aci surety & fidelity presentation: interplay between equitable subrogation and gia's...
TRANSCRIPT
ACI National Advanced Forum on Lit igat ing Contract Surety Bond & Fidel ity Insurance Claims
Phi ladelphia, PA
Oct. 17-18, 2012
The Interplay Between Equitable
Subrogation and The GIA’s Assignment
RightsMatthew Bouchard Lewis & Roberts, PLLC
Mark OertelLewis Brisbois Bisgaard & Smith LLP
A surety who discharges or performs the obligations of its principal is entitled to step into the shoes and assert the rights of those persons to whom or on whose behalf the surety has performed or made payment. Pearlman v. Reliance Ins. Co., 371 U.S. 132 (1962).
Types of rights to which surety becomes equitably subrogated:
Obligee’s right to apply earned but unpaid progress payments and retainage in Obligee’s hands to cost of completion
Principal’s rights against subs and suppliers whose work was delayed, defective or otherwise deficient
Subcontractors’ rights against contract balances, trust funds, other sureties, mechanic’s lien rights
Powerful stuff !
EVERYONE’S FAVORITE SOURCE OF SALVAGE: EQUITABLE
SUBROGATION
Assignment right “seems to add nothing to the [equitable subrogation] rights here asserted.” Nat’l Sur. Corp. v. Allen-
Codell Co., 70 F. Supp. 189, 191 (E.D. Ky. 1947)
WHAT ABOUTASSIGNMENT RIGHTS?
Some hypotheticals
DOESN’T THE ASSIGNMENT CLAUSEDESERVE OUR RESPECT?
Timing is everything! Rights arise upon principal’s “default,” as defined in GIA;
bond performance not a condition precedent to exercise of right Fid. & Deposit Co. of Md. v. U.S. , 31 Fed. Cl. 540, 542-43 (1994)
(equitable subrogation rights do not vest until surety has performed principal’s obligation)
Supports notice to owner not to pay contract funds to principal
ADVANTAGES OF ASSIGNMENT
Broader protection than equitable subrogation
Rights against job supplies, tools, equipment, plant, material
Salvage from other bonded contracts not in default
Salvage from non-bonded contracts not in default
ADVANTAGES OF ASSIGNMENT
“Some assembly required” -- fi ling Agreement of Indemnity as UCC Financing Statement to perfect interest in supplies, tools, plant, equipment and materials on job site and establish priority over completing claims Downside of fi ling – drying up potential sources of financing Industry practice – don’t fi le until signs of distress Could be too late vis-à-vis principal’s lender
Late fi ling of UCC = inferior priority v. other secured creditors
Applicability to contract funds on federal projects limited
DISADVANTAGES OF ASSIGNMENT
“No assembly required” – rights arise automatically as matter of equity In most jurisdictions, UCC action not necessary to perfect
surety’s priority interest over proceeds of bonded contracts. Nat’l Shawmut Bank of Boston v. New Amsterdam Cas. Co ., 411
F.2d 843 (1st Cir. 1969)
Relation back to date of issuance of bonds
Avoiding privity/non-assignability problems
ADVANTAGES OF EQUITABLE SUBROGATION
Performance of bonded obligation is a condition precedent to eff ectiveness – no performance, no right Although some jurisdictions recognize “contingent equitable
subrogation”
Right may not reach principal’s equipment or personal property Potential argument for job-related material and equipment based on
prime contract language Virtually no argument for principal’s material and equipment not
dedicated to bonded contract in default
May be limited to bonded contract in default Split in authority re: whether right reaches proceeds of other
contracts
Right likely does not include claim expense recovery
DISADVANTAGES OF EQUITABLE SUBROGATION
Contract proceeds either due or to become due Includes progress payment, retainage, compensation for
extras, proceeds from damages claims Depending on language utilized, may include other bonded
contracts not in default or even non-bonded contracts not in default
Right, title and interest in job-related supplies, tools, plant, equipment and materials Includes stored materials and components in process of
manufacture Permits sale of property not utilized for completion without
