a geothermal hydro wind pv hybrid system with energy

19
A geothermal hydro wind PV hybrid system with energy storage in an extinct volcano for 100% renewable supply in Ometepe, Nicaragua Fausto A. Canales 1 , Jakub K. Jurasz 2-3 and Alexandre Beluco 4, * 1 Universidad de la Costa, Department of Civil and Environmental, Barranquilla, Atlántico, Colombia; faus- [email protected] 2 AGH University, Faculty of Management, Department of Engineering Management, Kraków, Poland 3 MDH University, School of Business Society and Engineering, Västerås, Sweden; [email protected] 4 Universidade Federal do Rio Grande do Sul, Instituto de Pesquisas Hidráulicas, Porto Alegre, Rio Grande do Sul, Brazil; [email protected] * Correspondence: [email protected] (F.A.C.); [email protected] (A.B.) Abstract: Renewable resources are constantly increasing their share in energy systems around the world. This paper evaluates how the capital cost of renewable technologies affects the optimal configu- ration and cost of energy of an isolated power system, comprising only renewable resources. HOMER software was adapted to include and simulate pumped storage hydropower and geothermal power plants. Ometepe island, Nicaragua, was selected as case study because wind, solar and geothermal re- sources are available, but more importantly, it has an extinct volcano with a crater lake on its top that could be used as the upper reservoir for pumped storage hydropower. When geothermal is considered, the results show that this technology is able to serve the base load of the system, reducing the required installed capacity of other resources, as well as decreasing the storage requirements and excess electric- ity production. When the geothermal option is not included, the low complementarity in time of the oth- er variable resources increases the required size of the solar and wind parks , amounting to up to 6.5 times the peak power, consequently rising the cost of energy and excess electricity production. The dif- ferent system configuration results demonstrated that economic aspects of renewable generation are at least as important as the natural resources availability. Keywords: hybrid systems modeling, solar power, wind energy, pumped storage hydropower, geother- mal energy, software Homer. Abbreviations, Acronyms, and Symbols used in this paper AC: Alternating Current C B : Battery capacity, in Ampere·hour [Ah] CO2: Carbon dioxide COE: Cost of electricity, in $/kWh E S : Stored energy, in kWh GWh/y: Gigawatt hour per year gCO 2 /kWh: Grams of carbon dioxide per kilowatt hour H: Effective head, in meters [m] HOMER: Hybrid Optimization Model for Electric Renewables I: Electric current, in Amperes [A] kV: Kilovolts kWh: Kilowatt hour m.a.s.l.: Meters above sea level MERRA-2: Modern-Era Retrospective Analysis for Research and Applications, Version 2 MW: Megawatt MWh: Megawatt hour NASA: National Aeronautics and Space Administration NPC: Net present cost

Upload: others

Post on 26-Jun-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: A geothermal hydro wind PV hybrid system with energy

A geothermal hydro wind PV hybrid system with energy storage in an extinct volcano for 100% renewable supply in Ometepe, Nicaragua

Fausto A. Canales1, Jakub K. Jurasz2-3 and Alexandre Beluco4,*

1 Universidad de la Costa, Department of Civil and Environmental, Barranquilla, Atlántico, Colombia; [email protected]

2 AGH University, Faculty of Management, Department of Engineering Management, Kraków, Poland 3 MDH University, School of Business Society and Engineering, Västerås, Sweden; [email protected] 4 Universidade Federal do Rio Grande do Sul, Instituto de Pesquisas Hidráulicas, Porto Alegre, Rio Grande do Sul,

Brazil; [email protected] * Correspondence: [email protected] (F.A.C.); [email protected] (A.B.)

Abstract: Renewable resources are constantly increasing their share in energy systems around the

world. This paper evaluates how the capital cost of renewable technologies affects the optimal configu-

ration and cost of energy of an isolated power system, comprising only renewable resources. HOMER

software was adapted to include and simulate pumped storage hydropower and geothermal power

plants. Ometepe island, Nicaragua, was selected as case study because wind, solar and geothermal re-

sources are available, but more importantly, it has an extinct volcano with a crater lake on its top that

could be used as the upper reservoir for pumped storage hydropower. When geothermal is considered,

the results show that this technology is able to serve the base load of the system, reducing the required

installed capacity of other resources, as well as decreasing the storage requirements and excess electric-

ity production. When the geothermal option is not included, the low complementarity in time of the oth-

er variable resources increases the required size of the solar and wind parks , amounting to up to 6.5

times the peak power, consequently rising the cost of energy and excess electricity production. The dif-

ferent system configuration results demonstrated that economic aspects of renewable generation are at

least as important as the natural resources availability.

Keywords: hybrid systems modeling, solar power, wind energy, pumped storage hydropower, geother-

mal energy, software Homer.

Abbreviations, Acronyms, and Symbols used in this paper

AC: Alternating Current

CB: Battery capacity, in Ampere·hour [Ah]

CO2: Carbon dioxide

COE: Cost of electricity, in $/kWh

ES: Stored energy, in kWh

GWh/y: Gigawatt hour per year

gCO2/kWh: Grams of carbon dioxide per kilowatt hour

H: Effective head, in meters [m]

HOMER: Hybrid Optimization Model for Electric Renewables

I: Electric current, in Amperes [A]

kV: Kilovolts

kWh: Kilowatt hour

m.a.s.l.: Meters above sea level

MERRA-2: Modern-Era Retrospective Analysis for Research and Applications, Version 2

MW: Megawatt

MWh: Megawatt hour

NASA: National Aeronautics and Space Administration

NPC: Net present cost

Page 2: A geothermal hydro wind PV hybrid system with energy

2 / 19

O&M: Operation and Maintenance

Pbat: Electric power delivered by the battery, in kilowatts [kW]

PSH: Pumped Storage Hydropower

PV: Photovoltaic

QP: Pump flow

RES: Renewable Energy Sources

SIN: National Interconnected System

VRES: Variable Renewable Energy Sources

V: Voltage, in volts [V]

Vol: Active volume of a reservoir, in cubic meters [m³]

y: Year

Z: Altitude, in m

ηhyd: Conversion efficiency, %

Content

1. Introduction

2. Method

2.1. Pumped Storage Hydropower modeling in HOMER

2.2. Geothermal modeling in HOMER

2.3. Sensitivity analysis, optimal system configuration and simulation with HOMER

3. A hybrid system in the island of Ometepe

3.1. Solar resource

3.2. Wind turbine and wind speed data

3.3. Representing pumped storage hydropower

3.4. Geothermal

3.5. Load

3.6. Additional considerations

4. Simulation results and discussion

4.1. System configuration when considering geothermal option

4.2. System configuration without geothermal option

4.3. Additional remarks

5. Conclusions

1. Introduction

Non-combustion renewable energy sources (solar, wind, hydropower, and geothermal) are becoming

the pillars of electric power systems around the world. The goal of achieving an electric power system

based entirely on renewables, besides been investigated by numerous authors [1 -6], has also become a

reality over the recent years in many areas across the globe. The following locations (cities, regions, is-

lands) are examples where renewables penetration reached 100%: Aspen, Colorado, in the United States,

which in 2015 removed coal plants and now it covers its energy demand with hydroelectricity, wind

power, photovoltaics an geothermal energy [7]; Tokelau islands, administered by New Zealand, use pho-

tovoltaic systems with battery backup [8]; Costa Rica, which in 2016 and 2017 had its electricity produced

entirely using renewables for over 300 days, and set a goal of becoming carbon-neutral within this centu-

ry [9]; the Danish island of Samso, with a negative carbon footprint, uses biomass and wind power to

serve its load, and is connected to the mainland for energy export and balancing [10]. The list is obviously

not complete, but the growing number of communities supplied entirely from renewables tread the new

ground and prove that such situation is possible.

The aforementioned examples confront a common notion, described in [11], that variable renewable

energy sources (VRES), like wind and solar power, are unreliable and intermittent to a degree that they

are unable to contribute significantly to electric power supply or to serve baseload power. To overcome

the intermittency and stochastic nature of these energy sources, autonomous power systems with high

levels of these renewables need adequate actions to balance energy supply and demand, in order to main-

Page 3: A geothermal hydro wind PV hybrid system with energy

3 / 19

tain the electricity supply quality by controlling grid frequency and voltage. To achieve this balance, one of

the most common approaches is the combination of dispatchable technologies and energy storage.

