addendum no. 2 to the project manual and drawings …
TRANSCRIPT
Kenosha County KCDC Rooftop Equipment Replacement Phase 1 Addendum No. 2
Clark Dietz, Inc. – K0450060 Page - 1
ADDENDUM NO. 2 TO THE PROJECT MANUAL AND DRAWINGS FOR: County of Kenosha KCDC Rooftop Equipment Replacement Project Phase 1 Bid #2111 Clark Dietz Project No. K0450060 DATED: May 26, 2021 PREPARED BY: CLARK DIETZ, INC. _____________________________________________________________________________________________ Note: This Addendum is hereby declared a part of the Contract Documents for the project designated above
and in case of conflict, the following Addendum shall govern. Bidders shall state in their Bid Form that this Addendum has been received and is reflected in the Bid submitted.
_____________________________________________________________________________________________ PROJECT MANUAL
1. Section 01 30 00 Administrative Requirements, Add: 3.3 Additional Requirements
A. 1 rooftop unit to be replaced at a time. Allow for 3 weeks of construction per unit. Awarded contractor to coordinate final sequencing of work with owner.
B. Requirements per area 1. GYM – Site will be unoccupied during construction. Additional protection not required. 2. MEDICAL/ADMISSION – Site will be occupied during building normal occupied hours.
Additional protection not required. 3. KITCHEN – Site will be occupied during building normal occupied hours. Provide zip
wall dust barrier during construction. 4. DINING – Site will be unoccupied during construction. Additional protection not
required. 5. MAINTENANCE – Site will be unoccupied during construction. Additional protection
not required. 6. LAUNDRY – Site will be occupied during building normal occupied hours. Additional
protection not required. 7. DORMITORY D – Site will be unoccupied during construction. Additional protection not
required. 2. Section 23 34 00 HVAC Fans, 2.3 Energy Recover Ventilator, A. Manufacturers: add Loren Cook
Company. 3. Section 23 74 13 Packaged Outdoor Central Station Air-handling Units:
• Revise paragraph 2.2.I. to “Furnish structure to brace casings for suction pressure of 2.5 inch wg, and shall not exceed 0.0042 per inch of panel span (L/240).”
• Add: 2.2 CASING
J. Air Leakage: Casing air leakage shall not exceed leak class 6 (CL = 6) per ASHRAE 111 at specified casing pressure, where maximum casing leakage (cfm/100 ft2 of casing surface area) = CL X P0.65. Air leakage shall be determined at 1.00 times maximum casing static pressure up to 8 inches w.g. Specified air leakage shall be accomplished without the use of caulk. Total estimated air leakage shall be reported for each unit in CFM, as a percentage of supply air, and as an ASHRAE 111 Leakage Class.
• Revise paragraph 2.3.G. to “Fan Modulation: Variable Frequency Drive or ECM per fan.”
4. Section 23 81 07 Packaged Rooftop Units – Medium Capacity:
• Revise paragraph E.6. to “Each Direct Drive Fan shall have its own VFD or dual ECM fans. If one fan motors goes down, second fan continues operation to provide partial capacity.”
Kenosha County KCDC Rooftop Equipment Replacement Phase 1 Addendum No. 2
Clark Dietz, Inc. – K0450060 Page - 2
• Add: 2.1 PACKAGED ROOFTOP AIR CONDITIONING UNITS, E. SUPPLY FANS
7. Factory-provided automatic backdraft damper per fan
• Revise paragraph F.6. to “ECM for each fan to be provided or variable frequency drives shall be factory wired and mounted in the unit. Fan motors shall be premium efficiency.”
• Add: 2.1 PACKAGED ROOFTOP AIR CONDITIONING UNITS, F. EXHAUST FANS
8. Factory-provided automatic backdraft damper per fan
5. Section 23 81 07 Packaged Rooftop Units – Medium Capacity:
• Revise paragraph E.2. to “Designed to meet the wind load rating per IBC 2017 Chapter 15.”
• Revise paragraph P.5 to “Ventilation Override (RTU 04-1 & 04-2 only): Factory installed. Binary input from independent fire or life safety panel causes unit to override standard operation and assumes one of two factory preset ventilation sequences - purge or pressurization.
DRAWINGS
1. Replace S1.01 with the attached. 2. Replace H4.01 with the attached. 3. Sheet H5.03, Detail 1 ROOFTOP UNIT SCHEMATIC:
a. Replace RETURN FAN references to EXHAUST FAN throughout details and sequence of operation.
4. Sheet H5.05, Detail 1 ROOFTOP UNIT SCHEMATIC: a. Replace RETURN FAN references to EXHAUST FAN throughout details and sequence of
operation. 5. Sheet H5.06, Detail 1 & 2 ROOFTOP UNIT SCHEMATIC:
a. Replace RETURN FAN references to EXHAUST FAN throughout details and sequence of operation.
