4 tappan zee bridge replacement options · the form or arrangement of the main spans is outside the...

8
New York State Department of Transportation New York State Thruway Authority MTA Metro-North Railroad Tappan Zee Bridge/I-287 Corridor Project Alternatives Analysis for Rehabilitation and Replacement of the Tappan Zee Bridge Page 27 Ove Arup & Partners Consulting Engineers PC March 2009 4 Tappan Zee Bridge Replacement Options This chapter describes possible options to replace the existing Tappan Zee Bridge. Three Replacement Options representative of possible crossing span arrangements have been developed. See Appendix C for detailed drawings of the three Replacement Options. 4.1 Replacement Option 1 This chapter outlines the details of Replacement Option 1 for the Tappan Zee Bridge. The option assumes the same highway and transit arrangement as Rehabilitation Options 2 and 3, as defined by Alternative 3 of the Alternatives Analysis Report of January 2006, but with the existing structure replaced. The option consists of two new single-level bridges, each carrying four general purpose lanes, one BRT/HOV lane and full sized shoulders, plus paths for pedestrians and cyclists. See Figure 4-1. 4.1.1 Rockland Landing The features of the landing are exactly the same as those for Rehabilitation Option 2. 4.1.2 Replacement Structure The replacement Tappan Zee Bridge has the same structural form and arrangement as the Supplemental Bridge in Rehabilitation Option 3. It would be constructed to the north of the existing Tappan Zee Bridge. To avoid impacting the foundations of the existing Tappan Zee Bridge, the new bridge would be constructed at an offset of approximately 300 feet. The alignment of the new bridge is to the north of the existing Tappan Zee Bridge for the following reasons: 1. There is available NYSTA ROW to the north of the existing Tappan Zee Bridge on both sides of the river that is sufficient to accommodate construction. Sufficient ROW is not available on the south side at the Rockland landing, 2. A north alignment allows for a straight approach to the Westchester toll plaza. A south alignment would result in conflict between the bridge horizontal curvature and the approach to the toll plaza 3. The rail connection from the Hudson Line at the Westchester landing to the Tappan Zee Bridge aligns with the north side of the existing bridge. 4. Adequate space to accommodate a potential Tappan Zee Bridge station is located only on the north side of the existing bridge at the Westchester landing. 5. Adequate storage and staging space is available on the north side of the existing bridge on both sides of the river. For the above reasons the alignment of a new supplemental or replacement Tappan Zee Bridge is to the north of the existing bridge. Depending on which options are progressed into the DEIS a further assessment of the alignment options will be included in the DEIS. The new bridge would incorporate two decks, each 109 feet wide, with spans of 230 feet except at the Main Spans. The central channel crossing spans of the Main Spans would likely be 2,600 feet supported on 4 towers. The form or arrangement of the Main Spans is outside the scope of this report. The new Tappan Zee Bridge and its foundations would be designed to resist seismic loading. Preliminary investigations indicate that the foundations would be comprised of 4-foot diameter steel piles founded 250-350 feet beneath the river bed. This is discussed further in Chapter 5.3.6 of this report. 4.1.3 Westchester Landing The ROW at the Westchester Landing is approximately 260 feet wide at its narrowest point. Approximately 90 feet of the available space is on the north side and 80 feet is on the south side of the existing crossing. East of this constriction, the space available for the widening of the highway reduces because of the Toll Plaza and the on-ramp from Route 9 (Broadway). This available width compares to the 109 feet required to accommodate half of the replacement bridge in this arrangement option. The northern edge of the 220-foot wide replacement arrangement option is placed coincident with the northern intersection of the NYSTA and Metro-North ROW boundaries. The bridge is orientated such that there is a straight alignment from the Route 9 overbridge onto the replacement bridge. In this position and orientation there are no permanent property impacts with the exception of the additional ROW required to the north of the constriction to account for the space required for an access ramp to the Pedestrian and Bicycle Path. Given this positioning and orientation of the replacement Tappan Zee Bridge, the challenge at the Westchester Landing is to accommodate all the facilities required within the space available, while also ensuring that traffic operations can be maintained during the transition from the existing to the replacement Tappan Zee Bridge. The provisions for the following are the same as Rehabilitation Option 3: x Highway and BRT/HOV Lanes x Toll Plaza x Pedestrian and Bicycle Path x BRT access to Tarrytown Station x NYSTA Maintenance Facility and access x Special landing structure Replacement Option 1 Two New Parallel Structures to Provide Alternative 3 Components 8 General Purpose lanes 2 BRT/HOV Lanes 2 Pedestrian and Bicycle Paths Figure 4-1 Replacement Option 1