Geothermal power and hydropower reservoirs are the two non-combustion renewables capable of

providing dispatchable generation. With a capacity factor between 45% and 90%, geothermal energy is

not heavily affected by weather like solar, wind or even hydro; and it can serve both base load and peak

loads. However, it is generally more economical to use geothermal plants to supply base load [12].

Pumped storage hydropower (PSH) is a mature and efficient form of bulk energy storage which has

drawn significant attention as a viable option to facilitate the integration of VRES in isolated areas and

national power grids [13, 14]. One the most important costs associated to hydropower with storage is the

one related to building the reservoirs. Specifically, for PSH, the cost per kilowatt·hour (kWh) for a PSH

plant that already has the two reservoirs available is around 18% of the cost of a PSH plant that requires

two new reservoirs, and 40% of a system including one new reservoir [15]. In general, PSH can present

various configurations: both reservoirs are man-made (e.g.: Goldisthal Pumped-Storage Plant, Germany);

natural lakes connected by canal (e.g.: Żydowo Pumped Storage Hydroelectric Power Plant, Poland); one

of the reservoirs is a natural water body and the second one is an artificial reservoir (e.g.: Żarnowiec

Pumped Storage Power Station, Poland); the lower reservoir is using salt water from the ocean (e.g.: Oki-

nawa Yanbaru Seawater Pumped Storage Power Station, Japan); PSH using exploited (abandoned) deep

mines [16, 17]. Despite many possible configurations of PSH plants, the main factor determining suitabil-

ity of given site for PSH development is a beneficial ratio of vertical (head) to horizontal distance between

reservoirs [18].

The sustainability of communities living on islands and in remote communities across the world has

been directly tied to fuel oil availability and their increasing price. This commodity propels ships and

trucks that allow transporting goods into and from the island; fuels the vehicles that allow tourism and

mobilization within these areas, and, perhaps most important, has enabled these communities to consist-

ently generate electricity [19].

There is a rich body of literature on hybrid systems based on VRES coupled with PSH operating on

islands. We briefly introduce some of those works written over the last years. Duić et al. [20] showed how

PSH can be used to increase VRES penetration in Porto Santo island. Bueno and Carta [21] presented a

techno-economic analysis of wind powered PSH for El Hierro island. Their follow-up study investigated

how wind-PSH hybrid power systems could increase the penetration of renewables in the Canary Is-

lands [22]. Caralis and Zervois [23] analyzed the operation of a wind-PSH project applied to Greek islands,

and in their next study [24] they assessed the market potential of wind-PSH for autonomous power sys-

tems on Islands. Papaefthimiou et al. [25] presented operating policies for wind-PSH stations for island

grids. Katsaprakakis et al., [26] proposed a wind-PSH system for an insular power system for the islands

Karpathos and Kasos. Kapsali et al., [27] performed a sensitivity analysis of wind-PSH from the economic

perspective, using the Greek islands as case study. Ma et al. [28] considered adding photovoltaic (PV)

modules to a wind-PSH hybrid power system and analyzed it from a technical perspective, for a remote

island in Hong Kong. Papaefthymiou and Papathanassiou [29] presented an optimal sizing method for

wind-PSH stations for insular systems. A similar approach was presented by Ma et al., [30] aiming the

optimal design of an autonomous solar-wind-PSH station. Barreira et al. [31] considered an off-stream

PSH project as an option to increase VRES penetration in Santiago island (Galápagos). Tsamaslis et al. [32]

showed a concept of hybridizing PVs with PSH to increase VRES penetration and achieve grid benefits for

Cyprus.

The most extensively used software tool in research studies associated to hybrid power systems is

HOMER (Hybrid Optimization Model for Electric Renewables) [33]. HOMER can be described as a com-

puter model that assists in the prefeasibility and design process of hybrid power systems involving dif-

ferent energy sources (PV modules, wind turbines, run-of-river hydropower, batteries, generators, etc.).

HOMER is primarily an economical model which is able of modeling the physical behavior and lifecycle

cost of a power system, in order to select the best system configuration. HOMER is able to perform three

main tasks: simulation, optimization and sensitivity analysis.

A limitation of HOMER is that it does not include the features to directly model some renewable

technologies, among these, PSH and Geothermal. Nevertheless, using some equivalent representations and

considerations, as explained in Canales and Beluco [34] and the user support available in the HOMER en-

ergy website [35], the user is able to use HOMER for assessing a hybrid power system that considers PSH

Page 4: A geothermal hydro wind PV hybrid system with energy

4 / 19

and geothermal options. Upcoming HOMER releases or custom versions could include specific elements to

model these technologies, but the Legacy Version, universally available and used in this study, does not

have these tools.

Ometepe island, in Nicaragua, Central America, was selected as case study for this paper because it

presents some interesting features for evaluating the method and assessing the technical feasibility of a

100% non-combustion RES system: a) it has a crater lake at the top of an extinct volcano that could be

used as the upper reservoir of a PSH plant; b) it is located in a large tropical fresh water lake that could act

as the lower reservoir of the PSH system; c) the island has identified geothermal potential, d) solar and

wind energy resources are available.

The recent paper by Meza et al.[36] also works with the idea of reaching 100% of the energy supply

to the island of Ometepe with renewable resources. Relatively detailed survey of the wind and solar po-

tentials are presented and the possibility of energy storage in the crater of the Maderas volcano is also

considered. Geothermal energy is mentioned, but according to the authors investments in research and

development are still required. This work is focused on surveying the available renewable resources, also

discussing their possible complementarity, and comparing them with consumption of the island's popula-

tion, suggesting actions to reduce or optimize energy consumption.

Within this context, the aim of this paper is to evaluate how the capital cost of renewable technolo-

gies affects the optimal configuration and cost of electricity of an isolated electric power system, compris-

ing only non-combustion renewables (geothermal, wind, solar, PSH). Some of the merits of this paper

related to filling the gap in the literature are: 1) It shows how to simultaneously include geothermal power

and PSH in a HOMER model, along with other VRES; 2) The method presented here, and similar data

sources can be adapted to other places around the world with similar geographic characteristics, espe-

cially regarding the PSH potential of extinct crater lakes. The structure of this paper, following this brief

introduction, includes a description of the method adopted and the presentation of the case study (a hy-

brid system on the island of Ometepe, Nicaragua); after that, the results are presented and discussed,

closing with the main conclusions of this work.

2. Method

This paper evaluates how the capital cost of wind turbines and PV panels affects the system configu-

ration of a 100% non-combustion renewable isolated system, using PSH as energy storage system, and

considering the impact of geothermal power. The Legacy Version of HOMER Energy software [37] is used

as the main working tool, because it allows the user to simulate, optimize and conduct sensitivity analysis

on hybrid systems including different renewable energy resources and PSH, using some useful modifica-

tions explained in this section.

2.1. Pumped Storage Hydropower modeling in HOMER

Just like batteries, hydropower reservoirs can store energy and supply it according to the load de-

mands. Based on this similarity, Canales and Beluco [34] proposed a method for allowing representing

PSH as an equivalent battery in HOMER (with properties that remain constant during its lifetime), using

a converter to represent the installed capacity of the hydropower plant. The following equation can be

used to estimate the total stored energy ES [kWh] in the active volume of a reservoir Vol [m³]:

(1)

In Eq. (1), H is the effective head [m], which is considered constant, and ηhyd is the conversion effi-

ciency of the electromechanical equipment [%].

Similarly, and assuming a fixed voltage V [volts] and capacity CB [Ampere·hour, Ah], the following

equation can be used to calculate the stored energy in the equivalent battery representing the hydropow-

er reservoir:

(2)

The electric power delivered by the battery Pbat, measured in kilowatts [kW], is proportional to the

product of electric current I in Amperes [A] and the voltage V, and can be calculated by the expression:

Page 5: A geothermal hydro wind PV hybrid system with energy

5 / 19

(3)

HOMER finds the optimal configuration in terms of the total net present cost (NPC) of the system, in-

cluding the size of the battery bank, which can be translated as the optimal size of the active volume of the

upper reservoir. The unitary equivalent battery represents the minimum active volume of the upper res-

ervoir, therefore, for the method presented in Canales and Beluco [34], the quantity of batteries are direct

multiples of the reference volume.

