    Report No:

    VCS/ ONGC/ RMD/ WQR/ 09ReportDate:14.08.2009

    Page 1 of 5

    W eekl y Quali ty R epor t

    Project : KG3-Ramnad Gas pipeline project, Ramnad

    Client : M/s ONGC Ltd

    T P I A : M/s Velosi Certification Services (I) Pvt. Ltd.

    E PC : M/s Tolani Fabricators

    Dates of Inspection : 07.08.09 to 13.08.09

    Mandays for the period : 7 x 4 = 28 mandays

  • 8/2/2019 WQR-09

    2/5

    Report No:

    VCS/ ONGC/ RMD/ WQR/ 09ReportDate:14.08.2009

    Page 2 of 5

    A- Mechanical Work.

    PERSONS PRESENT:-

    For M/s Velosi Certification Services (I) Pvt Ltd.1. Mr. Madhusoodhanan Nair.G, (Surveyor).2. Mr. Sivaram Kumar.S, (Surveyor)3. Mr. Prabu.C, (Surveyor)4. Mr. Vijayarahavan.D, (Surveyor)

    For M/s Tolani Fabricators.5. Mr. Arvind Singh, (Project Manager)

    6. Mr.Parmar, (QC Manager)7. Mr. Sanam, (Site-in Charge)8. Mr.Subbarao (QC Engineer)9. Mr. Mohammed Abuhasim.M, (QC Engineer)

    INSPECTION CARRIEDOUT:-

    Stringing of pipes upto chainage 7540 metres (0 to 1675, 1825 to 4200, 4800 to7000, and 8000 to 9300) checked.

    Weld visual check of 152 jointsdone and found acceptable.

    Welder Mr.Sajil(welder no 14) tested for WPS-6. Radiography reviewed and foundacceptable. Hence, the welder gets qualified for WPS-6.

    Radiographs of 223 jointsreviewed and 182 joints found acceptable. 24 joints tobe repaired.

    Welders Pravin(welder no 2) and Vinod Kumar (welder no 12) disqualified due topoor performance.

    Coating of 125 joints accepted.

    STATUS OF WORK.10 MAIN LINE:

    KM-00 Total 395 joints welding completed, visually accepted. Radiography of 367joints reviewed and 314 joints accepted. 39 joints to be repaired.

    Coating of total 270 joints accepted.

    LOWERING OF 10 MAI N LIN E:

    Lowering of 722 metres from chainage 139 metres done. Level check and backfillingof first 406 metres done.

  • 8/2/2019 WQR-09

    3/5

    Report No:

    VCS/ ONGC/ RMD/ WQR/ 09ReportDate:14.08.2009

    Page 3 of 5

    WPS and respective qualified welders details given below :

    WPS Welders name Welder number

    B.Jacob (All Passes) 01Anil Kumar (All Passes) 04

    Praveen.K.P (AllPasses)

    02 disqualified

    WPS -01 (Main LineJoint for thickness14.3 mm & 18.3 mm)

    Vinod Kumar (AllPasses)

    12 disqualified

    K.Munuswamy (AllPasses)

    05WPS -02 (Main LineJoint for thickness20.6 mm) Joseph Johny (All

    Passes)06

    B.Jacob (All Passes) 01WPS -03 (Tie-in jointfor thickness 14.3mm & 18.3 mm)

    Praveen.K.P (AllPasses)

    02

    Vellaisamy(All Passes) 03WPS -04 (Tie-in jointfor thickness 20.6mm)

    Anil Kumar(All Passes) 04

    Joseph Johny 06WPS -06 ( Throughrepair procedure for14.3 & 18.3 mm) Anil Kumar 04

    Babu 08Jayanandasen 09Ajay Biswas 10Antony 11

    Filling and Cappingonly

    Sajeev 13

    Electrode qualification status

    S.No Electrode Classification Manufacturer Qualified Batch No

    1 AWS A-5.1 E 6010 (3.2 mm) Lincoln Electric S-19420836

    2 AWS A-5.1 E 7010G (4 mm) Lincoln Electric S-18389947, S -19432513

  • 8/2/2019 WQR-09

    4/5

    Report No:

