workshop on treatment ofworkshop on treatment of
TRANSCRIPT
Workshop on Treatment ofWorkshop on Treatment of Conventional Generators
Gate 3 ITC Update – Simon Grimes
Grid25 Update – Andrew Cooke
26th August 2009
Outline
• Conventional Plant in Gate 3
• Progress on ITCg
• Grid25 Update
• Summary
Conventional Plant in Gate 3
• 6500MW + being considered in the ITC
• Conventional applications being modelled in same way as renewables
• Draft Direction proposes c. 1600MW plus an interconnector eligible for an offer
• 500MW to be chosen based on ITC
Gate 3 ITC Status (1)
• Initial ITC run started Q1 2009
• Initial results highlighted potential improvements to provide earlier firm access
• Decision made to re-start ITC to include changes to the schedule & scale of line uprates, new build schedule & demand growth
• Overall changes should serve to provide earlier firm access
• ITC runs re-started July 2009
Gate 3 ITC Status (2)
• Completed 2010, 2011 & 2012 ITC runs
• On course to finish ITC runs by January 2010
• ITC Results provision schedule:
– 2010-2013: September 2009– 2014-2017: November 20092014 2017: November 2009– 2018-2021: Early January 2010– 2022-2025: End January 2010
• Connections offers to conventionals will issue within the agreed Gate 3 offer delivery schedule for renewables
Offer Schedule
Area Offers Issue
K 1 7/12 /200 9
D 0 2/04 /201 0
H2 2 9/07 /201 0
H1 1 7/09 /201 0
B 1 3/10 /201 0
F 23 /11/2 010
E 07 /03/2 011
J 13 /04/2 011
A 10 /06/2 011
C 15 /06/2 011
G 17 /06/2 011
I 21 /06/2 011
Amendments to ITC Program Assumptions
• Line uprates
– key aspect in providing firm access (particularly in early years)
– have identified HTLS conductor which enables quicker line uprating
– Schedule prioritised in first instance on basis of overload levels observed in Grid25Grid25
– re-prioritisation following each annual ITC run
• New build
– schedule based on ongoing work on Grid25
• Demand growth
– using revised growth projections
• Conventionals
– progressing runs on basis of draft CER direction
Advancing Gate 3 Firm Access Quantities
• Proposing to perform additional constraints modelling to determine if FAQs id d b ITC P b d dprovided by ITC Program can be advanced
• High level proposal is to offer firm access where level of constraints below certain thresholds
• Possible methodologies currently being looked atg y g
• Methodology employed will need to align with emerging scheduling & dispatch policiespolicies
• May result in FAQs provided as part of initial offers being improved
G id25 U d tGrid25 Update
Primary Corridors for Reinforcement
• Grid25 identified primary corridors for reinforcement
*
reinforcement
• The analysis gave a good indication of the type of solutions that would work
– 2,300km uprating of existing circuits – 1,150km new build
• These “solutions” are being used in the Gate 3These solutions are being used in the Gate 3 process
• They give correct scale and capacity required
• The projects we bring forward may be variants of these but will have the required capacity and will be of similar scale, so differences will be second order
Gate 3 Network Programmingg g
• 2,300 km Line Uprates– Programmed over next 15 years to 2025– Prioritised in first instance on basis of overload levels observed in Grid25– Re-prioritisation following Gate3 ITC runs
• New conductor type (GAP) being adopted– Years of experience using GAP in other countries, but new to Ireland– Efficient and cost effective way to uprate– Test on real 220 kV line programmed for next year
• 1,150 km New Build– Major reinforcements being advanced in each region
• Cork – Dublin• Kerry – Cork• Mayo to East• Donegal to rest of System
– These corridors represent major blocks to renewable generation
Next Stepsp
