 220-132-33 KV SS PROJECT                    1/17 PROJECT COMPLETION PERIOD: 30 MONTHS WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 KV SUB-STATION PROJECT COMPLETION PERIOD: 30 MONTHS SL. Description Months 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 Approval of Project Schedule 4 5 Mobilization  Advance 6 7 Levelling of Land 8 Soil Investigation 9 Master Plan Preparation 10 11 Submission of Drawing 12 Drawing  Approval 13 14 Inspection of materials 15 Despatch of materials 16 Sub station Lay-out Signing of Contract Agreement by CPC Submission of detail Project Schedule by Contractor Handing over Land to Contractor Approval of Sub Vendor/sub contractor Submission of Drawing submission schedule Submission of Inspection schedule

Upload: hoangtu

Post on 06-Jul-2018

242 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 …old.optcl.co.in/ten/BAR_26_chart.pdf · 22013233 kv ss project 1/17 project completion period: 30 months work schedule/bar chart for

 220­132­33 KV SS PROJECT                    1/17 PROJECT COMPLETION PERIOD: 30 MONTHS

WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 KV SUB­STATION PROJECT COMPLETION PERIOD: 30 MONTHS

SL.  DescriptionMonths

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

1

2

3Approval of Project Schedule

45 Mobilization  Advance

67 Levelling of Land8 Soil Investigation9 Master Plan Preparation

1011 Submission of Drawing12 Drawing  Approval

1314 Inspection of materials15 Despatch of materials16 Sub station Lay­out

Signing  of  Contract Agreement by CPCSubmission  of  detail  Project Schedule by Contractor

Handing  over  Land  to Contractor

Approval  of  Sub  Vendor/sub contractor

Submission  of  Drawing submission schedule

Submission  of  Inspection schedule

Page 2: WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 …old.optcl.co.in/ten/BAR_26_chart.pdf · 22013233 kv ss project 1/17 project completion period: 30 months work schedule/bar chart for

 220­132­33 KV SS PROJECT                    2/17 PROJECT COMPLETION PERIOD: 30 MONTHS

17

18

19

20 Foundation of  Column

2122 Foundation of  Equipment 

23

2425 Installation of  Equipment

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

2627 Cable Trench

28

29

Construction  Power  and water SupplyConstruction  of  Boundary wall, Site Store, Site Office & Security shed  etc.Control  Room  With  Office Building

Erection  of  Column  and Beam

Erection  of  Equipment StructuresBus  Bar  Stringing, Jumpering,  Equipment Connection

Earthmat  Laying  and Earthing

Cable  Laying  and TerminationFoundation  &  Erection  of Station Transformer

Page 3: WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 …old.optcl.co.in/ten/BAR_26_chart.pdf · 22013233 kv ss project 1/17 project completion period: 30 months work schedule/bar chart for

 220­132­33 KV SS PROJECT                    3/17 PROJECT COMPLETION PERIOD: 30 MONTHS

3031 Transformer Foundation32 Erection of Transformer.

3334 Switch Yard Illumination35 Switch Yard Fencing36   A/c system37   Erection of C. R. Panel

38

39

40

4142   Road43   Quarters

4445 Plantation46 Testing 47 Inspection  48 Metering

    Sand  &  Metal  spreading/ site surfacing

Supply  &  Erection  of  Fire fighting system

Installation  of  Battery  with ChargerErection  of  A.C.D.B.  and D.C.D.B.Installation  of  PLCC Equipments    Illumination  of  Control Room

Drainage  system/  Rain harvesting

Page 4: WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 …old.optcl.co.in/ten/BAR_26_chart.pdf · 22013233 kv ss project 1/17 project completion period: 30 months work schedule/bar chart for

