2019 06:38 pm
TRANSCRIPT
SUPREME COURT OF THE STATE OF NEW YORK COUNTY OF NEW YORK --------------------------------------------------------------------X INDECK ENERGY SERVICES, INC., : Index No. 652171/2014 Plaintiff, : Justice Jennifer Schecter
- against - : MERCED CAPITAL, L.P., MERCED PARTNERS III, L.P., : MERCED HALYARD VENTURES, LLC, and CARSON BAY ENERGY HOLDINGS IV, LLC, : Defendants. : --------------------------------------------------------------------X
DEFENDANTS’ POST-TRIAL BRIEF (August 29, 2019)
Of Counsel: Terrence J. Fleming, Esq. (pro hac vice) Sandra Smalley-Fleming, Esq. (pro hac vice) Jonathan P. Baker, Esq. (pro hac vice) George Brunelle, Esq. Anna Hadjikow, Esq. BRUNELLE & HADJIKOW, P.C. FREDRIKSON & BYRON, P.A. 39 Broadway, 33rd Floor 200 South Sixth Street New York, NY 10006 Suite 4000 (212) 809-9100 Minneapolis, MN 55402 (612) 492-7000
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
1 of 48
- i -
TABLE OF CONTENTS
PAGE NO.
I. INDECK FAILED TO PROVE REASONABLY CERTAIN EVIDENCE TO SUPPORT AN AWARD OF FUTURE LOST PROFITS. ................................................ 3 A. Indeck offered no evidence of harm to Indeck. ...................................................... 3 B. Indeck offered no evidence that it took steps to mitigate its damages. ................... 3 C. Defendants invested significant resources into developing their own
projects. ................................................................................................................... 3 D. Indeck based its “lost profits” theory on a foundation of unfounded
assumptions regarding future events. ...................................................................... 4 1. Indeck’s expert limited his analysis to the Halyard Wharton
project. ........................................................................................................ 4 2. Kubow’s analysis relied upon the occurrence of a number of future
events. ......................................................................................................... 4 3. Kubow’s analysis contains arbitrary adjustments to the data on
which his analysis is based. ........................................................................ 5 E. Defendants’ experts demonstrated the flawed nature of Kubow’s analysis. ......... 5
1. Lynn Lednicky highlighted many issues with Kubow’s reliance on Defendants’ pro forma for his calculations. ............................................... 5
2. Arthur Cobb highlighted additional problems with Kubow’s analysis. ....................................................................................................... 6
F. Defendants’ experts demonstrated that Defendants’ projects have no value. ....................................................................................................................... 7 1. Lednicky showed that the value of a power project is directly tied
to developmental milestones. ...................................................................... 7 2. Cobb demonstrated that it is speculative to attribute tens of
millions of dollars in value to what amounted to Defendants’ business plan. .............................................................................................. 7
II. THE ILLINOIS COURT RULED THAT INDECK IS NOT ENTITLED TO THE “LOST PROFITS” DAMAGES IT SEEKS IN THIS CASE. ............................................ 8
III. INDECK’S OWN WITNESSES UNDERCUT ITS DAMAGES CLAIM. ....................... 9 A. There is little benefit to being the so-called “first-mover.” .................................... 9 B. Lagowski testified to the necessity of securing a revenue stream and the
speculative nature of the ERCOT market. ............................................................ 10 C. Indeck’s history with power projects confirms that it is difficult to turn a
concept into a revenue-generating operation. ....................................................... 10
IV. INDECK’S WITNESSES OFFERED LITTLE EVIDENCE OF OTHER DAMAGES. ...................................................................................................................... 11 A. Confidential studies. ............................................................................................. 11 B. Retention bonuses. ................................................................................................ 11 C. Replacement costs and salary differences. ............................................................ 11 D. Management fees. ................................................................................................. 12
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
2 of 48
- ii -
V. DEFENDANTS’ MARKETING EFFORTS UNDERSCORED THE LACK OF VALUE ATTRIBUTABLE TO DEFENDANTS’ PROJECT. ........................................ 12 A. Defendants retained Scotiabank to market the project. ........................................ 12 B. Defendants’ marketing efforts yielded little interest. ........................................... 13 C. Feedback from potential investors confirmed that Defendants could not
attract investors to develop a power plant............................................................. 14 1. Beowulf. .................................................................................................... 14 2. Castleman. ................................................................................................. 14 3. Hull Street. ................................................................................................ 15 4. Rockland Capital. ...................................................................................... 15
VI. DEFENDANTS DID NOT OBSCURE THEIR MARKETING EFFORTS AND ENDEAVORED TO MAXIMIZE THE VALUE OF THEIR PROJECT. ...................... 15 A. Defendants apprised Indeck and the Court of their marketing efforts. ................. 15
I. INDECK FAILED TO PROVE ITS ENTITLEMENT TO FUTURE LOST PROFITS........................................................................................................................... 17 A. Indeck failed to prove the existence or value of a “first-mover advantage.” ........ 17 B. Indeck failed to establish that the purported value of Defendants’ project
serves as a proxy for its alleged damages. ............................................................ 18 C. Measuring damages from the date of the breach does not discharge Indeck
from its obligation to prove damages with reasonable certainty. ......................... 20 D. The manner in which Indeck measured its purported lost profits is
speculative............................................................................................................. 21 1. Kubow’s date-of-the-breach analysis relied upon numerous
hypothetical assumptions. ......................................................................... 21 2. Events since the date of the breach further underscore the
speculative nature of Kubow’s analysis. ................................................... 25 3. Kubow’s use of DCF methodology to value a nonexistent project
was unreliable. .......................................................................................... 25 4. Indeck provided the Court no evidence to support its contention
that it is entitled to lost profits based upon the alleged value of the Halyard Henderson project. ...................................................................... 26
5. Using Defendants’ pro forma does not establish the reliability of Indeck’s damages theory. .......................................................................... 27
6. Kubow’s self-serving adjustments to the numbers in Defendants’ pro forma undercut the reliability of his analysis. .................................... 27
7. Indeck’s invocation of the “wrongdoer rule” is unavailing. ..................... 28 8. Indeck’s own history with failed power projects undermines the
reliability of Kubow’s projections. ........................................................... 29 E. Defendants’ experts demonstrated that Indeck’s lost profits analysis is
speculative and unreliable. .................................................................................... 29 1. Kubow failed to account for the fact that the value of power
projects increases in proportion to the progress of the project. ................ 29 2. The vast differences in Kubow’s damages analyses underscore the
speculative nature of his analysis. ............................................................. 30 3. Defendants’ experts were credible. ........................................................... 30
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
3 of 48
- iii -
F. Defendants’ marketing efforts buttress the conclusion that Indeck’s damages claim is speculative. ............................................................................... 32
G. The Illinois Court’s ruling that Indeck’s damages claim is speculative precludes a different finding by this Court. .......................................................... 32
II. INDECK FAILED TO MITIGATE ITS DAMAGES. ..................................................... 33
III. INDECK FAILED TO PROVE ITS OUT-OF-POCKET LOSSES and entitlement to management fees. .......................................................................................................... 34 A. Indeck’s purported out-of-pocket losses and management fee claims
pertain to Indeck’s dismissed aiding-and-abetting claim. ..................................... 34 B. Indeck failed to introduce a sufficient evidentiary basis for its purported
out-of-pocket losses. ............................................................................................. 35 C. Indeck failed to prove that Defendants caused its out-of-pocket losses. .............. 35 D. Indeck is not entitled to recover management fees ............................................... 36
IV. INDECK IS NOT ENTITLED TO ATTORNEYS’ FEES. .............................................. 37 A. Indeck should be precluded from recovering attorneys’ fees and costs if
Indeck recovers only nominal damages. ............................................................... 37 B. New York law precludes Indeck from recovering attorneys’ fees in excess
of the amount actually recovered. ......................................................................... 38
V. INDECK’S RIGHT TO PREJUDGMENT INTEREST IS LIMITED............................. 39
VI. AT MOST, THE COURT SHOULD AWARD INDECK DEFENDANTS’ HALYARD WHARTON PROJECT. ............................................................................... 39
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
4 of 48
- iv -
TABLE OF AUTHORITIES
Page(s) Cases
Aldaloro v. PFPC Worldwide, Inc., No. Civ. A. 20289, 2005 WL 2045640 (Del. Ch. Aug. 19, 2005) ...........................................26
Bank of Am., N.A. v. Bear Stearns Asset Mgmt., 969 F. Supp. 2d 339 (S.D.N.Y. 2013) ......................................................................................28
Baskin-Robbins, Inc. v. S & N Prinka, Inc., 78 F. Supp. 2d 226 (S.D.N.Y. 1999) ........................................................................................35
Britestarr Homes, Inc. v. Piper Rudnick LLP, 256 Fed. Appx. 413 (2d Cir. 2007) ..............................................................................22, 23, 24
Chainani v. Lucchino, 942 N.Y.S.2d 735.....................................................................................................................37
Delulio v. 320-57 Corp., 99 A.D.2d 253 (1st Dep’t 1984) ..............................................................................................39
E.J. Brooks Co. v. Cambridge Security Seals, 80 N.Y.S.3d 162 (2018) .....................................................................................................18, 19
Excelsior 57th Corp. v. Winters, 227 A.D.2d 146 (1st Dep’t 1996) ............................................................................................37
F.H. Krear & Co. v. Nineteen Named Trustees, 810 F.2d 1250 (2d Cir. 1987)...................................................................................................38
Finkelstein v. Liberty Digital, Inc., No. Civ. A. 19598, 2005 WL 1074364 (Del. Ch. Apr. 25, 2006) ...........................................26
Holy Props. Ltd., L.P. v. Kenneth Cole Prods., Inc., 661 N.E.2d 694 (N.Y. 1995) ....................................................................................................33
Homkow v. Musika Records, Inc., No. 04 Civ. 3587, 2009 WL 721732 (S.D.N.Y. Mar. 18, 2009) .......................................22, 23
Indeck Energy Servs., Inc. v. Merced Capital, L.P., No. 652171/2014, 2018 WL 801541 (Sup. Ct. N.Y. Co. Feb. 9, 2018) .......................... passim
Kachkovskiy v. Khlebopros, 164 A.D.3d 568 (2d Dep’t 2018) .............................................................................................38
Matter of Kemp & Beatley, Inc., 473 N.E.2d 1173 (N.Y. 1984) ..................................................................................................39
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
5 of 48
- v -
Kenford Co. v. County of Erie, 67 N.Y.2d 257 (1986) ..................................................................................................22, 23, 24
Kidder, Peabody & Co., Inc. v. IAG Intern. Acceptance Grp. N.V., 28 F. Supp. 2d 126 (S.D.N.Y. 1998) ..................................................................................22, 24
Mack Cali Realty, L.P. v. Everfoam Insulation Sys., Inc., 110 A.D. 3d 680 (2d Dep’t 2013) ............................................................................................34
Pesa v. Yoma Dev. Grp., 18 N.Y.3d 527 (2012) ..............................................................................................................35
Richard C. Mugler Co. v. A.C. Mgmt. Corp., 29 A.D. 548 (2d Dep’t 1967) ...................................................................................................33
Sanni, Inc. v. Fiocchi, 443 N.E.2d 1108 (Ill Ct. App. 1982) .......................................................................................33
Schonfeld v. Hillard, 218 F.3d 164 (2d Cir. 2000).........................................................................................21, 22, 28
Sudit v. Labin, 148 A.D.3d 1073 (2d Dep’t 2017) ...........................................................................................40
Superior Vending Servs., Inc. v. Workmen’s Circle Home and Infirmary Foundation for Aged, 148 A.3d 960 (2d Dep’t 2017) .................................................................................................21
Wooten v State of New York, 302 A.D.2d 70 (4th Dept 2002) ...............................................................................................34
Zink v. Mark Goodson Prods., 261 A.D.2d 105 (1st Dep’t 1999) ............................................................................................27
Other Authorities
CPLR 5001(a) ................................................................................................................................39
CPLR 5001(b) ................................................................................................................................39
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
6 of 48
- 1 -
PRELIMINARY STATEMENT
This Post-Trial Brief is submitted on behalf of Merced Capital, L.P., Merced Partners III,
L.P., Merced Halyard Ventures, LLC, and Carson Bay Energy Holdings IV, LLC
(“Defendants”).
