E2482 v4 TEIAS TURKEY ELECTRICITY TRANSMISSION CORPORATION GENERAL DIRECTORATE 380 kV YENIBOSNA GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN (ISTANBUL) FILE COpy ANKARA-JULY 2009 (Revised) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 23-Oct-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

  • E2482 v4

    TEIAS

    TURKEY ELECTRICITY TRANSMISSION

    CORPORATION

    GENERAL DIRECTORATE

    380 kV YENIBOSNA GIS SUBSTATION

    ENVIRONMENTAL MANAGEMENT PLAN

    (ISTANBUL)

    FILE COpy

    ANKARA-JULY 2009

    (Revised)

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

  • TEIAS 380 kV YEMBOSNA GIS SUBSTATION ENVIRONMENTAl_ MANAGEMENTM PLAN I}/'/'

    ' I / ,

    SECTION -1

    GENERAL POLICIES

  • TEIAS 380 kV YENIBOSNA GIS SUBSTATION ENVIRONMENTAL MANAGEMENTM PI..AN

    ENVIRONMENT AL LIABILITIES

    According to the Environmental Law with No: 2872 and related regulations, the contractor is required to obey the commitments, defined by the Project Owner, in the Final EIA Report/Final Project Description File of Electric Transmission Plant (overhead line, underground cables, substations etc.) whose "EIA Positive Verdict/EIA Not Necessary Verdict" is obtained from the Ministry of Environment and Forestry or Related Governorate.

    Commintments, which should be obeyed by the Contractor in accordance with the Environmental Legislation, are described in the "Mitigation and Monitoring Plans". Environmental Management Plan (EMP) Application Report covering the processes within the scope of EMP is required to be prepared by a firm having received licence from the Ministry of Environment and Forestry as to the "Necessity Certificate Communique" published in the offical gazzette with No:26961 and on the date of 8 August 2008.

    Following the signing of the contract and hand-over of the site, until the operational acceptance, the contractor is supposed to submit the EMP Application Reports, which are prepared in a quarterly basis, to the Project Owner to be transmitted to the Ministry of Environment and Forestry/Related Governorate/the World Bank.

    The contractor shall be required to present the Application Report to the Project Owner within maximum 7 (seven) days as from the end of the reporting period. If EMP Application Reports is not submitted to the Project Owner in due time, 10000 - TL (Ten Thousand Turkish Liras) is fined from the progress payment of the Contractor.

    If it is determined by the Project Owner, Ministry of Environment and Forestry/Governorate or third parties that the commintments within the scope of the Environmental Legislation are not obeyed by the Contractor, all the responsibilities are on the Contractor.

  • TEIAS 380 kV YENIBOSNA GIS SlJBSTATION ENVIRONMENTAL MANAGEMENTM PLAN

    SECTION - 2

    MITIGATION PLAN

  • TEIAS 380 kV YENIBOSNA GIS SUBSTATION ENVIRONMENTAL MANAGEMENTM PLAN

    1. MITIGATION PLAN

    In this section, feasible and cost-effective mitigations to be taken for the prevention of, reducing to acceptable levels or compensation of the probable adverse impacts of 380 kV Yenibosna GIS Substation Project, which were determined in the Project Description File (PDF), are presented. For ease-of-use, mitigation measures taken in each phase of the project are prefered in a tabular form (Table 2.1). Mitigation plan have been prepared as to cover the following subjects.

  • TEIAS 380 kV YENlBOSNA GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN

    -

    Ise Subject

    Cultural and Historical Assets

    Mitigation Measures"""

    In case of coinciding any cultural asset, the construction studies will be stopped immediately and the Cultural and Natural Assets Protection Committee will be informed. Until the response is taken, any action will not be done at the site. After taking the positive response (no cultural assets) the construction studies will continue.

