3) primary cementing overview
TRANSCRIPT
-
8/3/2019 3) Primary Cementing Overview
1/21
Primary Cementing
Overview
-
8/3/2019 3) Primary Cementing Overview
2/21
2
Primary Cementing
The introduction of a cementacious material into
the annulus between casing and open hole to :
Provide zonal isolation
Support axial load of casing strings and strings to be run
later
Provide casing support and protection
Support the borehole
-
8/3/2019 3) Primary Cementing Overview
3/21
3
Types of Casings
Conductor
Surface
Intermediate
Production
Liner
-
8/3/2019 3) Primary Cementing Overview
4/21
4
Conductor
Purpose
Prevents washing out under the rig
Provides elevation for flow nipple
Common sizes and depths:
30 - 20 Welded
20 - 16Threaded
30 - 200 (< 100 common)
-
8/3/2019 3) Primary Cementing Overview
5/21
5
Conductor
Other Remarks:
Plugs not used
Careful pumping practices
Large excess required
Thru-drill pipe cementing common
BOPs not unusually connected
Common Cements
Accelerated Neat
-
8/3/2019 3) Primary Cementing Overview
6/21
6
Thru-Drill Pipe Cementing
Key Points:
Cement contamination
Channelling
Displacement
Pump until cement to surface
-
8/3/2019 3) Primary Cementing Overview
7/21
7
Outside Cementing
Purpose
Bring cement to surface
Macaroni tubing used
Max. depth 250-300 ft
High friction pressures
Non-standard connections
Tubing movedduring job
-
8/3/2019 3) Primary Cementing Overview
8/21
8
Surface
Purposes:
Protects surface fresh water formations
Cases off unconsolidated or lost circulation areas
Supports subsequent casing strings
Provides primary pressure control (BOP support)
Common sizes and depths:
20 - 9 5/8 threaded
100 - 3000 (or more)
-
8/3/2019 3) Primary Cementing Overview
9/21
9
Surface Cementing
Excess of 100% plus not uncommon
Recommend thru-drill pipe method to save
Cement
Rig time
Common cements:
Lead light weight slurries with high yields
Neat tail slurries with good compressive strength
Reduce WOC to a minimum with accelerators
-
8/3/2019 3) Primary Cementing Overview
10/21
10
BOP
Rotary tableRig Floor
Choke Line
Mud Outlet
Annular Preventor
BLIND RAMS
SHEARRAMS
PIPE RAMS
Conductor pipe
Cement
Surface Casing Head
Surface Casing
-
8/3/2019 3) Primary Cementing Overview
11/21
11
Intermediate (Also called Protection)
Purposes:
Separates hole into workable sections
Lost Circulation
Salt Section
Overpressured Zones
Heaving Shales
Common sizes and depths:
133/8, 103/4, 9 5/8
3000 to 10,000
-
8/3/2019 3) Primary Cementing Overview
12/21
12
Intermediate Casings
Cemented to surface or to previous casing shoe
Two stage jobs common
Plugs, casing equipment, casing accessories usual
Good cementing practices are required
Large cement volumes
Common Cements:
Typically filler slurries followed by high compressive tail
Specialised (light, heavy, salt - saturated, etc)
-
8/3/2019 3) Primary Cementing Overview
13/21
13
Two Stage Cementing
Key Points: Separation and
isolation of zones
Reduces hydrostatic Can leave zone in
the annulus
uncemented (cement
at TD and surface) 1st Stage
Stage
Collar
2ndStage
-
8/3/2019 3) Primary Cementing Overview
14/21
14
Production
Purposes: Isolates the pay zone from other formations and the fluids
in them.
Protective housing for production equipment.
Subsurface artificial lift
Multiple zone completion
Screens for sand control
Covers worn or damaged intermediate string.
Common sizes:
4 1/2,5,7, & 9 5/8
-
8/3/2019 3) Primary Cementing Overview
15/21
15
Liners
Liner Wiper
Plug
Drill pipe
Wiper Plug
Liner
HangerRunning
Tool
Shear
Pin
Key Points:
Requires less casing
Deeper wells
Small annular clearance
Specialized equipment
-
8/3/2019 3) Primary Cementing Overview
16/21
16
Casing API Casing Specs
OD 9 5/8
Weight 53.5 lbs/ft (determines ID)
Grade C75 (yield point allowable tension)
Burst pressure 7430 PSI
Collapse pressure 6380 PSI Thread Buttress
Tapered string used to minimize well cost.
Casing program for well based on :
Burst Pressure
Collapse Pressure
Tensile Load
-
8/3/2019 3) Primary Cementing Overview
17/21
17
Thread Types 8 Round
Seals on threads
Use of couplings
Buttress Seals on threads
Use of couplings
VAM Seals on threads &
shoulder
Use of couplings
Hydrill Seals on threads &
shoulder
Integral
2 sets of threads
-
8/3/2019 3) Primary Cementing Overview
18/21
18
Running Casing
Inspection of Casing Tuboscope
Pipe tally
Hole Preparation
Mud condition Clearance
Running
Casing crews
Too fast
Landing Casing
Nippling up
-
8/3/2019 3) Primary Cementing Overview
19/21
19
Job Procedures
Pre Job: Check calculations with co-man
Rig up
Stem 1 on equipment
Check materials
Safety and organisation meeting
Prepare mix fluids, spacers and washes
-
8/3/2019 3) Primary Cementing Overview
20/21
20
Job Procedures
The Job: Test lines
Load plugs
Pump Washes / Spacers
Drop bottom plug
Mix and pump cement
Drop top plug
Displace Bump plug and check returns
-
8/3/2019 3) Primary Cementing Overview
21/21
21
Job Procedures
Post Job: Wash up
Rig down
Stem equipment Paper work