10/31/2018 district irrigation...

31
10/31/2018 District Irrigation Profiles http://irrigationap.cgg.gov.in/wrd/getDistricts 1/31 IRRIGATION PROFILE OF CHITTOOR DISTRICT *Click here for Ayacut Map INTRODUCTION Chittoor District is situated in South Eastern part of Andhra Pradesh in Rayalaseema Region. The District is located in Geographic coordinates of 12° 37' to 14° 08' of North latitude and 78° 33' to 79° 55' of the Eastern Longitude. The population of the District is 41,70,468 (2011 census).The District is surrounded by Nellore, Kadapa, Ananthapur Districts and bordered by Tamilnadu and Karnataka States. There are 8 main River basins in the District Viz: Swarnamukhi, Kalangi, Arani, Kushastali, Palar (including Koundinya, Bheema, chittoor&Ponniar), Cheyyeru, Papagni and Upputeru (Major basin Pennar). The Diatrict principally depends upon Agriculture. The principal crops are Paddy, Sugarcane and Ground nut. The District headquarter is connected by Broad-Gauge Railway line from Secunderabad, Hyderabad, Vijayawada, Bangalore. The famous temple of Lord Sri VenkateswaraSwamy of Tirumala and the temple city Tirupati lies in the District. The Tirupati city is connected all over the country by Railways, Airways and Roadways. The area of the District is covered under Major Irrigation, Medium Irrigation and Minor Irrigation Sources. The Major Irrigation projects are NTR-Telugu Ganga Project (NTR-TGP), Handri Neeva Sujala Sravanthi (H.N.S.S) and Galeru Nagari Sujala Sravanthi (G.N.S.S). There are 3 No. of completed Medium Irrigation Projects in the District Viz: Swarnamukhi Anicut System, Araniar and Krishnapuram with total ayacut of 21,875 Acres. There are 668Nos of Minor Irrigation Sources (more than 100 acres )with an ayacut of 1,69,218 Acres, including 5 Nos of Medium projects

Upload: others

Post on 04-Nov-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 1/31

IRRIGATION PROFILE OF CHITTOOR DISTRICT

*Click here for Ayacut Map

INTRODUCTION

Chittoor District is situated in South Eastern part of Andhra Pradesh in Rayalaseema Region. TheDistrict is located in Geographic coordinates of 12° 37' to 14° 08' of North latitude and 78° 33' to 79° 55' of theEastern Longitude. The population of the District is 41,70,468 (2011 census).The District is surrounded byNellore, Kadapa, Ananthapur Districts and bordered by Tamilnadu and Karnataka States. There are 8 main Riverbasins in the District Viz: Swarnamukhi, Kalangi, Arani, Kushastali, Palar (including Koundinya, Bheema,chittoor&Ponniar), Cheyyeru, Papagni and Upputeru (Major basin Pennar). The Diatrict principally dependsupon Agriculture. The principal crops are Paddy, Sugarcane and Ground nut.

The District headquarter is connected by Broad-Gauge Railway line from Secunderabad,Hyderabad, Vijayawada, Bangalore. The famous temple of Lord Sri VenkateswaraSwamy of Tirumala and thetemple city Tirupati lies in the District. The Tirupati city is connected all over the country by Railways, Airwaysand Roadways. The area of the District is covered under Major Irrigation, Medium Irrigation and MinorIrrigation Sources. The Major Irrigation projects are NTR-Telugu Ganga Project (NTR-TGP), Handri NeevaSujala Sravanthi (H.N.S.S) and Galeru Nagari Sujala Sravanthi (G.N.S.S).

There are 3 No. of completed Medium Irrigation Projects in the District Viz: Swarnamukhi AnicutSystem, Araniar and Krishnapuram with total ayacut of 21,875 Acres. There are 668Nos of Minor IrrigationSources (more than 100 acres )with an ayacut of 1,69,218 Acres, including 5 Nos of Medium projects

Page 2: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 2/31

transferred as Minor Projects as their ayacut is less than 5000 Acres. In addition there are 7395Nos ofMinorIrrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres.

S.No Name of the Basin % of the total Geographical area of District1 Swarnamukhi River Basin 15.312 Kalangi River Basin 6.293 Araniar River Basin 6.154 Kushastali River Basin 6.025 Palar River Basin 32.856 Papagni River Basin 9.807 Cheyyeru River Basin 23.038 Upputeru (Major Basin: Pennar) 0.55

Total 100.00

The Structure of Irrigation Circle, Chittoor is as follows. There are Five Irrigation divisions, 24 No.of Sub-Divisions, having the jurisdiction of 66 mandals of Chittoor district and 2 mandals of Nellore District (inwhich 7 system tanks of Medium Irrigation source namely SwarnamukhiAnicut) are under control of IrrigationCircle, Chittoor. The details of Irrigation divisions are 1) Irrigation Division, Srikalahasti 2) Irrigation Division,Tirupati3) Irrigation Division, Chittoor 4) Irrigation Division, Palamaner and 5) Irrigation Division,Madanapalle.

Sociological features such as population, literacy rate etc.

Population - 4170468 No's - 100 %

Literacy - 2711432 No's - 72.36%

Geographical Area Area ( in acres) in % with total areaTotal geographical area 37,43,565 100Forest area 11,25,990 30.08Cultivable area 4,08,797 10.92Barren and un culturable land 4,15,904 11.11Land put to Non Agricultural use 3,61,777 9.66Sown area 9,97,726 26.65Irrigated area 4,33,507 11.58Normal Average Rainfall 934 mm

Details Of Irrigation Projects

S.No Projects Nos Ayacut in acresA Completed ProjectsI Major Irrigation Projects Nil NilII Medium Irrigation Projects 3a) Swarnamukhi Anicut 1 10,200b) Araniar Project 1 5500