    Cost

    No additional cost

    Responsible Institution""

    -- ~

    Contractor

    Start Date Finish Date

    Start of Construction Works

    Completion of construction works

    ~.--

    :UCTION

    Dust - Particulate Matter

    .~-

    • •

    • •

    The regulated limit value of Dust/Particulate matter emision being 3 mg/Nm3 (Industrial Air Pollution Control Regulation) is not to be exceeded. Watering will be done in the dry seasons Loading and unloading will be carried out with care and without scettering. In order not to lead to scattering, loading/unloading works will be performed in an area allocated for loading/unloding and water sprays will be used in this area. While loading/unloading, a limit drop height will be applied for the dusty materials. Additionally, the workers are warned being careful. In addition, wind direction and strength will be taken into account while loading and unloading. The trucks will be covered and speed limitation will be applied. Speed limit on trucks is 30 km/hr (at project site) and 50 km/hr (outer of the project site - within the city) Vehicles with emission stickers will be used In the case of storing vegetable soil at the site, it will be ensured to be covered with canvas or with the matter having particle size greater than 10 mm Tires of the trucks will be cleaned where necessary to prevent dirt being carried onto the roads

    -- .... ~-.- ....-- ....- .....- .... ~-.- .. ~-.- ...-- ...--------. ....- .... ~-

    Not High Contractor

    Start of the excavation work

    Completion of the excavation works

    - ....-

    5

  • --

    -- - -

    --

    TEIAS 380 kV YENIBOSNA GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN

    Finish Date Start Date ResponsibleSubject Mitigation Measures""" Cost se Institution""

    • The continuous work-site noise (day times) will be ensured

    to be under 70 dBA (according to the Turkish Evaluation of

    Environmental Noise Regulation.

    • During the construction, noise measurement will be done

    and according to the measurement, in the case of

    exceeding the noise level of 70 dBA, barriers preventing or

    reducing noise level (sound absorbing barriers) will be

    placed by the contractor.

    • All construction works will be done between 7am and 7pm. If.

    it is required to work after 7 pm, local authorities and public

    will be informed about these working hours. No additional

    Contractor Start of Construction:UCnON cost Completion of construction works Noise • People, living at the population centers around, will be Works informed about the working durations

    • The noise levels of the construction machines change with

    the power of the machines. Generally, the average noise

    level generated by the machines at the origin is around 80100 dB if they are worked altogether at the same time. The

    machines having less noise level will be preferred as much

    as possible. Maximum allowable noise level for the

    machines will be 120 dBA. If the noise limit is not satisfied,

    contractor will not work all the machines at the same time.

    When it is not possible or practical to reduce the number of

    the working machine, sound absorbing barriers will be used.

    Contractor Start of ConstructionlUCTION Wastewater Not High Completion of construction works • Wastewaters due to work-site will be given to the sewerage Workssystem of present istanbul Province Sewerage System

    6

  • TEIAS 380 kV YENIBOSNA GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN

    lse Subject

    I I Excavation, solid and

    hazardous wastes due

    I to construction

    -

    Mitigation Measures·_·

    Excavation wastes will not be dumped illegally other than Istanbul Greater Municipality Taya Kadln Excavation Wastes Disposal Area (40 km away from the city center) Solid wastes and packaging wastes (plastic, paper, glass etc.) will be systematically and separately collected and it will be ensured to be taken by Bahcelievier Municipality or a licensed recycle firm. Organic domestic wastes will be collected separately than the other types of wastes and it will be ensured to be taken by Bahcelievier Municipality and disposed to the Odayeri/GokWrk Solid Waste Landfill of Istanbul No wastes, which could not be broken down biologically, will be left at the construction area. Hazardous wastes such as oil, dye etc. will be collected separately in leak proof, metal and labeled containers and it will be ensured to be taken by a licensed firm ensured by the Contractor

    Cost

    Not high (changing by depending on municipalities

    and/or licensed recovery

    plant)

    Responsible Institution·

    Contractor

    Start Date

    Start of Construction Works

    Finish Date

    Completion of construction works

    --

    I

    Wastes due to vehicle parking

    ---

    -

    Waste oil due to construction machines and vechicles will be collected in rustles barrels and will be sent to a licenced firm by the contractor. The barrels will be placed onto an impermeable ground to protect rain and sun and all necessary precautions against fire will betaken Batteries, tires and similar items due to construction machines and vehicles will be sent to a licenced firm and will be ensured to be disposed