As explained in [38], the method assumes asynchronous electromechanical equipment (pumps and

turbines), enabling the equipment to adjust the rotation speed and regulate the amount of energy ab-

sorbed or delivered, allowing to reduce the number of starts and stops of the machinery. However, it is

common practice to use rectifiers and multiple units of synchronous equipment. More details and consid-

erations to use this method are described in [34] and [38].

2.2. Geothermal modeling in HOMER

According to the directions described in [35] and also based on the considerations in [34], geother-

mal modeling in HOMER requires creating a new AC (Alternating Current) generator. It is also necessary

to define a new fuel representing the properties of the geothermal resource, being the most important, the

fuel carbon content. The carbon dioxide (CO2) emissions from geothermal fields in tropical areas range

from 13 to 380 g/kWh, much lower than for natural gas (453 g/kWh), oil (906 g/kWh) and coal (1042

g/kWh) [12]. Because of the nature of the geothermal resource, the fuel cost is set to zero in HOMER, but

the Operation and Maintenance (O&M) costs are expressed in US$/hr. In this paper we want to assess if

the capital cost and lack of complementarity between the different available VRES affect the optimal con-

figuration of the system. Because of this, the minimum load ratio in HOMER is set to 100%, indicating that

the generator is considered to run only at full blast and serve base load. For the entire period, the operat-

ing mode is set to “optimized” in HOMER.

2.3. Sensitivity analysis, optimal system configuration and simulation with HOMER

One of the main features of HOMER is the capacity to perform sensitivity analysis under a range of

uncertainties or/and assumptions in the model inputs. This capacity, along with its user-friendly interface,

detailed documentation and solidity proven by its thousands of users around the world [33], is the reason

why the authors of this paper selected HOMER as the working tool to perform the analysis and simulation

of the system described in the case study.

The preliminary assessment and design of hybrid power systems usually involves a large number of

options and uncertainties related to key parameters like the load size, stochastic behavior of renewable

sources, storage or backup power requirements, etc., thus making the process a difficult task. Particularly

for systems including intermittent renewables sources, like wind and solar radiation, HOMER is able to

overcome these challenges by running simulation in one-hour time steps, allowing acceptable accuracy by

capturing the most important features of how the load demands are served by these VRES, without de-

manding excessive computation resources that would make the optimization and sensitivity analysis im-

practical [39].

HOMER is able to simulate, optimize and conduct sensitivity analysis for many system configurations

at one run, and for each one of them and based on the set of constraints, the model evaluates the perfor-

mance of the system for each hour of the year, determining its technical feasibility and estimating its

life-cycle cost. The hybrid system proposed in this study is represented in the diagram of Figure 1.

In the optimization process, the NPC is the measure used by HOMER to rank the feasible system con-

figurations, prioritizing from the most economic to the most expensive. The NPC includes initial capital

cost, replacements, O&M, fuel and the cost of purchasing electricity from the grid within the project life-

time, discounted to the present. More detailed information about HOMER is available at [37] and [39].

The sensitivity analysis of this paper tries to offer insight of how HOMER can assess the impact of re-

newable energy capital costs on the systems configuration in a scenario of 100% non-combustion renew-

ables, with solar and wind as the VRES. It will also evaluate the effect of considering geothermal power to

serve baseload.

Page 6: A geothermal hydro wind PV hybrid system with energy

6 / 19

Figure 1. Schematic diagram of the proposed hybrid system for Ometepe Island. ‘MADERAS’, ‘Converter’

and DC bus bar jointly simulate the use of the Maderas’ crater lake as an upper reservoir in a PSH plant.

Additionally, HOMER is able to estimate the harmful pollutant emissions that could be reduced by

shifting to power systems with high percentages of non-combustion renewables. Besides compelling de-

veloped countries to apply environmental friendly energy policies, the common global agenda is to help

developing countries to reduce their CO2 and other greenhouse gases emissions, without thwarting their

economic progress [40]. This paper uses information available at the electricity map site [41] related to

CO2 estimates of electricity consumption for several countries around the world, and the following ap-

proach is adopted: 1) The average CO2 emissions (including all energy sources) produced by the national

power grid during a 24 hour period were calculated and used in HOMER to estimate the CO2 emissions

that the demand would produce if all electricity was provided by the national grid; 2) when geothermal is

being considered, the reference values of the CO2 emissions are used to calculate the emissions of the

100% non-combustion renewable power system , allowing to compare and estimate the CO2 emissions

that might be reduced by implementing this hybrid power system.

3. A hybrid system in the island of Ometepe

This section describes the renewable resources, loads and components considered in this case study

and included in the HOMER simulation to evaluate an autonomous hybrid power system to serve the elec-

tricity demands at Ometepe island, Nicaragua. By 2014, non-combustion renewables accounted for

~35.2% of the installed capacity of the National Interconnected System (Sistema Interconectado Nacional

– SIN) of this Central American country [42].

In order to keep the quality of the electricity supply, power systems based on high shares of renewa-

bles require backup power to balance the intermittent and fluctuating behavior of sources like wind and

sun radiation. In Nicaragua, this balance is provided by fuel generators. However, in this paper, a 100%

renewable system is assessed, by using PSH instead of fuel to supply electricity in periods of high demand.

Table 1 presents the search space used in HOMER for the case study.

In order to reduce infrastructure investment, PSH frequently uses exhausted mines or natural water

reservoirs. For this case study, the crater lake at the top of Maderas, an extinct volcano, and Lake Nicara-

gua, a large tropical fresh water lake, are used as upper and lower reservoirs of the PSH plant. The island

of Ometepe is formed by two volcanoes and is located in Lake Nicaragua, in the southwestern part of Nic-

aragua [43].

Ometepe has an area of 276 km2, about 31 km long by 5 km to 10 km wide, housing a population of

just over 40,000 inhabitants. Ometepe is formed by two volcanoes:Concepcion, reaching 1634 meters

above sea level (m.a.s.l), and Maderas, with 1394 m.a.s.l. Figure 2 shows a satellite image of the island of

Ometepe, appearing in the upper right part of the image. The shape of the island clearly shows the shape

of two peaks formed by volcanoes, Maderas being located on the right and Concepcion on the left. The

largest concentration of the population that occupies the island is located in the surroundings of Concep-

cion and the economy of the island revolves around the tourism, taking advantage of some archeological

sites of the pre-Columbian era.

Page 7: A geothermal hydro wind PV hybrid system with energy

7 / 19

Table 1. Search space for the case study.

COMPONENT UNIT OF MEASURE QUANTITIES IN SEARCH SPACE

Enercon E-53 WT Wind Turbine

[Rated Power 800 kW] 0; 1; 3; 4; 5; 6; 7; 8; 9; 12; 15; 18; 21; 24; 27; 30; 33; 36

Solar Park Installed MW 0; 2; 4; 6; 8; 10; 12; 14; 16; 18; 21; 24; 27; 30

Converter (representing installed

hydropower capacity) Installed MW 0; 5.74; 6.90; 8.60; 10.33; 11.48; 13.78; 17.22

Maderas’ active volume of PSH

reservoir

Batteries

[1 battery = 2000 m³] 0; 1; 3; 6; 9; 12; 15; 18; 21; 27

Geothermal Installed MW 0, 1; 2; 3; 4; 5; 6

According to Ranaboldo et al. [44], most of the past efforts in Nicaragua related to electrification of

areas far from the main cities were focused on grid extensions. However, for many parts of the country,

such solutions are technically and financially unfeasible due to the remote and dispersed nature of small

communities, or because of geography features that pose a major obstacle to the extension of the electric

grid (mountains, forests, lakes, etc.).

Figure 2. Satellite image showing the region of the island of Ometepe in Nicaragua.

Page 8: A geothermal hydro wind PV hybrid system with energy

8 / 19

The reminder of this section is composed of six subsections, now dedicated to a better detailing of the

components of the system in HOMER, describing the photovoltaic modules, wind turbines, PSH plant, ge-

othermal plant and load profile, finishing with a last subsection mentioning additional considerations.

Based on Figure 1, the hybrid system considers the possible installation of PV modules, wind tur-

bines of the Enercon E-53 type, a geothermal generating plant and a PSH plant to meet a total demand of

70 MWh per day, with a maximum demand value of 4 MW. The PSH plant is modeled in this system by the

combination of a battery and a converter, reserving the DC bus for this purpose only.