Page 3: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 3/31

c) Krishnapuram Reservoir 1 6125III Minor Irrigation Projects/Schemes1 Minor Projects transferred from Mediuma) Kalangi Reservoir 1 4650b) Mallimadugu Reservoir 1 3951c) Bahuda Reservoir 1 2884d) Pedderu Reservoir 1 4300e) Siddalagandi Reservoir 1 2252 M.I. Tanks (>100Ac) 668 1692183 M.I. Tanks (<100Ac) 7,395 136609B Ongoing ProjectsI Major Irrigationa) NTR Telugu Ganga Project 1 54,326(Contempalted) and 22,826(Created)b) Galeru Nagari Sujala Sravanthi Project 1 1,03,500c) Handri Neeva Sujala Savanthi Scheme 1 1,81,400II Medium Irrigation Projectsa) Krishnapuram Project near Krishnapuram (v) 1 6125(Contemplated)b) Araniar project near Pitchatur(v) 1 5500(Contemplated) and 3200(Created)c) SwarnamukhiAnicut System 1 10200(Contemplated) and 8646(Created)III Minor Irrigation Projectsa) M.I. Tanks (>100Ac) 668 169218b) M.I. Tanks (<100Ac) 7,395 136609

ONGOING MAJOR IRRIGATION PROJECTS

1. Telugu Ganga Project

Page 4: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 4/31

Preamble

SatyaSai Ganga Canal ( K.P.Canal ) runs for a length of 151.887 Kms from Kandaleru Reservoirupto Andhra Pradesh / Tamilnadu border to irrigate 3,00,000 Acres in Nellore and Chittoor Districts in additionto supply of 15 TMC of drinking water to Chennai city. The canal takes off from the Right side of KandaleruReservoir with sill level at +60.000 M and with a head discharge of 113.27 cumecs (4000 Cusecs). The ayacut of3,00,000 Acres under SatyaSai Ganga Canal is distributed through 1 to 9 Branch Canals in Nellore and ChittoorDistricts. The T.G.P & GNSS. Circle, Srikalahasti is entrusted the C.C. lining works in the balance reaches ofS.S.G.Canal from Km.0.000 to Km.151.887 and also execution of 6th to 9th Branch Canals & their distributorysystems to provide irrigation facilities to a contemplated Ayacut of 1,45,000 (Nellore :90674 Acres,Chittor:54326 Acres)

Salient Features

Excavation of the entire length of SatyaSai Ganga Canal (the then K.P.Canal) was completed,including construction of structures.C.C. Lining for Canal Bed and Sides was done at most vulnerable reachesby the Department and by Sri SatyaSai Charitable Trust.

Before Jalayagnam, against the contemplated Ayacut of 17,352 Acres under the distributariesof 7thBranch Canal (except 13L, 14R, 15L majors), 7A, 7B, 8A-1R Branch Canals, Ayacut to an extent of 17,664Acsis identified and 16,003Acs of Ayacut was developed. Action is being initiated to develop balance Ayacut of1349 Acres.

During Jalayagnam balance lining works of S.S.G.Canal between Km 0.000 to Km 151.887 to alength of Km 73.350 and balance contemplated Ayacut 0f 76,776 Acres was taken up under E.P.C. turnkeySystem in two No's of packages, viz., T.G.P. packages No. 10 & 11.

Components of Package-10 work:

a) Lining of Canal: 51.345 Kms

b) Excavation of Branch Canals ie., 6 Branch Canal, 13-L Major, 14-R Major & 15-L Major of 7Branch Canal and their distributory systems

c) To create an irrigation potential of 69,548Acres.

Components of Package-11 work:

a) Lining of Canal: 21.995 Kms

b) Excavation of Branch Canals 8-"A", 8-"B", 9, 9-"A" and Mambattu(9-B).

c) To create an irrigation potential of 28,139 Acres.

Mandals Benifited : 1)Thottambedu, 2) Varadaiahpalem, 3)B.N.KandrigaCropping Pattern : -I.D. Crops such as Groundnut, Sajja, Mirchi etc.,Population Benifited (for Projectsin progress) : 25 Lakhs

AyacutContemplated : 54326Deleted due to formation of SEZ : 23297

Page 5: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 5/31

and on the representations ofRythos etc.,Ayacut identified : 31030I.P. created : 22826The balance to be created : 8204Stabilization proposed underM.I.Tanks : 20584(179 Nos)

Proposed utilization of waterDrinking water supply to TamilNadu : 15 TMC (Krishna River water from the Share of Andhra

Pradesh, Karnataka and Maharashtra States)

Irrigation :

30 TMC (Flood waters of River Pennar) for thecontemplated Ayacut of 3,00,000 Acres under Nellore &Chittoor districts under SSLC & SB Circle, Nellore andTGP & GNSS Circle, Tirupati.

Status of Main CanalTotal length of MainCanal : Km.151.887Length completed along with CM& CD works : Km.151.887 (during 1983 - 1996)

Length of cement concrete lining : Km.144.02Branch Canals & Distributaries:6th, 7th, 8A, 8B, 9th and Mambattu branch canals taken upunder Jalayagnam under 10 & 11 packages.Total length in Chittor District : 222.00Length completed Kms : 134.00Balance to be completed : 88.00Length of canals in forest lands : 8.00Length of canals in non forest lands : 81.20Total No. of CM & CD worksa) Completed : 478b) Balance : 267Balance Land Acquisition : 233.951 AcresForest Lands : 6.67 HaFinanciala) Expenditure incurred so far : Rs.209.37 Crores under Jalayagnam.b) Bills pending up to 10/2014 : 0c) Amount required for completionUp to 10/2014 : Rs.64.036 Crores

Issuesa) Forest : Stage II clearance is awaited from Govt. of India.b) Payments : Rs. 64.036 Crores required for Completion.

c) Land Acquisition : Pending due to DKT lands, assigned Lands and Courtcases.

2. Galeru Nagari Sujala Sravanthi Project:

Page 6: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 6/31

Page 7: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 7/31

Preamble

Page 8: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 8/31

The Galeru Nagari Sujala Sravanthi Project was conceived by the Govt. of Andhra Pradesh inG.O.Ms.No.236, dt:22-9-88 to take up GNSS. Project. The Project is envisaged to provide Irrigation facilities toan extent of 2,60,000Acres (1,55,000Acres in Kadapa Dist., 1,03,500Acres in Chittoor Dist. And 1,500Acres inNellore Dist.) and also to provide drinking water facilities to 5,00,000 people. It also envisages drawal of38TMC flood water of Krishna River from the foreshore of Srisailam Reservoir during the period from Augustto November.

Administrative approval was accorded for Rs.2189.26Crores by the Govt. of A.P. for Phase-II ofGNSS. Vide G.O.Ms.No.185, I&CAD. (Major.IRR.VI) Dept., Dtd:15-10-2005. Revised Administrative approvalwas accorded for Rs.2525.91Crores vide G.O.Ms.No.50, I&CAD.(Major.IRR.VI) Dept., Dtd:25-03-2008.