    Not High I

    Contractor Start of Construction

    Works Completion of construction works

    'uctlon

    Substation Oil

    Grounding, Health and Safety, Training

    -

    • •

    Substation oil exists in a container and will never be stored at the construction site temporarily. In the case of necessity of storing the oil at the site, it will be placed upon impermeable ground, covered to be prevented from rain and sun and the around of the stored area will be surrounded by placing warning sign. All precautions againts fire will be also taken

    All necessary protective equipments(hard hat, safety belt, gloves, protective clothes etc.} will be provided to the workers Proper notification signs will be placed The personal will be trained in first aid and "work health and safety"

    Not High

    No Additional Cost (as a

    part of proj ect budget)

    Contractor

    Contractor

    of the storing substation oil

    --

    Start of Construction Works

    Untill the transportation of substation oil

    --

    Completion of construction works

    7

  • TEIAS 380 kV YENIBOSNA GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN

    Finish Date Start Date ResponsibleSubject Mitigation Measures··· Cost Institution··

    • Within the framework of the program prepared by TEIAS Environmental Department, the noise will be measured at certain points around the substation. The measurements are

    ional tance

    Noise I • done around the substation (at fences surrounding the substation area, near ihlas Collage, recruiting office) If the measurement results exceed the limit values mentioned in the the Environmental Noise Evaluation and Control Regulation (Ldaytime:60 dBA, Lnighj:50 dBA), the sound absorbing barriers will be used and the levels are kept under the limit values.

    • Within the framework of the program prepared by TEIAS Environmental Department, the EMA strenght will be measured at certain points around the substation (fences surrounding the substation area). If the measurement results exceed the limit values mentioned in ICNIRP (5 kV/m for electric field/for public, 1000 mG for magnetic field), substation building, equipments (operation and protection), wall and fence will be grounded. In any case of sign of a failure (such as failure in the operation of an equipment, increasing the contact

    No Additional Cost (as a Start of Operational Completion of Operational Acceptance Contractor

    part of project Acceptance I budget

    Electro-Magnetic Field (EMF)

    .

    current, electrical arc, local warming etc.)the grounding

    resistance will be measured and according to the I measurement results the grounding og the ones having the

    problem will be strengthened by local rehabilitation

    (rehabilitation of loose, broken, corresioned grounding

    connection points), maintaining the continuity of the No Additional

    connections. Cost (as a Start of Operational Completion of Operational Acceptance Contractor

    part of project Acceptance• All the equipments of the substation (transformer, disconnector, circuit breaker, surge-arrester, current budget

    transformer, voltage transformer etc.) will be taken according

    ot the IEC and the controls and maintainance will be done in

    accordance with IEC.

    • Electrical and magnetic fields are measured by Electric-Magnetic Field (EMF) Meter. Measurement Units for Electric field (E) Vim while for Magnetic field (H) Aim (EMF can be . explained as Magnetic Field Intensity (B)/Unit: Gauss or Tesla. The measurements done by EMF Meter are done at 1 m above the earth ground. Measurement of electro-magnetic field is possible at any point in global volume by EMF meter.

    • The meter is portable. The meter is protectable against other electro-magnetic Signa~__ _ J

    8

  • TEIAS 380 kV YENIBOSNA GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN

    Ise Subject Mitigation Measures ....* Cost

    Responsible Institution**

    Start Date Finish Date

    --

    Landscape

    • •

    The work-site will be reassembled. No hazardous, solid, liquid wastes will be left at the site,

    No Additional Cost (as a

    part of project budget)

    Contractor Start of Operational

    Acceptance Completion of Operational Acceptance

    ation Health and Safety

    The personal will be selected from the people having trained in first aid, electric safety, working at high levels for the maintanace fo the substation. The warning signs and climbing barriers will be placed around the substation

    No Additional Cost (as a

    part of project budget)