Upload: vutram

Post on 22-May-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 4 Tappan Zee Bridge Replacement Options · The form or arrangement of the Main Spans is outside the scope of this report. The new Tappan Zee Bridge and its foundations ... Tappan

New York State Department of TransportationNew York State Thruway AuthorityMTA Metro-North Railroad

Tappan Zee Bridge/I-287 Corridor ProjectAlternatives Analysis for Rehabilitation and Replacement of the Tappan Zee Bridge

Page 27 Ove Arup & Partners Consulting Engineers PCMarch 2009

4 Tappan Zee Bridge Replacement OptionsThis chapter describes possible options to replace the existing Tappan Zee Bridge. Three Replacement Optionsrepresentative of possible crossing span arrangements have been developed.

See Appendix C for detailed drawings of the three Replacement Options.

4.1 Replacement Option 1

This chapter outlines the details of Replacement Option 1 for the Tappan Zee Bridge. The option assumes thesame highway and transit arrangement as Rehabilitation Options 2 and 3, as defined by Alternative 3 of theAlternatives Analysis Report of January 2006, but with the existing structure replaced. The option consists oftwo new single-level bridges, each carrying four general purpose lanes, one BRT/HOV lane and full sizedshoulders, plus paths for pedestrians and cyclists. See Figure 4-1.

4.1.1 Rockland LandingThe features of the landing are exactly the same as those for Rehabilitation Option 2.

4.1.2 Replacement StructureThe replacement Tappan Zee Bridge has the same structural form and arrangement as the Supplemental Bridgein Rehabilitation Option 3. It would be constructed to the north of the existing Tappan Zee Bridge. To avoidimpacting the foundations of the existing Tappan Zee Bridge, the new bridge would be constructed at an offsetof approximately 300 feet.

The alignment of the new bridge is to the north of the existing Tappan Zee Bridge for the following reasons:

1. There is available NYSTA ROW to the north of the existing Tappan Zee Bridge on both sides of the riverthat is sufficient to accommodate construction. Sufficient ROW is not available on the south side at theRockland landing,

2. A north alignment allows for a straight approach to the Westchester toll plaza. A south alignment wouldresult in conflict between the bridge horizontal curvature and the approach to the toll plaza

3. The rail connection from the Hudson Line at the Westchester landing to the Tappan Zee Bridge aligns withthe north side of the existing bridge.

4. Adequate space to accommodate a potential Tappan Zee Bridge station is located only on the north side ofthe existing bridge at the Westchester landing.

5. Adequate storage and staging space is available on the north side of the existing bridge on both sides of theriver.

For the above reasons the alignment of a new supplemental or replacement Tappan Zee Bridge is to the north ofthe existing bridge. Depending on which options are progressed into the DEIS a further assessment of thealignment options will be included in the DEIS.

The new bridge would incorporate two decks, each 109 feet wide, with spans of 230 feet except at the MainSpans. The central channel crossing spans of the Main Spans would likely be 2,600 feet supported on 4 towers.The form or arrangement of the Main Spans is outside the scope of this report.

The new Tappan Zee Bridge and its foundations would be designed to resist seismic loading. Preliminaryinvestigations indicate that the foundations would be comprised of 4-foot diameter steel piles founded 250-350feet beneath the river bed. This is discussed further in Chapter 5.3.6 of this report.