risk of liability with respect to commercial reasonableness of the sale
RIGHTS TYPICALLY ASSIGNED
Subcontracts / Bonds covering subcontracts Useful in compelling subcontractors to ratify subcontracts
upon takeover Also useful in negotiating with subcontractors to return to
the project when surety takes over and uses its principal as completion contractor
Claims of the principal Includes right to settle claims on terms surety considers
reasonable under the circumstances
RIGHTS TYPICALLY ASSIGNED
Event of default as defined in GIA
Typically defined broadly Receipt of claims Failure or inability of principal to perform Failure to fulfill an obligation under GIA Declaration of default by obligee
NOT synonymous with default under bonded contract
TRIGGER
Attorney-in-fact provision providing surety full authority to: Handle claims and causes of action Execute documents necessary to facilitate assignment
rights Proceed without putting Indemnitors on notice of its actions
Right to settle affi rmative claims
Indemnity and collateral security provisions
COMPLEMENTARY PROVISIONS OF GIA
Hutton Constr. Co., Inc. v. County of Rockland , 52 F.3d 1191 (2d Cir. 1995)
Obligee disputed principal’s unanticipated subsurface conditions claim and terminated principal
Obligee sued principal and surety for completion and correction costs
Principal brought Spearin claims arising from defective plans and specs, unanticipated subsurface conditions and alleged wrongful termination
Surety compromised claims between and among obligee, principal and surety over principal’s objections, then moved to dismiss the action and for an order enforcing settlement agreement
PUTTING IT ALL TOGETHER:THE HUTTON DECISION
Hutton Constr. Co., Inc. v. County of Rockland , 52 F.3d 1191 (2d Cir. 1995)
Right-to-settle clause did not expressly grant surety right to settle affi rmative claims
Indemnitors failed and refused to make indemnity payments demanded by surety, triggering assignment clause
Assignment clause, which unambiguously assigned all rights “growing in any manner out of” bonded contracts, coupled with attorney-in-fact provision, allowed surety to settle affi rmative claims against the obligee
PUTTING IT ALL TOGETHER:THE HUTTON DECISION
What aff ect might UCC fi ling have on principal’s operations and financing?
Often times the Bank or Other Lenders have already filed.
STRATEGIC CONSIDERATIONS
What aff ect might UCC fi ling have on principal’s operations and financing?
STRATEGIC CONSIDERATIONS
Alternatives:
Demand that owner mitigate its damages by exercising contract clause giving owner dominion over materials purchased for the job
Cooperate with principal on filing a separate, voluntary financing statement on job-related property only
Negotiate with lender to allow materials and equipment to remain for project completion per the assignment clause of GIA
STRATEGIC CONSIDERATIONS
Does the exercise of the assignment clause prejudice subsequent exercise of equitable subrogation rights?
Majority rule: no Old Kent Bank v. City of Detroit , 444 N.W.2d 162 (Mich. Ct. App.
1989); Canter v. Schlager, 267 N.E.2d 492 (Mass. 1971)
Some jurisdictions have struggled with the question Transamerica Ins. Co. v. Barnett Bank of Marion County, N.A. ,
524 So.2d 439 (Fla. Dist. Ct. App. 1988), rev’d, 540 So.2d 113 (Fla. 1989) Trial court initially held that after failing to file assignment under UCC
Article 9, surety could not rely on remedy of equitable subrogation to “ambush a financing bank”
The Supreme Court of Florida disagreed
STRATEGIC CONSIDERATIONS
How should the right be exercised?
Enlisting the Cooperation of the Principal
Compelling reason for Principal to cooperate is “hold harmless and indemnify” Clause of GIA
Right to Compel Collateral
Power of Attorney coupled with Right to Collateral
STRATEGIC CONSIDERATIONS
Seeking Judicial Assistance in Compelling Cooperation
Quia Timet / Injunctive Relief
Specific Performance
Declaratory judgment action
Power-of–Attorney Clause
STRATEGIC CONSIDERATIONS
QUESTIONS?