    TEIAS Taking the substation into operation

    After the completion of the economic life of the substation

    'ation Fire Risk

    \--

    Electromagnetic field (EMA)

    ,------

    Substation oil

    , •

    • •

    The substation will be establihed as to the fire safety elements in the "Electric Intensive Current Plant Regulation" For the operation of the substation there is a standard yearly maintenance/operation and test program, The program will be followed during the operation of the substation, If there is a sign of failure unexpectedly (arc, local warming, decrease in the level of isolation, instability of current/voltage etc,) the enegy will be ceased and the trained operational personel working at the substation will provide technical support to solve the problem,

    It will be under the limit values determined in ICNIRP, For this purpose, substation building, equipments (operation and protection), wall and fence will be grounded, In any case of sign of a failure (such as failure in the operation of an equipment, increasing the contact current, electrical arc, local warming etc,)the grounding resistance will be measured and according to the measurement results the grounding og the ones having the problem will be strengthened by local rehabilitation (rehabilitation of loose, broken, corresioned grounding connection points), maintaining the continuity of the connections. All the equipments of the substation (transformer, disconnector, circuit breaker, surge-arrester, current transformer, voltage transformer etc.) will be taken according ot the IEC and the controls and maintainance will be done in accordance with IEC,

    Substation oil will be analyzed physically and chemically. When the oil completes its economic life, it will be replaced with new one and disposal of it will be ensured by conducting required test (to determine the category of the oil) and applying proper disposal method as to the category test results,

    No Additional Cost (as a

    part of project budget)

    Not High

    No additional cost

    TEIAS

    TEIAS

    TEIAS

    Taking the substation into operation

    -

    Taking the substation into operation

    -

    Taking the substation into operation

    After the completion of the economic life of the substation

    -

    After the completion of the economic life of the substation

    After the completion of the economic life of the substation

    I

    9

  • TEIAS 380 kV YENIBOSNA GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN

    --

    lse Subject Mitigation Measures*** Cost Responsible Institution""

    -

    Start Date Finish Date

    I

    Solid-liquid and Hazardous Wastes

    Solid wastes, junk materials and construction wastes will be collected seperately and they will be ensured to be taken by the municipality or a licenced firm No wastes which can not be broken down biologically will be left at the site. Wastes which can not be broken down biologically will be collected in a container and taken by the Bah

  • TEIAS 380 kV YENIBOSNA GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN

    • Decommisioning Phase, has been evaluated in the face of the completion of facility's economic life and the demolishing the substation come to order. After the completion of economic life of the substation, in case of taking decision on the continuation of the facility, studies will be conducted for the new substation in accordance with the subjects determined with the scope of EIA Regulation •• Valid in the case of handing over of the proposed works to subcontractors. Otherwise, responsibilities defined for contractor will belong to TEIAS ••• While taking the proposed measures, compliance with all related regulations (Air Quality Evaluation and Control Regulation, Water Pollution Control Regulation, Environmental Noise Evaluation and Control Regulation, Solid Waste Control Regulation, Soil Pollution Control Excavation, Construction and Demolishion Wastes Control Regulation, Hazardous Waste Control Regulation, Package and Packaging Waste Control Regulation, Grounding in Power Installations Regulation, Work Health and Safety Regulation, Health and Safety Conditions on Usage of Work Equipments Regulation) will be complied

    11

  • TEIAS 380 kV YENIBOSNA GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN

    SECTION - 3

    MONITORING PLAN

  • TEIAS 380 kV YENIBOSNA GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN

    3. MONITORING PLAN

    Environmental monitoring provides information about key environmental issues, especially about the efficiency ofmeasures taken and environmental impacts of the project, at the implementation phase of the project. This information enables project owner and audit mechanism to evaluate the effectiveness ofthe mitigation and to allow correct actions to be taken in the case of necessity. Therefore, EMP describes the aims and the types of monitoring by relating the impact assessments defined in PDF and the mitigation measures defined in EMP.