In view of the large magnitude of the project and to derive early benefits, the project was taken up intwo phases.

The works are entrusted in 14 Packages under G.N.S.S. Phase-II. Among 14 Packages, 7 Packageworks, i.e., from Package No.8/06 to 14/06 were entrusted to TGP & GNSS. Circle, Srikalahasti. One Packagework, i.e., Package No.8/06, comes under Kadapa District and 6 Packages i.e., Package No.9/06 to PackageNo.14/06 works come under Chittoor District.

Salient Features

GNSS. Main Canal - 94Kms. i.e., from Km.240.000 to Km.334.000, Which includes Balaji Tunnel-I for a length of 11.300Kms. i.e., from Km.243.000 to Km.254.300 and Balaji Tunnel-II for a length of9.436Kms.i.e., from Km.266.206 to Km.275.642 and 7 Nos. of enroute off-line reservoirs.

(1)Sri BalajiReservoir , 2)Mallimadugu Reservoir (3)Padma Sagar Reservoir (4)SrinivasaSagarReservoir

(5)Venu gopala Sagar Reservoir (6) Vepagunta Reservoir (7)AdaviKothuru Reservoir

Components Of Project

1) Main Canal from Km.240.000 to 334.000 (Part of Tunnel and part of open channels) and

2) I. Sri Balaji Reservoir (3 TMC, 1TMC for Drinking water to Tirupathi& 2 TMC for Irrgn. To Mallimadugu Reservoir) & its distributories.

II. Mallimadugu Reservoir (2.650TMC, 55,000Acres Ayacut) & its distributories.

III. Padma Sagar Reservoir (0.450TMC, 5000Acres Ayacut) & its distributories.

IV. SrinivasaSagar Reservoir (0.448TMC, 4200Acres Ayacut) & its distributories.

V. VenugopoalaSagar Reservoir (2.683TMC, 258000Acres Ayacut) & its distributories.

VI. Vepagunta Reservoir (0.533TMC, 5000Acres Ayacut) & its distributories.

VII. AdaviKothuru Reservoir (1.000TMC, 10000Acres Ayacut). & its distributories.

Mandals Benifited :

(1)Tirupati, (2)Renigunta,(3) Yerpedu, (4)Srikalahasthi (5)KVB.Puram (6)Pitchatur (7)Nagalapuram (8)Nindra(9)Vijayapuram (10)Vadamalpet (11) R.C.Puram(12)Puttur(13) Narayanavanam (14) Nagiri

Page 9: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 9/31

Cropping Pattern : I.D. crops such as Ground nut,Sunflower, Sajja etc.,Population Benifited : 500000(FOR Projects in progress)I.P.Contemplated : 1,05,000 AcresI.P.Created : NilCumulative Expenditure : Rs.157.698 CroresBottlenecks(for Projectscontemplated) : Forest clearance and L A.

Sailent Features Of Existing /Under Construction Reservoirs Of GNSS Phase-II Under GNSS Division, Tirupati

SlNo.

Name oftheProject

GNSS Phase-II Works - Excavation and lining of the balance length of Galeru NagariSujala Stravanthi Canal from Km .33.170 to km 338.721 and the Distributory system,Excavation and lining of Kailasagiri Canal from km.0.000 to km 61.000 includingformation of B Nos. Reservoirs to provide Irrigation fecilities to 2.25 lakh Ac.Anddrinking water to a population of 5 lakhs and

2Name oftheReservoir

PackageNo.12/06Padma SagarReservoir

PackageNo.12/06SrinivasaSagarReservoir

Package No.13/06Venugopala SagarReservoir

PackageNo.14/06VepaguntaReservoir

Package No.14/06Adavikottur Reservoir

3 Location Latitude 13°33' 0"

Latitude13°33'05" Latitude 13°29'08 Latitude

13°22'05" Latitude 13°20"30

Longitude79°25'10"

Longitude79°26'07" Longitude 79°33'52" Longitude

79°33'30" Longitude 79°33'00"

4 Catchmentarea

2.60Sq.miles

4.37Sq.Miles

Self catchment i.e., 55.25Sq.Km. entire yield fromself catchment is let outfor LRR

4.123Sq.Km 4.930 Sq.Km

5

Waterspreadarea atFRL

2214332M2 2123441 M2 8235642 M2 1139650 M2 1475980 M2

6GrossStoragecapacity

0.450 TMC 0.448 TMC 2.683 TMC 1.533 TMC 1.000 TMC

7Livestoragecapacity

0.445 TMC 0.419 TMC 2.503 TMC 0.513 TMC 0.990 TMC

8MaximumfloodDischarge

70 Cumecs 103 Cumecs 340 Cumecs 48.20Cumacs 55.00 Cumacs

9 F.R.L +163.000 M +165.000 M + 172.500 M +170.000 M +171.500 M10 M.W.L +163.900 M +165.900 M +172.500 M +170.900 M +172.100 M11 T.B.L +166.000 M +168.000 M +175.500 M +173.000 M +174.000 M12 Length of

the4.80 Km-0.030=4.770Km

4.30-0.065=4.235Km

6.59 Km-0.036=6.560 Km 2.29 Km 0.946 Km

Page 10: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 10/31

earthenbund

13MaximumHeight ofearth bund

14.725 M 17.110 M 27.453 M 27.114 M 33.076 M

14Length ofthe spillway

--

15 Ayacut inAcres 4,800 5,200 25.8 5,000 10,000

16No.ofgates withsizes

Ungatedsurplus weir

Ungatedsurplus weir 3+1 (Emergency) 7.5x4 Ungated

surplus weir Ungated surplus weir

17Sill Levelof theO.T.Sluice

-- -- + 157.850m for Left andRight Main canals + 149.800n

+ 140.575 m forIrrigation and'+140.650m for drinkingwater supply to Nagari

3. HNSS Project

Page 11: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 11/31

Preamble

The Handri Neeva Sujala Sravanthi Project proposes to utilize 40.0 TMC of Krishna river water bylifting at 12 suitable locations enroute the main canal for providing irrigation benefits to an Ayacut of about6,02,500 acres (2.438 Lakhs hectares) Khariff I.D and drinking water facilities enroute in the up land anddrought prone areas of Kurnool, Anantapur, Kadapa and Chittoor Districts to 33 Lakhs people (both HNSSPhase I & Phase II).