4.1.3 Westchester LandingThe ROW at the Westchester Landing is approximately 260 feet wide at its narrowest point. Approximately 90feet of the available space is on the north side and 80 feet is on the south side of the existing crossing. East ofthis constriction, the space available for the widening of the highway reduces because of the Toll Plaza and theon-ramp from Route 9 (Broadway). This available width compares to the 109 feet required to accommodate halfof the replacement bridge in this arrangement option.

The northern edge of the 220-foot wide replacement arrangement option is placed coincident with the northernintersection of the NYSTA and Metro-North ROW boundaries. The bridge is orientated such that there is a

straight alignment from the Route 9 overbridge onto the replacement bridge. In this position and orientationthere are no permanent property impacts with the exception of the additional ROW required to the north of theconstriction to account for the space required for an access ramp to the Pedestrian and Bicycle Path.

Given this positioning and orientation of the replacement Tappan Zee Bridge, the challenge at the WestchesterLanding is to accommodate all the facilities required within the space available, while also ensuring that trafficoperations can be maintained during the transition from the existing to the replacement Tappan Zee Bridge.

The provisions for the following are the same as Rehabilitation Option 3:Highway and BRT/HOV LanesToll PlazaPedestrian and Bicycle PathBRT access to Tarrytown StationNYSTA Maintenance Facility and accessSpecial landing structure

Replacement Option 1 Two New Parallel Structures to Provide Alternative 3 Components

8 General Purpose lanes2 BRT/HOV Lanes

2 Pedestrian and Bicycle Paths

Figure 4-1

Replacement Option 1

Page 2: 4 Tappan Zee Bridge Replacement Options · The form or arrangement of the Main Spans is outside the scope of this report. The new Tappan Zee Bridge and its foundations ... Tappan

New York State Department of TransportationNew York State Thruway AuthorityMTA Metro-North Railroad

Tappan Zee Bridge/I-287 Corridor ProjectAlternatives Analysis for Rehabilitation and Replacement of the Tappan Zee Bridge

Page 28 Ove Arup & Partners Consulting Engineers PCMarch 2009

4.2 Replacement Option 2

This chapter outlines the details of Replacement Option 2 for the Tappan Zee Bridge. The option has the samehighway and transit arrangement as Rehabilitation Option 4, as defined for Alternative 4 (A, B, C & D). Theoption consists of three new single-level structures. Two carry four general purpose lanes, one BRT/HOV laneand full sized shoulders, plus a path for pedestrians and cyclists. The third carries two CRT tracks and amaintenance way along the central axis. See Figures 4-2 and 4-3 (Page 30).

To minimize the property impacts at the Rockland landing, the two highway structures are located above theCRT structure at the western end of the Tappan Zee Bridge.

4.2.1 Rockland LandingThe overall width of the possible replacement bridge at the Rockland Landing would be exactly the same asReplacement Option 1 and would have similar impacts.

A replacement Tappan Zee Bridge, in the form of Replacement Option 2, would require a width of up to 220feet at the landing. The edge of pavement would be typically 30-35 feet closer to the adjacent properties thanexisting conditions. Outside this 220-foot roadway width, additional space would be required at the landing forthe NYSTA maintenance access ramps, the maintenance area below, ramps for pedestrian access and thepedestrian/bicycle connections.

Details of the interchange ramps, South Broadway Bridge, Pedestrian and Bicycle Path, NYSTA docksidefacility and access, and retaining and noise walls are the same as Rehabilitation Option 2.

As the CRT tracks are located below the highway at the Rockland shore, the overall elevation of the proposedhighway is significantly higher (15-25 feet) than the existing. This higher roadway elevation is needed tomaintain the required clearance over River Road and the Hudson River. See Figure 4-3 (Page 30).

