zone 2 distance protection coordination with distribution feeder protection
DESCRIPTION
Zone 2 Distance Protection Coordination With Distribution Feeder ProtectionTRANSCRIPT
Fenghai Sui, Miroslav Kostic - Hydro One Network Inc., Canada
Zhiying Zhang - GE Digital Energy, Canada
Zone 2 Distance Protection Coordination
with Distribution Feeder Protection
Texas A&M Relay Conference 2015
Outline
IntroductionCurrent Practices and LimitationsThe Proposed SolutionSimulation TestingConclusions
Introduction
In recent years, renewable energy generators have been widely promoted in OntarioMost of them are connected to Hydro One transmission system at nearby HV transmission linesSuch connections can cause significant increase of the measured apparent impedance due to the infeed effect of the renewable energy sourcesZone 2 reach setting needs to be adjusted based on the maximum apparent impedance in order to cover the entire lineAs a result, LV feeder faults may cause HV transmission line zone 2 operate. Proper coordination is required.
IntroductionS
Equ.Gen.
Equ.Gen.
G11
G12
G21
G22
G24
RJ
CBS CBRCBJ
T
CBL
F1 F2 F24F11
F12 F21 F22 F23G23
Bus
CBF1 CBF2
IntroductionS
Equ.Gen.
Equ.Gen.
RJ
CBS CBRCBJ
Equ.Gen.
Zsj Zrj
Is IrIj
Us
Uj
𝒁𝒂𝒑𝒑=𝑼𝒔𝑰𝒔 =
𝑰𝒔∗ (𝒁𝒔𝒋 )+ ( 𝑰𝒔+𝑰𝒋 )∗𝒁𝒓𝒋𝑰𝒔 =(𝒁𝒔𝒋+𝒁𝒓𝒋 )+ 𝑰𝒋
𝑰𝒔 ∗𝒁𝒓𝒋=𝒁𝒔𝒓 + 𝑰𝒋𝑰𝒔 ∗𝒁𝒓𝒋
The apparent impedance consists of two parts: 1) Line impedance Zsr2) An additional part due to the tapped
generation
Introduction
C1
C2
This will cause some coordination issues
Apparent impedance measured at bus S can be much bigger than the line impedance Zsr due to infeed effectThe large apparent impedance will result in large zone 2 reach setting
Problem
The zone 2 element may operate on a fault beyond direct adjacent lines. This issue may be solved with additional time delay.The zone 2 element may pick up under heavy load condition. This issue may be solved with load encroachment feature embedded in IED.The zone 2 element may pick up faults on LV bus or LV feedersIn this paper, only this problem is discussed and
addressed
Current Practices
Building a new switching station
Current Practices
Splitting one large step-up transformer into two smaller transformers
Current Practices
Multi-terminal current differential protectionS
Equ.Gen.
Equ.Gen.
G11
G12
G21
G22
G24
RJ
CBS CBRCBJ
T
CBL
F1 F2 F24F11
F12 F21 F22 F23G23
Bus
CBF1 CBF2
87L
Proposed Solution
A method has been developed by using programmable logic within a modern digital relayIn this method, the timed zone 2 distance protection is automatically switched to a short delay or a long delay based on the operation sequence and timing conditionDistance zone 2 element will provide regular protection to the transmission line faults as usual, and also provide coordinated backup protection to the distribution feeder faults
Proposed Solution
No additional communication is required within this solutionCompared to current practices, it’s a cost saving solution. High capital investment can be avoided.The proposed solution has been verified with fault simulations on both HV transmission lines and LV feeders
Zone 2 Setting Review
Pilot Schemes
Pilot schemes are also employed in Hydro One grid, most commonly POTT and DCBIn order to avoid maloperation of the pilot scheme on the LV feeder fault, a blocking signal is required to be sent to the terminal station from the tapped station
SEqu.Gen.
Equ.Gen.
RJ
CBS CBRCBJ
T
CBL
F1 F2 F24F11 F12 F21 F22 F23
BusCBF1 CBF2
LV Feeder Protection and Auto-reclose
Main feeder protection
Sub-feeder or branch protectionSub-feeder or branch protection
SEqu.Gen.
Equ.Gen.
RJ
CBS CBRCBJ
T
CBL
F1 F2 F24F11 F12 F21 F22 F23
BusCBF1 CBF2
LV Feeder Protection and Auto-reclose
Zone 2 Operation Sequence
For a transient LV feeder fault, the zone 2 element picks up and drops down after the fault is cleared by LV feeder protectionFor a permanent feeder fault, the zone 2 element picks up and drops down for a certain period and then picks up again for a longer periodFor a fault on HV transmission line, the zone 2 element will continuously pick up before CB is open
Proposed Solution – LogicLogic below is designed for zone 2 distance protection to properly coordinate with feeder protection and avoid mis-operation for faults on LV feeders
Proposed Solution – Logic Implementation
Simulation – Transient Fault on LV Feeder
Z2
GA1-1
GA1-2
GA1-3
DT-2
T2-2
10 seconds
50ms 400ms
Falling edge
Fault is cleared by feeder protection, Z2 resetFeeder reclose successfully
Simulation – Permanent Fault on LV Feeder
Z2
GA1-1
GA1-2
GA1-3
DT-2
T2-2
50ms 400ms50ms 400ms
10 sec.
Fault is tripped by
feeder protection587ms
Breaker Dead Time
Reclose to a permanent faultT2-2 is high
Timed Z2 did not operate on LV permanent fault
Simulation – Permanent Fault on HV Feeder
Z2
GA1-1
GA1-2
GA1-3
DT-2
Other Protection Trip
50ms 400ms50ms 400ms
25ms
520ms
GA2-3
GO1-1 400ms
Never see a falling edgeDT-2 keeps low
Breaker Dead Time
Reclose to a permanent fault
Fault is intentionally held for 520ms though other protection has operated.
SummaryThe large zone 2 protection reach setting value may result in that the timed zone 2 protection operates on a permanent LV feeder fault
A solution has been proposed in this paper to deal with coordination issue between timed zone 2 protection of HV transmission line and LV feeder protection
It is a cost-saving method. High capital investment, such as building switching stations, is not required.
The requirement of this solution is that the protection relay must have flexible programming logic capability
Thank You
Questions?