HNSS Project, Phase II consists of Main Canal, Seven Branch Canals and three reservoirs

Salient Features

To provide irrigation benefit to an Ayacut of about 3,98,300 acres in HNSS Project, Phase II out ofwhich 1,81,400 acres Khariff I.D and drinking water facilities to 10 Lakh Population in Chittoor District.

I.P. created : As the Project is under execution stage, I.P. created may betaken as

Components of Project : In Chittoor DistrictSl.No Name of the Branch Canal Length in

KMsAyacut in

acres1 Main Canal 50.07 12002 Thambalapalli Branch Canal 29.43 15,000

3 Punganur Branch Canal (GudamPalli Village @ Km 75.800 Package27) 138.12 37,300

4 Vayalpadu Branch Canal 23.50 17,2005 Neeva Branch Canal 132.10 57,500

Page 12: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 12/31

6 Chintaparti Distributory 44.20 22,4007 Ellutla Distributory 25.17 15,4008 Sodum Distributory 50.00 5,4009 Electro Mechanical Package (28 Lifts) 10000

Total 493.00 181400Reservoir

SNo Name of theReservoir Location Capacity in

TMC

1 AdavipalliReservoir

At Km. 554.000 Main Canal near Titavaguntapalli (V), K.V.Palle (M)(Tail End) 1.418

2 KalicherlaReservoir

At Km. 5.075 on Thamballapalle Branch Canal , Kalicherala (V),Gurramkonda (m) 0.125

3 1 TMC reservoir At Km. 13.900 on Chinthaparthy Distributory , NearEguvathotlavaripalli (V), Gurramkonda (M) 0.702

Total 2.245 TMC

Summer Storage Tanks

SNo Name of the Tank Location Capacity inTMC

1 Chippili SS Tank At Km 156.950 on Punganur Branch canal near Chippili(V), Madanapale (M) 0.079

2 Guntivaripalli SS Tank At Km 167.25 of Punganur Branch canal, Guntivaripalle(V), Madanapalle (M). 0.131

3(a) Pedda Thippa SamudranmTank (Supplement)

At km 2.075 of Feeder Channel to Vyasasamudram Tank,Near P.T.M (V & M) 0.25

3(b) Vyasasamudram Tank(Supplement)

At km 15.55 of Feeder Channel to Vyasasamudram Tank,Near Kandurkur (V), P.T.M (M). 0.25

Total 0.71R & R:No. of Villages : 3(Adavipalle, Kataruvandlapalle & Nayanivaripalle)No of familiesdisplaced : 129

N.H. Crossings : 9 Nos - completed.Railway Crossings : 4 Nos - completedForest Land : 91.13Ha - Stage-2 clearance obtained on 25-05-2015.Mandals to bebenefited : Proposed Ayacut in 28 Mandals (Statement-I) enclosed.

Water allocation forayacut : 9.8 TMC

Cropping Pattern : The Water flow period is proposed for 120 days in Khariff season. SoKhariff cropping pattern in adopted.

Population Benefited(for Drinking purpose) : 10 Lakh people.

I.P. Contemplated : 1,81,400 acres in Chittoor DistrictI.P. Created : Nil, Project is under execution stage.

Page 13: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 13/31

Budget allocation2015-16 : 212.00 Crores

CumulativeExpenditure UPTO03/2015

: 1314.68 Crores in Chittoor District.

Bottlenecks : Balance Land Acquisition 2,806.599 acres to be acquired which islooked after by two Special Deputy Collectors of Madanapalle & Piler.

HNSS Project - Phase II

Adavipalli Reservoir is located near Adavipalli Village of K.V.Palle Mandal in Chittoor Districtwith the coordinates Latitude :13047'30'' N and Longitude :78052'20'' E and at the tail end of HNSS Main Canal@ Km.554.175.

The Balancing Reservoir is proposed to provide an ayacut of 80,000 Acres and drinking water todrought prone 13 mandals in Chittoor District i.e., K.V.Palle, Piler, Sodum, Pulicherla, Rompicherla, Pakala,Irala, Puthalapattu, Tavanampalle , Bangarupalem, Chittoor, Gudipala and Penumur through twoBranch canals,

1. Neeva Branch Canal - 114.677 Km (62,800 Acres),

2. Vayalpadu Branch Canal - 23.000 Km (17,200 Acres).

Salient Features

F.R.L : +492.000 MM.W.L : +492.900 MM.D.D.L : +480.000 MT.B.L : +495.000 MM.F.D = 14 Cumecs(from Cacthment area)+ 16cumecs (from Canal) : 30.00 cumecsGross Storage Capacity : 1.418 T.M.CLive Storage : 1.089 T.M.CDead Storage : 0.329 T.M.CArea of Submergence : 877 AcresLength of Left Earth Bund : 633.0MMax Height of Left Earth Bund : 37.20MLength of Right Earth Bund : 585.0 MMax Height of Right Earth Bund : 18.68 M

HNSS Project -Phase II

P 22-Main Canal

HNSS Main Canal from Km 523.000 to 546.000 Hydraulic ParticularsCanal Discharge starting : +21.15 CumecsCanal Discharge ending : +21.15 CumecsC.B.L starting : +475.500 MF.S.L starting : +460.00 MBed Width : 6.75 MF.S.D : 2.5 M

Page 14: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 14/31

Surface fall : 1 in 8900Side slopes : 1.5: 1Velocity : 0.83M/sec

4. Somasila Swarnmukhi Link Canal

Preamble

Page 15: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 15/31

The Somasila Swarnamukhi Link Canal takes off At Km 12.520 of Somasila Kandaleru Flood FlowCanal which is component of Telugu Ganga Project and runs for a length of 100.425kms, with a carryingcapacity of 2500 c/s at head and with starting F.S.L. of +93.580M.

This canal is intended to provide irrigation facilities to the high level layout situated on Right Sideof K.P. Canal. There are 316 M.I. Tanks in Nellore and Chittoor Districts with contemplated ayacut of 1.10LakhAcres which is not commendable by K.P. Canal. Somasila Swarnmukhi Link Canal is intended to stabilize1.10Lakh Acres under 316 MI tanks and also providing drinking water facility to 2.50Lakh population in en-routing Mandals (0.20 TMC) by diverting 4.45TMC of Pennar Flood Waters.