The MCA1 (PX1, DX44) between Indeck and Defendants is dated March 5, 2013. Indeck
Energy Servs., Inc. v. Merced Capital, L.P., No. 652171/2014, 2018 WL 801541, at *1 (Sup. Ct.
N.Y. Co. Feb. 9, 2018). The parties entered into the MCA for the purpose of allowing Indeck
and Defendants to explore whether Indeck wanted to develop a power project utilizing turbines
owned by Carson Bay. Id. at *2. Ultimately, the parties decided not to move forward with this
arrangement. Id.
On summary judgment, the Court determined that Defendants breached sections 2 and 5
of the MCA, which prohibited Defendants from hiring Dahlstrom and DePodesta for a period of
two years and from using Indeck’s Confidential Information (as defined in the MCA). Id. at *4-
5. The Court determined that a fact issue remained regarding Indeck’s entitlement to damages
beyond nominal damages. Id. at *5.
Prior to this trial, a 54-day trial was conducted in Illinois in which Indeck sued Dahlstrom
and DePodesta for breach of confidentiality agreements, conspiracy, misappropriation of trade
secrets, and disgorgement. (SSF Decl. Ex. 4.) Indeck requested disgorgement of all
compensation, bonuses, and other benefits received from Indeck while Dahlstrom and DePodesta
were in breach of their fiduciary duties to Indeck, as well as all benefits they would receive after
leaving Indeck’s employ (which, Indeck claimed, included profits Dahlstrom and DePodesta
would realize upon the sale of a future power project). (Id.)
1 Unless otherwise noted, Defendants adopt the abbreviations used in Indeck’s post-trial brief.
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
7 of 48
- 2 -
Prior to and after trial, the Illinois court made determinations that limited the damages
Indeck recovered in that case. First, the Illinois court determined (1) that Indeck had failed to
demonstrate “usurpation of any corporate opportunity involving the turbines,” and (2) that any
funding opportunity Indeck might have had in 2013 is still available today. (DX49, at 15:13-15,
16:10-12.) Indeck’s damages claim took further blows following 54 days of trial when the
Illinois court determined that (1) Dahlstrom and DePodesta’s breaches ended with their
employment at Indeck, (2) Dahlstrom and DePodesta did not have to return management fees
earned from Defendants, and (3) Indeck’s claim for disgorgement of lost profits was too
speculative. (DX47, at 92:1-94:2.) Ultimately, the Court awarded Indeck only $204,992 – the
compensation paid to Dahlstrom and DePodesta during the time they were in breach of their
fiduciary duties while employed at Indeck. (DX48, at ¶ 8.)2
The only issues remaining for trial in this case were whether Indeck was damaged and, if
so, the amount of any damages, whether any damages were the result of Defendants’ actions, and
whether Indeck made reasonable efforts to mitigate its damages. See Indeck, 2018 WL 801541.3
The trial record, informed by the Illinois court’s determinations, leads to the conclusion that
Indeck has not met its burden.
2 This Court has taken judicial notice of the record from the Illinois action, and that record is part of the trial record here. 3 Consequently, damages-related evidence is the only evidence relevant to this Court’s post-trial decision.
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
8 of 48
- 3 -
FACTS PROVED AT TRIAL
I. INDECK FAILED TO PROVE REASONABLY CERTAIN EVIDENCE TO SUPPORT AN AWARD OF FUTURE LOST PROFITS.
A. Indeck offered no evidence of harm to Indeck.
With respect to Indeck’s “lost profits” theory of damages, Indeck offered no evidence of
any harm to Indeck itself. Mark Kubow, the expert Indeck retained to opine on the amount of its
lost profits, offered no analysis of any harm done to Indeck. (Tr.120:22-121:2.) Kubow “did not
look at the condition of the Indeck project, per se, as relevant.” (Tr.121:1-2.) Kubow (and
Indeck) did not provide any nexus between the purported value of Defendants’ projects and the
damages Indeck allegedly incurred. (Tr.578:7-11, 20-25-579:1-7.)
B. Indeck offered no evidence that it took steps to mitigate its damages.
At trial, Indeck presented no evidence that it attempted to market its project or of any
attempts to secure revenue contracts or financing, or that Indeck had entered into cost contracts
with construction companies. Nor did Indeck produce, or introduce at trial, any offers,
proposals, or term sheets from potential investors, even though Indeck claims to possess “‘the
market and technical expertise to successfully develop a natural gas generation project.”’
(DX41, at 10 (quoting Indeck’s Verified Complaint).) This is because Indeck simply “decided to
close down [its] development activities.” (Tr.585:13-14.)
C. Defendants invested significant resources into developing their own projects.
The steps involved in developing a power project are “well known to anyone that is
operating in the power space.” (Tr.577:20-22.) The difficulty in the process is bringing all of
the steps together in a finished project. (Tr.577:24-25.) Defendants “started from scratch.”
(Tr.517:7.) Defendants retained a site location consultant, who identified approximately 300
potential site locations. (Tr.517:7-16.) Ultimately, Defendants narrowed those 300 potential
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
9 of 48
- 4 -
sites to five locations for which they acquired site control. (Tr.517:16-19.) Defendants retained
an engineering consultant to render conceptual designs for the projects, an environmental
consultant to assist with air permitting, two financial consultants to assist with financial
modeling, and invested approximately $10.6 million in their projects, excluding attorneys’ fees.
(Tr.522:3-12, 514: 7-14.)
D. Indeck based its “lost profits” theory on a foundation of unfounded assumptions regarding future events.
1. Indeck’s expert limited his analysis to the Halyard Wharton project.
As proof of its contention that Defendants’ projects are worth many millions of dollars,
Indeck offered testimony and reports from Mark Kubow. Kubow was retained for the purpose of
providing an opinion on the “value of the Merced Halyard project in the ERCOT market
specifically, Wharton County in Texas[.]” (Tr.62:24-63:2.) Kubow’s first report provided a
valuation only for the Halyard Wharton project. (Tr.133:11-14; PX2.) Kubow’s first report
contained no analysis regarding any alleged value of the Halyard Henderson project. (PX2.) In
his subsequent reports, without proving any analysis, Kubow included the Halyard Henderson
project in his damages estimate based on his bald assumption that the projects are comparable
and would, therefore, be worth the same. (Tr.97:21-98:3; 673:13-674:2; PX4, at 4.)
2. Kubow’s analysis relied upon the occurrence of a number of future events.
Kubow assigned value to Defendants’ project based upon a DCF analysis. That analysis
assumed the occurrence of many future events, including:
The project would deploy GE 7FA.03 turbines;
Turbine and equity commitments would be completed and the project would receive notice to proceed before December 31, 2015;
The project would be completed and in operation by January 1, 2017;
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
10 of 48
- 5 -
Defendants would secure a 15-year PPA at $4.75 per Kw-mo and reimbursement for variable costs at a rate of $2.25/MWh;
The project would be 80% financed with senior debt with an interest rate of Libor plus 450 basis points; and
The project would be sold at the end of 2018, after two years of operations, with the price based on an eight-times EBIDTA multiple.
(PX2, at 9-10.) Kubow acknowledged at trial that none of these events have come to pass.
(Tr.132:8-136:14.) Kubow further acknowledged, as he did in the Illinois trial, that the ERCOT
market is volatile and that the volatility affects the valuation of power generation projects.
(Tr.78:9-11, 21-79:1.)
3. Kubow’s analysis contains arbitrary adjustments to the data on which his analysis is based.
Kubow based his analysis on Defendants’ pro forma, which itself is simply a collection
of assumptions. (Tr.87:3-5, 86:5-87:5; PX2, at 4-5.) In his analysis, however, Kubow made a
number of adjustments to the data on which he relied. For example, while Defendants’ pro
forma assumed that the GE 7FA.03 turbines were worth $25 million per turbine, Kubow reduced
that figure to $14 million per turbine, based solely on conversations Kubow had with
unidentified individuals. (PX2 at 8.) In addition, while Defendants’ pro forma assumed $7.5
million for development costs, Kubow adjusted those costs downwards to $3 million because, in
his opinion, that figure was “more in line with industry assumptions.” (Id.)
E. Defendants’ experts demonstrated the flawed nature of Kubow’s analysis.
1. Lynn Lednicky highlighted many issues with Kubow’s reliance on Defendants’ pro forma for his calculations.
First, Lednicky highlighted the problems associated with Kubow’s reliance on
Defendants’ pro forma in his calculations. A pro forma is not a definitive statement of value;
rather, it is a “tool to help assess [a project’s] viability.” (Tr.581:21-22.) As Lednicky further
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
11 of 48
- 6 -
explained, “So you are using [a pro forma] as a tool to help guide your decisions with respect to
continued development, not as a proof of value that you could realize at this point in time.”
(Tr.582:3-5 (emphasis added); Defs.’ Ex. 38, at 8.)
Second, Lednicky shed light on the arbitrary adjustments Kubow made to Defendants’
pro forma numbers on which he relied. Kubow “began his calculations from information that he
obtained from Halyard, and then he began to make adjustments to that.” (Tr.587:12-13.) Those
adjustments included lowering the cost of the Carson Bay turbines and reducing Defendants’
development costs based on Kubow’s bare opinion that they should be so adjusted. (Tr:587:14-
23; Defs.’ Ex. 38, at 9-11.) The result of Kubow’s adjustments “increase[d] the value” Indeck
ascribed to Defendants’ project. (Tr.587:24-25.) Had Kubow “taken the pro forma as it was
presented through [Defendants], he would have seen a negative return, which would have
indicated that [Defendants] would not have gone forward with the project[.]” (Tr.591:3-6.)
