wqr-09
TRANSCRIPT
-
8/2/2019 WQR-09
1/5
Report No:
VCS/ ONGC/ RMD/ WQR/ 09ReportDate:14.08.2009
Page 1 of 5
W eekl y Quali ty R epor t
Project : KG3-Ramnad Gas pipeline project, Ramnad
Client : M/s ONGC Ltd
T P I A : M/s Velosi Certification Services (I) Pvt. Ltd.
E PC : M/s Tolani Fabricators
Dates of Inspection : 07.08.09 to 13.08.09
Mandays for the period : 7 x 4 = 28 mandays
-
8/2/2019 WQR-09
2/5
Report No:
VCS/ ONGC/ RMD/ WQR/ 09ReportDate:14.08.2009
Page 2 of 5
A- Mechanical Work.
PERSONS PRESENT:-
For M/s Velosi Certification Services (I) Pvt Ltd.1. Mr. Madhusoodhanan Nair.G, (Surveyor).2. Mr. Sivaram Kumar.S, (Surveyor)3. Mr. Prabu.C, (Surveyor)4. Mr. Vijayarahavan.D, (Surveyor)
For M/s Tolani Fabricators.5. Mr. Arvind Singh, (Project Manager)
6. Mr.Parmar, (QC Manager)7. Mr. Sanam, (Site-in Charge)8. Mr.Subbarao (QC Engineer)9. Mr. Mohammed Abuhasim.M, (QC Engineer)
INSPECTION CARRIEDOUT:-
Stringing of pipes upto chainage 7540 metres (0 to 1675, 1825 to 4200, 4800 to7000, and 8000 to 9300) checked.
Weld visual check of 152 jointsdone and found acceptable.
Welder Mr.Sajil(welder no 14) tested for WPS-6. Radiography reviewed and foundacceptable. Hence, the welder gets qualified for WPS-6.
Radiographs of 223 jointsreviewed and 182 joints found acceptable. 24 joints tobe repaired.
Welders Pravin(welder no 2) and Vinod Kumar (welder no 12) disqualified due topoor performance.
Coating of 125 joints accepted.
STATUS OF WORK.10 MAIN LINE:
KM-00 Total 395 joints welding completed, visually accepted. Radiography of 367joints reviewed and 314 joints accepted. 39 joints to be repaired.
Coating of total 270 joints accepted.
LOWERING OF 10 MAI N LIN E:
Lowering of 722 metres from chainage 139 metres done. Level check and backfillingof first 406 metres done.
-
8/2/2019 WQR-09
3/5
Report No:
VCS/ ONGC/ RMD/ WQR/ 09ReportDate:14.08.2009
Page 3 of 5
WPS and respective qualified welders details given below :
WPS Welders name Welder number
B.Jacob (All Passes) 01Anil Kumar (All Passes) 04
Praveen.K.P (AllPasses)
02 disqualified
WPS -01 (Main LineJoint for thickness14.3 mm & 18.3 mm)
Vinod Kumar (AllPasses)
12 disqualified
K.Munuswamy (AllPasses)
05WPS -02 (Main LineJoint for thickness20.6 mm) Joseph Johny (All
Passes)06
B.Jacob (All Passes) 01WPS -03 (Tie-in jointfor thickness 14.3mm & 18.3 mm)
Praveen.K.P (AllPasses)
02
Vellaisamy(All Passes) 03WPS -04 (Tie-in jointfor thickness 20.6mm)
Anil Kumar(All Passes) 04
Joseph Johny 06WPS -06 ( Throughrepair procedure for14.3 & 18.3 mm) Anil Kumar 04
Babu 08Jayanandasen 09Ajay Biswas 10Antony 11
Filling and Cappingonly
Sajeev 13
Electrode qualification status
S.No Electrode Classification Manufacturer Qualified Batch No
1 AWS A-5.1 E 6010 (3.2 mm) Lincoln Electric S-19420836
2 AWS A-5.1 E 7010G (4 mm) Lincoln Electric S-18389947, S -19432513
-
8/2/2019 WQR-09
4/5
Report No:
VCS/ ONGC/ RMD/ WQR/ 09ReportDate:14.08.2009