Benefits of the project:

The inletted water is proposed to be utilized for the drinking water needs of Tirupathi city andRenugunta, Yerpadu and Srikalahasti towns and en-routed villages by storing this water in proposed 1.018TMCbalancing reservoir near Althurpadu village and also in Thondamanadu and Uranduru MI tanks by the increasingthe capacities by another 600Mcft and 300Mcft respectively.

Salient Features

To provide irrigation benefit to an Ayacut of about 97,000 Ac under Somasila Swarnmukhi LinkCanal and drinking water facilities to 2.5 Lakh Population of 0.20 TMC.

Mandals to be benefited : Srikalahasti, Yerpadu and Thottambedu (74 no.of MI tanks)Population Benefited(For drinkingpurpose) : 2.5 Lakh people

Water allocation : 0.20 T.M.CI.P. Contemplated : 18240 acres in Chittoor DistrictI.P. Created : Nil, Project is under execution stage.

(A) Ayacut both Stabilization of Tanks & Direct Ayacut :

Package No. Stabilization of Tank Ayacut in Acres Direct Ayacut in Acres Total ayacut in Acres15 0 0 016 12,775 14,000 26,77517 84,225 0 84,225

Total 97,000 14,000 1,10,000

(B) Drinking Water Facility

Population : 2.50 LakhsQuantum of Water : 0.20 TMC

Land Acquisition In Non Forest Lands

Out of total length of 100.425kms, the canal traverses in non-forest lands for a length of about58.958 kms. The total requirement of Non forest lands are as follows.

Length of Canal inKms

Extent of Land Required inAcres

Extent of Land handedover

Balance Extent inAcres

Page 16: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 16/31

58.958 4879 1994 2885

COMPLETED MEDIUM IRRIGATION PROJECTS

1. Swarnamukhi Project in SrikalahasthiMandal of Chittoor District

Preamble

Swarnamukhi originates from Nallamalai ghats in Chandragiri (M) and runs through Chandragiri,tirupathi, Renigunta, Yerpedu and Srikalahasthi in Chittoor District. Swarnamukhi anicut system wasconstructed in the year 1956 at a cost of Rs 1932.00 lakhs.

The anicut has a main canal (Chembedu canal from head regulator) for a length of 15.4 km,covering 8.40km in Srikalahasthi and Thottambedu mandals and 7.00km in Nellore District. There is no leftcanal to this anicut. The project was constructed for providing irrigation facilities to an extent of 10,200 Acresduly feeding 46 tanks in 25villages of Buchinaidu kandriga, Thottambedu of Chittoor District and Pellakurmandal of Nellore district.

Salient Features

Cost of Construction : 1932.00 lakhsLocation : Srikalahasthi Town and Mandal in Chittoor dist.Latitude : 13° 45' 36''Longitude : 79° 47' 02''I.P.Created : 10,200 AcI.P.Utilized during 2014-15 : 10,000 AcKhariff : NillRabi : 8,647 Ac

Components of Project :Main canal side walls, bed lining ,system tanks restoration,CM & CD works in main canal,Restoration of Sluice &Surplus weir works for System of tanks.

Mandal Benefited : Thottambedu, B.N.Kandriga. PellWater utilization : 56.000 TMCCropping Pattern : Paddy, Ground nutPopulation Benefited : 8000

Page 17: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 17/31

2. Araniar Project

Preamble

The Araniar Project was constructed across Araniar river in the year 1958.The Project is feeding toan ayacut of 5500 acres in Kharif and 3600 acres in Rabi season .The ayacut is classified as (a) Direct ayacut of3400 acres (b) supplementation of 2100 acres under 10 system tanks.Thisayacut is spreading in Pichatur andNagalapuram mandals of Sathyavedu constituency. The capacity of the reservoir is 1853 Mcft.

Salient Features

The capacity of the reservoir is 1853 Mcft at F.R.L of 281 feet.The total length of tank bund is 3.60KM .The reservoir has three head sluices with different sill levels for delivering the discharge to the ayacut. TheM.F.D of 30500 cusecs will be discharged through the newly constructed spill way with four vents of size 10.0

Page 18: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 18/31

m X 5.50 m and through a natural bye wash located on extreme left flank of the reservoir.This spill way isintended to discharge the flood water.All the Radial gates are operable both with power and generator.A dieselgenerator with 50 kva capacity is also installed. Sufficient lighting arrangements are made at the site of new spillway for operation during night time.

Cost of Construction : Rs.126.43 lakhsYear of Completion : 1958Location : Pichatur (V) & (M) in Chittoor distLatitude : 13° 35' 00''Longitude : 79° 25' 02''Ayacut : 5500Reservoir capacity : 1853 McftFRL : 281 feetThe total length of tank bund : 3.60 KMspill way with four vents of size : 10.0 MX 5.50 MM.F.D : 30500 cusecs.I.P. Created : 1st crop 5500 acres & 2nd crop 3600 acresI.P .Utilized during 2011-12Khariff : Khariff - 3200 AcresRabi : Rabi-1200 Acres

Components of Project : 1) Earthen bund, 2) Right side sluice 3) Middle sluice 4)Old regulator 5) Left side sluice 6)New spill way.

Mandal Benefited : 1) Pichatur 2) NagalapuramWater utilization : Irrigation purposeCropping Pattern : Paddy, Groundnut.

3. Krishnapuram Project

Page 19: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 19/31

Preamble

The Krishnapuram Project was Constructed across LAVA River near Krishnapuram Village inKarvetinagaram Mandal of Chittoor District in 1981 to provide Irrigation facilities to the ayacut to an extent of6125 Acres.

Two Irrigation Canals i.e., left main canal of 7.00 KM in length and right side canal of length 3.23KM were excavated and lined for providing irrigation facilities to the ayacut through the system tanks and alsothrough the channels in direct pertaining to the villages both in Karvetinagar & S.R. Puram mandals of ChittoorDistrict.

The total length of distributaries under left side and right side is 9.50 Kms and 6.90 Kmsrespectively, all the distributaries were lined except Chillamakulapalle distributary. Total length of field channelsunder Krishnapuram Reservoir Project: 65.50 KMs.Length executed to the end of 03/1990: 65.50 KMs. TotalAyacut Contemplated under Krishnapuram Project: 6125 Acres. There are 16 Nos of system tanks underKrishnapuram Project. Out of which 10 tanks were situated on right side and 6 tanks are situated on left side.The total ayacut served under tanks is 498 Acres Wet.