3.1. Solar resource

HOMER requires solar resource inputs for calculating the PV array power output for each hour of the

day and year. Based on the latitude and longitude, HOMER is able to retrieve monthly solar data for the

specified latitude and longitude from NREL's (National Renewable Energy Laboratory) and NASA's (Na-

tional Aeronautics and Space Administration) satellite databases. Using this HOMER capacity, Figure 3

presents the results for the daily radiation (in kWh/m²/d) at Ometepe.

By 2014, solar accounted for only 0.10% (1.4 MW) of the total installed capacity of the SIN was solar

[42]. Even with great potential for solar energy production, PV arrays in Nicaragua are almost entirely

used for self-generation in households and small industry. In more recent years, the most important solar

project in Nicaragua is Polaris Solar Park, with 12 MW of installed capacity, which was completed in No-

vember 2017 [44].

Figure 3. Solar resource inputs for Ometepe.

In order to limit the land-use requirements for the solar power plant, the maximum size considered

for the solar park was set at 30 MW. According to the information available at [45], the land requirements

for a PV solar park could range between 0.89 to 4.90 ha/MW, with a capacity-weighted average of 2.80

m²/MW. Ometepe total area is 276 km² (27,600 hectares) [47], meaning than in the worst-scenario, the

land use requirements would be 150 hectares (0.53% of the island area).

3.2. Wind turbine and wind speed data

For wind power estimation, HOMER can make use of time series data with 8,760 values representing

the average wind speed, in meters per second, for each hour of the year. The wind resource for Ometepe

was obtained from the Modern-Era Retrospective Analysis for Research and Applications, Version 2

(MERRA-2), which is a reanalysis dataset produced by Global Modeling and Assimilation Office (GMAO) at

NASA [48]. The average wind data used in HOMER for each hour of the year was the average for the cor-

responding hour from January 1998 to April 2018. Based on these considerations and information, the

wind resource input used by HOMER is shown in Figure 4.

Page 9: A geothermal hydro wind PV hybrid system with energy

9 / 19

Figure 4. Wind resource inputs for Ometepe.

Ometepe is one of the regions with significant wind power potential in Nicaragua [49]. However, the

only relevant wind parks of the country are located in Rivas, a few kilometers (~30 km) from the island.

Amayo wind farm, which started operating Phase I in 2009, and Phase II in 2010, has an installed capacity

of 63 MW, corresponding to 30 SUZLON S88 wind turbines of 2.1 MW each [50]. An initial set of simula-

tions were completed in HOMER and, for the wind regime found by using data from MERRA-2, it was

found that better power output from the available wind in Ometepe could be achieved by using ENERCON

E-53 wind turbines (800 kW rated power), described in [51], thus, this type of turbine is used when eval-

uating this case study. The turbine could be placed offshore the island, in the shallow waters of lake Nica-

ragua.

3.3. Representing pumped storage hydropower

Crater lakes situated in dormant or extinct volcanos usually have fresh water. The existing crater lake

at Maderas volcano (11°26′44″ N, 85°30′54″ W) will be used as the upper reservoir of the PSH plant. This

volcano is a small, asymmetrical stratovolcano that, along with the Concepción volcano and connected by

the Istián isthmus, forms the dumbbell-shaped Ometepe island located in Lake Nicaragua, Nicaragua. Ac-

cording to studies and evidence, Maderas volcano has been inactive for tens of thousands of years and

future volcanic eruptions are not considered a threat [46]. Lake Nicaragua, with an elevation around 32

m.a.s.l. and average depth of 13 m, will serve as the lower reservoir.

According to [52], Maderas’ crater lake volume is approximately 239,000m³, with the water surface

ranging within 1203 and 1214 meters above sea level. Based on the information described, it was consid-

ered that the available head, taken as a fixed value, is H = 1170 m, both for pumps as for turbines. From

[53], some pumped storage plants with a head above 1000 m can be found in Austria, France, Italy, Roma-

nia and Spain.

As stated by [34], a combination of a battery bank and a converter can be used in order to represent a

PSH plant in Homer. For estimating the PSH cost, where important savings can be achieved by the fact that

no dam would need to be built, the set of cost functions presented in [54], which were created from real

information for Small Hydropower Projects in Nicaragua, was used for this purpose. As shown in Table 1,

this case study considers several options for the installed capacity of the PSH plant. The conversion effi-

ciency, both for pumps and for turbines, is assumed at 85%, an acceptable value according to [15].

For the upper reservoir, the authors of this paper considered that the lake could never be totally

emptied, thus the dead storage volume is the one corresponding to the height 1203 m (~4578 m³). Based

on that, the unitary battery (equivalent) for this case study is the one corresponding to the volume be-

tween heights 1203 m and 1204 m (~2000 m³). Using this volume, H = 1170 m as available head, and 10

kV as reference voltage in Eqs. (2) and (3), it produces an ES = 6.33 MWh and CB = 633 Ah, resulting in a

stored energy of 3.2 kWh/m³. The maximum charge current is set to 1,377 A, equivalent to a maximum

installed pumping capacity of 13.7 MW with 85% efficiency and a maximum pump flow QP = 1.2 m³/s. This

Page 10: A geothermal hydro wind PV hybrid system with energy

10 / 19

pump flow would refill from dead storage level to the maximum active level in 12 hours. The storage ca-

pacity assessed in this paper ranges within 1 (Z = 1204 m; Vol ≈ 2000 m³) and 27 (Z = 1212 m; Vol ≈

54,000 m³) equivalent batteries.

Even if there is no need to build a dam, and with a good extent of forestation in the Maderas’ volcanic

cone, it is important to mention that there are some geological hazards on this volcano, like earthquakes

and lahars [46], meaning that sound geological studies, an adequate design of the water intake, and rein-

forcing the stability of some areas of the mountainside could be required in order to implement this tech-

nical solution.

3.4. Geothermal

Because of its several lagoons and lakes, and the chain of volcanoes that runs along the Pacific region

of the country, Nicaragua is commonly referred to as "the land of lakes and volcanoes". The 16 active vol-

canoes, crater lakes, volcanic calderas, and numerous areas with hydrothermal activity, are clear indica-

tors of magmatic bodies with high geothermal potential. By 2016, the estimated geothermal potential for

Nicaragua was 1197 MW, from which 146 MW were identified for Ometepe island [55].

For estimating the capital cost per installed kW, it was used the average price of US$5,140/kW for

geothermal projects in Nicaragua found in [56], which is within the range of cost around the world shown

in [15]. The O&M costs are considered proportional to the energy production. Following the remarks de-

scribed in [57], this O&M cost was set at HOMER as US$20/MWh.

Based on the information found at the at the electricity map site [40] , the average geothermal CO2

emissions used in this paper are set at 38 gCO2/kWh.

3.5. Load

The AC load profile used in this case study was created from load curves of years 2014 and 2015, re-

lated to hourly demand along the day [58] and monthly demands along the year [42] in Nicaragua. The

annual average demand per person in Nicaragua is approximately 580 kWh/y [59]. Based on these load

profiles and annual demand, the latter were scaled, and a synthetic data series was created for its HOMER

use, based on the corresponding monthly and hourly scaled demand and standard deviation, in order to

generate the 8760 hours of energy demand for a population in Ometepe island of 44,000, according to

[46]. The hourly demand along the day and monthly demands along the year are shown in Figure 5.

Based on the information found at the electricity map site [40], and using information from July 12th,

2018 to July 15th, 2018 as sample, the average CO2 emissions of the SIN was estimated as 316 gCO2/kWh

(standard deviation = 48 gCO2/kWh). The average cost of energy for this period was $0.123/kWh.

Figure 5. Scaled load profiles for the case study.

3.6. Additional considerations

Besides the information previously described for the resources and components of the system, there

are some additional considerations and assumptions that must be included in the HOMER model in order

to run the simulation for the proposed 100% renewable system. The lifetime of the project and equipment

was assumed as 20 years, a common assumption for electromechanical equipment, with an annual real

interest rate of 6%. As for the Maderas’ crater lake, the upper reservoir of the PSH represented by the

equivalent battery bank, the technical lifetime for this component was set as 60 years, based on [15]. The

Page 11: A geothermal hydro wind PV hybrid system with energy

11 / 19

lifetime for the steam turbines of the geothermal plant, expressed in operating hours, was set at 100,000

hours, following what is mentioned in [60]. When HOMER calculates the NPC, and according to Lambert et

al. [39], if the upper reservoir lifetime is 60 years, the salvage value of this component will be two-thirds

of its capital cost at the end of the 20-year project lifetime.