  • ---

    ---

    TEIAS 380 kV YENIBOSNA GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN

    Phase Subject

    Cultural and Historical Assets '

    What are the parameters,

    which would be monitored?

    Cultural assets at the site

    Dust Formation due to the

    Movement and Exhaust of the Construction Machinery

    Complaints from public

    Whe I would

    he

    parameters be How would the mon tored·Where would parameters be

    frequ sncyofthe monltoredityp heparameters be es ofthe

    me as Irementmonitored? monitoring s/co Itinuousequipment me as Irement

    ?

    In :ase of coin ciding a Construction

    Visual cultu ral assetsite

    conti lously by an a leogolist

    Visual observations Du ing the

    exc9vationConstruction Talking to the weekiIy I in the

    site local people c Ise of near the site co nplaint

    ~ ...

    Why would the parameters be

    monitored?

    Obeying the Cultural

    and Natural Assets

    Protection Law

    Industrial Air

    Pollution Control

    Regulation

    Cost

    Not high if no cultural assets are damaged

    No additional cost (within the project

    budget)

    The Institute that controls frequency of the control

    Provincial

    Culture and

    Museum

    Directorate

    (Controlled in

    case of

    coinciding a

    cultural asset)

    TEIAS

    Provincial

    Directorates of

    MoEF

    Start Date

    Start of the cunstruction

    works

    Start of construction

    works

    Finish Date

    Completion of

    construction works

    Completion of

    construction works

  • TEIAS 380 kV YENIBOSNA GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN

    onstruct ion

    Subject

    Noise

    What a param

    whichw monit,

    Noise

    re the tters, )uld be Ired?

    Level

    Where would the

    parameters be monitored?

    Construction site

    Ihlas Collage, recruiting Office

    around the substation

    How would the parameters be monitoredltyp

    e50fthe monitoring equipment

    Interviews to be conducted in

    near residential areas

    Noise level measurement with portable

    sound pressure measurement

    device

    When would the

    parameters be monitored

    frequency of the

    measurement s I continuous measurement

    ?

    Weekly observation of noise (tracking)

    Near residential areas, in the

    case of complaint

    Why would the parameters be

    monitored?

    Environmental Noise Evaluation and

    Control Regulation

    Cost

    Not High

    The Institute that controls frequency of the control

    TEiAS

    Provincial Directorate of Environment and Forestry

    Start Date

    Start of the cunstruction

    works

    Finish Date

    Completion of

    construction

    I works

    -- --

    15

  • ---------

    TEIAS

    What are the parameters,Phase I Subject which would be monitored?

    -+

    Wastewater due to construction sites

    and washing water

    Contamination (oil, ~onstruct I Wastewater Iturbidity) in the soil ion

    and water around the project site

    Odor generated at the project site

    Where would the

    parameters be monitored?

    Sewerage system

    (Wastewater generated by

    the workers will be given to the sewer system of the city. The connection to

    the sewer system and whether any

    wastewater is discharged to

    soil, water or to any receiving

    body except the permitted one

    will be observed and

    controlled" )

    How would the parameters be monitored/typ

    es of the monitoring equipment

    Visual

    When would the

    parameters be monitored

    frequency of the

    measurement s I continuous measurement

    ?

    Weekly

    380 kV YENIBOSNA GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN

    The Institute Why would the

    that controls - I Start Date parameters be Cost frequency of monitored? the control

    In accordence with Completion

    the Water Pollution No additional TEiAS Start of the ofControl Regulation cost (within the cunstruction

    and Soil Pollution project budget) works works

    Control Regulation Municipality

    LL_'L

    16

  • TEIAS

    Phase

    -

    Subject

    --

    Constru ction

    Excavation, Solid 3nd Hazardous

    Wastes

    Wastes due to lehicle Parking

    What are the parameters,

    which would be monitored?

    The disposal ofthe excavation wastes

    Seperation of solid wastes for

    recycle/recovery/re use, disposal at the

    Municipality's landfill

    Collection of hazardous wastes

    seperately in conteiners and disposal by a licenced firm

    Waste oils, automobile

    batteries,used tires and junk materials

    Where would the

    parameters be monitored?