Modernisation Proposals

It is very much essential to Modernize entire canal system duly providing cc side walls with bedlining to the canals and carrying restoration works to the CM & CD Works under this project. Proposals(Estimates) costing about Rs. 275.00 Lakhs for modernization of project and canal system were submitted andworks of Worth Rs. 70 Lakhs are executed with estimate rates of 2006-07 SSR. As funds are not releasedregularly, the works have been stopped midway in incomplete state.

At Present an ayacut of 1500 Acres is only irrigated by the waters of Krishnapuram Reservoir asagainst the 6125 Acres because the Canal distribution is in dilapidated state. By reinstating the canal anddistributory system including system tanks.

The intended ayacut under the Krishnapuram Reservoir will be improved.The weakersection,SC&ST Ayacutdars/ Farmers of the villages K.P.Agraharam, Thungamitta Eguva and Diguva

Page 20: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 20/31

Kunchevari palli, Lakshmipuram, Sekuvaripalli, Eguva and DiguvaMudikuppam, Chokkamadugu ,Battuvaripalliand Katherapalli have irrigated land and Irrigation potential can be improved if the grants released with externalfunding bodies like JICA or ABIP. This proposal may cost upto 36 Crores with SSR 2014-15 rates.

Salient Features

Cost of Construction : Rs.437 lakhsYear of Completion : 1982

Location : Andhra Pradesh, Chittoor District, Krishnapuram Village,Karvetinagaram

Latitude : 13° 22' 16''Longitude : 79° 21' 22''Average Rain fall : 100.50 CM ( 1005 MM)Gross Storage : 0.203 TMCFRL : 213MDead Storage : 0.0166 TMCMDDL : 203.6 MM.F.D : 30500 cusecs.Ayacut : 6125 AcresKhariff : NilRabi : NilComponents of Project : Earth Dam, Spillway, canalsMandal Benefited : Karvetinagaram, S.R.PuramWater utilization : 200 McftCropping Pattern : Paddy, Groundnut,Sugarcane.Population Benefited : 4500I.P.Contemplated : 6125 AcresI.P.Created : 1500 AcresBottlenecks : Getting water for one filling onlyPresent Stage : Completed

COMPLETED MINOR IRRIGATION PROJECTS

1. Kalangi Reservoir

Page 21: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 21/31

Preamble

Kalangi Reservoir is constructed a/c Kalangi River located one and half KM South of Adaram (v) inK.V.B.Puram Mandal. The Global Coordinates of the Project one Longitude 79° - 48' and Latitude 13° �� 36'and is accessible by road from Srikalahasti. The reservoir is formed abutting the existing hill range on right sideand joining the Ponnagunta and Panacheruvu tank bunds of Kandluru (v) on left side.

Salient Features

Location : : Kalangi Reservoir is Constructed across Kalangi Rivernear Kalangi Village in K.V.B.PuramMandal

Longitude : 79° 48' 00''Latitude : 13° 36' 00''

:

This Reservoir is having a left channel of 7.10 KMS inlength and Right Channel of 12.20 KMS in length to feedan ayacut of 4650 Acres in 3 Mandals namelyK.V.B.Puram, Thottambedu and B.N.Kandriga.

Ayacut : 4650 AcresMandals Benifited : K.V.B.Puram, Thottambedu, B.N.KandrigaEstimated Cost : Rs. 32.80 LakhsCatchment Area : 194 Sq.Kms( or) 75 Sq.MilesDependable Net Yield : 7388 Mcft.Utilisation : 4763 Mcft.Canal LengthRight Canal : 12.20 KmsLeft Canal : 7.10 KmsFeeding : IrrigationCropping Pattern : paddy, Sugarcane, Groundnut.Designed Flood Discharge : 4900 CubicsVillages Benefitted : R/S- Kalluru, Kalangi, Hanumaiahkandriga, Bonupalle,

Thummalagunta.

Page 22: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 22/31

L/S:- Katuru, Venugopalapuram,Vedalasreenivasapuram,Vijayagopalapuram, Racheruvu,B.N.Kandriga, Peddapalavedu, Chinnapalavedu,Karavanambedu, Neerupakakota, Kampalem,Guttapelluru.

2. Bahuda Reservoir Project

Preamble

Bahuda reservoir project is constructed across river Bahuda. The catchment area upto dam site is435.46Sq miles.The Bahuda reservoir poject is 1Km west of Mustoor (V) and 5 Km from Thamballapalle (M) ofChittoor dist.

The project was originally takenup for construction in 1946 with an estimated cost of Rs 27.59 lakhsto benefit an ayacut of 1166 Ha.The project was completed during 1974 at a cost of Rs 63.32 Lakhs. The livecapacity of reservoir is 398 Mcft.The water conveyance system comprises of two head sluices for teo maincanals, 01 branch canal to left main canal, 03 main anicuts and 06 pickup anicuts across the river and 29 springchannels taking of from the river course 09 tanks are fed through supply channels taking of from this anicut.

Salient Features

Location :

This project was constructed across Bahuda river aTributary of Chayyeru near Valasapalle(v) inNimmanapalle (M) of Chittoor district This project ishaving 7.60 KM of L/s canal and 1.00 KM R/s canal tofeed seies of pick up anicuts for feeding chain of tanks andspring channel for an ayacut of 2884 Acres.

Longitude : 78° 38'05''Latitude : 13° 32' 10''Ayacut : 2884 Acres

Page 23: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 23/31

Mandals Benifited : Nimmanapalle and ValmikipuramEstimated Cost : Rs. 70.83Lakhs.Catchment Area : 168.00 Sq milesDependable Net Yield : 398 Mcft.Utilisation : 378 Mcft.Canal Length : 7.60 Km on left side, 1.00 on right side

Feeding : 13 Nos of tanks, 9 Nos of anicuts, 20 Nos of Supplychannels and direct ayacut under 10 villages

Cropping Pattern : PaddyDesigned Flood Discharge : 30000 Cusecs (or) 863.67 Cumecs.