    VCS/ ONGC/ RMD/ WQR/ 09ReportDate:14.08.2009

    Page 4 of 5

    Document Approval status pertaining to Mechanical works:

    First Submission Second SubmissionSr.No. Description Of Procedures Comment Date Comment Date

    1 QAP Procedure Approved 23/7/2009

    2 QA Plan Commented 18/5/2009 Approved 23/07/2009

    3 HSE Procedure Approved 5/6/2009 Approved

    4 Procurement Plan Approved 20/7/2009

    5 Incoming Material Commented 13/5/2009 Approved 30/5/2009

    6

    Transportation and Storage of

    Pipes, Materials and Equipments Commented 13/5/2009 Approved 25/6/20097 Pipe Hauling &Stringing Commented 13/5/2009 Approved 4/6/2009

    8 Welding Procedure Specification Commented 5/5/2009 Approved 7/5/2009

    9 Electrode Qualification Approved 7/5/2009 Approved

    10 Welder's Qualification Commented 15/5/2009 Approved 2/7/2009

    11 Mainline Welding Commented 7/5/2009 Approved 26/5/2009

    12 Tie-in Welding Commented 5/5/2009 Approved 6/5/2009

    13 Pipe Bending Commented 7/5/2009 Approved 4/6/2009

    14 Weld Joint numbering Commented 7/5/2009 Approved 4/6/2009

    15 NDT-Radiography(X-Ray) Commented 14/5/2009 Approved 21/6/2009

    16 NDT-Radiography(Gamma-Ray) Commented 23/6/2009

    17 Ultrasonic Testing Commented 5/4/2009 Approved 12/7/200918 NDT-Liquid Penetrant Test Commented 17/04/2009 Approved 5/4/2009

    19 Repair of Accidental Arc Burn Commented 12/5/2009 Approved 3/6/2009

    20 Weld Joint Repair Commented 5/4/2009 Approved 4/6/2009

    21 Field Joint Coating & Repair Commented 7/5/2009 Approved 26/5/2009

    22 Pipe Book Approved 23/6/2009 Approved

    23 Lowering Commented 14/5/2009 Approved 17/7/2009

    24 Pre- Hydro Testing Commented 14/5/2009 Approved 30/5/2009

    25 Hydrotesting Commented 17/5/2009

    26 Swabbing Commented 17/5/2009 Approved 6/6/2009

    27 Document Control Approved 23/6/2009 Approved

    28 Painting Of Structure And Piping Commented 12/5/200929 Insulation Joint - ITP Commented 12/08/2009

    30Piping fabrication welding andInstallation Not Submitted

    31WPS For Piping Not Submitted

    32Procedure for Commissioning

    Not Submitted

  • 8/2/2019 WQR-09

    5/5

    Report No:

    VCS/ ONGC/ RMD/ WQR/ 09ReportDate:14.08.2009

    Page 5 of 5

    B- Civil Work.

    PERSONS PRESENT:-

    1. Mr. Madhusoodhanan Nair.G, (Surveyor), Velosi Certification Services (I) Pvt, Ltd.

    2. Mr. Radhakrishnan, Tolani Fabricators.

    3. Mr. Patel, Tolani Fabricators.

    4. Mr. Sanam, Tolani Fabricators.

    INSPECTION CARRIEDOUT:-

    RoU, Clearing and Grading upto 10900 metres total (0 to 1675 & 1825 to 11050)checked.

    Trenching done for 1315 meteres total from chainage 139 m.

    Document Approval Status pertaining to Civil works :

    First Submission Second SubmissionSr.No. Description Of Procedures Status Date Status Date

    1 ROU Cleaning and Grading Commented 13/5/2009 Approved 4/6/2009

    2 Trenching Commented 12/5/2009 Approved 13/7/2009

    3 Cased Crossing Commented 14/5/2009 Approved 5/6/2009

    4 Back-filling Commented 12/5/2009 Approved 13/7/2009

    5 Restoration of ROW Commented 12/5/2009 Approved 21/6/2009

    6

    Pipeline Marker fabrication and

    Installation Not Submitted