    Construction site and

    disposal site

    At the vehicle parking area

    How would the parameters be mon Itoredltyp

    es of the monitoring equipment

    Visual

    In the case of failure I periodic

    maintenance (half yearly)

    When would the

    parameters be monitored

    frequency of Why would the the parameters be

    measurement monitored? s I continuous measurement

    ?

    During Compliance with

    excavation Conservation of

    works Habitat Regulation,

    Solid Waste Control

    Regulation and Soil

    Pollution Control

    Regulation

    I Achievement of the Weekly disposal of hazardous

    wastes, which are collected seperately from the other types

    of wastes, by complying Hazardous

    Waste Control Regulation

    requirementsMonthly

    During the Achievement of the failure and disposal of the wastes

    regular compliance with maintanence Waste Oil Control

    Regulation, Waste Battery and

    ~m""to" eoot'olRegulation, End-of

    tires Control Regulation

    380 kV YENIBOSNA GIS SUBSTATION ENVIRONMENT AL MANAGEMENT PLAN

    Cost

    The Institute that controls Finish Date Start Date frequency of

    the control

    Not High

    (I hanging by

    d pending on

    TElA:;>IT nicipalities

    an lor licensed

    recovery plant) Completion

    Municipality Start of the of

    cunstructionNot High constructionProvincial works(! hanging by works

    Directorate ofd pending on

    Environmentlicensed

    and Forestry re overy plant)

    I

    Not High

    (! hanging by

    d pending on

    licensed Start of the Completion

    re overy plant) cunstruction of

    works construction works

    Contractor

    -~

    17

  • --

    --

    --- ---

    --

    --

    --

    --

    -----

    I TEIAS 380 kV YENIBOSNA GIS SUBSTATION

    ENVIRONMENTAL MANAGEMENT PLAN

    -

    [~

    Cons

    etlo

    perat

    al

    Acce

    '~r=pce FieldJ:om"o."

    J I

    Subject

    Substation Oil

    Grounding, Health and

    Safety--1 Noise

    em

    What are the parameters,

    which would be monitored?

    -

    Leakages from the barrels containing

    substation oil, used barrels (where they are stored and how

    to sent to the related firms) and

    the propriety of the impermeable

    ground

    Documents related to workers health

    and safety training, equipments used

    by the worker during working for construction (hard

    hot. "".'. "f.~belt etc.)

    Noise level

    -

    Electric and magnetic fields

    vectors

    Where would the

    parameters be monitored?

    In the case of storing, at the storage area

    Construction sites

    Open and close switchyard and at the entrance

    and exit the lines of the substation

    At switchyard and under the entrance and

    exit the lines of the substation

    How would the parameters be monitoredltyp

    es of the monitoring equipment

    Visual

    Visual

    Sound level meter

    EMF M.,.,

    -

    When would the

    parameters be monitored·

    frequency of the

    measurement s I continuous measurement

    ?

    During storage

    Daily

    Operational

    Acceptance

    Phase

    OperationalI "''''p''''''Phase

    -

    Why would the parameters be

    monitored?

    To prevent the

    leakage of the

    storage area of the

    substation oil

    In accordance with

    Work Health and

    Safety Regulation

    Control of the limit

    values determined in

    the related regulation

    Control of satisfying

    the national and

    international

    referance values

    The Institute that controls Start DateCost frequency of

    the control

    Start of the Not High TEiAS

    storage

    --+ No additional I Start of the

    cost (within the TEIAS cunstruction roject budget) works~

    Fin!sh Date

    Com pletion of slmage

    Con pletion

    of

    cons ruction

    Vi orks

    Start of Corr pletion of Not High TEiAS Op, rationalOperational

    Acceptance Ac( eptance

    Start of Corr pletion of TEAlsNot High Operational Op' rational

    Acceptance Ac( eptance

    18

  • --

    TEIAS

    Phase

    peration al

    Accepta nce

    peration

    380 kV YENIBOSNA GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN

    How would the What are the Where would parameters be

    Subject parameters, which would be

    the parameters be

    monltoredltyp es of the

    monitored? monitored? monitoring equipment

    When would the

    parameters be Imonitored· The Institute Why would the frequency of that controls - Fil Ish DateStart Date parameters be Costthe frequency of

    monitored?measurement the control s I continuous measurement

    ?