Villages Benefitted :(1)Mushtur (2) Nimanapalli (3) Agraharam (4)Mugalamarri (5) Manchenu (6) Sakirellapalli (7)Medikonthy 8)Tateguntapalli (9) Sakirellapalli

3. Siddalagandi Project

Page 24: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 24/31

Preamble

The siddalagandi Project is a Medium Irrigation Tank constructed long back across talakona Erunear Kotakadapalli in Y V Palem (M) in Chittoor District. The tank was Situated towards East of Kotakada palli(V) and 7.00Km towards Narth of Bodevandlapalli in Y V Palem (M) of Chittoor district.

Salient Features

Location :This Project was constructed across TalakonaEru Which istributary to Gajuleru. The site is located at about 7 KmNorth of Bodevandlapalle (V) in Yerravaripalem (M)

Longitude : 13° 50' 0''Latitude : 79° 08' 56''

The project envisages providing Irrigation facilities to anextent of 224 Acres.

Ayacut : 224 AcresMandals Benifited : Y.V PalemEstimated Cost : Rs. 5.875 Lakhs.Dependable Net Yield : 35.52 Mcft.Utilisation : 70.64 Mcft.Canal Length : 3.40 KmsFeeding : Feeding an ayacut of 224 Acres under Project onlyCropping Pattern : PaddyDesigned Flood Discharge : 2352 Cusecs (or) 66.60 Cumecs.Villages Benefitted : 1) Kondakadapalli

4. Pedderu Reservoir Project

Page 25: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 25/31

Preamble

Pedderu Reservoir is constructed across river pedderu,a tributary to river Papagni in Pennarbasin.Most of the beneficiaries under the project are tribal families. Under stage I,Pedderu reservoir had beenconstructed to irrigate 4300 acres in Rabi season only.

Salient Features

Location :This Project was constructed across Pedderu River, atributary to river Papagni near Kottala (V) inThamballapalli (M) of Chittoor District

Longitude : 78° 22' 11''Latitude : 13° 52' 38''

This Project is having a left canal of 17.49 KM to Irrigatenew ayacut of 2416 acres and stabilization of 84 Acres,total put together 2500 M. This project is also having right

Page 26: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 26/31

side canal of 17.67 Km with new ayacut of 1483 acres andstabilization of 401 acres and the ayacut total put togetherunder right side channel is 1800 acres.

Ayacut : 4300 AcresMandals Benifited : Thamballapalle and PeddamandyamEstimated Cost : Rs. 792.00 Lakhs.Catchment Area : 548.74 Sq milesDependable Net Yield : 792.70 Mcft.Utilisation : 529.11 Mcft.Canal Length : 17.49Km on left side and 17.67Km on right side

Feeding : 9 System tanks on Right Side channel and 6 system tanksunder Left side channel

Cropping Pattern : PaddyDesigned Flood Discharge : 112000 Cusecs (or) 8411 Cumecs.

Villages Benefitted :

1) Danduvaripalli (2) Jingurupenta (3) Kottala (4)Yeddulavarikota(5)Gollapalli (6)Mandalavaripalli(7)R.N.Tanda (8)ShukenaikTanda (9)Mange NaikTanda(10) AvikeNayakTanda (11) Eluguvaripalli (12)JerripataDinne (13) Diguvapalli (14) Boyapalli (15)Gollapalli (16) Bandroru (17) Kothapalli (18)Chedureandlapalli (19) Kothareddivaripalli (20)Beruvhipalli (21) Irrullapalli (22) DeninanTanda.

5. NTR Jalasayam

Preamble

NTR Jalasayam (Kalvakunta Barriage) is located about 10km North to Chittoor town. The schemeis intended for utilizing a yield of 180 Mcft of water for drinking purpose to Chittoor town. The work wascommenced during January 2002 and completed by March 2005.Capacity of the reservoir 109.17 Mcft.

Salient Features

Page 27: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 27/31

Location : This Project was constructed across Ponnai River and nearKalavagunta (V) Penumur(M) of Chittoor District

Longitude : 79° 08' 04''Latitude : 13° 17' 04''

The scheme is intended for utilizing an yield of 180Mcftof water for Drinking purpose to Chittoor Town.

Estimated Cost : Rs. 66.536 CroresCatchment Area : 1389.56SqkmsDependable Net Yield : 307 McftUtilisation : 180.00 Mcft.Date Of Completion : March/2005.

6.Sadasivakona Reservoir

Preamble

The Sadasivakona Reservoir was formed across Sadadivakona vagu near Chellur (V) in Yerpedu(M) of Chittoor district.The reservoir is situated about 4Km towards South-East of Chellur (V) which is at adistance of 30Km from Tirupathi town.

Page 28: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 28/31

The catchment area of the reservoir id 16.00Sq.miles and the total yield available is 312.43Mcft.The maximum flood discharge is 6350 Cusecs.Capacity of the reservoir is 152.38 MCft.

Salient Features

Location : This Project was constructed across Sadasivakonavagunear Chellur (V) in yerpedu (M) of Chittoor District .

Longitude : 79° 36' 56''Latitude : 13° 55' 34''

The reservoir was intended to stabilize the wet ayacut of793.00 acres under 07 system tanks, 206.00 acres underKonakalva and also for feeding direct wet ayacut of1126.00 acres in YerpeduMandal of Srikalahasthi town.

Ayacut : 1506 AcresCapacity Of Reservoir : 152.38 McftYield Available : 312.43 McftEstimated Cost : Rs.484.00 Lakhs.Catchment Area : 16Sq milesBenifited Mandal : YerpeduDesigned flood Discharge : 6350 Cusecs.Date Of Completion : 1979

7.Kalyani Dam

Preamble

The Kalyani Dam was constructed across the River Kalyani near Rangampeta village in Chandragirimandal. A main source of water supply for Tirupati and Tirumala, this dam is located around 23 kilometres fromTirupati.

The scheme is intended for supplying water to Tirupathimunicipality and TTD of Chittoor District.

The maintenance cost of both Irrigation and Public Health portion are to be borne by the T.T.D andtirupatiMuncipality in 1:2 ratio.Ever since completion, the project is being maintained by the Irrigation

Page 29: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 29/31

Department with the financial assistance from both the organizations.

Salient Features

Location : This Project was constructed across kalyani river nearRangampeta (V) in Chandragiri (M) of Chittoor District.