6. Sheet E0.01, Electrical General Notes:
a. Add Note 11: CONTRACTOR SHALL INCLUDE THE FOLLOWING SCOPE OF WORK IN THEIR BIDS. REVIEW CONDITIONS AND OPERATIONS OF EXISTING SMOKE DAMPERS. ENSURE THESE DAMPERS ARE SUBMITTING SIGNALS TO FIRE ALARM PANELS. DAMPERS SHALL BE POWERED OPEN UNDER NORMAL OPERATING CONDITIONS AND ALLOWED TO CLOSE (NORMAL POSITION) DURING ALARM CONDITION.
7. Replace E5.01 with the attached. 8. Sheet H5.07:
a. Replace sequences for Firefighter Smoke control panel with the following: SMOKE CONTROL SYSTEM AND FIREFIGHTER SMOKE CONTROL STATION (FSCS)
1. Smoke Control System and FSCS shall be provided by the BAS vendor and shall be listed in
accordance with ANSI/UL 864. This single control system shall coordinate the control functions,
specified herein, for the fire alarm system and FSCS. Smoke Control System shall comply with the
requirements of NFPA 92, UL Category UUKL, and applicable IBC, as specified herein. FSCS shall
replace the existing FSCS in the same location. FSCS shall override all other controls.
2. The FSCS shall have:
a. Panel Power ON LED light.
b. Panel enable key switch.
3. The FSCS shall be easily recognized graphics that include:
a. Building Floor Plan with color coded areas for each Smoke Control Zone.
b. Switches located in matching color coded blocks corresponding to each Smoke Control Zone.
c. Indicate direction of airflow and relationship of components.
4. Each Smoke Control color coded block shall have:
a. Fans:
i. Fan control switches and LEDs for fan status (On/Off/Auto). Status shall be
determined by duct pressure sensors.
ii. Fault LEDs for failures.
Kenosha County KCDC Rooftop Equipment Replacement Phase 1 Addendum No. 2
Clark Dietz, Inc. – K0450060 Page - 3
iii. Push buttons for lamp test.
b. Motorized Dampers:
i. Damper control switches and LEDs for damper status (Open/Closed/Auto). Status
shall be determined by damper end switches.
ii. Fault LEDs for failures.
iii. Push buttons for lamp test.
5. The panel shall have two (2) color block areas for Smoke Control Zones D-North and Smoke Control
Zone D-South.
6. Panel shall have audible alarm for all fault conditions and key switch to silence alarms. Alarm shall be
active if fans and dampers exceed response time.
7. LED lights shall be color coded as required by applicable code.
8. BAS vendor shall provide interconnection wiring to perform the specified functions. Panel face shall
graphically show the building floor plan and equipment locations.
9. FSCS shall allow responding firefighters to control operation of the Smoke Control Systems equipment
and override normal and automatic functions.
10. FSCs shall have the following functions:
a. RTU 04-1 (OFF-POSITIVE PRESSURE-AUTO selector switch, and proof of air flow)
b. SEF 04-1 (OFF-SMOKE EVACUATION-AUTO selector switch, and proof of air flow)
c. RTU 04-2 (OFF-POSITIVE PRESSURE-AUTO selector switch, and proof of air flow)
d. SEF 04-2 (OFF-SMOKE EVACUATION-AUTO selector switch, and proof of air flow)
11. Firefighter strategy to control smoke is to run SEFs to remove smoke, run associated RTU in override
mode to provide make-up air, and run adjacent RTU in override to provide positive pressure in
adjacent Smoke Zone. Adjacent zones are D-North and D-South.
12. FSCS shall override all other controls.
SEF 04-1/ RTU 04-1 and SEF 04-2/RTU 04-2 (Smoke Evacuation/Make-up Fans)
1. The owner’s proprietary BAS vendor shall provide hardwired ANSI/UL 864 controllers to provide
control functions as specified herein to comply with the requirements of NFPA 92.
Sequence of Operation 1. RTU 04-1 and RTU 04-2 shall be provided with manufacturer’s Ventilation Control Override. Owner’s
proprietary BAS vendor shall provide ANSI/UL 864 controllers to provide control functions as specified.
2. Normal Mode:
a. SEF Fans shall remain off and gravity and motorized backdraft damper shall be closed.
b. RTU 04-1 and 04-2 shall operate as specified.
3. Auto Smoke Mode:
a. Any of the duct mounted smoke detectors in each Smoke Control Zone (D-North and D-South)
shall generate one signal, per zone, thru the Fire Alarm System to start the SEF for that
Smoke Control Zone and allow gravity backdraft damper to open. The RTU control shall be
overridden and the supply fans shall run and OA damper shall open as directed by the Smoke
Control System. Override shall close RA and EA dampers shall remain closed and shut down
ERV.
b. The supply fans in the RTU of the adjacent Smoke Control Zone fans shall run and OA damper
shall open as directed by the Smoke Control System. Override shall close RA and EA dampers
shall remain closed and shut down ERV.
