Air Quality PermittingAir Quality Permitting
Air Quality CommitteeWilliam D. Willets, P.E.Engineering SupervisorDAQ Permitting SectionMay 7, 2014
![Page 2: 10/1/2015 1 Air Quality Permitting Air Quality Committee William D. Willets, P.E. Engineering Supervisor DAQ Permitting Section May 7, 2014](https://reader035.vdocuments.site/reader035/viewer/2022070409/56649e725503460f94b71be7/html5/thumbnails/2.jpg)
2
Do I need a permit?Do I need a permit?
Yes– By statute, codified under …– Title 15A NCAC Subchapter 2Q .0101
(a) No owner or operator shall do any of the following activities … without first applying for and obtaining an air quality permit …
Unless you don’t– Exemptions under 15A NCAC 2Q .0102
Currently undergoing revision for clarification and simplification
![Page 3: 10/1/2015 1 Air Quality Permitting Air Quality Committee William D. Willets, P.E. Engineering Supervisor DAQ Permitting Section May 7, 2014](https://reader035.vdocuments.site/reader035/viewer/2022070409/56649e725503460f94b71be7/html5/thumbnails/3.jpg)
3
What kinds of permits are there in NC?What kinds of permits are there in NC? Construction Permits
– State pre-construction– PSD/NSR permits
Operating Permits– State permits– Title V permits
Developed under the federal 1990 CAAA to consolidate all applicable requirements into a single compliance tool
Construction/Operating Permits– “Traditional” combination of the above
Air toxics permits– Not exclusive of other permitting programs
![Page 4: 10/1/2015 1 Air Quality Permitting Air Quality Committee William D. Willets, P.E. Engineering Supervisor DAQ Permitting Section May 7, 2014](https://reader035.vdocuments.site/reader035/viewer/2022070409/56649e725503460f94b71be7/html5/thumbnails/4.jpg)
4
What’s in a permit?What’s in a permit?
Applicable requirements– State enforceable, federally enforceable, both– Construction and operation
Means to demonstrate compliance with applicable requirements– Monitoring, recordkeeping, and reporting
requirementsGeneral conditions
![Page 5: 10/1/2015 1 Air Quality Permitting Air Quality Committee William D. Willets, P.E. Engineering Supervisor DAQ Permitting Section May 7, 2014](https://reader035.vdocuments.site/reader035/viewer/2022070409/56649e725503460f94b71be7/html5/thumbnails/5.jpg)
5
What can I do without a permit?What can I do without a permit?
2Q .0102 activitiesBasic earth work (clearing and grubbing)NC construction bill
– Notification– Public notice– Fee
![Page 6: 10/1/2015 1 Air Quality Permitting Air Quality Committee William D. Willets, P.E. Engineering Supervisor DAQ Permitting Section May 7, 2014](https://reader035.vdocuments.site/reader035/viewer/2022070409/56649e725503460f94b71be7/html5/thumbnails/6.jpg)
6
How do I get a permit?How do I get a permit?
Procedures in 15A NCAC 2Q .0300 and .0500– Subchapters designate permitting procedures based on
State or Title V processes– PSD/NSR procedures also in 2D .0530/.0531
Permit application submittal Completeness review Engineer review
– May include requests for additional information Public/EPA participation Final agency action
– Issue or deny permit
![Page 7: 10/1/2015 1 Air Quality Permitting Air Quality Committee William D. Willets, P.E. Engineering Supervisor DAQ Permitting Section May 7, 2014](https://reader035.vdocuments.site/reader035/viewer/2022070409/56649e725503460f94b71be7/html5/thumbnails/7.jpg)
7
How do I know what kind of permit to get?How do I know what kind of permit to get?
