WOODY 2000 PROJECT (Wideman, M., n.d.) Woody 2000 project analysis is based on the book 'Effective Project Management: Traditional, Agile, Extreme' (Wysocki, 2009). Costs and time for obtaining mandatory inspections and permits used in work are based on research of various costs and time required for those services in BC, Canada, mostly for City Pit Meadows (2007) and City Vancouver (2011). DEFINITION CONDITION OF SATISFACTION (Wysocki, 2009, pp52-56) 1. Obtaining required documentation; 2. Production capacity area enlarged by the equivalent of 25% of existing production capacity; 3. Installation of air conditioning for facility; 4. Dust free paint and finishing shop installation; 5. Additional compressor capacity installation; 6. Installation of semi-automatic woodworking production train; 7. Passing trough all mandatory inspections; 8. Budget $ 15,000,000.-; 9. Project duration 18 months PLAN CONDUCTING PLANNING SESSION 1. Create WBS including Activity List 2. Subject matter experts develop further decomposition 3. Estimate task duration and resource needs 4. Construct project network diagram 5. Determine critical path 6. Revision and approval of completion date 7. Finalization of resource schedule

Upload: wust53

Post on 05-Dec-2014

8.093 views

Category:

Technology


3 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Woody 2000 project

WOODY 2000 PROJECT (Wideman, M., n.d.)

Woody 2000 project analysis is based on the book 'Effective Project Management: Traditional, Agile, Extreme' (Wysocki, 2009). Costs and time for obtaining mandatory inspections and permits used in work are based on research of various costs and time required for those services in BC, Canada, mostly for City Pit Meadows (2007) and City Vancouver (2011).

DEFINITION CONDITION OF SATISFACTION (Wysocki, 2009, pp52-56) 1. Obtaining required documentation; 2. Production capacity area enlarged by the equivalent of 25% of existing production capacity; 3. Installation of air conditioning for facility; 4. Dust free paint and finishing shop installation; 5. Additional compressor capacity installation; 6. Installation of semi-automatic woodworking production train; 7. Passing trough all mandatory inspections; 8. Budget $ 15,000,000.-; 9. Project duration 18 months

PLAN CONDUCTING PLANNING SESSION 1. Create WBS including Activity List 2. Subject matter experts develop further decomposition 3. Estimate task duration and resource needs 4. Construct project network diagram 5. Determine critical path 6. Revision and approval of completion date 7. Finalization of resource schedule

Page 2: Woody 2000 project
Page 3: Woody 2000 project

GANTT CHART

Page 4: Woody 2000 project
Page 5: Woody 2000 project
Page 6: Woody 2000 project
Page 7: Woody 2000 project
Page 8: Woody 2000 project
Page 9: Woody 2000 project
Page 10: Woody 2000 project
Page 11: Woody 2000 project
Page 12: Woody 2000 project
Page 13: Woody 2000 project
Page 14: Woody 2000 project
Page 15: Woody 2000 project
Page 16: Woody 2000 project
Page 17: Woody 2000 project
Page 18: Woody 2000 project

WORK BREAKDOWN STRUCTURE

Page 19: Woody 2000 project
Page 20: Woody 2000 project
Page 21: Woody 2000 project
Page 22: Woody 2000 project
Page 23: Woody 2000 project
Page 24: Woody 2000 project
Page 25: Woody 2000 project
Page 26: Woody 2000 project
Page 27: Woody 2000 project

RISK IDENTIFICATION & MITIGATION Risks

a. Weather conditions – in BC weather, especially depending on where is Someplace may be located, during the winter time may have unpredictable consequences on works execution and, therefore, schedule as well.

b. Schedule – schedule is calculated with minimal flexibility. That is the reason to watch execution, delivery and mandatory inspections closely. In order to do that frequent audits should be performed in order to control development of the projected plan and in order to enable continuous analysis which may improve execution in the future. C

c. Obtaining mandatory licenses and permits timely Mitigation of the risks

a. Weather – considering that most of construction works will be during the period when is abundance of snow and very cold, we should provide for covers and physical protection of work site

b. Schedule – watching closely execution of the scheduled tasks, in the case that crucial tasks may fall behind the schedule, we shall use increased workforce round the clock as budget is providing maneuvering space for it.

c. Mandatory licenses and permits – S&P schedule is planned the way that allowing some spare time for obtaining mandatory licenses and permits and secure them as required

RISK MONITORING AND CONTROL Upon identification, assessment of probability and impact of possible risk is made, risks shall be noted. Risk log will be formed, stating ID number, description, owner, action to be taken and outcome (Wysocki, 2010, pp188-189). CRITICAL PATH There are few tasks on critical path, Project and Planning, Semi Automated Wood Train software development, Foundation Construction Preparation, Erection of I-beams for construction of extension, Roof and Walls construction and fitting and preparation of Semi-automated Wood Train preparation, which were allowed for extra time in addition to calculated requirement for execution in amount 10-12%. Most of the task on the critical path may be also under influence of weather conditions. REVISION AND APPROVAL OF COMPLETION TIME Revision of the current time schedule is not required. FINALIZATION OF RESOURCE SCHEDULE Schedule as shown in Gantt chart does not require changes in resource schedule and at this point there is no need for requesting additional resources. References:

Wideman, M. (n.d.) Project management case study: the custom woodworking company — Woody 2000 project [Online]. Available from: http://www.maxwideman.com/papers/woody2000/intro.htm (Accessed: 2 March 2011).

Wysocki, R.K. (2009), 'Effective Project Management: Traditional, Agile, Extreme', 5th ed., Indianapolis,

USA, Wiley Publishing Inc. City of Pit Meadows (2007), Website, Available at: http://www.pittmeadows.bc.ca/EN/main/business/1156/1187/1283.html, (Accessed: 22 April 2011) City of Vancouver (2011), Website, Available at: http://vancouver.ca/business.htm, (Accessed: 22 April 2011)