05/07/12 – 5/13/12 phase 1 demolition at west entry complete; drilled piers and footers started

4
05/07/12 – 5/13/12 Phase 1 Demolition at West Entry Complete; Drilled Piers and footers Started

Upload: zachery-heathcott

Post on 01-Apr-2015

219 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: 05/07/12 – 5/13/12 Phase 1 Demolition at West Entry Complete; Drilled Piers and footers Started

05/07/12 – 5/13/12

Phase 1 Demolition at West Entry Complete; Drilled Piers and footers Started

Page 2: 05/07/12 – 5/13/12 Phase 1 Demolition at West Entry Complete; Drilled Piers and footers Started

05/07/12 – 5/13/12

Demolition at 1927 wing nearing completion

Page 3: 05/07/12 – 5/13/12 Phase 1 Demolition at West Entry Complete; Drilled Piers and footers Started

05/07/12 – 5/13/12

Phase 1 Air Handler Units removed

Page 4: 05/07/12 – 5/13/12 Phase 1 Demolition at West Entry Complete; Drilled Piers and footers Started

•Field Measured Phase 3 Rotunda

•Completed Electrical Shutdown to relocate Main Electrical Panel

Exterior

•Complete drilled piers•Form and Pour Footings at South Side

Interior

•Continue with MEP in 1927 Wing•Prep for floor cut at main electrical room

•Wall off existing area at Spartan Grille to facilitate Taco Bell/C-Store Relocation

During the break…

NEXT WEEK LOOK AHEAD

Phase 3 Rotunda Field Measurement and Verification

05/07/12 – 5/13/12