straight profile.

• Dead loads were released following connection of the suspension elements.

• The substantial radial bars provided a direct support to the deck.

• Deck deflections following the removal of the temporary props are kept to a minimum.

© Hyder Consulting (UK) Limited

No Central Pier

© Hyder Consulting (UK) Limited

Central Pier with Preload in Bearings

© Hyder Consulting (UK) Limited

Typical Live Load

© Hyder Consulting (UK) Limited

Saddle Bearings

© Hyder Consulting (UK) Limited

Special Inspection

© Hyder Consulting (UK) Limited

Typical Deck Section

Douglas Fir

Jarrah Boarding

Douglas Fir

Timber Decking

© Hyder Consulting (UK) Limited

Deck Soffit

© Hyder Consulting (UK) Limited

Buckling Analysis

© Hyder Consulting (UK) Limited

Strengthening Requirements

• Corroded Cross Girder elements to be replaced in

order to restore adequate capacity

© Hyder Consulting (UK) Limited

Strengthening Requirements

• Longitudinal Girders to receive localised

strengthening/ repairs where necessary in the form of

additional plates on the top and bottom flanges

© Hyder Consulting (UK) Limited

Deck Timbers

• Footway Timbers to be strengthened with an additional support in order to resist Accidental Wheel Loading.

© Hyder Consulting (UK) Limited

Refurbishment Works

• Rotting Deck Timbers to be replaced where necessary

• Waterproofing and Drainage System to be renovated and improved in order to prevent further deterioration of the under deck elements

• Repainting Structure

• Bearings deck supports to be renovated

• New Lighting System

© Hyder Consulting (UK) Limited

Conclusion

• We have found during our analysis that due to the construction and form of the Albert Bridge it is not sensitive to geometric non linearities.

• A rigorous review and analysis has meant that strengthening requirements have been minimised and better placed.

• Refined analysis of the U-Frame behaviour was key in identifying residual capacity.

• We are presently finalising our analysis to identify areas that require strengthening.

• Contract to strengthen and refurbish the bridge to be let at the end of the year.

• Completion by Olympics 2012

© Hyder Consulting (UK) Limited