2. Arthur Cobb highlighted additional problems with Kubow’s analysis.
Cobb highlighted several issues with Kubow’s analysis. First, Cobb revealed several
basic mathematical errors in Kubow’s calculations. (DX41.) As a result, Kubow reduced his
damages figure by nearly $2 million. (PX4, at 13-14.)
Second, Cobb shed light on the extreme variations in the values Kubow attributed to
Defendants’ projects. (Tr.671:5-672:9.) Kubow’s October 16, 2015 report provided a value of
$17,054,000 for the Halyard Wharton project; Kubow’s September 7, 2018 report provided
values of $30,731,000 for each of Halyard Wharton and Halyard Henderson; Kubow’s April 10,
2019 report provided several values—a “reliable and accurate value” of $11,592,000 for each
project, and a total “reliable, accurate, and achievable” value of $6,000,000. (Id.; DX43, at 4
(citing Kubow’s reports.) This variation underscored the “randomness and a speculative nature
of the Kubow reports.” (Tr.672:8-9.)
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
12 of 48
- 7 -
Third, Cobb highlighted that Kubow provided no analysis as to why the Halyard
Henderson project and Halyard Wharton project should share the same purported value.
(Tr.673:7-674:2.) “There simply were statements of belief, estimation that Henderson had a
similar value, but there was no detail, no separate projections, no separate consideration, no
respect for the difference in timing of the projects.” (Tr.673:15-19.) As a result, the purported
value attributed to the Halyard Henderson project was “even more speculative in that there was
no separate analysis, no separate assumptions, [and] no separate fact base[.]” (Tr.673:24-674:1.)
F. Defendants’ experts demonstrated that Defendants’ projects have no value.
1. Lednicky showed that the value of a power project is directly tied to developmental milestones.
Lednicky demonstrated that the value of a power plant is tied to its developmental stage.
Developing a power plant involves many steps—“there are a number of elements that need to
come together.” (Tr.572:19-20; DX38.) As a developer progresses through those steps, the
value of a project generally increases. (Tr.574:12-15; DX38, at 7.) If the value of Defendants’
project is the proper measure of the damages, it is “the value of that particular development
project as the facts sit at the point in time that’s relevant.” (Tr.580:23-25.) Because Defendants’
project was still in the predevelopment stage at the date of the breach, which Indeck contends is
the date at which damages must be measured, the value of the project was “essentially zero.”
(Tr.591:15-17; DX38, at 13.) Relatedly, Lednicky demonstrated the speculative nature of
Kubow’s valuation, which assumes the construction, operation, and sale of Defendants’ project.
In Lednicky’s experience, “most projects are not successful.” (Tr.582:6-9.) This is especially
true for projects, like Defendants’ projects, that have not progressed to the point of securing a
revenue stream such as a PPA, let alone financing. (Tr.582:13-585:6.)
2. Cobb demonstrated that it is speculative to attribute tens of millions of dollars in value to what amounted to Defendants’ business plan.
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
13 of 48
- 8 -
Cobb’s analysis underscored that it is speculative to attribute tens of millions of dollars in
value to Defendants’ projects (DX41-43.) According to Cobb, it is “one thing to have a business
plan, it is another to execute on that business plan.” (Tr.674:24-675:1.) Cobb observed that,
although Kubow assumed Defendants would obtain a PPA, the Brattle Group’s September 2012
ERCOT analysis noted that market forces and increased competition had “reduced the number of
buyers willing to sign long-term PPAs.” (DX41, at 16.) Cobb highlighted the fact that the value
Kubow attributed to Defendants’ project depended on achieving the significant, hypothetical
sales price assumed by Kubow. (Tr.680:10-681:20; DX41, at 18; DX43.) Kubow’s April 10,
2019 report showed negative cash flows of $43 million in the first year and $109 million in the
second year. (Tr.680:16-681:20; DX41, DX43, at 6.) Accordingly, the sales price, which would
occur in “the most speculative of the years” is the “most important number” in Kubow’s
analysis. (Tr.677:12-678:10.) As Cobb summarized, estimating lost profits based on a “power
generation project that (1) does not have a power purchase agreement, (2) has not been
constructed, (3) does not have a construction start date, (4) has not been operated, (5) does not
have an operations start date, and (6) does not have an identified purchaser is speculative.”
(DX41, at 21; see also Tr.678:20-679:20.)
II. THE ILLINOIS COURT RULED THAT INDECK IS NOT ENTITLED TO THE “LOST PROFITS” DAMAGES IT SEEKS IN THIS CASE.
At the Illinois trial, Indeck asserted the exact same damages theory as it did in this case—
that it is entitled to damages based on the purported value of Defendants’ project. Indeck
supported this damages theory with the same expert presented here—Kubow. After 54 days of
trial, the Illinois court rejected as too speculative Indeck’s theory that it is entitled to some
measure of damages based on the alleged value of a hypothetical future project:
Here, the Court agrees with Defendants that a Court cannot order disgorgement of a hypothetical future benefit.
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
14 of 48
- 9 -
ERCOT is a volatile and speculative market and no one knows whether Defendants will obtain any future benefits.
. . . .
But, here, the damages are purely speculative.
The fact of damages is uncertain.
. . . .
Indeck did not prove its belief, which the Court recognizes is a heartfelt belief, that Defendants will profit handsomely as soon as trial is over.
It’s [sic] simply has not been proven and it’s a speculative argument.
(DX47, at Tr.93:4-94:2 (emphasis added).) III. INDECK’S OWN WITNESSES UNDERCUT ITS DAMAGES CLAIM.
A. There is little benefit to being the so-called “first-mover.”
Indeck has only provided general of definitions of “first-mover’s advantage.” Larry
Lagowski, Indeck’s President, defined it as “you get done whatever you’re going to do before the
other people do it.” (1/23/2018 PM IL Tr.32:23-33:1.)4 When asked if the first-mover’s
advantage gives a company an edge over others who may soon after try to enter the market,
Lagowski stated that the first-mover’s advantage only applies if a power developer can secure
financing for its project. (1/23/2018 PM IL Tr.34:17-23.) He explained that “if you move early
and you spend a lot of money to do that, and then you find out you can’t finance [the project],
you may not have an early mover advantage.” (1/23/2018 PM IL Tr.34:20-23.) Lagowski
explained that the risks of moving early can sometimes lead to a disadvantage, because “if you
don’t know if you can finance something” and “get ahead of yourself,” you can end up in
4 The Lagowski transcripts designations are set forth and filed in conjunction with the parties’ Stipulation.
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
15 of 48
- 10 -
bankruptcy. (1/23/2018 PM IL Tr.35:1-8.) This is consistent with Defendants’ view: “I think at
this point it has actually become a disadvantage, and the reason for that is that particularly air
permits have a finite life, so what originally appeared to be an advantage I think, at this point,
has probably turned into a disadvantage.” (Tr.505:5-10.)
B. Lagowski testified to the necessity of securing a revenue stream and the speculative nature of the ERCOT market.
Lagowski explained that before investing more in a project, power plant developers
should ensure that there is a path to financial closing. (02/24/2015 Lagowski IL Dep. at 97:4-6.)
However, before lenders or equity investors will commit to providing financing, they must also
see a clear path to the project making money. (02/24/2015 Lagowski IL Dep. at 97:21-98:1.)
Since ERCOT does not make a capacity payment, a power plant only makes money on
operation. (1/23/2018 PM IL Tr.24:2-6.) A developer can enter into hedges to help with
financing. (1/23/2018 PM IL Tr.24:7-9.) With respect to financing, Lagowski explained
“[t]here is nothing for certain.” (1/23/2018 PM IL Tr.38:14.) He acknowledged that energy
development can be “speculative in nature” and even when “you start a project, you can’t know
if it will be seen to completion.” (1/23/2018 PM IL Tr.39: 13-20.)
C. Indeck’s history with power projects confirms that it is difficult to turn a concept into a revenue-generating operation.
From 2010 through 2015, Indeck abandoned multiple projects because “they were not
going to happen.” (02/24/2015 Lagowski IL Dep. at 17:3-18.) In fact, from 2001 to 2016,
Indeck did not develop a single successful electric generating project. (04/04/2016 IL Tr.45:18-
24; 50:2-5.) Indeck spent in excess of $20 million on an unsuccessful power project in
Wisconsin, which Dahlstrom and DePodesta worked to develop. (04/04/2016 IL Tr.51:11-16.)
Aside from its Wharton project, Indeck has been involved in developing one other natural gas
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
16 of 48
- 11 -
power project. (02/24/2015 Lagowski IL Dep. at 18:22-19:10.) Indeck is no longer developing
that project. (02/24/2015 Lagowski IL Dep. at 19:9-10.)
IV. INDECK’S WITNESSES OFFERED LITTLE EVIDENCE OF OTHER DAMAGES.
A. Confidential studies.
Indeck seeks $71,000 for confidential studies, but did not enter an exhibit into evidence
demonstrating this expense. Indeck waited until the eve of trial to provide the invoices that
supposedly support its out-of-pocket losses. (Tr.14:5-6.) As such, the Court did not admit the
evidence. (Tr.14:12-17.)
William Garth, Indeck’s Vice-President, submitted an affidavit stating the confidential
studies, performed by Tetra Tech and Navigant, cost $71,000. (Garth Aff. ¶ 17.) Garth
confirmed that Indeck is only claiming damages for the studies related to the Houston area.
(Tr.36:12-15.) However, when asked to lay out a summary of the expenses, Garth stated “it’s
pretty self-explanatory in the invoices.” (Tr.36:21-23.) When asked to identify the number of
sites identified, Garth again directed the Court to the inadmissible purchase order. (Tr.35:5-10.)
B. Retention bonuses.
Indeck also seeks $100,000 for retention bonuses given to Kelly Inns and Mike Ferguson.
(PX153.) Garth admitted that neither Inns nor Ferguson gave any indication that they were
seeking other work. Rather, Indeck preemptively chose to give them retention bonuses.
(Tr.48:4-7.) Indeck failed to prove a causal link between this payment and Defendants’ actions.
C. Replacement costs and salary differences.
Indeck seeks $246,000 in damages for recruiting and salary differences allegedly caused
by the departure of Dahlstrom and DePodesta. Garth acknowledged that both Dahlstrom and
DePodesta were disgruntled employees. (Tr.44:23-45:2.) Garth also acknowledged that Indeck
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
17 of 48
- 12 -
routinely uses headhunters and that it is Indeck’s choice whether to pay relocation costs for new
employees. (Tr.45:22-46:6.) Dahlstrom and DePodesta were at-will employees who could have
left Indeck’s employ at any time for any reason, or no reason at all. (Tr.562:16-17.) Indeck
would have incurred all of the costs it is seeking if Dahlstrom and DePodesta had left for other
jobs other than with Defendants. (Tr.45:17-20.) Again, Indeck failed to prove a causal link
between these payments and Defendants’ actions.