4. Firefighter Override at FSCS – responding Firefighters shall be able to select the following:
a. OFF selections shall stop fans and close dampers.
b. SMOKE EVACUATION selection shall start SEF, and gravity backdraft damper shall open. SSF
shall start and motorized damper shall open. Feedback shall be provided to the FSCS from
the fans.
c. AUTO – Fans shall return to Normal/Auto Smoke Mode.
d. Smoke Control Zone will be unoccupied until new HVAC equipment and Smoke Control
System is operational and tested.
Kenosha County KCDC Rooftop Equipment Replacement Phase 1 Addendum No. 2
Clark Dietz, Inc. – K0450060 Page - 4
ATTACHMENTS
1. Drawing sheets – S1.01, H4.01, E5.01 2. Bidder RFIs and responses. 3. Rooftop equipment – Existing photos. See file link below.
DISCLAIMER: Clark Dietz makes no warranty, expressed or implied, regarding the contents of the images contained herein. These images are not part of the bidding documents. They are provided to bidders for reference only. They shall be used at the bidders own risk. These images were recorded at various points in time and may, or may not, reflect the actual conditions at this time.
View the Transfer in Newforma Project Center
Additional links:
Download all associated files
Project
Name:
Kenosha County - KCDC Roof Equipment
Project
Number:
K0450060
Subject: Existing Equipment Photos
Sent via: Info Exchange
Expiration
Date:
6/17/2021
D
E
F
G
H
A
B
C
2345
J
K
L
3.75 3.25
HV 02-1
KSU 02-3
KSU 02-4
KSU 02-7
KSU 02-01
KSU 02-2
RACU 01-1
RACU 02-1
NOTE: DIMENSIONAL DATA IS TO BE OBTAINED BY SCALING ANY PORTION OF THIS DRAWING
PROJECT No.
DRAWING No.
PR
OJE
CT
T
IT
LE
DR
AW
IN
G T
IT
LE
10
10
5
6th
S
tre
et
Ke
no
sh
a, W
I 5
31
40
C:\U
se
rs\m
be
hre
ns\D
ocu
me
nts\K
04
50
05
0,6
0_
Ce
ntra
l_
20
19
_M
Be
hre
ns.rvt
4/2
7/2
02
1 1
2:1
3:0
1 P
M
S1.01
K0450060
RO
OF
JO
IS
T
ST
RE
NG
TH
EN
IN
G P
LA
N
KC
DC
R
OO
FT
OP
EQ
UIP
ME
NT
R
EP
LA
CE
ME
NT
PR
OJE
CT
P
HA
SE
I
DESIGNED : SMM
DRAWN BY : SMM
CHECKED BY : - - -
PH
ON
E : 2
62
.6
57
.1
55
0 w
ww
.cla
rkd
ie
tz.co
m
DATE CHECKED : - - -
Ke
no
sh
a, W
I 5
31
40
62
5 5
7th
S
tre
et, 6
th
F
lo
or
NO. DATE REVISION
1 04/28/21 ISSUED FOR BID
16K2
16K2
16K2
26K10
26K10
26K10
26K1026K10
26K10
26K10
26K12
26K12
26K12
16K4
16K4
16K4
16K4
W12x14
16K2
16K2
26K10
26K10
26K10
26K10
26K10
26K12
26K12
26K12
26K10
L / 2 L / 2
L = LENGTH
(1) OR (2) REINFORCING BARS,
SEE SCHEDULE FOR OPTIONS
CL JOIST
4
TYP EA.
END
2
TYP AT EACH
PANEL POINT
0 4' 8' 16' 32'
SCALE 1/16" = 1'
PARTIAL ROOF FRAMING PLAN
1
16K2 OR
26K10 JOIST
(1) OR (2) REINFORCING
BARS, SEE SCHEDULE
FOR OPTIONS
NOT TO SCALE
JOIST ELEVATION
2
NOT TO SCALE
JOIST SECTION
A
24'-0" (16K2) OR 48'-0" (26K10)
48'-0"24'-0"48'-0"
24'-0"
24'-0"
24'-0"
24'-0"
24'-0"
24'-0"
24'-0"
36'-0"
24'-0"
24'-0"
8'-0"
8'-0"
8'-0"
8'-0"
4'-0"
4'-0"
4'-0"
20'-0"
4
N.T.S.
