ace team 2 - wk6 - ipd presentation
TRANSCRIPT
![Page 1: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/1.jpg)
INTEGRATED PROJECT DELIVERY
ACE Mentorship Program: Team 2, January 20th, 2015
![Page 2: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/2.jpg)
Design-Bid-Build: traditional approach – owner contracts separately with all
parties. Occasionally referred to as Design-Bid-ReDesign-ReBid-Build.
Design-Build: One entity performs both architectural\engineering design and
construction under one contract. Either an architect-led or contractor-led
approach.
CM-at Risk, or GMP: Construction Manager is a consultant to the owner during
design phases, and acts as general contractor during construction with a
commitment to deliver the project within a guaranteed maximum price.
Turnkey Project Delivery: frequently used in power plants, manufacturing
facilities, a method to provide an owner with a complete facility, ready to operate
and turn out product.
Traditional processes
![Page 3: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/3.jpg)
Design- Bid- Build Most common form of Project Delivery
•Three phases, three prime players
•Independent contracts between architect/owner and contractor/owner
•Linear sequence of work
•Common with public owners with requirements to select low bid
![Page 4: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/4.jpg)
•One entity hired by
Owner to complete
design and
construction
•May all be
Contractor's in-house
design expertise or
Contractor may
engage outside
Architect
•Early cost
commitment is made
(GMP) by Contractor
based upon
preliminary design
OWNER
DESIGN -
BUILDER
S
F
Design- Build
E
E
![Page 5: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/5.jpg)
Everyone Signs the Same Agreement
Full IPD
Owner
Sub.ContractorCons. Architect
Sub.Cons.
AIA C195
ConsensusDocs 300
![Page 6: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/6.jpg)
1/14/20166
Traditional (Today) Integrated Project Delivery (Tomorrow)
Fragmented, assembled on “just-
as-needed” or “minimum
necessary” basis, strongly
hierarchical, controlled
TEAMS An integrated team entity
composed of all project lifecycle
stakeholders, assembled early in
the process, open, collaborative
Linear, distinct, segregated;
knowledge gathered “just-as-
needed”; information hoarded
PROCESS Concurrent, multi-level,
integrated; early contributions of
knowledge and expertise;
information openly shared
Individually managed, transferred
to the greatest extent possible
RISK Collectively managed,
appropriately shared
Individually pursued; minimum
effort for maximum
return;(usually) first-cost based
COMPENSATION
REWARD
Team success tied to project
success; value-based
Paper-based, 2 dimensional;
analog
COMMUNICATION
S
TECHNOLOGY
Digitally based, virtual, 4
dimensional; BIM
Minimum effort for maximum
return; minimize or transfer risk;
don’t share
AGREEMENTS Encourage, foster, promote and
support open sharing and
collaboration, full integration
Individually focused, emphasis on
composition
EDUCATION Team-based, integrated,
collaborative; technologically
inclusive; materials and methods
focus in addition to compositionAIA California Council IPD FAQ - 2006
![Page 7: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/7.jpg)
1/14/20167
PD SD CD PR CA OPDD
Time
Eff
ort
/Eff
ec
t
PD: Pre-design
SD: Schematic design
DD: Design development
CD: Construction documentation
PR: Procurement
CA: Construction Administration
OP: Operation
Graphic originated by Patrick McLeay, AIA / HOK
Ability to impact cost and functional capabilities
1
1
Cost of design changes
2
2
Traditional design process3 3Preferred design process
4
4
• Owner Leadership
• Integrated Project Structure
• Open Information Sharing
• Virtual Building Models
It’s about Productivity
![Page 8: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/8.jpg)
AgencyOwnerArchitect
EngineersGCSubs
Predesign Schematic
DesignDesign
Development
Construction
Documents
Agency
Permit /
Bidding
Construction Closeout
WHO
REALIZEHOW
WHAT
Traditional
WHAT
WHO
HOW
AgencyOwnerArchitect
EngineersGC
Subs
Conceptual-
ization
Criteria
DesignDetailed
Design
Implementation
Documents
Agency Coord /
Final Buyout
Construction Closeout
REALIZE
Integrated
•Define the processes, structure and metrics up front!
Source: AIA Convention 2009 – Jim Bedrick
![Page 9: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/9.jpg)
![Page 10: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/10.jpg)
![Page 11: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/11.jpg)
Competitive Schematic Design. The winner was ($655,000)
under 2nd place.
Competitive approach to 3 systems, saving ($132,000) in
supplemental support steel.
LEAN approach to have contract documents designed to 1
curtain wall system manufacturer
Integrated approach with all stakeholders collaborating to
achieve the best solution
![Page 12: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/12.jpg)
Used pre-engineered
curtain wall system.
Architect spent less time
designing. Project relied
heavily on Trade Partner
shop drawings and Revit
model for final construction
drawings.
Saved time & money!
![Page 13: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/13.jpg)
![Page 14: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/14.jpg)
![Page 15: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/15.jpg)
![Page 16: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/16.jpg)
![Page 17: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/17.jpg)
![Page 18: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/18.jpg)
![Page 19: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/19.jpg)
Hand Drawing 2D CAD 3D CAD
EVOLUTION From Hand Drawing to Smart Models
BIM
![Page 20: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/20.jpg)
Electrical Detailer
Structural Steel Detailer
Mechanical Piping Detailer
MEP Manager
BIM Engineer
Model & CAD Drawings
Architect
Smartboard & Projector
3D MEP Coordination
![Page 21: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/21.jpg)
![Page 22: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/22.jpg)
![Page 23: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/23.jpg)
![Page 24: ACE Team 2 - WK6 - IPD Presentation](https://reader036.vdocuments.site/reader036/viewer/2022062523/58ef8e461a28abf2618b4567/html5/thumbnails/24.jpg)
ANY QUESTIONS?