D. Management fees.
Finally, Indeck seeks recovery of the project management fees paid to Dahlstrom and
DePodesta over the course of five years. (Tr.18:22-19:1.) Project management is not Indeck’s
business—Garth admitted that Indeck had not managed an energy project for a third party for 25
years, and Indeck has not received any such revenue during that time period. (Tr.30:10-14.)
Moreover, the MCA’s prohibition against hiring Indeck’s employees is limited to two years.
(PX1.) In addition, Garth acknowledged that, to obtain the benefit of management fees, Indeck
would have had to pay Dahlstrom and DePodesta (or some other Indeck employees), resulting in
a dollar-for-dollar diminution of any such management fees. (Tr.31:12-22.)
V. DEFENDANTS’ MARKETING EFFORTS UNDERSCORED THE LACK OF VALUE ATTRIBUTABLE TO DEFENDANTS’ PROJECT.
A. Defendants retained Scotiabank to market the project.
Defendants retained Scotiabank to locate investors for their project. (Tr.363:14-363:17.)
Seth Keller, co-head of the Power and Utilities Investment Banking Group for Scotiabank, led
that effort. (Tr.361:22-24, 363:14-17.) Keller has been leading execution and origination of
M&A transactions within the power and utilities space at Scotiabank for more than nine years.
(Tr.362:3-7.) Scotiabank created a CIM that described the project and summarized financial
projections. (PX124-A; Tr.363:22-363:25.) Like Defendants’ earlier pro forma, the CIM
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
18 of 48
- 13 -
estimated the costs to build the project and projected the potential returns on investment.
(Tr.364:5-10.)
Once the materials were prepared, Scotiabank emailed a teaser out to approximately 170
potential investors in early 2018. (Tr.365:18-365:19; 368:21-368:25; 385:5-8; 397:14-16;
526:20-23). After sending the teaser, Scotiabank executed NDAs with approximately 30
investors who expressed interest in the projects. (Tr.365:14-20; 526:24-527:1.) Once a potential
investor executed an NDA, Scotiabank provided the CIM to that party. (Tr.527:2-8.)
Towards the end of February 2018, Scotiabank delayed the bidding process out of fear
that any bids would become public as a result of a discovery order from the Illinois proceeding.
(Tr.386:16-386:20; 388:24-389:1.) After about a month pause, the bidding process resumed.
(Tr.389:25-390:9.)
The Scotiabank process yielded little interest in Defendants’ Halyard Wharton project.
(Tr.390:14-15.) The only company that sent a proposal was Metropolis. (PX137, Tr.393:22-
394:2.) Hendrik Vroege and Jim Kueser, the owner of Metropolis, discussed a possible deal
during a sit-down meeting at an industry convention in Las Vegas in April 2018. (Tr.527:25-
528:9,). That same day, Vroege and Kueser “concluded [the] deal would never happen.”
(Tr.528:5-9.) According to Keller, Metropolis Energy would never have been able to fund the
building of the project. (Tr.391:20-392:5.)
B. Defendants’ marketing efforts yielded little interest.
In fall 2018, Defendants relaunched the marketing process and began contacting potential
investors. (Tr.315:22-24.) In the new CIM, the parties assumed the power plant would use new
Siemens turbines, rather than the older models already owned by Defendants. (Tr.211:14-17.)
Potential buyers found the newer models more attractive than the GE 7FA.03 units owned by
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
19 of 48
- 14 -
Merced. (DX7). Ultimately, although several parties expressed interest in purchasing
Defendants’ project as-is, Defendants’ marketing process did not lead to a successful transaction.
C. Feedback from potential investors confirmed that Defendants could not attract investors to develop a power plant.
1. Beowulf.
In October 2018, Defendants started negotiations with Beowulf Energy. (Tr.315:25-316:
5.) In November 2018, Beowulf made an indicative proposal to purchase 100% of the equity
interests in Merced Halyard Ventures, LLC. (DX1.) The proposal did not include financing;
rather, Beowulf proposed to purchase the projects’ assets (which, at that time, included permitted
bare ground and site control). (DX1; Tr.510:18-20.) Later, on January 8, 2019, Beowulf sent an
updated proposal that included upfront consideration of $2.5 million and a closing of $2.5
million for Halyard Wharton, $1 million for Halyard Henderson, and $150,000 for the Bernard
project. (DX3.) After engaging in due diligence, Beowulf changed its proposal. (Tr.333:6-15.)
Beowulf’s new proposal was $500,000 upfront and $2.5 million at financial close. Id. In April
2019, after further due diligence, Beowulf pulled its proposal. (Tr.334:1-3.)
2. Castleman.
Castleman first contacted Merced regarding the power plant projects in February 2018.
(DX11.) Castleman had other projects competing with Halyard Wharton and Henderson and no
access to capital to fund the project. (Tr.398:9-22.) Castleman proposed to pay Defendants
$500,000 at closing and $1 million for each project after financial closing or commencement of
construction. (PX155-A; Tr.535:23-536:2.) Castleman declined to proceed with this proposal
and has not continued discussions with Defendants. (Tr.536:10-12.)
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
20 of 48
- 15 -
3. Hull Street.
Defendants also had preliminary discussions with Hull Street. (PX13.) Hull Street
received some of Defendants’ due diligence materials but neither made a proposal nor sent a
written term sheet. (Tr.258:23-259:5.) Hull Street declined to proceed with the investment
opportunity because of the risk in the market. (Tr.258:18-21.)
4. Rockland Capital.
Most recently, in May 2018, Defendants communicated with Rockland Capital.
Rockland proposed to invest $109,000 into the project, which would give Rockland the option to
purchase the Halyard Wharton and Halyard Henderson projects for a total of $1 million.
(Tr.537:11-22.)
VI. DEFENDANTS DID NOT OBSCURE THEIR MARKETING EFFORTS AND ENDEAVORED TO MAXIMIZE THE VALUE OF THEIR PROJECT.
A. Defendants apprised Indeck and the Court of their marketing efforts.
Indeck’s discovery-related arguments about Defendants’ marketing efforts are
quintessential red-herrings. (Indeck Br. at 13-14; Ellis Decl.) First, Defendants did not deceive
the Court about their marketing efforts. In October 2018, Vroege submitted an affidavit that
summarized the Scotiabank marketing efforts. In that affidavit, Vroege described the Scotiabank
process that produced no viable interest. (PX10.) Vroege did not omit mention of Defendants
cutting the Scotiabank process short, because Scotiabank, not Defendants, made the decision to
postpone the bidding process (and, regardless, as set out above, the Scotiabank process
proceeded after a short delay). (Tr.389:11-13, 419:19-420:3.) Vroege did not falsely claim that
Scotiabank had reengaged in October 2018—he stated that he had attempted to reengage with
Scotiabank. (PX10.) Keller confirmed that, while Scotiabank did not actively work on the
project after April 2018, he continued to have discussions with Vroege following April 2018.
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
21 of 48
- 16 -
(Tr.426:20-427:2.) In addition, Vroege confirmed that, because there was no interest in
financing Defendants’ project from any party, there was no reason for him to update his
affidavit. (Tr.506:7-15.)
Second, Indeck was kept apprised of each and every proposal Defendants received.
Defendants continued to produce emails up to May 6, 2019, which was the date Indeck requested
Defendants make their final production. (SSF Aff. ¶ 3.) And in the spring of 2019, Indeck
deposed, for the second time, both Vroege and Keller regarding marketing Defendants’ projects.
(Id. ¶ 4.) While Dahlstrom and DePodesta emailed with potential investors independently, the
vast majority of those emails were forwarded to Defendants and produced to Indeck. (Id. ¶ 5.)
The “hidden” emails Indeck cites were sent on May 10, and May 28, 2019—days beyond the
May 6, 2019 discovery cutoff Indeck requested. (Id. ¶ 6; Ellis Decl. Exs. A-B.) In addition,
Indeck deposed Dahlstrom and DePodesta after trial (and after receiving supplemental
productions of their emails) and does not now claim that it learned of any new proposals through
those depositions. (Id. ¶ 7.)5 To be sure, Indeck submitted transcripts from the Illinois
proceeding where Dahlstrom and DePodesta were found to have violated their discovery
obligations. (Ells Decl. Exs. D-E.). Dahlstrom and DePodesta’s conduct in Illinois has nothing
to do with Defendants, and, as set forth above, the Illinois court limited Indeck’s recovery to the
salaries paid to Dahlstrom and Depodesta near the end of their employment. (DX48, at ¶ 8.)
Defendants have invested approximately $10.6 million in their project, excluding
attorneys’ fees. (Tr.514:7-14.) In addition, from 2013 through 2017, Defendants undertook
efforts to make their projects shovel ready, including obtaining site control, hiring an engineering
5 Indeck complains about Defendants’ discovery productions up to the eve of trial, yet simultaneously contends that such information is irrelevant to the issue of damages. Indeck cannot have it both ways.
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
22 of 48
- 17 -
consultant to create conceptual designs, obtaining interconnection and air permits, and
attempting to obtain revenue agreements with utility companies. (Tr.517:3-525:25.) In addition,
Defendants retained Scotiabank, who was motivated to generate interest in the projects because
Scotiabank’s payment was contingent upon a transaction. (Tr.446:17-18, 507:1-4.) Despite that
incentive, Scotiabank ceased its work around April 2018 because “the market did not have much
interest in the project at that time.” (Tr.447:6-9.) When the Scotiabank process yielded no
results, Defendants continued searching for interested parties, and ultimately decided to monetize
the projects and attempt to sell them as-is (as opposed to constructing the plants). (Tr.491:10-17,
533:21-534:9.)
Defendants have to answer to their investors, the majority of which are pension plans,
university endowments, and charitable foundations. (Tr.512:12-514:2.) Defendants’ investment,
including the projects at issue here, have time horizons which end in a “harvest period” during
which Defendants must use their best efforts to realize the best outcome for their investors.
(Tr.512:14-22.) Defendants did not renew the interconnection agreement because they “decided
that we did not want to throw good money after bad anymore.” (Tr.533:8-9.) Simple market
realities caused Defendants’ projects to fail.
ARGUMENT
I. INDECK FAILED TO PROVE ITS ENTITLEMENT TO FUTURE LOST PROFITS.
A. Indeck failed to prove the existence or value of a “first-mover advantage.”
Although Indeck contends that Defendants obtained a valuable first-mover advantage, the
record belies this assertion. (Indeck Br. at 17.)
Indeck’s witnesses failed to establish the existence and value of the first-mover
advantage. Garth had “not quantified” the supposed first-mover advantage and generically
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
23 of 48
- 18 -
described it as “the difference between getting a project done and not getting a project done.”
(Tr.41:17-18.) Lagowski testified that “if you move early and you spend a lot of money to do
that, and then you find out you can’t finance [the project], you may not have an early mover
advantage.” (1/23/2018 PM IL Tr.34:20-23.) Lagowski explained that the risks of moving early
can sometimes lead to a disadvantage, because “if you don’t know if you can finance something”
and get ahead of yourself, “you can end up in bankruptcy.” (1/23/2018 PM IL Tr.35:1-8.) This is
consistent with Defendants’ reality: “I think at this point it has actually become a disadvantage,
and the reason for that is that particularly air permits have a finite life, so what originally
appeared to be an advantage I think, at this point, has probably turned into a disadvantage.”