 220­132­33 KV SS PROJECT                    4/17 PROJECT COMPLETION PERIOD: 30 MONTHS

49 Commissioning

50Material  Reconciliation  & handing over of S/s

Page 5: WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 …old.optcl.co.in/ten/BAR_26_chart.pdf · 22013233 kv ss project 1/17 project completion period: 30 months work schedule/bar chart for

 220­132­33 KV SUB­STATION PROJECT                     5/17 PROJECT COMPLETION PERIOD:24 MONTHS

WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 KV SUB­STATION PROJECT COMPLETION PERIOD:24 MONTHS 

SL.  DescriptionMonths

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

1

23 Approval of Project Schedule

4Handing over Land to Contractor

5 Mobilization  Advance

67 Levelling of Land8 Soil Investigation9 Master Plan Preparation

1011 Submission of Drawing12 Drawing  Approval

1314 Inspection of materials15 Despatch of materials16 Sub station Lay­out

Signing  of  Contract  Agreement by CPCSubmission  of  detail  Project Schedule by Contractor

Approval  of  Sub  Vendor/sub contractor

Submission  of  Drawing submission schedule

Submission  of  Inspection schedule

Page 6: WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 …old.optcl.co.in/ten/BAR_26_chart.pdf · 22013233 kv ss project 1/17 project completion period: 30 months work schedule/bar chart for

 220­132­33 KV SUB­STATION PROJECT                     6/17 PROJECT COMPLETION PERIOD:24 MONTHS

17

18

1920 Foundation of Column21 Erection of Column and Beam22 Foundation of  Equipment 

23

2425 Installation of Equipment

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 242627 Cable Trench28 Cable Laying and Termination

29

3031 Transformer Foundation32 Erection of Transformer.

Construction  Power  and  water SupplyConstruction  of  Boundary  wall, Site Store, Site Office & Security shed etc.Control  Room  With  Office Building

Erection  of    Equipment StructuresBus  Bar  Stringing,  Jumpering, Equipment Connection

 Earthmat Laying and Earthing

Foundation & Erection of Station TransformerSand  &  Metal  spreading  /  Site surfacing

Page 7: WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 …old.optcl.co.in/ten/BAR_26_chart.pdf · 22013233 kv ss project 1/17 project completion period: 30 months work schedule/bar chart for

 220­132­33 KV SUB­STATION PROJECT                     7/17 PROJECT COMPLETION PERIOD:24 MONTHS

3334 Switch Yard Illumination35 Switch Yard Fencing36   A/c system37   Erection of C. R. Panel

38

39

40Installation of PLCC Equipments

41   Illumination of Control Room42   Road43   Quarters

4445 Plantation46 Testing 47 Inspection  48 Metering49 Commissioning

50

Supply & Erection of Fire fighting system

Installation  of  Battery  with ChargerErection  of  A.C.D.B.  and D.C.D.B.

Drainage  system/Rain harvesting

Material  Reconciliation  & handing over of S/s

Page 8: WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 …old.optcl.co.in/ten/BAR_26_chart.pdf · 22013233 kv ss project 1/17 project completion period: 30 months work schedule/bar chart for

 

 220­132­33 KV SUB­STATION PROJECT                    8/17 PROJECT COMPLETION PERIOD:18 MONTHS

WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 KV SUB­STATION PROJECT COMPLETION PERIOD: 18 MONTHS

SL.  DescriptionMonths

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

1

2

3Approval of Project Schedule

45 Mobilization  Advance

67 Levelling of Land8 Soil Investigation9 Master Plan Preparation

1011 Submission of Drawing12 Drawing  Approval

1314 Inspection of materials15 Despatch of materials16 Sub station Lay­out

Signing  of  Contract Agreement by CPCSubmission  of  detail  Project Schedule by Contractor

Handing  over  Land  to Contractor

Approval  of  Sub  Vendor/sub contractor

Submission  of  Drawing submission schedule

Submission  of  Inspection schedule

Page 9: WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 …old.optcl.co.in/ten/BAR_26_chart.pdf · 22013233 kv ss project 1/17 project completion period: 30 months work schedule/bar chart for