    Whether any wastes

    (construction, SOlid, hazardous, liquid) are left at the site, The substation

    Landscape the excavated

    Visual area

    areas/soil, roads

    Operational Acceptance

    Phase

    Compliance with Environmental Law

    and Regulations

    No additional cost (within the project budget)

    TEIAS Start of

    Operational Acceptance

    Cc 0 A

    mpletion of erational ceptance

    are reassembled is monitored, controlled.

    Technical trainning in terms of

    maintenance, operation and .

    Health and technical IThe substation V· I Safety area Isua

    ~'''dOlh'' and use ~

    Maintanace works - semi

    annually / in the case of

    necessary

    Compliance with related health and safety regulation

    No additional cost (within the

    operation budget)

    TEiAS Taking the

    substation into operation

    co thE

    I

    ~

    .fter the pletion of economic e of the

    "la'''" I _ Safety equipment __ _ I I

    19

  • TRIAS 380 kV YRNIBOSNA GIS SUBSTA nON ENVIRONMENTAL MANAGEMENT PLAN

    Phase Subject

    Fire Risk

    peration

    ~-~

    Ele :tromagnetic Field

    Substation Oil

    -~

    What are the parameters,

    which would be monitored?

    -~

    SF6 gas pressure

    Isolation oil

    Cable ends, isolators, cable

    connection points.

    Electric and magnetic field

    vectors

    Oil characteristic parameters

    (density, acidity, viscosity, corrosive sulfide, flash point,

    PCB, color)

    How would the Where would parameters be

    the monltored/typ parameters be es of the

    monitored? monitoring equipment

    Visual observation of

    pressureI manometers, emergency

    ~ warning and

    Substation

    Substation area

    Transformers

    signs

    Daily/weekly/m onthly

    electrical, chemical and physical tests

    and gas analysis

    Visual observation with thermo

    vision devices

    Magnetic field test

    Test Method (physical, chemical analysis)

    When would the

    parameters be monitored·

    frequency of the

    measurement s I continuous measurement

    ?

    ~-

    semi-annually / in the case of

    necessary

    ~-~

    In the case of complaints

    Bi yearly

    Why would the parameters be

    monitored?

    -

    Due to fire risk

    To comply Electric Intence Current

    Plants Regulation requirements related

    to fire safety, to repair the worn, broken parts, to

    minimize the risk of accident and to

    prevent the outage

    Reducing/preventing the risk of affecting people due to EMA

    Quality control of the substation oil

    The Institute that controls

    Cost frequency of the control

    -

    No additional cost (within the TEiAS

    operation budget)

    No additional cost (within the TEiAS

    operation budget)

    Not high (within operation TEIAS budget) l

    ~-

    Start Date Fin sh Date

    -~

    I~ fter the Taking the pletion of substation into

    operation

    Taking the substation into

    operation

    -~

    Taking the substation into

    operation

    the economic iii'e of the su

    can the

    iiI su

    can the

    lif su

    bstation

    After the pletion of economic 'e of the bstation

    After the pletion of economic 'e of the bstation

    20

  • -- --

    --

    TEIAS

    Phase Subject

    Solid-Liquid and

    Hazardous

    Wastes':>peration (automobile accumulator, substation oil)

    $I] Dustt-ml Particulate Matter

    When would the

    How would the parameters be

    What are the parameters,

    which would be monitored?

    Where would the

    parameters be monitored?

    parameters be monltoredltyp

    es of the monitoring equipment

    monitored· frequency of

    the measurement s Jcontinuous measurement

    Why would the parameters be

    monitored?

    ?