Progress to Planning Permission
Wide Range of Possible Options(all must be adequately assessed)
Environmental Assessment
Detailed Techno-Economic Modelling
Smaller Range of Options
Detailed Technical & Environmental Analysis of Alternatives p
Statutory Consultation O
Single Option
on Alternative Options
Planning Application
Preparation of Environmental Impact Statement and Planning Submission
Consultation
Optimisation Example: Cork – Dublin Route
Consideration given to inter-alia:
*
• Assessment of Environmental Impacts in the study area including offshore
• All plausible routes and connections between Cork and Dublin
• Synergies with other potential network requirements e.g. routing the circuit so it can be used to reinforce south midlands and east midlands
• Range of technologies: HVDC v HVAC, UGC v OHL etc
• Capital and Life-Time Costs
• Reliability, Operability and Longevity of the alternative options
• Feedback from Public Consultation
Other Efforts to Achieve Success
• Grid25 Implementation Plan
• Ongoing stakeholder engagement to build publicSORNE
HILLTRILLICK
ARDNAGAPPARY• Ongoing stakeholder engagement to build public acceptability for infrastructure rollout
• Engaging with Regional Planning Authorities to ensure
KILTOY
CATHALEEN'SFALL
TAWNAGHMORE
TO STRABANE
TO ENNISKILLEN
GOLAGH
MEENTYCAT
DRUMKEEN
NORTHERNIRELAND
LETTERKENNY
SLIGO
BINBANE
LISDRUM
TIEVEBRACK
CORDERRY
CLIFF
MULREAVY
inclusion of Policy Framework for transmission grid into Regional Planning Guidelines
• Planning Authorities are required to comply with
MOY
RICHMOND
PLATIN
-ON-
DRYBRIDGE
DUNDALK
MEATHHILL
BELLACORICK
GILRA
KINNEGAD
DALTON
CORRACLASSYCUNGHILL
STEVENSTOWN
GORMAN
GORTAWEE
ARVA
MULLAGHARLIN
ARIGNA
TONROE
NAVAN
KNOCKUMBER
SHANKILL
RATRUSSAN
KENTSTOWN ROAD
MID CAVAN
SCREEBCLOON
CARRICK
GLENREE
LOUTH
RB
MAYNOOTH INCHICORE
FINGLASCOLLEGE
PARK
RINAWADE
CORDUFF
HUNTSTOWNGLASMORE
NORTH WALLPOOLBEG
SHELLYBANKS
IRISHTOWN
DUNFIRTH
BALTRASNA
BALGRIFFIN
FLAGFORD
SHANNON
ATHLONE
CARROWBEG
CASTLEBAR
MULLINGAR
SRANANAGH
DERRYIRON
GARVAGH
EAST WEST HVDC INTERCONNECTOR
WOODLAND
LANESBORO
Planning Authorities are required to comply with Regional Planning Guidelines (formally ‘shall have regard for’)
Engaging with other TSOs in Europe to ensure best
CASHLA
GALWAY
ENNIS
DALLOWTURLOUGH
HILL
CRANE
CARLOW
RATHKEALE
MONEYPOINT
KELLIS
CASHLA
TULLABRACK
MUNGRET
MONETEEN
SOMERSET
STRATFORD
OLDSTREET
BALLYBEG
TIPPERARY
NENAGH
PROSPECT
DERRYBRIEN
AGANNYGAL
AUGHINISH
BOOLTIAGH
BALLYWATER
KILLONAN
LIMERICK
PORTLAOISE
IKERRIN
TARBERT
THORNSBERRY
WEST MIDLAND
CASTLEFARMSEALROCK
BALLYCUMMIN
TYNAGH
LAOIS
SINGLANDBANOGE
LODGEWOOD
ATHY
THURLES
COOKSTOWNBLAKE
FASSAROE
POLLAPHUCA
CARRICKMINES
IRISHTOWN
CHARLESLANDBARODA
DUNSTOWN
KILTEEL
CHERRYWOOD
DRUMLINE
SALTHILL
CAUTEEN
CASTLEDOCKRILL
BALLYRAGGET
KILKENNY
MONREAD
SOUTHGREEN
ARKLOW
LISHEEN
CUSHALING
KEELDERRY
DROMADA
NEWBRIDGE
SHANNONBRIDGE
• Engaging with other TSOs in Europe to ensure best practice applied here
• Seeking out new technologies e.g. GAP conductor, WHITEGATE
CAHIRDOON
ANNER
BALLYDINE
GREAT ISLAND
BARRYMORE
CHARLEVILLE
BANDON
DUNMANWAY
KNOCKEARAGH
BRINNY
BUTLERSTOWN
RAFFEEN
AGHADA
BALLYLICKEY
KILLOTERANCULLENAGH
TIPPERARY
GLENLARA
INNISCARRA
WEXFORD
KNOCKRAHA
OUGHTRAGH
TRALEE
CARRIGADROHID
COOLROE
TRABEGMARINA
CROSSHARTNETT’S
MACROOM
TRIEN
GARROW
DUNGARVANMALLOW
WATERFORD
CLAHANE
GLANLEE
CLASHAVOONCOOMAGEARLAHY
CLONKEEN
BOGGERAGH
KNOCKACUMMERCLOGHBOOLA
DROMADAATHEA
KILBARRY
Tower Types
Summary
• ITC is running on schedule and first results expected to be published in October 2009
• Current ITC is based on draft direction
• EirGrid is seeking to increase the allocation of firm access quantities where feasible
• Grid25 is progressing including identification of new build projects
Thank You