Page 4 of 5
Document Approval status pertaining to Mechanical works:
First Submission Second SubmissionSr.No. Description Of Procedures Comment Date Comment Date
1 QAP Procedure Approved 23/7/2009
2 QA Plan Commented 18/5/2009 Approved 23/07/2009
3 HSE Procedure Approved 5/6/2009 Approved
4 Procurement Plan Approved 20/7/2009
5 Incoming Material Commented 13/5/2009 Approved 30/5/2009
6
Transportation and Storage of
Pipes, Materials and Equipments Commented 13/5/2009 Approved 25/6/20097 Pipe Hauling &Stringing Commented 13/5/2009 Approved 4/6/2009
8 Welding Procedure Specification Commented 5/5/2009 Approved 7/5/2009
9 Electrode Qualification Approved 7/5/2009 Approved
10 Welder's Qualification Commented 15/5/2009 Approved 2/7/2009
11 Mainline Welding Commented 7/5/2009 Approved 26/5/2009
12 Tie-in Welding Commented 5/5/2009 Approved 6/5/2009
13 Pipe Bending Commented 7/5/2009 Approved 4/6/2009
14 Weld Joint numbering Commented 7/5/2009 Approved 4/6/2009
15 NDT-Radiography(X-Ray) Commented 14/5/2009 Approved 21/6/2009
16 NDT-Radiography(Gamma-Ray) Commented 23/6/2009
17 Ultrasonic Testing Commented 5/4/2009 Approved 12/7/200918 NDT-Liquid Penetrant Test Commented 17/04/2009 Approved 5/4/2009
19 Repair of Accidental Arc Burn Commented 12/5/2009 Approved 3/6/2009
20 Weld Joint Repair Commented 5/4/2009 Approved 4/6/2009
21 Field Joint Coating & Repair Commented 7/5/2009 Approved 26/5/2009
22 Pipe Book Approved 23/6/2009 Approved
23 Lowering Commented 14/5/2009 Approved 17/7/2009
24 Pre- Hydro Testing Commented 14/5/2009 Approved 30/5/2009
25 Hydrotesting Commented 17/5/2009
26 Swabbing Commented 17/5/2009 Approved 6/6/2009
27 Document Control Approved 23/6/2009 Approved
28 Painting Of Structure And Piping Commented 12/5/200929 Insulation Joint - ITP Commented 12/08/2009
30Piping fabrication welding andInstallation Not Submitted
31WPS For Piping Not Submitted
32Procedure for Commissioning
Not Submitted
-
8/2/2019 WQR-09
5/5
Report No:
VCS/ ONGC/ RMD/ WQR/ 09ReportDate:14.08.2009
Page 5 of 5
B- Civil Work.
PERSONS PRESENT:-
1. Mr. Madhusoodhanan Nair.G, (Surveyor), Velosi Certification Services (I) Pvt, Ltd.
2. Mr. Radhakrishnan, Tolani Fabricators.
3. Mr. Patel, Tolani Fabricators.
4. Mr. Sanam, Tolani Fabricators.
INSPECTION CARRIEDOUT:-
RoU, Clearing and Grading upto 10900 metres total (0 to 1675 & 1825 to 11050)checked.
Trenching done for 1315 meteres total from chainage 139 m.
Document Approval Status pertaining to Civil works :
First Submission Second SubmissionSr.No. Description Of Procedures Status Date Status Date
1 ROU Cleaning and Grading Commented 13/5/2009 Approved 4/6/2009
2 Trenching Commented 12/5/2009 Approved 13/7/2009
3 Cased Crossing Commented 14/5/2009 Approved 5/6/2009
4 Back-filling Commented 12/5/2009 Approved 13/7/2009
5 Restoration of ROW Commented 12/5/2009 Approved 21/6/2009
6
Pipeline Marker fabrication and
Installation Not Submitted