(Tr.505:5-10.)
In addition, the steps Defendants had to undertake to develop their project undercut any
assertion of a first-mover advantage. Defendants had to “start from scratch.” (Tr.517:7-8.)
Defendants also had to hire a GIS consultant to identify potential locations, distill those locations
down to a management list, conduct site visits, and secure site control. (Tr.517:7-19.)
Defendants also retained an engineering consultant for permitting assistance and two separate
financial modelling consultants for financial projections. (Tr.522:4-7.) Under Indeck’s own
definition of first-mover advantage, Defendants, who have spent more than $10 million on
unsuccessful projects, are actually at a disadvantage. Plainly, Defendants did not obtain any
first-mover advantage.
B. Indeck failed to establish that the purported value of Defendants’ project serves as a proxy for its alleged damages.
Under New York law where, as here, a defendant is alleged to have exploited “the skill,
expenditures and labors” of the plaintiff, “[d]amages must correspond to the amount which the
plaintiff would have made except for the defendant’s wrong . . . not the profits or revenues
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
24 of 48
- 19 -
actually received or earned by the defendants.” E.J. Brooks Co. v. Cambridge Security Seals, 80
N.Y.S.3d 162, 168-69 (2018). There is “no presumption of law or fact” that a defendant’s
purported gains whether measured “by the defendant’s profits, revenues, cost savings, or any
other measure of unjust gain” will “approximate the losses incurred by the plaintiff.” Id. at 171.
Rather, a plaintiff must always show that “there is some approximate relation of correspondence
... between the gains of the aggressor and those diverted from his [or her] victim,” without which
damages “would cease to serve the compensatory goals” of recovery. Id.
Indeck failed to prove that the supposed value of Defendants’ project bears any relation
to the damages it allegedly suffered. In the first instance, Kubow acknowledged at trial that he
did not undertake any analysis of harm to Indeck. (Tr.120:22-121:2.) Kubow’s reports confirm
that Indeck’s damages theory is not based upon any harm it actually suffered: “Indeck Energy
suffered harm . . . . In valuing this harm, I looked to quantify the reasonable value of the Merced
Halyard Project.” (DX31, at 4.) After analyzing Kubow’s reports, Cobb concluded that
Kubow’s did not identify any harm to Indeck: “No they don’t. They, in effect, are attempting to
look at benefit to Merced. He did not use Indeck information, Indeck estimates, at all. He is
looking at Merced information.” (Tr.690:16-19.) Lednicky pointed out the same flaw in
Kubow’s analysis: “In my view there ought to be a clear nexus between the measure of damages
and the damages that were incurred, and I did not see any nexus that was presented by Kubow.
In fact, Indeck continued to move forward[.]” (Tr.578:7-11.) The Illinois court’s determinations
that Indeck failed to show “usurpation of any corporate opportunity involving the turbines,” and
(2) that any funding opportunity Indeck might have had in 2013 is still available today further
undermines any connection between Defendants’ projects and the damages Indeck seeks here.
(DX49, at 15:13-15, 16:6-9.)
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
25 of 48
- 20 -
Because Indeck has not established a connection between the losses that it asserts it
sustained and the value Indeck attributes to Defendants’ project, the Court should reject Kubow’s
analysis in its entirety.
C. Measuring damages from the date of the breach does not discharge Indeck from its obligation to prove damages with reasonable certainty.
In arguing that measuring breach of contract damages as of the date of the breach
essentially discharges Indeck from its obligation to prove its lost profits theory with reasonable
certainty, Indeck takes this straightforward proposition too far.
Unsurprisingly, the cases Indeck cites do not support its extreme position. Kaminsky v.
Herrick, Feinstein LLP was not a lost profits case. In Kaminsky, the dispute centered around the
proper measure of damages “for breach of a contract to deliver shares in an IPO.” 59 A.D.3d 1,
11 (1st Dep’t 2008). Applying the date-of breach rule, the court determined that “the arbitrators
properly rejected evidence of value of [the] shares after trading began.” Id. at 11-12. Another
case Indeck cites, Credit Suisse First Boston v. Utrecht-America Finance Co., actually undercuts
its position. 84 A.D.3d 579, 580 (1st Dep’t 2011). Credit Suisse was not a lost profits case,
and, in affirming the Supreme Court, the First Department made clear that the factfinder “should
be able to make its valuation determination on all relevant elements of the case.” Id. at 581.
Sharma v. Skaarup Ship Management Corp. stands for nothing more than the proposition that
where a breach of contract involves deprivation of an item with a discernable market value,
damages are determined by measuring the market value at the time of the breach. 916 F.2d 820,
825 (2d Cir. 1990). Finally, in Simon v. Electrospace Corp., the Court confirmed that damages
should be based on the value of stock at the date of the breach, which value was “precisely
determinable on the public market.” 269 N.E.2d 21, 26 (N.Y. 1971).
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
26 of 48
- 21 -
In the first instance, it is questionable whether these cases are applicable in light of the
fact that Kubow conceded—both in his reports and in his testimony—that he did not conduct a
fair market value analysis of Defendants’ projects. (DX31, at 4; Tr.115:6-7.) In addition,
conspicuously absent from these cases is a statement that measuring damages at the date of the
breach discharges the duty of a plaintiff to prove future lost profits with reasonable certainty, or
that a court cannot consider the totality of the circumstances, whether before or after the breach,
to assess whether a plaintiff has met that burden.
That is because it is black-letter law in New York that a plaintiff seeking lost profits must
prove that such damages are capable of measurement with reasonable certainty. Superior
Vending Servs., Inc. v. Workmen’s Circle Home and Infirmary Foundation for Aged, 148 A.3d
960, 961 (2d Dep’t 2017). Future lost profits must be “capable of measurement based upon
known reliable factors without undue speculation.” Id. Where, as here, lost profits are based on
hypothetical profits of a new business venture, such evidence “receives greater scrutiny because
there is no track record on which to base an estimate. Projections of future profits based upon a
multitude of assumptions that require speculation and conjecture and few known factors do not
provide the requisite certainty.” Schonfeld v. Hillard, 218 F.3d 164, 172 (2d Cir. 2000) (citations
omitted) (applying New York law). Thus, Indeck, like any other plaintiff in New York, must
establish future lost profits with reasonable certainty, and all circumstances are relevant for
determining whether a plaintiff, like Indeck, has met that burden.
D. The manner in which Indeck measured its purported lost profits is speculative.
1. Kubow’s date-of-the-breach analysis relied upon numerous hypothetical assumptions.
Courts applying New York law routinely deny claims for future lost profits when such
claims are supported by numerous, unfounded assumptions about what might happen in the
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
27 of 48
- 22 -
future. See, e.g., Kenford Co. v. County of Erie, 67 N.Y.2d 257, 261 (1986); Schonfeld, 218
F.3d at 174 (concluding that “the district court properly held that Curtis’s projections based on
INN’s Business Plan are legally insufficient”); Britestarr Homes, Inc. v. Piper Rudnick LLP, 256
Fed. Appx. 413, 414 (2d Cir. 2007) (“As to the amount of lost profits from a power plant that
was to have been built on Britestarr’s property: The expert report . . . measured lost profits
on . . . improperly speculative assumptions[.]”); Kidder, Peabody & Co., Inc. v. IAG Intern.
Acceptance Grp. N.V., 28 F. Supp. 2d 126, 137 (S.D.N.Y. 1998) (“Despite the extensive
calculations made by IAG’s expert, undoubtedly applying the latest accounting and economic
principles, the assumptions it rests upon prove too unsupportable and far-reaching to be
reasonably certain.”); Homkow v. Musika Records, Inc., No. 04 Civ. 3587, 2009 WL 721732, at
*11 (S.D.N.Y. Mar. 18, 2009) (“[T]he Court concludes that Plaintiff’s lost profits request is
based upon highly speculative, if not erroneous, assumptions.” . . . As a new business venture,
with no track-record of sales, the Court concludes that there is no ‘reasonable certainty’ that
Plaintiff would sell 7,000 CDs in a four-year period.”).
Here, even setting aside future events (which establish the speculative nature of Kubow’s
analysis) Kubow’s date-of-the-breach damages analysis, which is Indeck’s sole evidence of its
purported lost profits, fails to establish lost profits with reasonable certainty. Kubow built the
value he ascribes to Defendants’ projects upon numerous unfounded assumptions about what
might happen in the future. (Supra at 4-5; PX2, at 9-10.)
At the date of the breach, these assumptions were speculative. Among other things,
Carson Bay, who owned the GE 7FA.03 turbines, was free to sell them at any time to any other
party. (Tr.593:18-21; DX39, at 3-4.) The 15-year PPA Kubow assumed that Defendants would
secure was simultaneously the “fundamental piece” Defendants would need “to move forward”
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
28 of 48
- 23 -
and “very rare” because of the “buyer dynamics in the ERCOT market.” (Tr.589:8-21.) Indeed,
the value Kubow attributed to Defendants’ project was entirely dependent upon the sale price of
a project that had yet to be financed, constructed, or operated. (Tr.677:14-17; DX41, at 18-23.)
Given that so many future events needed to come to fruition for Defendants to realize the value
Kubow attributed to their project, Indeck failed to establish that it incurred millions in damages
on the date of the breach. This is especially true in light of the fact that Defendants’ project was
not (and is not) a going concern with a history of revenue on which to base assumptions about
future revenues. See Homkow, 2009 WL 721732, at *11 (“As a new business venture . . . there is
no ‘reasonable certainty’ that Plaintiff would sell 7,000 CDs in a four-year period.”). Thus, even
measured at the date of the breach, Indeck failed to demonstrate future lost profits with
reasonable certainty.
Britestarr, which also involved a claim for lost profits based on a nonexistent power
plant, is instructive. In that case, Britestarr Homes attempted to establish its entitlement to lost
profits based on a power plant that was supposed to have been built on its property. 256 Fed.
Appx. at 414. As the basis for its lost profits claim, Britestarr Homes’s expert assumed that “a
hypothetical power plant developer would have secured $1 billion in debt and equity financing in
time to start construction in December 2003; that the debt financing would have included a loan
of $740 million at 7.25% interest; and that the developer would have entered into a construction
contract for the plant.” Id. at 415. The Britestarr Court rejected reliance on such “improperly
speculative assumptions.” Id. at 414.