KEYPLAN
KEYNOTE
JOIST
TYPE
REBAR
SIZE
BAR
LENGTH
116K2 #4 1 10'-0"
216K2 #41 13'-0"
316K2 #4 1 6'-0"
426K10 #51 27'-0"
5#41 15'-0"
6#51 24'-0"
26K10
26K10
JOIST STRENGTHENING SCHEDULE
NO. OF
JOISTS
1
1
1
5
2
1
1. ALL DETAILS AND SECTIONS SHOWN ON THIS SHEET ARE TYPICAL AND SHALL BE USED
WHEREVER A SIMILAR CONDITION OCCURS UNLESS NOTED OTHERWISE.
2. CONTRACTOR SHALL FIELD VERIFY ALL EXISTING DIMENSIONS AND CONDITIONS.
CONTRACTOR SHALL REPORT ANY DISCREPANCIES TO THE ENGINEER.
3. DAMAGE TO ADJACENT FACILITIES DURING CONSTRUCTION SHALL BE REPAIRED AT NO
ADDITIONAL COST TO THE OWNER.
4. CONTRACTOR SHALL REMOVE AND RESTORE CEILING MATERIAL AS NECESSARY TO GAIN
ACCESS AND PERFORM WORK. CONTRACTOR SHALL COORDINATE WORK WITH OTHER
TRADES. SEE MECHANICAL AND ELECTRICAL DRAWINGS.
5. STRENGTHENING STEEL JOISTS SHALL ONLY BE PERFORMED WHEN THE ROOF JOISTS
ARE NOT SUPPORTING SNOW AND BEFORE NEW ROOF TOP MECHANICAL EQUIPMENT IS
INSTALLED.
6. IF WORK MUST BE PERFORMED WITH SNOW ON THE ROOF OR WITH SIGNIFICANT
CONSTRUCTION LOADS, TEMPORARILY SUPPORT THE JOISTS AS DIRECTED BY A
WISCONSIN LICENSED PROFESSIONAL ENGINEER.
7. CONCRETE DEFORMED REINFORCING BARS USED TO STRENGTHEN THE JOISTS SHALL BE
ACCORDING TO ASTM A706 WITH MINIMUM YIELD STRENGTH OF 60 KSI.
8. A36 OR A572 STEEL PLATES AND BARS MAY BE USED AS SUBSTITUTE FOR REINFORCING
BARS WITH THE APPROVAL OF THE ENGINEER. THE BARS SHALL HAVE AN AREA PER UNIT
LENGTH THE SAME OR EXCEEDING THAT OF THE REINFORCING BARS.
9. WELDED CONNECTIONS SHALL BE IN ACCORDANCE WITH THE LATEST EDITION OF
ANSI/AWS D1.1 STRUCTURAL WELDING CODE, MADE WITH E70XX ELECTRODES AND
PERFORMED BY CERTIFIED WELDERS.
10. ALL SURFACES OF EXISTING BASE METAL IN CONTACT WITH NEW BASE METAL SHALL BE
CLEANED OF ALL DIRT, RUST, AND OTHER FOREIGN MATTER EXCEPT ADHERENT PAINT.
SURFACES TO BE WELDED SHALL BE THOROUGHLY CLEANED OF ALL FOREIGN MATTER.
11. STEEL ANGLE FRAMES SHALL BE SHOP PRIMED.
12. AFTER WELDS ARE COMPLETE APPLY A COAT OF PRIMER TO WELDED AREAS.
13. REPAIR EXISTING ROOF AFTER FRAME INSTALLATION.
14. CONTRACTOR SHALL REVIEW CONDITION AND ARRANGEMENT OF EXISTING STRUCTURAL
ELEMENTS TO ENSURE MODIFICATIONS MADE DO NOT REQUIRE REMOVAL/REPLACEMENT
OF ANY EXISTING CONDUITS, WIRES, DUCTWORK, PIPING, ACCESSORIES, OR LIGHT
FIXTURES. ANY MODIFICATIONS REQUIRED TO AUXILIARY SYSTEMS SHALL BE
COMMUNICATED TO OWNER/ENGINEER PRIOR TO COMMENCING ANY WORK.
NOTES (THIS SHEET)
TYP
TEMPORARILY SUPPORT JOISTS TO FLOOR BELOW
AT APPROXIMATE 1/4 LENGTH OF SPAN. PLACE
SUPPORTS DIRECTLY BELOW PANEL POINT.
COLUMN LINE
COLUMN LINE
*
*
THREE (3) LAPPED BARS MAY BE USED TO PROVIDE THE LENGTH OF REINFORCEMENT
NECESSARY. THE THREE BARS SHALL BE CENTERED OVER THE SPAN AND BARS LAPPED A
MINIMUM OF 24" AND WELDED ACROSS THE FULL LENGTH OF THE LAP. THERE SHALL BE NO
LAPPED OR WELDED BARS WITHIN 3'-0" ON EITHER SIDE OF THE CENTER OF THE SPAN.