As for the system constraints, the arrangement must count with enough spare capacity to serve sud-

den increases in the load. HOMER includes this consideration in the operating reserve parameter, and the

10% default value is used. The load-following strategy was adopted as the dispatch policy, and the maxi-

mum acceptable capacity shortage value was set at zero, meaning that electricity shortfalls are not al-

lowed to happen.

As stated before, one aim of this paper is to assess the impact of the generation cost in the comple-

mentarity between solar and wind power generation and optimal configuration of the system. Because of

that, some important assumptions made for modeling this case study in HOMER are:

The system will be assessed for two conditions for serving base load: using geothermal power and

using only VRES (wind and solar).

The operating reserve for solar and wind power was set at 20% for both. This means that the hy-

brid power system must keep sufficient spare capacity in operation to attend the load even if the

output suddenly increases 20%. In addition to serve as spinning reserve, the importance of this

operating reserve is supported by the fact that accurately forecasting renewables is difficult. For

example, even though is possible to forecast wind power output a day in advance, forecast errors

of 20% - 50% are not uncommon [11].

To perform the sensitivity analysis related to the impact of cost per installed kW on the system

configuration, the capital cost for installed kW, both for PV panels as for wind turbines, was set at

US$2000/kW, and the multipliers of this cost used as sensitivity values were 0.75 and 1.25,

meaning that the costs range within US$1500/kW and US$2500/kW, acceptable values for re-

newable projects in Nicaragua [42, 49, 61, 62].

For estimating the O&M cost, it was assumed that the annual O&M cost equals 3% of the capital

cost for wind turbines and solar park, based on [63]-[64]. For PSH, represented in the HOMER

model as the combination of the battery bank and the converter, the O&M cost was set at 6% of

the capital cost, according to the remarks made by [65]. This O&M cost is independent of the sen-

sitivity values applied to the capital cost for PV and Wind power installed kW.

4. Simulation results and discussion

Based on the method and case study previously described, this section presents and discusses the

main results of the simulation and sensitivity analysis made with HOMER. Besides the sensitivity analysis

related to the impact of cost per kW installed on the hybrid system configuration, this paper evaluated the

importance of a reliable and continuous energy source (i.e.: geothermal power) to serve the base load.

For all conditions described for the case study, HOMER was able to find a feasible system configura-

tion. This suggests that is technically feasible to supply Ometepe island with electricity coming entirely

from its renewable energy resources.

This section has three subsections. The first presents results related to systems including the geo-

thermal alternative, while the second subsection deals with systems that do not include it. A third subsec-

tion includes some additional considerations that are not related only to these two possibilities.

4.1. System configuration when considering geothermal option

When the existence of a geothermal plant for serving base load is considered, the optimal system

configuration is almost uniform for all sensitivity analysis cases. The results are summarized and shown in

Table 2. As expected, due to its dispatchable nature and based on the constraints and operating conditions

previously described, geothermal power provides the capacity for serving the baseload for the island. For

all sensitivities regarding solar and wind power capital cost, wind was always part of the optimal system

configuration found by HOMER, energy storage is required for all cases, and solar power was never in the

mix. Intermediate and peak loads are supplied by the intermittent source and PSH , limiting the excess

electricity, and minimizing the size and quantity of wind turbines, required hydropower and energy stor-

age. The excess electricity values shown in Table 2 include the electricity required to pump water to refill

Page 12: A geothermal hydro wind PV hybrid system with energy

12 / 19

the upper reservoir.

Figure 6 shows the optimization space for the hybrid systems that consider the geothermal power

plant option. Even if they were not specified in the sensitivity analysis, HOMER also calculated results for

PV capital cost multipliers lower than those shown in Table 2. Optimal solutions close to multiplicative

factors equal to one do not include photovoltaic modules. But there is an inclined dividing line, between

approximately the values of 0.35 and 0.60 for the PV capital cost multiplier, from which the solutions

begin to include them. These amounts correspond to relatively low acquisition costs that can be reached

in eventual situations like the purchase of large quantities of PV panels or with some kind of governmental

financial support.

Table 2. Summarized results for the sensitivity analysis considering geothermal power plant.

PV Capital Cost (USD/kW) $2000 $2000 $2000 $1500 $1500 $2500 $2500

Wind Power Capital Cost (USD/kW)

$2000 $1500 $2500 $2000 $2500 $2000 $1500

Description Units 1 2 3 4 5 6 7

Primary Load MWh/d 69.92 69.92 69.92 69.92 69.92 69.92 69.92

PV MW - - - - - - -

E-53 Units (800 kw

each) units 4 5 3 4 5 3 4

Maderas active volume m³ 4000 4000 4000 4000 4000 4000 4000

Geothermal power

installed MW 3 3 3 3 3 3 3

Converter MW 5.74 5.74 5.74 5.74 5.74 5.74 5.74

Total Capital Cost x10^6 USD 27.36 26.96 26.96 27.36 26.96 26.96 27.36

Total NPC x10^6 USD 37.86 36.03 39.12 37.86 36.03 39.12 37.86

Total O&M Cost x10^6

USD/year 0.86 0.85 0.86 0.86 0.85 0.86 0.86

Cost of Energy USD/kWh 0.13 0.12 0.13 0.13 0.12 0.13 0.13

Geothermal

Production

GWh/yr

(% of

total)

16.61

(61.6%)

14.05

(52.1%)

19.16

(71.2%)

16.61

(61.6%)

14.05

(52.1%)

19.16

(71.2%)

16.61

(61.6%)

Wind Production

GWh/yr

(% of

total)

10.33

(38.4%)

12.92

(47.9%)

7.75

(28.8%)

10.33

(38.4%)

12.92

(47.9%)

7.75

(28.8%)

10.33

(38.4%)

Tot. Electrical

Production GWh/yr 26.94 26.97 26.91 26.94 26.97 26.91 26.94

AC Primary Load

Served GWh/yr 25.51 25.51 25.51 25.51 25.51 25.51 25.51

Excess Electricity % 5.3% 5.4% 5.2% 5.3% 5.4% 5.2% 5.3%

Battery Throughput MWh/yr 4415.05 4391.14 4336.81 4415.05 4391.14 4336.81 4415.05

Battery Autonomy hours 4.35 4.35 4.35 4.35 4.35 4.35 4.35

Even when it’s possible to serve the load entirely with geothermal, the optimal configuration found

by HOMER always included wind power and energy storage from PSH. This supports what is mentioned in

[12], that in most cases, geothermal plants are more economical serving base load.

Page 13: A geothermal hydro wind PV hybrid system with energy

13 / 19

Using the sensitivity case scenario where the capital cost favors the installation of 5 wind turbines,

Figure 7 shows the average monthly electrical production. The total installed capacity for this case, not

including PSH turbines, is 7MW (the peak load for the system is ≈4MW). From December to April, the

wind speed regime at Ometepe would allow to serve the most part of the load using Wind Power. For this

scenario, the average capacity factor for the wind turbines is 36.9%, and 53.5% for geothermal, with this

latter required to work 4700 hours per year in average, allowing to extend the operational life of the

steam turbines beyond the project lifetime. The estimated cost of electricity (COE, expressed in $/kWh)

for this system configuration, and under the assumed conditions, would be around US$0.13/kWh, includ-

ing energy storage. This capacity factors and COE are within the range of acceptable values for electricity

production from renewables, according to [12] and are even better than the simulated costs for renewa-

bles in Nicaragua found in [49]. Nevertheless, it is important to remark that the geothermal potential in

Ometepe is on reconnaissance status and has not been completely assessed [55], therefore, more feasibil-

ity studies are required in order to provide a more accurate COE for this alternative.

Figure 6. Optimization space for the systems with geothermal power plant.

Because of the small size required for the upper reservoir of the PSH, the environmental and eco-

nomic aspects would be extremely important to determine if PSH is the better option for energy storage

and backup power for this system configuration, instead of actual battery banks or using fuel plants for

serving intermediate and peak loads. Alternatively, if PSH is found feasible, a greater active volume of the

upper reservoir could provide stability in the electricity supply for future population growth or intense

economic development of the island.

Figure 7. Monthly average electric production for system configuration with geothermal plant.