Longitude : 79° 16' 20''Latitude : 13° 39' 15''Estimated Cost : Rs. 555.00LakhsCatchment Area : 9.73 SqKmsMaximum Yield : 2387 Mcft.Average yield : 796 M.Cft.Max. flood discharge : 21,200 cusecsFull reservoir elevation : RL+900.00Emergency M.W.L : RL+898.15T.B.L. : RL+904.00Gross storage capacity of ReservoirFRL +900.00 : 910.00 M.Cft

Live storage or reservoir Abovelowest Inlet pipe Level RL+834.00 : 876.00 M.Cft

Submersible forest land area : 625.00 AcresPeriod of construction : 1972-1977

Water User Associations (WUAs)SNo Name of the Project Number of WUAs1 Medium Irrigation 172 Minor Irrigation 568Total 585

MINOR IRRIGATION TANKS

Abstract of Minor Irrigation Tanks under Control of Irrigation Circle, Chittoor District, A.P. (Mandal wise)

S.No. Name of theMandal

Ayacut Less than 40Hect./100 Acres

Ayacut more than 40Hect./100 Acres Total

No.ofTanks

Ayacut inAcres.

No.ofTanks

Ayacut inAcres.

No.ofTanks

Ayacut inAcres.

1 Chandragiri 2 63.92 11 3196.95 13 3260.872 Chinna Gottigallu 195 3541.44 3 651.46 198 4192.903 Pakala 102 1962.91 10 2426.71 112 4389.624 Ramachandrapuram 5 91.72 11 3883.9 16 3975.625 Tirupathi (Rural) 19 778.39 5 799.47 24 1577.866 Yerravariipalem 247 3218.36 6 1739.75 253 4958.117 Chittoor 76 2008.58 9 1719.63 85 3728.218 Gudipala 81 2581.85 6 1165.4 87 3747.25

Page 30: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 30/31

9 G.D.Nellore 102 2321.73 10 1527.48 112 3849.2110 Karvetinagar 51 1379.83 6 1398.27 57 2778.1011 Palasamudram 16 439.91 7 1432.16 23 1872.0712 Penumur 89 2014.26 4 739.79 93 2754.0513 S.R.Puram 39 1128.63 5 1614.05 44 2742.6814 Vedurukuppam 95 894.21 4 645.21 99 1539.4215 Gudupalle 174 1739.81 2 406.73 176 2146.5416 Kuppam 114 1122.40 10 1834.01 124 2956.4117 Ramakuppam 106 1605.80 7 1020.28 113 2626.0818 Santhipuram 106 2933.37 4 631.03 110 3564.4019 Madanapalle 201 3484.18 5 893.14 206 4377.3220 Nimmanapalle 126 2159.28 4 3537.43 130 5696.7121 Ramsamudram 168 3344.30 8 1397.2 176 4741.5022 Nagari 17 596.55 10 1586.68 27 2183.2323 Nindra 13 283.92 14 2644.72 27 2928.6424 Puttur 17 658.03 7 1835.81 24 2493.8425 Vadamalapeta 10 319.92 10 1889.07 20 2208.9926 Vijayapuram 11 303.12 11 1971.76 22 2274.8827 Baireddipalle 162 2387.08 2 544.88 164 2931.9628 Gangavaram 172 3169.11 4 772.07 176 3941.1829 Palamaner 100 1774.52 4 554.09 104 2328.6130 Peddapanjani 271 4791.00 7 1982.53 278 6773.5331 V.Kota 180 3031.76 3 363.39 183 3395.1532 Gurramkonda 167 3008.59 6 1919.91 173 4928.5033 K.V.Palle 263 2848.91 2 296.52 265 3145.4334 Kalakada 176 2361.58 8 4740 184 7101.5835 Kalikiri 194 6569.33 4 3107.76 198 9677.0936 Piler 261 1169.34 5 657.5 266 1826.8437 Valmikipuram 143 5514.51 9 2579.7 152 8094.2138 Chowdepalle 294 3596.61 13 2042.38 307 5638.9939 Pulicherla 187 2910.47 5 569.37 192 3479.8440 Punganur 192 4228.28 14 2450.61 206 6678.8941 Rompicherla 173 2091.68 6 1653.27 179 3744.9542 Sadum 288 3412.85 9 2375.32 297 5788.1743 Somala 238 2722.42 14 3295.68 252 6018.1044 Bangarupalem 91 2019.03 7 3638.63 98 5657.6645 Irala 129 3232.22 14 2358.19 143 5590.4146 Puthalapattu 89 1950.88 10 1602.23 99 3553.1147 Thavanamapalle 51 1372.91 6 1275.71 57 2648.6248 Yadamari 54 1597.60 3 1533.61 57 3131.2149 B.N.Kandriga 51 1587.12 18 4911.5 69 6498.62

Page 31: 10/31/2018 District Irrigation Profilesapcada.in/APIIATP/Apiiatp_Ref_Files/Documents/CHITTOOR...Irrigation Sources (less than 100 acres) with an ayacut of 1,36,618Acres. S.No Name

10/31/2018 District Irrigation Profiles

http://irrigationap.cgg.gov.in/wrd/getDistricts 31/31

50 K.V.B.Puram 54 1319.98 34 6434.52 88 7754.5051 Nagalapuram 8 401.32 12 3570.09 20 3971.4152 Narayanavanam 14 392.62 7 1196.51 21 1589.1353 Pitchatur 14 357.08 9 2350.21 23 2707.2954 Sathyavedu 88 2745.85 22 4903.15 110 7649.0055 Varadaiahpalem 44 1450.92 32 9342.18 76 10793.1056 Renigunta 26 944.91 12 2460.09 38 3405.0057 Srikalahsti 52 3064.34 63 16130.38 115 19194.7258 Thottambedu 51 1758.96 30 6956.43 81 8715.3959 Yerpedu 55 2175.15 40 10515.66 95 12690.8160 B.Kothakota 169 2952.15 4 1020.05 173 3972.2061 Kurabalakota 177 2218.59 4 616.18 181 2834.7762 Molakalacheruvu 118 2231.58 8 1236.87 126 3468.4563 P.T.M 106 2419.31 7 4531.41 113 6950.7264 Peddamandyam 175 2193.75 7 875.2 182 3068.9565 Thamballapalle 136 1658.81 13 8996.48 149 10655.2966 Tirupati (Urban) 0 0.00 2 269.74 2 269.74

Total Of ChittoorDistrict 7395 136609.53 668 169218.09 8063 305827.62