CRT ConfigurationAt the Rockland shore, the CRT tracks are located below the Thruway on their own structure, with a provisionfor a central 10-foot wide maintenance way. The maintenance way ends at the Rockland Landing, where localaccess would be provided for maintenance and emergency vehicles. The two CRT tracks would enter a tunnelimmediately at the landing and stay in tunnel for some distance under the Thruway.

4.2.2 Replacement StructureThe replacement Tappan Zee Bridge is the same structural form and arrangement as Replacement Option 1 andthe supplemental bridge in Rehabilitation Option 3.

A new bridge would be constructed to the north of the existing Tappan Zee Bridge at an offset of approximately300 feet to avoid impacts to the foundations of the existing structure.

The new Tappan Zee Bridge would incorporate two decks each 109 feet wide and one deck 62 feet wide withspans of 230 feet except at the Main Spans. The central channel crossing spans of the Main Spans would likelybe 2,600 feet supported on four towers. The form or arrangement of the Main Spans is outside the scope of thisreport.

The new Tappan Zee Bridge and its foundations would be designed to resist seismic loading. Preliminaryinvestigations suggest that the foundations would comprise 4-foot diameter steel piles founded 250-350 feetbeneath the river bed. This is discussed further in Chapter 5.3.6 of this report.

Replacement Option 2Three New Parallel Structures to Provide Alternative 4 Components

8 General Purpose lanes2 BRT/HOV Lanes

2 CRT Tracks2 Pedestrian and Bicycle Paths

Figure 4-2Replacement Option 2

Page 3: 4 Tappan Zee Bridge Replacement Options · The form or arrangement of the Main Spans is outside the scope of this report. The new Tappan Zee Bridge and its foundations ... Tappan

New York State Department of TransportationNew York State Thruway AuthorityMTA Metro-North Railroad

Tappan Zee Bridge/I-287 Corridor ProjectAlternatives Analysis for Rehabilitation and Replacement of the Tappan Zee Bridge

Page 29 Ove Arup & Partners Consulting Engineers PCMarch 2009

4.2.3 Highway and CRT ProfilesTo pass over the shipping channel, it is necessary for the CRT tracks to start climbing from the Rockland shore.(Figures 4-4 and 4-5, pages 31 and 32)

The transitioning of the CRT structure from below the highway structure to the point where the highway andCRT decks are at the same elevation takes a distance of almost 10,000 feet. From the Rockland shore to theMain Spans, the highway and CRT decks are always at different elevations. This transition is made up of twocomponents:

In the area of the horizontal curve near the Rockland shore, the highway structures above the CRTstructure separate to make room for the CRT structure to climb up to their level. It is only at the end of thehorizontal curvature that there is sufficient space between the two highway structures to fit the CRTstructure between them.From the end of the horizontal curve to the start of the Main Spans over the channel, the grade of the CRTtracks (1.5%) is greater than that of the highway structures (1.08%) to allow the structures to reach thesame elevation at the Main Spans.

The elevation of the highway at the end of the horizontal curve is +90 feet compared to +23 feet for the existinghighway.

4.2.4 Westchester LandingThe provisions for the highway and BRT/HOV Lanes, a Toll Plaza, the Pedestrian and Bicycle Paths, a possibleTappan Zee Station, the NYSTA Maintenance Facility and its access, and the special landing structure are thesame as for Rehabilitation Option 3.

Page 4: 4 Tappan Zee Bridge Replacement Options · The form or arrangement of the Main Spans is outside the scope of this report. The new Tappan Zee Bridge and its foundations ... Tappan

New York State Department of TransportationNew York State Thruway AuthorityMTA Metro-North Railroad

Tappan Zee Bridge/I-287 Corridor ProjectAlternatives Analysis for Rehabilitation and Replacement of the Tappan Zee Bridge

Page 30 Ove Arup & Partners Consulting Engineers PCMarch 2009

Figure 4-3Replacement Option 2: Typical Cross Sections

Cross Section located at main spans (NTS)