Construction and operation permit(s)Operating permitType of facilityPotential to emit regulated air pollutants
![Page 8: 10/1/2015 1 Air Quality Permitting Air Quality Committee William D. Willets, P.E. Engineering Supervisor DAQ Permitting Section May 7, 2014](https://reader035.vdocuments.site/reader035/viewer/2022070409/56649e725503460f94b71be7/html5/thumbnails/8.jpg)
8
Potential to EmitPotential to Emit
Maximum capacity Physical and operational design Physical or operational limitation Air pollution control equipment Restrictions Definable by the permit
![Page 9: 10/1/2015 1 Air Quality Permitting Air Quality Committee William D. Willets, P.E. Engineering Supervisor DAQ Permitting Section May 7, 2014](https://reader035.vdocuments.site/reader035/viewer/2022070409/56649e725503460f94b71be7/html5/thumbnails/9.jpg)
9
Major Source ThresholdsMajor Source Thresholds
PSD
– 250 tpy or 100 tpy
– Depends on source type
– Lower thresholds for modifications NAA
– 100 tpy Title V
– 100 tpy
– 10/25 tpy
![Page 10: 10/1/2015 1 Air Quality Permitting Air Quality Committee William D. Willets, P.E. Engineering Supervisor DAQ Permitting Section May 7, 2014](https://reader035.vdocuments.site/reader035/viewer/2022070409/56649e725503460f94b71be7/html5/thumbnails/10.jpg)
10
Small FacilitiesSmall Facilities
Unrestricted PTE below all major source thresholds
State (2Q .0300) construction and operation permit
Administered by Regional Office
![Page 11: 10/1/2015 1 Air Quality Permitting Air Quality Committee William D. Willets, P.E. Engineering Supervisor DAQ Permitting Section May 7, 2014](https://reader035.vdocuments.site/reader035/viewer/2022070409/56649e725503460f94b71be7/html5/thumbnails/11.jpg)
11
Synthetic Minor FacilitiesSynthetic Minor Facilities
Permit restrictions (including control devices) to maintain PTE below all major source thresholds
State (2Q .0300) construction and operation permit
Administered by Regional Office
![Page 12: 10/1/2015 1 Air Quality Permitting Air Quality Committee William D. Willets, P.E. Engineering Supervisor DAQ Permitting Section May 7, 2014](https://reader035.vdocuments.site/reader035/viewer/2022070409/56649e725503460f94b71be7/html5/thumbnails/12.jpg)
12
Non-PSD/NSR Major FacilitiesNon-PSD/NSR Major Facilities
Title V facilitiesPermitted PTE above one or more Title V
major source thresholdsState (2Q .0300) construction and
operation permitTitle V operation permit (2Q .0500) Administered by Central Office
![Page 13: 10/1/2015 1 Air Quality Permitting Air Quality Committee William D. Willets, P.E. Engineering Supervisor DAQ Permitting Section May 7, 2014](https://reader035.vdocuments.site/reader035/viewer/2022070409/56649e725503460f94b71be7/html5/thumbnails/13.jpg)
13
PSD/NSR Major FacilitiesPSD/NSR Major Facilities
Also Title V facilitiesPermitted PTE above one or more
PSD/NSR major source thresholdsPSD (2D .0530/.0531) construction permitState pre-construction permitTitle V operation permitAdministered by Central Office
![Page 14: 10/1/2015 1 Air Quality Permitting Air Quality Committee William D. Willets, P.E. Engineering Supervisor DAQ Permitting Section May 7, 2014](https://reader035.vdocuments.site/reader035/viewer/2022070409/56649e725503460f94b71be7/html5/thumbnails/14.jpg)
14
Permit ModificationsPermit Modifications
Depends on type of permit and scope of modification
Non-Title V modifications administered by Regional Office
Title V and PSD/NSR modifications administered by Central Office
![Page 15: 10/1/2015 1 Air Quality Permitting Air Quality Committee William D. Willets, P.E. Engineering Supervisor DAQ Permitting Section May 7, 2014](https://reader035.vdocuments.site/reader035/viewer/2022070409/56649e725503460f94b71be7/html5/thumbnails/15.jpg)
15
Air Toxics PermitsAir Toxics PermitsCoupled with other permitting programsProcedures under 2Q .0700Air toxics rules have recently been revised
(effective May 1, 2014) in accordance with State statute
![Page 16: 10/1/2015 1 Air Quality Permitting Air Quality Committee William D. Willets, P.E. Engineering Supervisor DAQ Permitting Section May 7, 2014](https://reader035.vdocuments.site/reader035/viewer/2022070409/56649e725503460f94b71be7/html5/thumbnails/16.jpg)
16
Permitting Section Emerging Permitting Section Emerging IssuesIssuesRevisions to 02Q .0102 permitting
exemptionsRecent revisions to Toxic Air Pollutant
regulationsOngoing incorporation of MACTs/GACTs
into permits
![Page 17: 10/1/2015 1 Air Quality Permitting Air Quality Committee William D. Willets, P.E. Engineering Supervisor DAQ Permitting Section May 7, 2014](https://reader035.vdocuments.site/reader035/viewer/2022070409/56649e725503460f94b71be7/html5/thumbnails/17.jpg)
17
Questions?Questions?