 

 220­132­33 KV SUB­STATION PROJECT                    9/17 PROJECT COMPLETION PERIOD:18 MONTHS

17

18

19

20 Foundation of Column

2122 Foundation of Equipment 

23

2425 Installation of  Equipment

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

2627 Cable Trench

28

29

Construction  Power  and water SupplyConstruction  of  Boundary wall, Site Store, Site Office & security shed  etc.Control  Room  With  Office Building

Erection  of  Column  and Beam

Erection  of  Equipment StructuresBus  Bar  Stringing, Jumpering,  Equipment Connection

Earthmat  Laying  and Earthing

Cable  Laying  and TerminationFoundation  &  Erection  of Station Transformer

Page 10: WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 …old.optcl.co.in/ten/BAR_26_chart.pdf · 22013233 kv ss project 1/17 project completion period: 30 months work schedule/bar chart for

 

 220­132­33 KV SUB­STATION PROJECT                    10/17 PROJECT COMPLETION PERIOD:18 MONTHS

3031 Transformer Foundation32 Erection of Transformer.

3334 Switch Yard Illumination35 Switch Yard Fencing36   A/c system37 Erection of C. R. Panel

38

39

40

41 Illumination of Control Room

42   Road43   Quarters

4445 Plantation46 Testing 47 Inspection  48 Metering

Sand & Metal spreading/ Site surfacing

Supply  &  Erection  of  Fire fighting system

Installation  of  Battery  with ChargerErection  of  A.C.D.B.  and D.C.D.B.Installation  of  PLCC Equipments

Drainage  system/Rain harvesting

Page 11: WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 …old.optcl.co.in/ten/BAR_26_chart.pdf · 22013233 kv ss project 1/17 project completion period: 30 months work schedule/bar chart for

 

 220­132­33 KV SUB­STATION PROJECT                    11/17 PROJECT COMPLETION PERIOD:18 MONTHS

49 Commissioning

50Material  Reconciliation  & handing over of S/s

Page 12: WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 …old.optcl.co.in/ten/BAR_26_chart.pdf · 22013233 kv ss project 1/17 project completion period: 30 months work schedule/bar chart for

 220 KV & 132 KV TRANSMISSION LINE PROJECT PROJECT COMPLETION PERIOD: 30 MONTHS

WORK SCHEDULE /BAR CHART FOR 220 KV/132 KV TRANSMISSION LINE PROJECT COMPLETION PERIOD:30 MONTHS 

SL.  DescriptionMonths

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

1

2

3 Approval of Project Schedule

4 Mobilization  Advance

56 Approval of Sub Vendor7 Drawing Submission 8 Drawing Approval

910 Supply of Line Materials

10.1 Stubs10.2 Tower Structure10.3 Insulators and Hardware10.4 Conductors and Accessories11 Erection Activities

Signing  of  Contract AgreementSubmission  of  Project Schedule by Contractor

Check  Survey  (Land Schedule and Profile Plotting if necessary)

Submission  of  Inspection schedule

Page 13: WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 …old.optcl.co.in/ten/BAR_26_chart.pdf · 22013233 kv ss project 1/17 project completion period: 30 months work schedule/bar chart for

 220 KV & 132 KV TRANSMISSION LINE PROJECT PROJECT COMPLETION PERIOD: 30 MONTHS

11.1  Foundation 11.2 Earthing11.3 Erection of Towers 

11.4

11.5 Tower Accessories Fitting 

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

12 Stringing

12.1

1314 Statutary Inspection of Line

1516 Testing17 Charging of line

18

Punching/Welding of Towers (Bolt and Nut) 

Conductor and E/W Stringing including  Fixing  of Accessories Revetment/Stone Pitching for protection of Tower Base.

