1 task 19 sis100_3: semiconductor rf gap switch 15.04.2005 p. hülsmann problem description beam...
TRANSCRIPT
1
Task 19 SIS100_3: Semiconductor RF Gap Switch
15.04.2005 P. Hülsmann
Problem DescriptionBeam dynamics simulations have shown that the impedance
of the non-operating cavities may degrade the quality of the circulating beam at high current operation significantly.
Solution Equip the gaps of the non operating cavities with fast high
power switches, generating a short circuit with low intrinsic impedance.
Technical Description
2
Task 19 SIS100_3: Semiconductor RF Gap Switch
15.04.2005 P. Hülsmann
Requirements on the gap switch
Switch is open
Frequency
1 MHz
Voltage
25 kV
Duty Cycle
0,0005
Capacity
<100 pF
Switch is Closed
Current
60 A
Average Power
500 W
Duty cycle
3%
Resistance
< 10
3
Task 19 SIS100_3: Semiconductor RF Gap Switch
15.04.2005 P. Hülsmann
First Tests with MosFet Gap Switch(Behlke HTS 301-12-AC-B + Cooling
Fins,Category VII) Breakdown at 12 kV RF-amplitude (1 MHz)
after 3 minutes (open) Due to dielectric losses, the isolation material
at the high voltage output has started to boil. The isolation was damaged, but not the semiconductors.
Average of 50 W reached (closed) A resistive resistance of 10 reached RF-characteristics of the switch ok
Next Step Isolation of the switch with oil
Status of R&D
4
Task 19 SIS100_3: Semiconductor RF Gap Switch
15.04.2005 P. Hülsmann
Work Sharing GSI
Specification for manufacturing the switch Low-level testsPrototype cavity tests (0.8...5.4 MHz)
CERN Prototype cavity tests (2.8...10 MHz) Design of passive network for impedance reduction Shielding experiments for improvement of radiation
hardness Tentative schedule for 2005 available
Organizational Issues
5
Task 19 SIS100_3: Semiconductor RF Gap Switch
15.04.2005 P. Hülsmann
Schedule (Description of Work)
Personnel not yet available → 5...6 months shifted
6
Task 19 SIS100_3: Semiconductor RF Gap Switch
15.04.2005 P. Hülsmann
CostsTask 19: SIS100_3 (Fast Gap Switches)
2005 2006 2007 TotalScientists 0,4 0,3 0,3 1
33.600,00 € 25.200,00 € 25.200,00 € 84.000,00 €Technicians 0,3 0,3 0,3 0,9
25.200,00 € 25.200,00 € 25.200,00 € 75.600,00 €Investment 11.000,00 € 12.000,00 € 12.400,00 € 35.400,00 €
2005 2006 2007 TotalScientists 0 0 0 0
0,00 € 0,00 € 0,00 € 0,00 €Engineers 0,35 0,35 0,3 1
40.000,00 € 40.000,00 € 35.000,00 € 115.000,00 €Investment 10.000,00 € 20.000,00 € 20.000,00 € 50.000,00 €
Total 119.800,00 € 122.400,00 € 117.800,00 € 360.000,00 €
In 2005, a part of the GSI investment costs will be transferred from Task 18 to Task 19
GSI
CERN