Page 14: A geothermal hydro wind PV hybrid system with energy

14 / 19

Another beneficial impact of adopting a 100% non-combustion renewable power system for

Ometepe island would be the CO2 emission reduction. When considering the inclusion of geothermal

power and based on information available at [40], it might be possible to avoid the emission of more than

6,000 tons/year of CO2. Based on the 38gCO2/kWh considered by the electricity map site, the estimated

CO2 emissions for the geothermal plant is less than 700 tons/year. Nevertheless, it is important to men-

tion that the CO2 emissions for geothermal power of this study could range between 180 tons/year and

7200 tons/year if the reference values shown at [12] for tropical areas are considered, meaning that an

adequate design and O&M of the technology used is required. This becomes even more relevant if carbon

credits are part of the economic analysis.

4.2. System configuration without geothermal option

When the geothermal option is not included, the generation costs from VRES have significant impacts

on the system components. Based on the described conditions and sensitivities, the most important out-

comes of the sensitivity analysis are shown in Table 3. The optimization space in this case indicates that a

combination of both VRES and the PSH plant are always part of optimal solution, as shown in Figure 8.

Table 3. Summarized results for the sensitivity analysis without geothermal power plant.

PV Capital Cost (USD/kW) $2000 $2000 $2000 $1500 $1500 $2500 $2500

Wind Power Capital Cost (USD/kW)

$2000 $1500 $2500 $2000 $2500 $2000 $1500

Description Units 1 2 3 4 5 6 7

Primary Load MWh/d 69.92 69.92 69.92 69.92 69.92 69.92 69.92

PV MW 10.00 8.00 14.00 14.00 14.00 10.00 8.00

E-53 Units (800 kw

each) units 24 27 15 15 15 24 27

Maderas active volume m³ 18000 18000 30000 30000 30000 18000 18000

Converter MW 5.74 5.74 6.90 6.90 6.90 5.74 5.74

Total Capital Cost x10^6 USD 70.94 60.94 77.19 64.19 70.19 75.94 64.94

Total NPC x10^6 USD 99.67 89.94 105.17 92.17 98.17 102.80 93.94

Total O&M Cost x10^6

USD/year 2.50 2.53 2.44 2.44 2.44 2.50 2.53

Cost of Energy USD/kWh 0.34 0.31 0.36 0.32 0.34 0.36 0.31

PV Production

GWh/yr

(% of

total)

14.83

(19.3%)

11.87

(14.5%)

20.77

(35.0%)

20.77

(35.0%)

20.77

(35.0%)

14.83

(19.3%)

11.87

(14.5%)

Wind Production

GWh/yr

(% of

total)

62

(80.7%)

69.75

(85.5%)

38.75

(65.0%)

38.75

(65.0%)

38.75

(65.0%)

62

(80.7%)

69.75

(85.5%)

Tot. Electrical

Production GWh/yr 76.84 81.62 59.52 59.52 59.52 76.84 81.62

AC Primary Load

Served GWh/yr 25.51 25.51 25.51 25.51 25.51 25.51 25.51

Excess Electricity % 66.8% 68.7% 57.1% 57.1% 57.1% 66.8% 68.7%

Battery Throughput MWh/yr 19.56 19.56 32.59 32.59 32.59 19.56 19.56

Battery Autonomy hours 1245.06 982.12 2581.42 2581.42 2581.42 1245.06 982.12

Page 15: A geothermal hydro wind PV hybrid system with energy

15 / 19

The high excess energy results for all system configurations (>50%) suggests that there is little com-

plementarity in time between solar and wind resources, meaning that their availability often occur simul-

taneously. For example, it is worth noticing that the hour of peak wind speed is at noon (See Figure 4).

This little complementarity increases the required size of the solar and wind parks, thus increasing the

cost of electricity. The minimum installed capacity, excluding the PSH, is 26MW, 6.5 times the peak load,

for a system configuration including a 14 MW solar park and fifteen E-53 wind turbines. For this system

configuration, the capacity factors estimated by HOMER were 16.9% for the PV panels and 36.9% for the

wind park.

Figure 8. Optimization space for the systems without geothermal power plant.

Based on the results shown in Table 3, and for the conditions evaluated and described in the case

study, the most economic configuration, in terms of NPC and COE was system #2, and the most expensive

was system #3. In terms of COE, the values ranged within US$0.31/kWh and US$0.36/kWh. According to

Asturias [49], the generation cost in Nicaragua for non-combustion renewables varies between

$0.08/kWh (hydropower minimum cost) and $0.28/kWh (wind power maximum cost). However, it is

important to remember, that for this work, the lifetime of the project and the PV panels and wind turbines

was set as 20 years, and no sensitivity analysis was conducted on the O&M cost. These two parameters

have an important impact on the COE of each system configuration [38].

4.3. Additional remarks

Besides being required in all system configurations and for all sensitivities, energy storage through

the PSH system using the Maderas’ crater lake and lake Nicaragua as reservoirs poses an interesting op-

tion in terms of energy storage economy. For this case study, the balance provided by higher energy stor-

age capacities corresponded to smaller total electricity production. It is important to point out that all the

optimal solutions provided by HOMER and discussed in the two previous subsections include the PSH

plant, regardless of the inclusion of a geothermal power plant or photovoltaic panels.

To offset the high cost of a system completely based on VRES, the excess electricity could be sold to

the grid (Ometepe is 30 km far from the city of Rivas), or could be used in activities that do not require

on-demand power and are not affected by intermittency, for example, water purification, wastewater

treatment, air conditioning or irrigation pumps [66-67]. Drinking water supply problems in Ometepe are

not uncommon, as evidenced in [68-69]. Another interesting option to consider, both for social and for

economic development of the island, is to improve water quality of lake Nicaragua and commercial fish

production through aeration using this excess energy, which could translate into positive environmental,

social and economic impacts that may well justify these investments through government subsidies.

Finally, the most important comment that can be made based on the results, is that the sensitivity

analysis performed using the HOMER software capacities proved that the economic aspects of electricity

production from renewable energy resources are at least as important as the energy resources availability

itself. Obviously, the availability of renewable resources is necessary to meet a demand with this type of

Page 16: A geothermal hydro wind PV hybrid system with energy

16 / 19

resource, but the technical and economic feasibility of the use of these resources is also necessary.

5. Conclusions

The aim of this paper was to evaluate how the capital cost of renewable technologies affects the op-

timal configuration and cost of electricity of an isolated electric power system, comprising only

non-combustion RES (geothermal, wind, solar, PSH). Ometepe island, in Nicaragua, was used as case

study, especially because it is located in a sweet water lake, has geothermal potential and the crater lake at

the top of one of its volcanoes makes it an interesting option for considering PSH. The methods described

and used in this paper are based on Canales and Beluco [34] and the recommendations provided by the

user support at HOMER Energy website [35]. The simulation, optimization and sensitivity analysis were

performed in the Legacy Version of HOMER Energy software [37].

The obtained results are in line with the general comments found in the literature. When geothermal

power is considered, this technology is able to serve the base load of the system, reducing the installed

capacity of other renewables, as well as decreasing the storage requirements and excess electricity pro-

duction. This configuration also evidenced that, for the case study, wind power is a more reliable and ef-

fective energy source than solar power. Shifting to a 100% non-combustion renewable power system

drastically reduces the carbon footprint of the power generation of the system.

When the geothermal option is not included, and the intermittent renewable resources have low

complementarity in time, the required size of the solar and wind parks is enormous, consequently rising

the COE and excess electricity production.

For the conditions evaluated in the case study the optimum solution for the hybrid system including

the geothermal plant would include four wind turbines, an upper PSH reservoir with a capacity of 4,000

m3 and a geothermal power plant with a capacity of 3 MW. The capital cost for this system would be US$

37,723,856 with COE of US$ 0.129 per kWh. The optimum solution for the hybrid system without the ge-

othermal plant would inclued 24 wind turbines, an upper PSH reservoir with capacity of 18,000 m3 and a

10 MW solar park, for a capital cost of US$ 98,168,616 and COE of US$ 0.366 per kWh.

The different hybrid system configuration results demonstrated that economic aspects of renewable

energy generation (e.g.: different capital costs combinations) are at least as important as the natural re-

sources availability. Also, regarding economic aspects of this work, Ometepe was selected as case study

because the use of a crater lake as the upper reservoir for PSH significantly reduces infrastructure in-

vestment. All the optimal system configurations found by HOMER required energy storage capacities.

