Zian Zhu

• The Tension/Pitch Machine Status and Anode Panel Measurements

• The Strip Capacitance Meter Status and Measurements

Production Readiness Review at IHEP

August 2, 2001

Page 2: Zian Zhu The Tension/Pitch Machine Status and Anode Panel Measurements The Strip Capacitance Meter Status and Measurements Production Readiness Review

Wire Tension

and Pitch Machine

CSC Production at IHEP Beijing

Page 3: Zian Zhu The Tension/Pitch Machine Status and Anode Panel Measurements The Strip Capacitance Meter Status and Measurements Production Readiness Review

Tension/Pitch Machine Setup

CSC Production at IHEP Beijing

• Preparation:• Buy Video Monitor, Survey Tools: Flatness Ruler Gradienter, ..

• Transportation:• 2001.3.29 Machine arrived, Using Rail Moving Method.

• Install: • Stand up the frame, Repair injured cable of the stand up motor.

• Mounting sensor head.

• 2001.4.24 Power on, Basic function check ok.

Page 4: Zian Zhu The Tension/Pitch Machine Status and Anode Panel Measurements The Strip Capacitance Meter Status and Measurements Production Readiness Review

• Alignment:• Mounting the anode panel hold bar with newly machined screws, Adjust position ac

cording to the size of ME1/2 prototype panel.

• 2001.5.31 Start tuning the machine with the ME1/2 panel.

• Error happened: Some 0 tension: found 1 cable connection problem; 3~4 thin wires, their tension are 0, they are closed to the thick wires: adjust the camera position, re-align the camera with sensors, modify the parameters in the DEFAULTS file.

• 2001.6.21 Measurement is ok. Take ~1.5 hours for one single side.

• Problem: Transformer Wetted Accidentally• 2001.5.17, there are 220V on the machine frame: solved with drying.

Tension/Pitch Machine Setup

CSC Production at IHEP Beijing

Page 5: Zian Zhu The Tension/Pitch Machine Status and Anode Panel Measurements The Strip Capacitance Meter Status and Measurements Production Readiness Review

Tension Measurement

Results(within the range)

12A008-N(Thick wire excluded)

CSC Production at IHEP Beijing

Page 6: Zian Zhu The Tension/Pitch Machine Status and Anode Panel Measurements The Strip Capacitance Meter Status and Measurements Production Readiness Review

Tension Measurement

Results12A008-N (Thick wire)

CSC Production at IHEP Beijing

Page 7: Zian Zhu The Tension/Pitch Machine Status and Anode Panel Measurements The Strip Capacitance Meter Status and Measurements Production Readiness Review

Tension Measurement

Results12A008-N

(Wire tension all)

CSC Production at IHEP Beijing

Page 8: Zian Zhu The Tension/Pitch Machine Status and Anode Panel Measurements The Strip Capacitance Meter Status and Measurements Production Readiness Review

Tension Measurement

Results12A008-N

CSC Production at IHEP Beijing

Page 9: Zian Zhu The Tension/Pitch Machine Status and Anode Panel Measurements The Strip Capacitance Meter Status and Measurements Production Readiness Review

Pitch Measurement

Results12A008-N

(Thick wire excluded)

CSC Production at IHEP Beijing

Page 10: Zian Zhu The Tension/Pitch Machine Status and Anode Panel Measurements The Strip Capacitance Meter Status and Measurements Production Readiness Review

Pitch Measurement

Results12A008-N

(Thick wire included)

CSC Production at IHEP Beijing

Page 11: Zian Zhu The Tension/Pitch Machine Status and Anode Panel Measurements The Strip Capacitance Meter Status and Measurements Production Readiness Review

Pitch Measurement

Results12A008-N

(All wires pitch)

CSC Production at IHEP Beijing

Page 12: Zian Zhu The Tension/Pitch Machine Status and Anode Panel Measurements The Strip Capacitance Meter Status and Measurements Production Readiness Review

Strip Capacitance

Measurement Set up

CSC Production at IHEP Beijing

Page 13: Zian Zhu The Tension/Pitch Machine Status and Anode Panel Measurements The Strip Capacitance Meter Status and Measurements Production Readiness Review

Capacitance Meter Setup

CSC Production at IHEP Beijing

• Preparation:• Buy a new PC, Cable making, PC board mounting, Software setup...

• Problem:• Power problem: Fuse burns on SCM-16 when connected SCM-16 with the new

PC, when with the 110V PC, no fuse burn. Finally built new lab. Ground, and connect the GND of 220V to the GND of 110V power, problem solved.

• Software problem 1: Run error, Invalid Board Number: Install CDAS8JR driver, this problem was solved, But

• Software problem 2: ADC result is always 0. Finally, we dig out that the problem comes from the Labview software package and solved the problem.

Page 14: Zian Zhu The Tension/Pitch Machine Status and Anode Panel Measurements The Strip Capacitance Meter Status and Measurements Production Readiness Review

Strip Capacitance

Results

CSC Production at IHEP Beijing

Stri p to STri p Capaci tance of ME1/ 3 Prototype

0102030405060708090

1001 6 11 16 21 26 31 36 41 46 51 56 61

Stri p Number

pF

Pl ane1Pl ane2Pl ane3Pl ane4Pl ane5Pl ane6

Stri p to STri p Capaci tance of ME1/ 2 Prototype

0102030405060708090

100

1 8 15 22 29 36 43 50 57 64 71 78

Stri p NumberpF

Pl ane1Pl ane2Pl ane3Pl ane4Pl ane5Pl ane6

Page 15: Zian Zhu The Tension/Pitch Machine Status and Anode Panel Measurements The Strip Capacitance Meter Status and Measurements Production Readiness Review

Conclusion

CSC Production at IHEP Beijing

We have : • Finished the Measurements for the two ME1/2 and ME1/3

prototypes.

• Wrote the Device Operation Manual in Chinese.

• Set up the network for the CMS Group.

We plan:• Modify the anode panel clamps in both ME1/2 and ME1/3 cases.

• Calibrate the tension measurement: Plan to use the device from MDC group; Make a new wiring device for thick wire(tensions were always too low,<450g).