*
1
2
3
4
6
5
5
OPTION 1 OPTION 2
#6
#7
#6
#7
NO. OF
BARS
2
2
2
2
NO. OF
BARS
REBAR
SIZE
2 05/26/21 ADDENDUM #2
2"±1"
3
16
EXISTING JOIST
L3 x3 x
1
4
TYP,
STRIP HORIZ LEG
2" AT EACH END
NOT TO SCALE
SECTION
B
NOT TO SCALE
ROOF OPENING FRAME
3
A
B
CL JOIST
Δ
Δ
CL JOIST
Δ = DIMENSION BY MECHANICAL
CONTRACTOR
L3x3x
1
4
, TYP
2
2
2
2
NOTE: DIMENSIONAL DATA IS TO BE OBTAINED BY SCALING ANY PORTION OF THIS DRAWING
PROJECT No.
DRAWING No.
PR
OJE
CT
TIT
LE
DR
AW
ING
TIT
LE
10
10
56
th S
tre
et
Ke
no
sh
a, W
I 5
31
40
C:\U
sers
\mbehre
ns\D
ocum
ents
\K04500
50, 6
0_C
entr
al_
2019_m
behre
ns.r
vt
5/2
6/2
021 1
:05
:02 P
M
H4.01
K0450060
HV
AC
SC
HE
DU
LE
SK
CD
C R
OO
FT
OP
EQ
UIP
ME
NT
RE
PL
AC
EM
EN
TP
RO
JE
CT
PH
AS
E I
DESIGNED : MCB
DRAWN BY : MCBCHECKED BY : KRP
PH
ON
E : 2
62
.65
7.1
55
0 w
ww
.cla
rkd
ietz
.co
m
DATE CHECKED : 2021.04.06
Ke
no
sh
a, W
I 5
31
40
62
5 5
7th
Str
ee
t, 6
th F
loo
r
NO. DATE REVISION
1 04/29/21 ISSUED FOR BID
2 05/26/21 ADDENDUM #2
ROOFTOP AIR CONDITIONING UNIT SCHEDULE
TAG SERVICE LOCATIONMIN OA(CFM)
SUPPLY FAN DATA EXHAUST FAN DATA HEATING COIL DATA COOLING COIL DATA COMPRESSOR DATA CONDENSER DATA ELECTRICAL DATA
NOTES
DESIGN BASIS
AIR VOL(CFM)
ESP(IN.WC)
NO.FANS
FANSPEED(RPM)
MOTORHP
(EACH) DRIVEAIR VOL
(CFM)
ESP(IN.
W.C.)
FANSPEED(RPM)
MOTORHP DRIVE
EAT(°F)
LAT(°F)
EWT(°F)
LWT(°F) GPM
CAP.(MBH)
EAT(°F)
DB/WB
LAT(°F)
DB/WBSENSIBLE
CAP. (MBH)
TOTALCAP.
(MBH)NO.
COMPRSRLA
(EACH)TYPE NO.
FANSFLA
(TOTAL) V PH HZ
CIRCUIT 1 CIRCUIT 2
MANUF. MODELMCA MOCP MCA MOCP
RACU 01-1 ADMISSIONS ROOF 2400 6000 2.00 2 1355 7.5 DIRECT 3600 1.5 898 5 DIRECT 38 88 140 120 70.0 333.0 85/71 55/55 206.7 329.6 2 22 SCROLL 3 5.4 480 3 60 15 20 52 70 1-3 TRANE SLHL25
RACU 02-1 DINING ROOF 2630 8765 2.00 2 1259 8 DIRECT 6135 1.5 918 5 DIRECT 34 78 140 120 70.0 422.3 83/69 55/55 269.3 394.0 2 25 SCROLL 3 5.4 480 3 60 17 20 59 80 1-3 TRANE SLHL30
RACU 07-2 GYM ROOF 1920 4800 1.00 2 1035 4 DIRECT 2880 1 721 3 DIRECT 47 96 140 120 60.0 258.4 81/67 53/53 170.7 265.7 2 19 SCROLL 2 3.6 480 3 60 11 15 46 60 1-3 TRANE SLHL20
HEATING AND VENTILATING UNIT
TAG SERVICE LOCATIONMIN OA(CFM)
SUPPLY FAN DATA EXHAUST FAN DATA HEATING COIL DATA
V PH HZ MCA MOCP NOTES
DESIGN BASIS
AIR VOL(CFM)
ESP (IN.W.C.)
NO.FANS
FANSPEED(RPM)
MOTORHP
(EACH) DRIVEAIR VOL
(CFM)ESP (IN.
W.C.)NO.