Rectification  of  Defects noticed during Inspection

Reconciliation  of  material and final handing over

Page 14: WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 …old.optcl.co.in/ten/BAR_26_chart.pdf · 22013233 kv ss project 1/17 project completion period: 30 months work schedule/bar chart for

 220 KV & 132 KV TRANSMISSION LINE PROJECT                    14/17 PROJECT COMPLETION PERIOD: 24 MONTHS

WORK SCHEDULE/BAR CHART FOR 220 KV & 132 KV TRANSMISSION LINE PROJECT COMPLETION PERIOD: 24 MONTHS

SL.  DescriptionMonths

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

1

2

3 Approval of Project Schedule4 Mobilization  Advance

5

6 Approval of Sub Vendor7 Drawing Submission 8 Drawing Approval

9

10 Supply of Line Materials10.1 Stubs10.2 Tower Structure10.3 Insulators and Hardware10.4 Conductors and Accessories11 Erection Activities

Signing  of  Contract AgreementSubmission  of  Project Schedule by Contractor

Check  Survey  (Land Schedule and Profile Plotting if necessary)

Submission  of  Inspection schedule

Page 15: WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 …old.optcl.co.in/ten/BAR_26_chart.pdf · 22013233 kv ss project 1/17 project completion period: 30 months work schedule/bar chart for

 220 KV & 132 KV TRANSMISSION LINE PROJECT                    15/17 PROJECT COMPLETION PERIOD: 24 MONTHS

11.1  Foundation 11.2 Earthing

11.3 Erection of Towers 

11.4

11.5 Tower Accessories Fitting 

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

12 Stringing

12.1

13

14 Statutary Inspection of Line15 Testing 

16

17 Charging of line

18

Punching/Welding of Towers (Bolt and Nut) 

Conductor  with  E/W Stringing  including  Fixing  of Accessories Revetment/Stone Pitching for protection of Tower Base.

Rectification  of  Defects noticed during Inspection

Reconciliation  of  material and final handing over

Page 16: WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 …old.optcl.co.in/ten/BAR_26_chart.pdf · 22013233 kv ss project 1/17 project completion period: 30 months work schedule/bar chart for

 220 KV & 132 KV TRANSMISSION LINE PROJECT                    16/17 PROJECT COMPLETION PERIOD: 18 MONTHS

WORK SCHEDULE/BAR CHART FOR 220 KV & 132 KV TRANSMISSION LINE PROJECT COMPLETION PERIOD: 18 MONTHS

SL.  DescriptionMonths

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

1

2

3 Approval of Project Schedule4 Mobilization  Advance

5

6 Approval of Sub Vendor7 Drawing Submission 8 Drawing Approval

9

10 Supply of Line Materials10.1 Stubs10.2 Tower Structure10.3 Insulators and Hardware

10.4Conductors and Accessories

11 Erection Activities

11.1  Foundation 11.2 Earthing

Signing  of  Contract AgreementSubmission  of  Project Schedule by Contractor

Check  Survey  (Land Schedule and Profile Plotting if necessary)

Submission  of  Inspection schedule

Page 17: WORK SCHEDULE/BAR CHART FOR 220 KV/ 132 KV/33 …old.optcl.co.in/ten/BAR_26_chart.pdf · 22013233 kv ss project 1/17 project completion period: 30 months work schedule/bar chart for

 220 KV & 132 KV TRANSMISSION LINE PROJECT                    17/17 PROJECT COMPLETION PERIOD: 18 MONTHS

11.3 Erection of Towers 

11.4

11.5 Tower Accessories Fitting 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

12 Stringing

12.1

13

1415 Testing 

16

17 Charging of line

18

Punching/Welding of Towers (Bolt and Nut) 

Conductor  with  E/W Stringing  including  Fixing  of Accessories Revetment/Stone Pitching for protection of Tower Base.

Statutary Inspection of Line

Rectification  of  Defects noticed during Inspection

Reconciliation  of  material and final handing over