Pedestrian/Bicycle

Highway Lanes

BRT/HOV Lanes

15’ minimum clearanceon River Road

River Road

17’ 9” minimum clearancefor CRT

17’ 9”

15’

8’ (structure)

7’ (structure)

47’ 9” absolute minimum

57’ practical minimum

Elevation+15

Cross Section located at River Road

For this report the minimumclearance is not adopted.Instead a height of 57 feet isused to allow for:

Increased separation betweenthe CRT clearance envelopeand the highway structure toallow for maintenanceIncrease in structural depth ofthe CRT structure to facilitatethe adoption of a standardbridge deck section over theriver

A minimum clearance of 14’ 6’’ isassumed in the NYSTAmaintenance area.

Page 5: 4 Tappan Zee Bridge Replacement Options · The form or arrangement of the Main Spans is outside the scope of this report. The new Tappan Zee Bridge and its foundations ... Tappan

New York State Department of TransportationNew York State Thruway AuthorityMTA Metro-North Railroad

Tappan Zee Bridge/I-287 Corridor ProjectAlternatives Analysis for Rehabilitation and Replacement of the Tappan Zee Bridge

Page 31 Ove Arup & Partners Consulting Engineers PCMarch 2009

Figure 4-4Replacement Option 2: Exaggerated Highway and CRT Profile at Rockland Landing

Detail of Thruway Profile

3% Grade SagCurve

1.08%Grade

CrestCurve

0%Grade

Detail of CRT Profile

0%Grade

SagCurve

1.5%Grade

CrestCurve

0%Grade

1.08%Grade

CrestCurve

1.08%Grade

SagCurve

Page 6: 4 Tappan Zee Bridge Replacement Options · The form or arrangement of the Main Spans is outside the scope of this report. The new Tappan Zee Bridge and its foundations ... Tappan

New York State Department of TransportationNew York State Thruway AuthorityMTA Metro-North Railroad

Tappan Zee Bridge/I-287 Corridor ProjectAlternatives Analysis for Rehabilitation and Replacement of the Tappan Zee Bridge

Page 32 Ove Arup & Partners Consulting Engineers PCMarch 2009

Figure 4-5Replacement Option 2: Highway and CRT Separation

Horizontal Transition Zone (3000ft)

In this area, the CRT tracks would bebelow the highway lanes.

At the Rockland shore the structuressupporting the highway lanes would be

side by side. At the other end of this area,in the river, the structures supporting the

highway would be separated to allowspace for the CRT tracks.

Vertical Transition Zone (6500ft)

In this area, the elevation of the CRTtracks is below that of the highway.

Vertical Transition Zone (3500 ft)

In this area, the elevation of the CRTtracks is below that of the highway.

Common Elevation Zone (3500 ft)

In this area, the CRT tracks and thehighway are at the same elevation.

CRT Structure

Highway Structure

HighwayLanes

CRTTracks

HighwayLanes

HighwayLanes

CRTTracks

HighwayLanes

HighwayLanes

CRTTracks

HighwayLanes

HighwayLanes

CRTTracks

HighwayLanes

Nyack

Tarrytown

All lengths are approximate

Page 7: 4 Tappan Zee Bridge Replacement Options · The form or arrangement of the Main Spans is outside the scope of this report. The new Tappan Zee Bridge and its foundations ... Tappan

New York State Department of TransportationNew York State Thruway AuthorityMTA Metro-North Railroad

Tappan Zee Bridge/I-287 Corridor ProjectAlternatives Analysis for Rehabilitation and Replacement of the Tappan Zee Bridge

Page 33 Ove Arup & Partners Consulting Engineers PCMarch 2009

4.3 Replacement Option 3

This chapter outlines the details of Replacement Option 3 for the Tappan Zee Bridge. The option accommodatesthe same highway and transit facilities as Rehabilitation Options 4 and Replacement Option 2, as defined forAlternative 4 (A, B, C & D). The option consists of two dual-level structures, each carrying four generalpurpose lanes and one BRT/HOV lane. See Figures 4-6 and 4-7 (page 34). A double deck structure was chosento reduce the width of the structure compared to Replacement Option 2.