FANS
FANSPEED(RPM)
MOTORHP (EACH) DRIVE
EAT(°F)
LAT(°F)
EWT(°F)
LWT(°F) GPM
CAP.(MBH) MANUF. MODEL
HV 02-1 KITCHEN ROOF 13575 13575 2.00 2 2301 15 DIRECT 13575 1 2 1343 6 DIRECT -10 100 140 120 174.0 1619 480 3 60 60 80 1,2 TRANE CSAA030
HV 03-1 LAUNDRY ROOF 7100 7100 2.00 2 2947 5 DIRECT 7100 1 2 1438 6 DIRECT -10 100 140 120 91.0 847 480 3 60 32 40 1,2 TRANE CSAA017
ROOFTOP UNIT SCHEDULE
TAG SERVICE LOCATIONMIN OA(CFM)
SUPPLY FAN DATA HEATING DATA
TURNDOWN
INLETPRESSURE
(IN WC) COOLING DATA COMPRESSOR DATACONDENSER
DATA ELECTRICAL DATA
NOTES MANUF.
DESIGNBASIS
AIR VOL(CFM)
ESP (IN.W.C.)
FANSPEED(RPM)
MOTORHP DRIVE
EAT(°F)
LAT(°F)
CAP.INPUT(MBH)
CAP.OUTPUT
(MBH) MIN MAXEAT (°F)DB/WB
LAT (°F)DB/WB
SENSIBLECAP. (MBH)
TOTALCAP. (MBH)
NO.COMPRS RLA TYPE
NO.FANS FLA V PH HZ MCA MOCP MODEL
RTU 02-1 KITCHEN OFFICE ROOF 260 1600 0.75 911 1 DIRECT 57 100 120 96 4:1 4.5 14 80/67 58/58 38.8 48.9 1 4.5 SCROLL 1 1.3 480 3 60 9 15 1-3 TRANE YZC048
RTU 03-1 MAINTENANCE OFFICE ROOF 480 2000 0.75 1030 1 DIRECT 67 100 130 104 4:1 4.5 14 80/67 58/58 48.0 60.0 1 6 SCROLL 1 1.2 480 3 60 11 15 1-3 TRANE YZC060
RTU 04-1 D DORM - SOUTH 2740 3665 1.00 1472 3 DIRECT 57 100 250 203 4:1 2.5 14 80/67 58/58 82.0 122.0 1 18.8 SCROLL 1 3.1 480 3 60 31 45 1-3 TRANE YZC120
RTU 04-2 D DORM - NORTH 2740 4075 1.00 1565 3 DIRECT 57 100 250 203 4:1 2.5 14 80/67 58/58 86.7 123.3 1 18.8 SCROLL 1 3.1 480 3 60 31 45 1-3 TRANE YZC120
KITCHEN SUPPLY UNIT SCHEDULE
TAG SERVICE LOCATION
SUPPLY FAN DATA HEATING DATA EXHAUST FAN DATA ELECTRICAL DATA
NOTES MANUF.
DESIGN BASIS
AIR VOL(CFM)
OA VOL(CFM)
ESP (IN.W.C.)
FANSPEED(RPM)
MOTORHP DRIVE
EAT(°F)
LAT(°F)
CAP.INPUT(MBH)
CAP.OUTPUT
(MBH) MODELAIR VOL
(CFM)
ESP (IN.W.C.)
FANSPEED(RPM)
MOTOR HP DRIVETYPE V PH HZ MOCP MODEL
KSU 02-01KITCHEN
HOODROOF 5520 5520 1.00 695 3 BELT -10 97 800 640 CUBE-300HP-50 6900 2 959 5 BELT 480 3 60 20 1,2 GREENHECK IGX-118-H32-Q
KSU 02-2KITCHEN
HOODROOF 2640 2640 1.00 896 5 BELT -10 88 350 280 CUBE-180-20 3300 2 1475 2 BELT 480 3 60 20 1,2 GREENHECK IGX-112-H22-L
KSU 02-3KITCHEN
HOODROOF 3360 3360 1.00 967 3 BELT -10 78 400 320 CUBE-200HP-30 4200 2 1515 3 BELT 480 3 60 15 1,2 GREENHECK IGX-112-H22-M
KSU 02-4KITCHEN
HOODROOF 4680 4680 1.00 1849 3 BELT -10 85 600 480 CUBE-300HP-50 5850 2 909 5 BELT 480 3 60 20 1,2 GREENHECK IGX-P116-H22-MF-O
KSU 02-7KITCHEN
HOODROOF 4080 4080 1.00 1124 3 BELT -10 80 500 400 CUBE-240HP-30 5100 2 1175 3 BELT 480 3 60 15 1 GREENHECK IGX-P120-H32-MF-N
ENERGY RECOVERY VENTILATOR SCHEDULE
TAG SERVICE LOCATIONOA AIR VOL.
(CFM)
EA AIRVOL.(CFM)
ESP (IN.W.C.)