Similarly, although it did not involve a power plant project, the Court of Appeals of New
York’s opinion in Kenford provides additional guidance here. In that case, the County of Erie
entered into a contract with a construction company and an operating company for the
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
29 of 48
- 24 -
construction and operation of a domed sports facility near the city of Buffalo. 67 N.Y.2d 257 at
260. After negotiations, the county and operating company were unable to come to terms on
either a lease or an operating agreement, nor was the stadium ultimately constructed. Id. The
operating company sued the county, seeking, among other things, lost profits for the 20-year
period of the proposed management contract. Id. at 261-62. On appeal, the operating company’s
lost profits damages were set aside on the grounds that they were unduly speculative, even
though the “quantity of proof [was] massive and, unquestionably, represent[ed] business and
industry’s most advanced and sophisticated method for predicting the probable results of
contemplated projects.” Id. at 236. The Kenford Court explained further its reasons for setting
aside the lost profits award:
[D]espite the massive quantity of expert proof submitted by DSI, the ultimate conclusions are still projections, and as employed in the present day commercial world, subject to adjustment and modification. . . . DSI assumed the facility was completed, available for use and successfully operated by it for 20 years[.] . . . Quite simply, the multitude of assumptions required to establish projections of profitability over the life of this contract require speculation and conjecture, making it beyond the capability of even the most sophisticated procedures to satisfy the legal requirements of proof with reasonable certainty.
Id. at 262. The facts here are strikingly analogous. As in Britestarr and Kenford, the Court should
reject Indeck’s attempt to establish its alleged lost profits via an analysis that depends upon
numerous, hypothetical occurrences, including the financing, construction, operation, and sale of
a project that, at the time of the breach, was nothing more than permitted bare ground. Indeck
has not established its entitlement to any amount of lost profits with reasonable certainty. See
Kidder, 28 F. Supp. 2d at 134 (“[A] claimant cannot establish lost profits with the law’s requisite
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
30 of 48
- 25 -
certainty where its calculation is dependent upon a host of assumptions concerning uncertain
contingencies, and applies numerous variables about which an expert can only surmise.”).
2. Events since the date of the breach further underscore the speculative nature of Kubow’s analysis.
The passage of time has shown that Kubow’s assumptions about the milestones
Defendants would achieve with their projects were simply wrong:
Kubow 2015 Assumptions
Kubow 2018 Assumptions Reality
“15 year average price would be $4.75 per kW-mo with reimbursement for variable costs at a rate of $2.25/MWh” (PX2, at 9).
“[I]t is appropriate to increase the related price assumption from $4.75/KW-month to $6.98/KW-month” (PX6, at 4).
Defendants never secured a PPA.
“First full year of operation, 2017, is projected to be $17,500,000 growing to $17,912,000 in 2018” (PX2, at 11).
“It is assumed that construction begins in Q4 2018 and that the project goes into operation on January 1, 2020” (PX6, at 8)
Construction never began; no plants are in operation..
“Sale of project is assumed to occur on January 1, 2019 at a sale price of $161,207,000 based on a 2018 EBITDA of 17,912,00 and a nine times multiple” (PX2, at 11).
“Updating the prior opinion for known changes creates an updated valuation range of $9,997,000 to $61,458,000 depending on the value used for the PPA price.” (PX6, at 9.)
The proposals Defendants received do not cover development expenses.
Not only was Kubow’s analysis speculative and unreliable as of the date of the breach,
his shifting projections and the fact that none of them came true further underscore the
undeniable conclusion that Indeck cannot establish an entitlement to future lost profits.
3. Kubow’s use of DCF methodology to value a nonexistent project was unreliable.
Indeck touts Kubow’s analytical methodology as the “proper method” to value
Defendants’ nonexistent project and cites case law in support of this assertion. (Indeck Br. at
23.) One of the cases Indeck cites stresses that DCF methodology must be “used responsibly.”
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
31 of 48
- 26 -
Aldaloro v. PFPC Worldwide, Inc., No. Civ. A. 20289, 2005 WL 2045640, at *9 n. 34 (Del. Ch.
Aug. 19, 2005) (“I stress ‘used responsibly’ for there are situations when the available data will
not support the use of the DCF model.”). A DCF analysis is not used responsibly where, as here,
the expert’s “assumptions bear no relationship to reality.” Finkelstein v. Liberty Digital, Inc.,
No. Civ. A. 19598, 2005 WL 1074364, at *14, 17 (Del. Ch. Apr. 25, 2006) (“[R]ather than
addressing the operative reality of Liberty Digital, as required by law, Feinstein imagines an
ideal world for Liberty Digital and values the Access Agreement on that basis[.]”). Kubow’s
unrealistic assumptions about the “ideal world” for Defendants’ project underscore the
conclusion that Kubow’s methodology, as well as the numbers he derived from that method, are
speculative and unreliable.
4. Indeck provided the Court no evidence to support its contention that it is entitled to lost profits based upon the alleged value of the Halyard Henderson project.
Kubow performed no analysis with respect to the Halyard Henderson project. Kubow
testified that he was retained to provide an opinion on the “value of the Merced Halyard project
in the ERCOT market specifically, Wharton County in Texas[.]” (Tr.62:23-63:2.) Indeed,
Kubow’s first report provided a valuation only for the Halyard Wharton project and is devoid of
any analysis regarding the alleged value of the Halyard Henderson project. (Tr.133:11-14; PX2.)
In his subsequent reports, Kubow included the Halyard Henderson project in his damages
estimate based on his bald assumption that the projects are comparable and would, therefore, be
worth the same. (Tr.97:21-98:3; 673:13-674:2; PX2, at 4.) While Kubow testified that the
ERCOT market is “relatively homogenous,” that testimony is directly contradicted by Kubow’s
acknowledgement that the ERCOT market is volatile and that the volatility affects the valuation
of power generation projects. (Tr.78:9-11, 21-79:1.) Kubow’s analysis of the purported value of
the Halyard Henderson project is not just speculative, it is nonexistent. Because Indeck offered
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
32 of 48
- 27 -
effectively no evidence of the value of this project, the Court should deny Indeck’s damages
based on the alleged value of the Halyard Henderson project.
5. Using Defendants’ pro forma does not establish the reliability of Indeck’s damages theory.
Indeck attempts to buttress its damages theory by touting Kubow’s reliance on
Defendants’ pro forma. A pro forma is not a definitive statement of value; rather, it is a “tool to
help assess [a project’s] viability.” (Tr.581:21-22.) As Lednicky explained, “So you are using [a
pro forma] as a tool to help guide your decisions with respect to continued development, not as a
proof of value that you could realize at this point in time.” (Tr.582:3-5 (emphasis added); DX38,
at 8.) In other words, Defendants’ hopes about what might happen in the future created for the
purpose of assessing whether to continue investing money into the project do not establish the
reliability of Kubow’s speculative analysis. See Zink v. Mark Goodson Prods., 261 A.D.2d 105,
105 (1st Dep’t 1999) (“[P]laintiffs’ claim for lost profits was properly dismissed since it was
predicated not upon the requisite reasonably certain assessment but upon nothing more than
assumptions, speculation and conjecture respecting the performance of the game show.”).
6. Kubow’s self-serving adjustments to the numbers in Defendants’ pro forma undercut the reliability of his analysis.
Kubow’s arbitrary modifications of the numbers in Defendants’ pro forma further
undercut the reliability of his analysis. When Defendants’ figures served the purpose of
increasing Indeck’s alleged damages, Kubow adopted them wholesale. (PX2, at 7-10.) When,
however, they would work to Indeck’s disadvantage, Kubow arbitrarily adjusted those numbers.
For example, while Defendants’ pro forma assumed that the GE 7FA.03 turbines were worth $25
million per turbine, Kubow reduced that figure to $14 million per turbine, based solely on
conversations Kubow had with unidentified individuals. (PX2 at 8.) In addition, while
Defendants’ pro forma assumed $7.5 million for development costs, Kubow adjusted those costs
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
33 of 48
- 28 -
downwards to $3 million because, in his opinion, that figure was “more in line with industry
assumptions.” (PX2 at 8.) As Lednicky explained, the result of Kubow’s adjustments
“increase[d] the value” Indeck ascribed to Defendants’ project. (Tr.587:24-25.) Had Kubow
“taken the pro forma as it was presented through [Defendants], he would have seen a negative
return, which would have indicated that [Defendants] would not have gone forward with the
project[.]” (Tr.591:2-7.) In other words, when Kubow saw fit to modify Defendants’ pro forma,
he only did so in ways that would drive up Indeck’s damages estimate. This is yet another
reason why Kubow’s analysis is speculative and unreliable.
7. Indeck’s invocation of the “wrongdoer rule” is unavailing.
Indeck cites cases in hopes of establishing the proposition that, because the Court has
determined liability, Indeck is essentially relieved of establishing damages with reasonable
certainty. (Indeck Br. at18.) But, the “wrongdoer rule” does not apply where “the existence of
lost profits damages cannot be established with the requisite reasonable certainty.” Schonfeld,
218 F.3d at 175. Indeck has not established either the existence or the amount of its purported
lost profits. The wrongdoer rule, therefore, has no application here. See Bank of Am., N.A. v.
Bear Stearns Asset Mgmt., 969 F. Supp. 2d 339, 360 (S.D.N.Y. 2013) (“But under the wrongdoer
rule, a plaintiff who prevails in a breach of contract action must still demonstrate a stable
foundation for a reasonable estimate as to damages.” (citation omitted)). Indeed, the Court’s
summary judgment order confirms that Indeck bears the burden of proving its damages. Indeck,
2018 WL 801541, at n. 9 (“[N]othing herein should be construed as the court relieving Indeck of
its obligation to prove that its alleged damages flowed from these breaches.”).
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
34 of 48
- 29 -
8. Indeck’s own history with failed power projects undermines the reliability of Kubow’s projections.
While Kubow’s reports assumed that the financing, construction, operation, and sale of
Defendants’ project was a sure thing, Indeck’s own history with failed power projects contradicts
that assumption. Indeck has a long list of failed development plants. From 2001 to 2016, Indeck
did not develop a single successful electric generating project. (04/04/2016 IL Tr.45:18-24; 50:2-
5.) Aside from its Wharton project, Indeck has been involved in developing one other natural
gas power project. (02/24/2015 Lagowski Dep. at 19:1-10.) Indeck is no longer developing that
project. (02/24/2015 Lagowski Dep. at 19:9-10.) Thus, while Kubow assumed that Defendants’
project would be a guaranteed success, Indeck’s experience with multiple failed power projects
undermines the reliability of that assumption.
E. Defendants’ experts demonstrated that Indeck’s lost profits analysis is speculative and unreliable.
1. Kubow failed to account for the fact that the value of power projects increases in proportion to the progress of the project.
Lednicky’s analysis and testimony further underscored that it is speculative to attribute
millions of dollars in value to an unfinished power project. Rather, a power project accrues
value as it progresses through development. (DX38, at 7-8; Tr.572:15-577:8.) To realize the full
value Kubow attributed to Defendants’ project, a power developer needs to “develop all of [the
steps] in a way that allows the project to be built, and then you can achieve a full valuation.”