The northern structure carries the westbound Thruway on its upper deck and two CRT tracks on the lower level.The southern structure carries the eastbound Thruway on its upper deck and nothing on its lower deck.

4.3.1 Rockland LandingThe overall width of the possible replacement bridge at the Rockland Landing would be the same asReplacement Option 1 and would have similar components and impacts. Similar to Rehabilitation Option 4, thewestbound Causeway is a deeper structure than the existing Tappan Zee Bridge to accommodate CRT on thelower level. Consequently, the highway lanes are at a higher elevation in the landing area – up to 40 feet abovethe existing Thruway.

Details of the interchange ramps, South Broadway Bridge, Pedestrian and Bicycle Paths, NYSTA docksidefacility and access, and retaining and noise walls are similar to Replacement Option 1.

Replacement Option 3 has a similar footprint at the Rockland landing to Rehabilitation Options 4. The onlydifference between this option and the other options is the maintenance and emergency access to themaintenance way, located between the CRT tracks. These access needs require local adjustment of themaintenance access ramps and realignment of the highway to make the best use of the existing ROW.

4.3.2 Replacement StructureThe replacement bridge is of the same structural form and arrangement as the Supplemental Bridge inRehabilitation Option 4 (Figure 3-9, page 24), except that two structures are required instead of one.

A new Tappan Zee Bridge would be constructed to the north of the existing bridge at an offset of approximately300 feet to avoid impacts to the foundations of the existing crossing.

The new Tappan Zee Bridge would incorporate two decks each 109 feet wide on spans up to 400 feet except atthe Main Spans. The central channel crossing spans of the Main Spans would likely be 2,600 feet on foursupporting towers.

The new Tappan Zee Bridge and its foundations would be designed to resist seismic loading. Preliminaryinvestigations suggest that the foundations would be comprised of 4-foot diameter steel piles founded 250-350feet beneath the river bed. This is discussed further in Chapter 5.3.6 of this report.

It is necessary to have a double deck southern structure in order that the superstructure is as structurally efficientas the northern structure so that the two structures’ columns can be spaced identically. (Superstructure is theterm used for all the components of a bridge above the top of the piers.) The design and construction of thesouthern structure has provided for only no live load on the lower deck.

4.3.3 Highway and CRT ProfilesThe highway and CRT profiles are vertically parallel to each other for the entire Tappan Zee Bridge. Themaximum grade is 2% at the Westchester shore approach. At the shipping channel, the highway elevation isapproximately +195 feet assuming a shipping clearance of 155 feet.

4.3.4 Westchester LandingThe provisions for the highway and BRT/HOV Lanes, a Toll Plaza, the Pedestrian and Bicycle Paths, a possibleTappan Zee Station, the NYSTA Maintenance Facility and its access, and the special landing structure are thesame as for Rehabilitation Option 4.

Replacement Option 3 Two New Parallel Structures to Provide Alternative 4 Components

8 General Purpose lanes2 BRT/HOV Lanes

2 CRT Tracks2 Pedestrian and Bicycle Paths

Figure 4-6

Replacement Option 3

Page 8: 4 Tappan Zee Bridge Replacement Options · The form or arrangement of the Main Spans is outside the scope of this report. The new Tappan Zee Bridge and its foundations ... Tappan

New York State Department of TransportationNew York State Thruway AuthorityMTA Metro-North Railroad

Tappan Zee Bridge/I-287 Corridor ProjectAlternatives Analysis for Rehabilitation and Replacement of the Tappan Zee Bridge

Page 34 Ove Arup & Partners Consulting Engineers PCMarch 2009

Figure 4-7Replacement Option 3: Typical Cross Section

Section 1 from Figure 18.3

Pedestrian/Cycle

Highway Lanes

BRT/HOV Lanes

MNR Maintenance

Min Separation 2’