NO. OFFANS
SUPPLYMOTOR
HP
EXHAUSTMOTOR
HPDRIVETYPE TYPE
ELECTRICAL DATA
NOTES
DESIGN BASIS
V PH HZ MCA MOCP MANUFACTURER MODEL
ERV 04-1 RTU 04-1 ROOF 2740 2740 1.00 2 3 3 BELT FIXED PLATE 480 60 3 10.5 15 1 RENEWAIRE HE 4XRTV
ERV 04-2 RTU 04-2 ROOF 2740 2740 1.00 2 3 3 BELT FIXED PLATE 480 60 3 10.5 15 1 RENEWAIRE HE 4XRTV
ROOF
ROOF
NOTES:
1. UNIT DISCONNECT SWITCH TO BE PROVIDED AND INSTALLED BY ELECTRICAL CONTRACTOR. (1) DISCONNECT PER CIRCUIT TO BE PROVIDED.2. HEATING COILS TO BE SELECTED AT 140/120 EWT/LWT HOT WATER WITH 35% PROPYLENE GLYCOL SOLUTION. ACTUAL OPERATIONS OF UNITS TO BE AT 180/160 EWT/LWT.
NOTES:
1. UNIT DISCONNECT SWITCH TO BE PROVIDED AND INSTALLED BY ELECTRICAL CONTRACTOR.2. HEATING COILS TO BE SELECTED AT 140/120 EWT/LWT HOT WATER WITH 35% PROPYLENE GLYCOL SOLUTION. ACTUAL OPERATIONS OF UNITS TO BE AT 180/160 EWT/LWT.
NOTES:
1. PROVIDE WITH MANUFACTURERS UNIT DISCONNECT SWITCH. 2. PROVIDE POWERED EXHAUST.3. PROVIDE WITH VARIABLE SPEED COMPRESSOR.
NOTES:
1. PROVIDE WITH MANUFACTURERS UNIT DISCONNECT SWITCH.
NOTES:
1. PROVIDE WITH MANUFACTURERS UNIT DISCONNECT SWITCH. 2. PROVIDE UNIT WITH A COMBINED ROOF CURB FOR THE MAKE UP AIR UNIT AND EXHAUST FAN.
2
2
2
22
2
2
2
2
NOTE: DIMENSIONAL DATA IS TO BE OBTAINED BY SCALING ANY PORTION OF THIS DRAWING
PROJECT No.
DRAWING No.
PR
OJE
CT
TIT
LE
DR
AW
ING
TIT
LE
10
10
56
th S
tre
et
Ke
no
sh
a, W
I 5
31
40
C:\U
sers
\mbehre
ns\D
ocum
ents
\K04500
50, 6
0_C
entr
al_
2019_m
behre
ns.r
vt
5/2
6/2
021 1
:05
:02 P
M
E5.01
K0450060
EQ
UIP
ME
NT
CO
NN
EC
TIO
NS
CH
ED
ULE
KC
DC
RO
OF
TO
PE
QU
IPM
EN
T R
EP
LA
CE
ME
NT
PR
OJE
CT
PH
AS
E I
DESIGNED : MLS
DRAWN BY : JRF
CHECKED BY : LMZ
PH
ON
E : 2
62
.65
7.1
55
0 w
ww
.cla
rkd
ietz
.co
m
DATE CHECKED : 2021.04.06
Ke
no
sh
a, W
I 5
31
40
62
5 5
7th
Str
ee
t, 6
th F
loo
r
NO. DATE REVISION
1 04/29/21 ISSUED FOR BID
2 05/26/21 ADDENDUM #2
2
2
2
2
Request for Information submitted by Bidders
County of Kenosha – KCDC Rooftop Equipment Replacement Project Phase 1
Bid #2111
Bidder RFIs are listed in “black text” and using “N.).” Responses are given in “red” below each RFI.
1.) Phasing – please confirm how much time the owner is allowing for us to have each system
down, and how the project should be phased. At the pre-bid meeting it was discussed a 3 week
duration per unit and one unit at a time. Please also clarify which areas will remain occupied
during the construction and which areas can be vacated. Also indicate what kind of construction
barriers the customer is requesting in each area.
a. For bidding purposes, one unit to be worked on at a time in a 3 week duration. Once
contractor is awarded, construction sequence to be coordinated with owner per
specifications. See addendum for additional details for each area in scope.
2.) Site staging. Please indicate what areas are available for staging / job trailers
a. At the Northeast area outside of the building (Near column lines R/1 on sheet G0.02) is
space available for staging / job trailers.
3.) Please clarify which components serving the new equipment will be controlled by the RTU
BACNet controls and which will be controlled separately by Kain (i.e. AFMS, Hot Water Control
valves, etc.)
a. Controls section in Part 2 Products of respective equipment in Project Manual list out
what to be furnished by temperature controls contractor and what to be furnished by
manufacturer’s controls.
4.) Structural work only shows reinforcing work for joists. There is nothing shown for reinforcing or
support at the new curbs and no details for new roof frames if the existing need to be
modified. Can you please clarify the work required and details for the following:
1. Is it intended to re-use the existing roof frames for duct openings or are new frames /
roof opening locations required?
a. New roof curbs are to be provided for new equipment per the Project Drawings and
Project Manual.