(Tr.574:12-15.) While the process to develop a power plant is conceptually simple, the
“execution to achieve all of those things is a very difficult thing to do.” (Tr.582:10-12.) Most
projects similar to Defendants’ project “are not successful.” (Tr.582:8-9.) Had Kubow actually
valued Defendants’ project based on its status on the date of the breach in 2013, he would have
concluded that it had a value that “was essentially zero.” (Tr.591:13-17.) Even in 2015, when
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
35 of 48
- 30 -
site control and air permits had been obtained, Kubow’s analysis “[skipped] to the end which
doesn’t recognize the current value that one ought to consider.” (Tr.586:25-587:2.) Kubow’s
failure to account for the reality of power project developments further buttresses the conclusion
that Indeck’s lost-profits claim is speculative.
2. The vast differences in Kubow’s damages analyses underscore the speculative nature of his analysis.
Second, Cobb shed light on the extreme variations in the values Kubow attributed to
Defendants’ projects. (Tr.671:5-672:9.) Kubow’s October 16, 2015 report provided a value of
$17,054,000 for the Halyard Wharton project; Kubow’s September 7, 2018 report provided
values of $30,731,000 for Halyard Wharton and Halyard Henderson individually; Kubow’s
April 10, 2019 report provided several values—a “reliable and accurate value” of $11,592,000
for each project, and a total “reliable, accurate, and achievable” value of $6,000,000. (Id.;
DX43, at 4.) According to Cobb, this variation underscored the “randomness and a speculative
nature of the Kubow reports.” (Tr.672:8-9.)
3. Defendants’ experts were credible.
Indeck cannot seriously question Defendants’ experts’ experience. Lednicky has been
working in the power industry since 1991. (Tr.567:19-20; DX38A.) From 1991 through 2011,
while working for Destec and Dynegy, Inc., Lednicky was responsible for developing and
financing dozens of power plant facilities around the country. (Tr.568:18-569:9.) Lednicky is
familiar with concepts of DCF analysis and business valuation and “had quite a bit of experience
at both Destec and Dynegy in power plant evaluations.” (Tr.569:17-22.) Lednicky has prepared
and maintained financial pro formas and internal valuations for power projects. (Tr.570:3-12.)
And, Lednicky has experience in the ERCOT market via several power projects he helped
develop while at Destec and Dynegy. (Tr.570:23-571:13.)
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
36 of 48
- 31 -
Cobb is the president of Cobb & Associates, Ltd. Prior to that, Cobb was a partner at
KPMG and also was a professional staff member at Touche Ross (now Deloitte & Touche LLP),
as well as PricewaterhouseCoopers LLP. (Tr.665:1-24.) Cobb has been performing damages
calculations since 1975. (Tr.666:22-23.) Cobb has testified in state and federal courts more than
225 times. (Tr.666:24-25.) The majority of Cobb’s practice is devoted to lost profits analysis
and business valuations. (Tr.667:1-11.) Cobb has been involved in hundreds of cases where
DCF is an issue and has “taught seminars regarding [DCF] in lost profits and in valuation.”
(Tr.667:20-25.) And, while Indeck made a spectacle of the few occasions in which Mr. Cobb
has been disqualified or limited as an expert, the Court observed that it is bound to happen to an
expert who testifies with such regularity. (Tr.701:6-15.)
Indeck insinuates that Lednicky and Cobb blindly relied upon information from
Defendants in forming their opinions. Their reports confirm, however, that Lednicky and Cobb
both reviewed Kubow’s reports and supporting exhibits, deposition transcripts, and other sources
of information, in addition to information supplied by Defendants. (DX38-43.) Notably, Indeck
only finds it problematic when Defendants’ experts rely on Defendants’ information. Indeck
touts the reliability of Kubow’s analysis because it is purportedly based upon Defendants’ pro
forma. Indeck’s attempts to discredit Defendants’ experts fail.
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
37 of 48
- 32 -
F. Defendants’ marketing efforts buttress the conclusion that Indeck’s damages claim is speculative.
Indeck protests the Court’s consideration of post-breach events. But, as set forth above,
Indeck has not cited a single case that precludes a Court from considering post-breach evidence
to assess whether a plaintiff has proved future lost profits with reasonable certainty.6
The results of Defendants’ marketing efforts buttress the conclusion that Indeck’s lost
profits claim is speculative. Defendants engaged Scotiabank to market their project and, when
those efforts did not yield results, carried the effort forward on their own. (See supra at 12-15.)
Despite these efforts, the only serious proposal Defendants received was from Beowulf, who
ultimately proposed paying a maximum of $3 million, but pulled that proposal after engaging in
due diligence. Thus, while Kubow projected that Defendants would be able to sell their project
for tens of millions of dollars, the open market demonstrates that the value Kubow ascribes to
Defendants’ project is speculative and unreliable.
G. The Illinois Court’s ruling that Indeck’s damages claim is speculative precludes a different finding by this Court.
Yet another reason to deny Indeck’s lost profits claim here is the fact that the Illinois
court rejected Indeck’s nearly identical damages claim in that case. After 54 days of trial, which
included reports and testimony from Kubow, the Illinois court rejected Indeck’s claim that it
was entitled to damages based upon the hypothetical value of Defendants’ project: “Indeck did
not prove its belief, which the Court recognizes is a heartfelt belief, that Defendants will profit
handsomely as soon as trial is over. It’s [sic] simply has not been proven and it’s a
speculative argument.” (DX47, at 93:4-94:2 (emphasis added).)
6 Indeck’s persistent demands for discovery regarding Defendants’ project up to the date of trial discredits Indeck’s assertion that evidence regarding the current status of Defendants’ project is irrelevant.
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
38 of 48
- 33 -
In this case, Indeck asserted a nearly identical theory of damages as it did in Illinois: that
it is entitled to a measure of damages based upon the hypothetical future construction, operation,
and sale of Defendants’ project. (Indeck Br. at 18-20.) Indeck’s sole evidence of this theory is
Kubow’s testimony and reports. At trial, Kubow acknowledged that he undertook the same
analysis in this case as he did in the Illinois case. (Tr.124:15-17, 128:24-129:2.) Kubow’s
reports from the Illinois case confirm that his analysis was based, as it was in this case, on the
funding, construction, and sale of a hypothetical future project. (See, .e.g., DX34A, at 11-12.)
The Illinois court’s ruling, which was made in response to Kubow’s testimony and reports, is
instructive for the proposition that Indeck’s lost profits damages claim is here, as it was in
Illinois, incapable of proof to a degree of reasonable certainty.
Indeck has repeatedly asserted that this ruling has no bearing here because the Illinois
ruling will not have preclusive effect until the appeals process is exhausted. But, in appealing
the Illinois trial court’s decision, Indeck faces a nearly insurmountable task. Illinois Appellate
courts cannot consider facts which are not in the record. Sanni, Inc. v. Fiocchi, 443 N.E.2d
1108, 1111 (Ill Ct. App. 1982). As such, all Indeck can do on appeal is argue that the Illinois
trial court’s legal conclusion that Indeck’s future lost profits are too speculative, which was
based upon many of the proposed findings Indeck submitted, was somehow wrong. But, Indeck
will have to make this argument against the weight of a substantial, 54-day trial record and the
findings Indeck itself proposed. (DX46.) Indeck is unlikely to succeed in this endeavor.
II. INDECK FAILED TO MITIGATE ITS DAMAGES.
Under New York law, the non-breaching party to a contract has a duty of making
reasonable exertions to minimize its injury. Holy Props. Ltd., L.P. v. Kenneth Cole Prods., Inc.,
661 N.E.2d 694, 696 (N.Y. 1995); see also Richard C. Mugler Co. v. A.C. Mgmt. Corp., 29 A.D.
548 (2d Dep’t 1967) (“[R]espondent was under a duty to make a reasonable effort to minimize
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
39 of 48
- 34 -
the damages resulting from the breach.”). The duty to mitigate arises from common law,
meaning that it need not expressly be stated in a contract to be enforceable against the party
claiming breach. Mack Cali Realty, L.P. v. Everfoam Insulation Sys., Inc., 110 A.D. 3d 680, 682
(2d Dep’t 2013). Defendants must only offer some proof of Indeck’s failure to mitigate. . See
Wooten v State of New York, 302 A.D.2d 70, 74 (4th Dept 2002).
Indeck failed to mitigate its damages. At trial, Indeck presented no evidence that it
attempted to market its project (such as through an investment bank like Defendants did with
Scotiabank). Despite its self-professed expertise in the industry, Indeck presented no evidence of
any attempts to secure revenue contracts or financing, or that Indeck had entered into cost
contracts with construction companies. Nor did Indeck produce, or introduce at trial, any offers,
proposals, or term sheets from potential investors. Indeed, Kubow’s reports were “silent on the
topic of mitigation”; there was a “dearth of information, even discussion, of mitigation.”
(Tr.689:19; 690:7-8.) Indeck failed to mitigate its damages because it “decided to close down
[its] development activities.” (Tr.585:13-14.) New York law does not permit Indeck to collect
damages from Defendants in the absence of any reasonable efforts to mitigate its alleged
damages.
III. INDECK FAILED TO PROVE ITS OUT-OF-POCKET LOSSES AND ENTITLEMENT TO MANAGEMENT FEES.
A. Indeck’s purported out-of-pocket losses and management fee claims pertain to Indeck’s dismissed aiding-and-abetting claim.
On summary judgment, Indeck contended that it was entitled to the following categories
of damages on its aiding-and-abetting claim: (1) the full equity stake of DePodesta and
Dahlstrom in the joint venture, (2) the management fees that Halyard Energy Ventures has
received each year since 2013, and (3) the compensation, bonuses, and benefits DePodesta and
Dahlstrom received at Indeck while being disloyal. That claim was dismissed on summary
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
40 of 48
- 35 -
judgment, and the Court did not grant Indeck’s motion to renew that claim for trial.
Accordingly, Indeck should be precluded from recovering damages that pertain to a dismissed
claim. In addition, ordering Defendants to pay back the compensation the Illinois court already
ordered Dahlstrom and DePodesta to pay would amount to a double-recovery.
B. Indeck failed to introduce a sufficient evidentiary basis for its purported out-of-pocket losses.
Under New York law, “[a] plaintiff in a breach of contract action must produce facts and
figures from which the trier of fact may make an estimate, and the mere statement that he
estimates his expenses at a specified figure, without more, is incompetent.” Baskin-Robbins, Inc.
v. S & N Prinka, Inc., 78 F. Supp. 2d 226, 232 (S.D.N.Y. 1999).
Here, Kubow admitted that he was not retained to opine on Indeck’s out-of-pocket losses
and provided no testimony to that effect. (Tr.138:16-19.) Garth admitted that he did not know
the exact amounts of Indeck’s out-of-pocket losses and repeatedly referred to invoices the Court
determined were inadmissible. (Tr.14:12-17; 36:22-23; 44:13-18.) Thus, Indeck failed to
provide a sufficient basis for an award of out-pocket losses.