    Compliance with Weekly Conservation of

    Habitat Regulation, Seperation of solid Solid Waste Control

    wastes, junk Visual Regulation and Soil materials for Pollution Control

    recyclelrecovery/re Regulation use and disposal at the Municipality's

    landfill Achievement of the Monthly disposal of hazardous

    wastes, which are Collection of Substat on area I ooll.ot.d "p"'''''Y

    hazardous wastes from the other types separately in of wastes, by

    conteiners and , complying Hazardous disposal by a Waste Control licensed firm Regulation

    requirements

    Waste substation Test Method Completion of Compliance with oil the economic Waste Oil Control

    life of the Regulation substation oil

    -~~-I

    Dust During the Dust due to the IMeasurements/' demolishment

    movement of the ",,,,'ruotloo momhly of ,"b"allOOJ Comp""'" wllh Ih. construction (demolishing) excavation Air Quality Evaluation

    machines and site ! Interviews to be works monthly and Control demolihing works 00",,'''''' ooa, I R'9"a'oo

    residential In the case of areas complaint

    -_._....... _-_ .......

    Start Date I Finish Date

    After Takir 9 the completion of

    substa opel

    on into the economic ation life of the

    substation

    AftE rthe

    Cost

    Not high (changing by depending on municipalities

    and/or licensed recovery plant)

    Not high (changing by

    . depending licensed

    recovery plant)

    Not high (depending on

    the firmllaboratory conducting the

    analysis)

    I N ddt· I

    °t '( 'tlhlont~ cos ;Ib I~ :) P'~" "

    380 kV YENlBOSNA GIS SUBST A nON

    ENVIRONMENTAL MANAGEMENT PLAN

    The Institute

    that controls frequency of

    the control

    TEIAS

    Municipality

    I Provincial Directorate of

    ,Environment and Forestry ,

    TEiAS

    tion of Until the compl onomic completion of the ec

    Provincial ,f the decommissionilife IDirectorate of

    sub~ ati~WorksEnvironment

    and Forestry

    21

  • TEIAS 380 kV YENIBOSNA GIS SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN

    Phase Subject

    What are the parameters,

    which would be monitored?

    Where would the

    parameters be monitored?

    How would the parameters be mon itored/typ

    es ofthe monitoring equipment

    When would the

    parameters be monitored· frequency of

    the measurement s I continuous measurement

    ?

    Whywo parame

    monitc

    uld the ers be red?

    Cost

    The Institute that controls frequency of the control

    Start Date Finish Date

    Noise NOise Level

    Residential areas and

    "',,",ct;oo(demolishing)

    site

    Noise level measurement with portable

    sound pressure measurement

    device

    I Interviews to be

    conducted in near residential

    areas

    Construction (demolishing period) site,

    Weekly

    In the case of complaints of

    public

    Environmer tal Noise nand gulation

    Evaluati( Control Re

    Not High

    TEIAS

    Provincial Directorate of Environment and Forestry

    After the completion of the economic

    life of the substation

    Until the completion of

    decommissioni ng works

    '8 S

    commi ioning

    Solid and Hazardous

    Wastes

    Seperation of solid wastes, junk materials for

    recycle/recovery/re use, and disposal ,

    at the Municipality's landfill

    Collection of hazardous wastes

    seperately in conteiners and disposal by a licenced firm

    Demolishing area

    Visual

    Weekly

    Monthly

    ~--~~-

    Complial Conserv

    Habitat RE Solid Was' Regulatior

    Pollution Regul

    Achievem disposal of

    wastes, ~ collected ~ from the 01

    of was 1 complying I

    Waste ( Regul

    require

    ce with lion of gulation, ~e Control and Soil Control tion

    nt of the azardous

    hich are eperately her types s,by azardous ontrol tion

    ments

    Not High (changing by depending on municipalities

    and/or licensed recovery plant)

    Not High (changing by depending on

    licensed recovery plant) ,

    TEIAS

    Municipality

    Provincial Directorate of Environment and Forestry

    After the completion of the economic

    life of the substation

    Until the completion of

    decommissioni ng works