2. Is there any support steel at the existing curb perimeter that would need to be modified
to match the new curbs or does the unit just sit directly on the deck? If there is existing
curb support steel is it angles below the deck or C-Channel on top of the deck?
a. Detail on S1.01 has been added where new or larger openings in the roof are
required.
5.) Please clarify who the CxA is for commissioning and who is responsible for their costs.
a. See Project Manual – Section 01 40 00 Quality Procedures, 1.2.H. The commissioning
authority for this project consists of representatives from owner and engineer.
Contractor does not need to include costs of the commissioning authority.
6.) Is there a specification section for ERV 04-1 and 04-2?
a. See Section 23 34 00 HVAC Fans in Project Manual.
7.) HV 02-1 and 03-1 show exhaust fans (keynote 6 on the diagram on H5.06) but the sequence calls
for a return fan (see 4b, 5b, 6a) please clarify.
a. It is an exhaust fan. See addendum for updates to sequence.
8.) From the Trane Rep: 23 81 06: E:-2 is seismic required for the curbs? This is not typical and other
curb specifications do not call for it
a. There are no seismic requirements.
9.) From the Trane Rep: Controls: Because there is an existing BAS contractor I think it makes sense
for the manufacturer to provide integration assistance. I would like the engineer to specify the
amount of time per unit needed. My recommendation would be 4 hours per packaged RTU and
8 hours per AHU.
a. See Field Quality Control section of each unit specifications in Project Manual for
minimum time required from manufacturer’s technical representative. This time can
also be used for integration assistance.
10.) From the Daikin / Aaon Rep: For rooftop units labeled RTU 02-1, RTU 03-1, RTU 04-1, and RTU
04-2 the spec and schedule show these units to be unitary/light commercial RTUs with variable
speed fans and compressors. Our RFIs below can help address the gap between manufacturers
and will allow at least 3 manufacturers to bid as equals.
1. Is a 2-speed belt-drive fan acceptable in lieu of supply fan with VFD?
a. No, 2-speed belt-drive fan is not acceptable. Provide supply fan with VFD.
2. Are multispeed EC blower motors acceptable in lieu of supply fan with VFD?
a. Yes, multispeed EC blower motors are acceptable.
3. Variable speed compressors are not available from most unitary rooftop manufacturers,
will a 2-staged compressor be acceptable in lieu of the variable speed compressor?
a. No, 2-stage compressor are not acceptable. Provide variable speed compressor.
11.) See below from my structural contractor from the walkthrough yesterday. I would suggest
having each contractor carry an allowance in the bid for moving of existing piping / electrical for
the joist reinforcing. That way you only pay for what we actually have to move and you get fair
bids without too much CYA on the front end.
a. Note 14 on S1.01 added in the event existing piping/electrical is required to me reworked.
1. Also is the shoring required for the joist reinforcement? I have done more intensive
reinforcing jobs without shoring. I'm not a structural engineer but I'm wondering if this
is needed. It will be very difficult in many of these areas...
a. Note 6 on S1.01 has been revised regarding shoring. Shoring is not required unless
there is snow on the roof or other significant construction loads. Temporary support
shall be as directed by a Wisconsin Licensed Professional Engineer.
2. Please refer to drawing S1.01. The Joist Strengthening Schedule calls out 5 joists
keynote 3, and 2 joists keynote 4. Per the plan there are 1 joist per keynote 3, and 5
per keynote 4. We plan to qualify our bid that we include reinforcing per the quantity of
joists on the framing plan rather than the schedule. You may want to ask for
clarification.
a. Schedule has been revised to match the roof framing plan.
3. See the joist elevation on S1.01. The designer calls for the joists to be temporarily
supported (shored) at 1/4 points. Is this required it will add a lot of cost.
a. See response 12) 1a above.
4. Keynotes 1,2,3 are at a Medical area. There is a tremendous amount of piping in the
way. Also, one joist is tight to a wall so we won't be able to get to the backside of the
joist if we need to add rods to both sides.
a. An option has been included to use one rebar on one side of the joist only. Note
than minimum overlap length for splicing bars together has been increased to
accommodate the larger diameter bars.
5. Keynote 4 are joists over an active kitchen. A lot of coordination will be required there.
a. No comment.
6. In all cases we will clarify that obstructions such as ceilings, electrical, plumbing
obstructions need to be removed and replaced by others.
a. No comment.
7. We don't plan to include anything for new curb support channels, field-fabricated roof
frames, or deck material or labor to fill existing roof openings.
a. No Comment.
8. All joist reinforcing material to be provided without paint due to field welding. No
touch-up or field painting will be included.
a. General contractor responsible to coordinate application of paint per requirements.