This paper assessed Ometepe island as an isolated system, in order to evaluate its capacity to become

completely independent from the SIN. Future studies could well evaluate how the RES available at

Ometepe could integrate within this system and how other storage devices can be used in hybrid storage

systems with the Maderas PSH plant.

Besides a deeper evaluation (including technical and environmental aspects) of the PSH plant feasi-

bility using the Maderas’ crater lake as upper reservoir, a possible future research is how excess energy

from VRES can be sold to the SIN or used to improve the overall life quality of the island.

Acknowledgments

The authors are grateful for the support received by their institutions for the research work that resulted

in this paper. The third author acknowledges the financial support received from CNPq for his research

work (proc. n.312941/2017-0).

Conflicts of Interest

The authors declare no conflict of interest.

References

1. Elliston, B.; Diesendorf, M.; MacGill, I. Reliability of 100% renewable electricity supply in the Australian

National Electricity Market. In Towards 100% Renewable Energy; Uyar, T.S. Ed.; Springer, Switzerland,

2017; p. 297-303.

2. Jacobson, M. Z.; Delucchi, M. A.; Bazouin, G.; Dvorak, M. J.; Arghandeh, R.; Bauer, Z. A.; Cotte, A.; de Moor,

G.M.T.H.; Goldner, E.G.; Heier, C.; Holmes, R.T.; Hughes, S.A.; Jin, L.; Kapadia, M.; Menon, C.; Mullendore, S.A.;

Page 17: A geothermal hydro wind PV hybrid system with energy

17 / 19

Paris, E.M.; Provost, G.A.; Romano, A.R.; Srivastava, C.; Vencill, T.A.; Whitney, N.S.; Yeskoo, T.W. A 100%

wind, water, sunlight (WWS) all-sector energy plan for Washington State. Renewable energy 2016, 86,

75-88.

3. Diesendorf, M.; Elliston, B. The feasibility of 100% renewable electricity systems: A response to critics.

Renewable and Sustainable Energy Reviews 2018, 93, 318-330.

4. Jacobson, M. Z.; Delucchi, M. A. Providing all global energy with wind, water, and solar power, Part I:

Technologies, energy resources, quantities and areas of infrastructure, and materials. Energy Policy 2011,

39 (3), 1154-1169.

5. Mason, I. G.; Page, S. C.; Williamson, A. G. A 100% renewable electricity generation system for New Zealand

utilising hydro, wind, geothermal and biomass resources. Energy Policy 2010, 38 (8), 3973-3984.

6. BačelićMedić, Z.; Ćosić, B.; Duić, N. Sustainability of remote communities: 100% renewable island of Hvar.

Journal of Renewable and Sustainable Energy 2013, 5 (4), 041806.

7. McLaren, J. Reaching 100% Renewable Energy: Lessons-Learned from Aspen, Colorado. In Urban Energy

Transition (pp. 525-528). Elsevier, 2018.

8. Weir, T. Renewable energy in the Pacific Islands: Its role and status. Renewable and Sustainable Energy

Reviews 2018, 94, 762-771.

9. Hansen, K., Breyer, C., & Lund, H. Status and Perspectives on 100% Renewable Energy Systems. Energy

2019, 175, 471-480.

10. Sperling, K. How does a pioneer community energy project succeed in practice? The case of the Samsø

Renewable Energy Island. Renewable and Sustainable Energy Reviews 2017, 71, 884-897.

11. Sovacool, B.K. The intermittency of wind, solar, and renewable electricity generators: Technical barrier or

rhetorical excuse? Utilities Policy 2009, 17 (3-4), 288-296.

12. Fridleifsson, I.B. Geothermal energy for the benefit of the people. Renewable and sustainable energy reviews

2001, 5 (3), 299-312.

13. Murage, M.W.; Anderson, C. L. Contribution of pumped hydro storage to integration of wind power in

Kenya: An optimal control approach. Renewable Energy 2014, 63, 698-707.

14. Jurasz, J.; Dąbek, P.B.; Kaźmierczak, B.; Kies, A.; Wdowikowski, M. Large scale complementary solar and

wind energy sources coupled with pumped-storage hydroelectricity for Lower Silesia (Poland). Energy

2018, 161, 183-192.

15. Carlsson, J.A. Energy Technology Reference Indicator projections for 2010-2050. European Commission –

Joint Research Centre. Institute for Energy and Transport. Luxembourg, 2014.

16. Pujades, E.; Willems, T.; Bodeux, S.; Orban, P.; Dassargues, A. Underground pumped storage hydro electric-

ity using abandoned works (deep mines or open pits) and the impact on groundwater. Hydrogeology Jour-

nal 2016, 24 (6), 1531-1546.

17. Menéndez, J.; Loredo, J.; Fernandez, J.M.; Galdo, M. Underground Pumped-Storage Hydro Power Plants with

Mine Water in Abandoned Coal Mines. In Proceedings of the IMWA 13th International Congress, 2017,

pp.6-13.

18. Lu, B.; Stocks, M.; Blakers, A.; Anderson, K. Geographic information system algorithms to locate prospective

sites for pumped hydro energy storage. Applied Energy 2018, 222, 300-312.

19. Bunker, K., Hawley, K., &Morris, J. (2015) Renewable Microgrids: Profiles from Islands and remote com-

munities across the globe. Rocky Mountain Institute, November 2015. Available online:

http://www.rmi.org/islands_renewable_microgrids (accessed on 15 March 2019)..

20. Duić, N.; Carvalho, M.G. Increasing renewable energy sources in island energy supply: case study Porto

Santo. Renewable and Sustainable Energy Reviews 2004, 8 (4), 383-399.

21. Bueno, C.; Carta, J.A. Technical–economic analysis of wind-powered pumped hydro storage systems. Part

II: model application to the island of El Hierro. Solar energy 2005, 78 (3), 396-405.

22. Bueno, C.; Carta, J.A. Wind powered pumped hydro storage systems, a means of increasing the penetration

of renewable energy in the Canary Islands. Renewable and Sustainable Energy Reviews 2006, 10 (4),

312-340.

23. Caralis, G.; Zervos, A. Analysis of the combined use of wind and pumped storage systems in autonomous

Greek islands. IET Renewable Power Generation 2007, 1 (1), 49-60.

24. Caralis, G.; Rados, K.; Zervos, A. On the market of wind with hydro-pumped storage systems in autonomous

Greek islands. Renewable and Sustainable Energy Reviews 2010, 14 (8), 2221-2226.

25. Papaefthimiou, S.; Karamanou, E.; Papathanassiou, S.; Papadopoulos, M. Operating policies for

Page 18: A geothermal hydro wind PV hybrid system with energy

18 / 19

wind-pumped storage hybrid power stations in island grids. IET Renewable Power Generation 2009, 3 (3),

293-307.

26. Katsaprakakis, D.A.; Christakis, D.G.; Pavlopoylos, K.; Stamataki, S.; Dimitrelou, I.; Stefanakis, I.; Spanos, P.

Introduction of a wind powered pumped storage system in the isolated insular power system of Kar-

pathos–Kasos. Applied Energy 2012, 97, 38-48.

27. Kapsali, M.; Anagnostopoulos, J. S.; Kaldellis, J.K. Wind powered pumped-hydro storage systems for remote

islands: a complete sensitivity analysis based on economic perspectives. Applied energy 2012, 99, 430-444.

28. Ma, T.; Yang, H.; Lu, L.; Peng, J. Technical feasibility study on a standalone hybrid solar-wind system with

pumped hydro storage for a remote island in Hong Kong. Renewable Energy 2014, 69, 7-15.

29. Papaefthymiou, S.V.; Papathanassiou, S.A. Optimum sizing of wind-pumped-storage hybrid power stations

in island systems. Renewable energy 2014, 64, 187-196.

30. Ma, T.; Yang, H.; Lu, L.; Peng, J. Optimal design of an autonomous solar–wind-pumped storage power sup-

ply system. Applied Energy 2015, 160, 728-736.

31. Barreira, I.; Gueifão, C.; Jesus, J.F. (2017). Off-stream Pumped Storage Hydropower plant to increase re-

newable energy penetration in Santiago Island, Cape Verde. In Journal of Physics: Conference Series (Vol.