C. Indeck failed to prove that Defendants caused its out-of-pocket losses.
New York law prohibits the recovery for breach of contract “where they were not
actually caused by the breach—i.e., where . . . the damage would have been suffered, even if no
breach occurred.” Pesa v. Yoma Dev. Grp., 18 N.Y.3d 527, 531 (2012).
Indeck failed to show that its out-of-pocket losses were actually caused by Defendants’
breach. First, there is no connection between Defendants’ breach and the retention bonuses—
Garth admitted that neither Kelly Inns, nor Mike Ferguson were looking for new work when
Indeck paid their “retention bonuses.” (Tr.48:4-7.) Second, there is no connection between
Defendants’ breach and Indeck’s supposed replacement costs—Garth acknowledged that
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
41 of 48
- 36 -
Dahlstrom and DePodesta were at-will employees who could have left at any time, and that
Indeck would have incurred the replacement costs regardless of Defendants’ breach. (Tr.45:17-
20.) In addition, Garth admitted that Indeck routinely uses headhunters to fill positions, and that
it is always Indeck’s choice whether to pay new employees’ relocation expenses. (Tr.Tr.45:22-
46:6.) Finally, with respect to the “confidential studies,” Garth testified that Indeck had already
selected its sites before they hired consultants and that the studies were site-specific (i.e., would
not have utility for a developer developing a different site). (Tr.34:6-17; 39:3-15.) Indeck failed
to establish a causal connection between its out-of-pocket expenses and Defendants’ breach.
D. Indeck is not entitled to recover management fees
For several reasons, Indeck failed to prove that it is entitled to management fees. (Indeck
Br. at 37.) First, Indeck’s claim for management fees fails to account for the simple fact that the
MCA’s prohibition on engaging Indeck’s employees was expressly limited to a two-year term.
(PX1.)7 Thus, any claim for fees based upon Dahlstrom and DePodesta managing Defendants’
project must be limited to two years in the first instance. Even more fatal to Indeck’s claim is
Garth’s admission that Indeck is not in the business of project management and has not managed
a power project for a third-party for 25 years, let alone realized revenues for any such
management. (Tr.30:10-14.) Further, Indeck failed to account for the fact that any management
fees it would have earned would have been reduced dollar-for-dollar by the amount Indeck
would have had to pay Dahlstrom and DePodesta, or other employees, to manage the projects.
The Court should reject Indeck’s attempt to recover fees for services it does not provide.8
7 It is unclear whether Indeck is attempting to recover $2.5 million in management fees or $1 million. (See Indeck Br. at 4, 37.) To the extent it is the former, the two-year time period in the MCA is applicable and limits Indeck’s ability to recover management fees. 8 Further, such damages are explicitly barred by the MCA, which provides, in relevant part:
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
42 of 48
- 37 -
IV. INDECK IS NOT ENTITLED TO ATTORNEYS’ FEES.
A. Indeck should be precluded from recovering attorneys’ fees and costs if Indeck recovers only nominal damages.
To be a prevailing party under New York law, the party must have “prevailed with
respect to the central relief sought.” Chainani v. Lucchino, 942 N.Y.S.2d 735, 736 (4th Dep’t).
“[S]uch a determination requires an initial consideration of the true scope of the dispute litigated,
followed by a comparison of what was achieved within that scope.” Excelsior 57th Corp. v.
Winters, 227 A.D.2d 146 (1st Dep’t 1996) (determining that landlord was the prevailing party in
an action by the landlord for 54 months’ rent in which tenants claimed constructive eviction and
breach of warranty of habitability for 24 months, but only established an entitlement to four and
a-half months’ worth of rent abatement).
Indeck initially brought six separate claims against Defendants and requested seven
forms of relief, including an injunction (enjoining Defendants from five separate activities),
compensatory and consequential damages, disgorgement of confidential information, and
disgorgement of profits, among other things. (See NYSCEF Doc. No. 1.) After the Court’s
Order on summary judgment, the scope of the dispute has been significantly narrowed: The
Court dismissed all of Indeck’s claims except for its breach of contract claim and indicated that
Indeck may be entitled to only nominal damages. See Indeck, 2018 WL 801541. Should Indeck
recover only nominal damages on its remaining claim, it can hardly be said that Indeck will have
“prevailed with respect to the central relief sought,” especially when Indeck initially requested
Neither Party will have any claims against the other Party or any of its Representatives arising out of or relating to any transaction other than as parties to such definitive agreement, and then only in accordance with the terms thereof, or as Parties to this Agreement, for the matters specifically agreed to herein.
The plain terms of the MCA bar Indeck from recovering management fees.
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
43 of 48
- 38 -
seven different remedies stemming from six separate claims and purports to have been damaged
in excess of $33 million. In short, a technical favorable ruling and an award of nominal damages
does not entitle Indeck to recover its fees and costs as a “prevailing party” under the MCA. See,
e.g., Kachkovskiy v. Khlebopros, 164 A.D.3d 568, 573 (2d Dep’t 2018) (affirming denial of
attorneys’ fees where “the court properly concluded that the plaintiff did not receive substantial
relief, so as to warrant the conclusion that he prevailed on a central claim”).
B. New York law precludes Indeck from recovering attorneys’ fees in excess of the amount actually recovered.
Under New York law, “when a contract provides that in the event of litigation the losing
party will pay the attorneys’ fees of the prevailing party, the court will order the losing party to
pay whatever amounts have been expended by the prevailing party, so long as those amounts are
not unreasonable.” F.H. Krear & Co. v. Nineteen Named Trustees, 810 F.2d 1250, 1263 (2d Cir.
1987) (emphasis added). As a guidepost to the standard of reasonableness, New York courts
“will rarely find reasonable an award to a plaintiff that exceeds the amount involved in the
litigation.” Id. at 1264.
For example, in Regan v. Conway, plaintiff’s counsel sought $203,617.40 in attorneys’
fees under the parties’ contractual fees provision following a verdict of $40,000. 768 F. Supp. 2d
412 (E.D.N.Y. 2011). The Court rejected plaintiff’s fee request on the grounds that “the fee
should not exceed the amount in this litigation. The plaintiff recovered the sum of
$40,000 . . . the Court finds that a total ‘reasonable’ attorneys’ fee is . . . the sum of $40,000.”
Id. at 419.
The Court should preclude Indeck from recovering attorneys’ fees and costs in excess of
the damages it actually recovers in this case. Under New York law, any award of fees and costs
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
44 of 48
- 39 -
in excess of the compensatory damages Indeck actually recovers would be unreasonable as a
matter of law.
V. INDECK’S RIGHT TO PREJUDGMENT INTEREST IS LIMITED.
Under CPLR 5001(a), the prevailing party in a breach of contract action is entitled to
prejudgment interest. When damages were incurred at various times, the interest can be
computed from “a single reasonable intermediate date.” CPLR 5001(b). Where, as here, there is
difficulty in fixing a single, reasonable intermediate date, the “appropriate date from which to
compute interest is the date of the commencement of the action.” Delulio v. 320-57 Corp., 99
A.D.2d 253, 255 (1st Dep’t 1984). Indeck’s right to prejudgment interest, if any, is limited in
several respects.
First, as set forth above, Indeck is not in fact a “prevailing party” because a recovery of
nominal or out-of-pocket losses (which is Indeck’s best-case scenario here) does not equate to
Indeck being the prevailing party in a case where it sought tens of millions of dollars in “lost
profits.” Second, to the extent the Court awards interest on any damages Indeck recovers, the
earliest date to impose interest is the date Indeck filed its complaint on July 15, 2014, nearly four
months later than the March 2014 date Indeck contends should apply.
VI. AT MOST, THE COURT SHOULD AWARD INDECK DEFENDANTS’ HALYARD WHARTON PROJECT.
At trial, the Court requested “briefing on . . . the potential for any other type of damage
award[.] For example, is there any authority in the law for transfer of the opportunity[.]”
(Tr.350:24-351:3.) Because Indeck has failed to establish its entitlement to a legal remedy, the
Court should, at most, award Indeck Defendants’ Halyard Wharton project.
In general, New York courts do not award equitable relief when there is an adequate
remedy at law. Matter of Kemp & Beatley, Inc., 473 N.E.2d 1173, 1177 (N.Y. 1984). Here,
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
45 of 48
- 40 -
because the future lost profits Indeck seeks are speculative, Indeck has failed to establish its
entitlement to a legal remedy (i.e., damages). A New York court fashioning an equitable remedy
“may, in its discretion, grant relief that is warranted by the facts plainly appearing on the papers
of both sides, if the relief granted is not too dramatically unlike the relief sought, the proof
offered supports it, and there is no prejudice to any party.” Sudit v. Labin, 148 A.D.3d 1073,
1075 (2d Dep’t 2017).
The gravamen of Indeck’s claim for breach of the MCA is that Defendants, by hiring
Dahlstrom and DePodesta and utilizing Indeck’s confidential information, were able to develop
the project that Indeck would have developed absent Defendants’ breach. Thus, if the Court is
inclined to award Indeck anything, the most it should award Indeck is the right to take over
Defendants’ project. Such relief is “not too dramatically unlike the relief sought.” See Id.9
CONCLUSION
Based on the foregoing and the trial record, Defendants respectfully request that the
Court deny Indeck’s request for any damages beyond nominal damages.
9 The Court should note that any such transition would not be seamless in light of the fact that Defendants’ site control agreements need to be redeemed, the interconnection studies will have to be redone, and some permits and agreements may not be assignable. In addition, any equitable remedy should take into account the fact that Indeck would benefit from the $10-plus million Defendants have invested in the projects.
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
46 of 48
DATED:
67740290 v5 {00110899}
New York, NY August 29, 2019
/ -· George Brun~ , Anna Hadjikow, Esq. BRUNELLE & HADJfKOW, P.C. 39 Broadway, 33rd Floor New York, New York 10006 (2 12) 809-9100 (Tel.) (212) 809-3219 (Fax) gbrunelle@brunellelaw .com ahadj ikow@brunellelaw .com
FREDRIKSON & BYRON, P.A. Terrence J. Fleming, Esq. Sandra Smalley-Fleming, Esq. Jonathan P. Baker, Esq. 200 South Sixth Street, Suite 4000 Minneapolis, MN 55402 (612) 492-7000 [email protected] ssmalleyflem ing@fredlaw .com j baker@fred law .com
ATTORNEYS FOR DEFENDANTS
-41 -
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
47 of 48
CERTIFICATE OF COMPLIANCE
Pursuant to Commercial Division Ru le 17, I hereby certify that this memorandum contains 11,998 words, not counting the caption, table of contents, table of authorities, signature block, and this certificate. Word counts were performed using Microsoft Word 2013.
DATED: August 29, 201 9 New York, NY
-42-
/ r ,
AnnaHadjiko~ Brunelle & Hadjikow, P.C. 39 Broadway, 33rd Floor New York, NY I 0006
FILED: NEW YORK COUNTY CLERK 08/29/2019 06:38 PM INDEX NO. 652171/2014
NYSCEF DOC. NO. 670 RECEIVED NYSCEF: 08/29/2019
48 of 48