813, No. 1, p.012011). IOP Publishing.

32. Tsamaslis, P.; Karagiorgis, G.; Katsanevakis, A. Hybridization of photovoltaics with pumped storage hydro-

electricity. An approach to increase RES penetration and achieve grid benefits. Application in the island of

Cyprus. Journal of Power Technologies 2018, 97 (4), 336-341.

33. Sinha, S.; Chandel, S.S. Review of software tools for hybrid renewable energy systems. Renewable and Sus-

tainable Energy Reviews 2014, 32, 192-205.

34. Canales, F.A.; Beluco, A. Modeling pumped hydro storage with the micropower optimization model

(HOMER). Journal of renewable and sustainable energy 2014, 6 (4), 043131.

35. HOMER Energy Support. (2017). Simulating Geothermal Power. Available online: http://usersupport.

homerenergy.com/customer/en/portal/articles/2188860-simulating-geothermal-power (accessed on 15

March 2019).

36. Meza, C.G.; Rodríguez, C.Z.; D’Aquino, C.A.; Amado, N.P.; Rodrigues, A.; Sauer, I.L. Toward a 100% renewa-

ble island.: a case study of Ometepe’s energy mix. Renewable Energy 2019, 132, 628-648.

37. HOMER Legacy (Version 2.68). Available online: http://www.homerenergy.com (accessed on 25 Septem-

ber 2018).

38. Canales, F.A.; Beluco, A.; Mendes, C.A.B. A comparative study of a wind hydro hybrid system with water

storage capacity: Conventional reservoir or pumped storage plant? Journal of Energy Storage 2015, 4,

96-105.

39. Lambert, T.; Gilman, P.; Lilienthal, P. Micropower system modeling with HOMER. In Integration of alterna-

tive sources of energy; Farret, F.A., Simões, M.G., Eds.; Wiley Interscience, USA, 2006; pp.379-418.

40. Zoundi, Z. CO2 emissions, renewable energy and the Environmental Kuznets Curve, a panel cointegration

approach. Renewable and Sustainable Energy Reviews 2017, 72, 1067-1075.

41. Electricity Map: Mapping the climate impact of electricity. Available online:

https://www.electricitymap.org/ (accessed on 25 October 2018).

42. FUNIDES. (2016) Informe final: El sector de energía eléctrica de Nicaragua.

43. https://goo.gl/maps/XEVVrMfKK632

44. Ranaboldo, M.; Domenech, B.; Reyes, G.A.; Ferrer-Martí, L.; Moreno, R. P.; García-Villoria, A. Off-grid com-

munity electrification projects based on wind and solar energies: A case study in Nicaragua. Solar Energy

2015, 117, 268-281.

45. Sánchez, P. (November 21st, 2017). Comienza el funcionamiento de la planta Solaris de 12 MW en Nicara-

gua. PV Magazine. Available online: https://www.pv-magazine-latam.com (accessed on March 15, 2019).

46. Ong, S.; Campbell, C.; Denholm, P.; Margolis, R.; Heath, G. Land-use requirements for solar power plants in

the United States. National Renewable Energy Laboratory (NREL), Report NREL/TP-6A20-56290, Golden,

CO, USA, 2013.

47. Kapelanczyk, L.; Rose, W. I.; Jicha, B. An eruptive history of Maderas volcano using new 40 Ar/39 Ar ages

and geochemical analyses. Bulletin of Volcanology 2012, 74 (9), 2007-2021.

48. Global Modeling and Assimilation Office (GMAO). MERRA-2 tavg1_2d_slv_Nx: 2d,1-hourly, time-averaged,

single-level, assimilation, single-level diagnostics V5.12.4, Greenbelt, MD, USA, Goddard earth sciences da-

ta and information services center (GES DISC). Available online: https://doi.org/10.5067/VJAFPLI1CSIV

Page 19: A geothermal hydro wind PV hybrid system with energy

19 / 19

(accessed on 15 December 2018).

49. Asturias, J. Desarrollo y situación actual del sector eólico en América Central. Organización Latinoamericana

de Energía (OLADE), Quito, Ecuador, 2012.

50. SUZLON. (2012). S88 - 2.1 MW technical overview. Available online: www.suzlon.com (accessed on 15

March 2019).

51. ENERCON. (2014). ENERCON product overview. Available online: www.enercon.de/en/products/ (ac-

cessed on 01 March 2019).

52. Gómez Navarrete, J.A. (2010). Volcán Maderas: identificación de áreas con potenciales riesgos de inunda-

ción y deslizamiento a través de geoprocesamiento con SIG.

53. International Water Power & Dam Construction. (2012). The world’s pumped storage plants. In Interna-

tional Water Power & Dam Construction Yearbook; Stocks, C., Ed..; Global Trade Media, London, England;

2012. pp.282-292.

54. Canales, F.A.; Beluco, A.; Mendes, C.A.B. A matter of cost. International Water Power & Dam Construction

2014, 60 (12), 43-45

55. Moya Rojas, P. Central and South America: Significant but constrained potential for geothermal power

generation. In Geothermal Power Generation, Developments and innovation; Di Pippo, R., Ed.; Woodhead

Publishing, 2016, pp.667-715.

56. Perard, E. High Level of Private Activity in Energy, Transport, and Water in IDA Countries in 2010. Availa-

ble online: http://openknowledge.worldbank.org (accessed on 15 March 2019).

57. Coskun, A.; Bolatturk, A.; Kanoglu, M. Thermodynamic and economic analysis and optimization of power

cycles for a medium temperature geothermal resource. Energy conversion and management 2014, 78,

39-49.

58. MINISTERIO DE ENERGÍA Y MINAS. (2016). Anuario estadístico del sector eléctrico nacional 2015.

59. The World Bank. Electric power consumption (kWh per capita). Available online:

https://data.worldbank.org/ indicator/EG.USE.ELEC.KH.PC (accessed on 15 March 2019).

60. Siemens. Life Time Assessment Life Time Extension. Power Generation Services Division. Available online:

https://www.energy.siemens.com (accessed on March 15, 2019).

61. Nueve parques eólicos para Rivas. El Nuevo Diario, December 5, 2011. Available online:

https://www.elnuevodiario.com.ni/nacionales/235126-nueve-parques-eolicos-rivas (accessed on 15

March 2019).

62. Calero, M. Proyecto solar del empresario italiano de los Go Kart está paralizado en Nicaragua. La Prensa,

July 7, 2017. Available online: https://www.laprensa.com.ni (accessed on 10 March 2019).

63. Lemming, J.K.; Morthorst, P.E.; Clausen, N.E.; Jensen, P.H. Contribution to the Chapter on Wind Power in

Energy Technology Perspectives 2008. Risø National Laboratory for Sustainable Energy; 2009. Available at

http://orbit.dtu.dk/files/3737903/ris-r-1674.pdf (accessed on 08 March 2019).

64. Enbar, N.; Weng, D.; Klise, G.T. Budgeting for Solar PV Plant Operations & Maintenance: Practices and Pric-

ing. Sandia National Laboratories (SNL-NM), Report SAND--2015-10851R, Albuquerque, USA, 2015.

Available online: https://prod-ng.sandia.gov/techlib-noauth/access-control.cgi/2016/160649r.pdf (ac-

cessed on 15 March 2019).

65. Sadden, B.E. Maintenance of pumped storage plants. In Pumped Storage: Proceedings of the conference

organized by the Institution of Civil Engineers at Imperial College of Science, Technology and Medicine, Lon-

don, April 2-4, 1990, Thomas Telford Publishing, pp.117-141.

66. Barnhart, C.J.; Dale, M.; Brandt, A.R.; Benson, S.M. The energetic implications of curtailing versus storing

solar-and wind-generated electricity. Energy & Environmental Science 2013, 6 (10), 2804-2810.

67. Papavasiliou, A.; Oren, S.S. Coupling wind generators with deferrable loads. In Energy 2030 Conference;

November, 2008. ENERGY 2008. IEEE, pp.1-7.

68. Calero, M. Denuncian contaminación del agua en Ometepe. La Prensa, June 9, 2016. Available online:

https://www.laprensa.com.ni (accessed on 09 March 2019).

69. Villareal, R. Falta agua potable en la Isla de Ometepe. Periódico Hoy, February 22, 2014. Available online:

http://www.hoy.com.ni (accessed on 15 March 2019).