wind collector

Upload: clyde-dy

Post on 07-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Wind Collector

    1/14

    POWER Engineers, Inc.

    Western Protective Relaying Conference

    Wind PlantWind Plant

    Collector Substation ProtectionCollector Substation Protection

    Mr. John J. Kumm, P.E.POWER Engineers, Inc.

    POWER Engineers, Inc.

    Wind Generation Resources

  • 8/3/2019 Wind Collector

    2/14

    POWER Engineers, Inc.

    Renewable Portfolio Standard: 20% by 2030

    POWER Engineers, Inc.

    Introduction & Outline

    Background & Objectives

    Utility Interface

    Transmission Line Protection

    Transmission-Voltage Bus Protection

    Collector Substation Transformer

    Protection Collector-Voltage Bus Protection

    Collector Protection

    Capacitor Bank Protection

  • 8/3/2019 Wind Collector

    3/14

    POWER Engineers, Inc.

    The Wind Plant

    Intertie

    Switchyard

    Collector

    Substation

    Collector System

    POWER Engineers, Inc.

    Background & Objectives

    Wind plants now have planned build-outsto 1,000 MW, interconnect voltages to345 kV

    Plants represent a large investment andappreciable production resource

    Protection objectives of Dependability,Security, Selectivity, Speed, Simplicity,Economics all apply

  • 8/3/2019 Wind Collector

    4/14

    POWER Engineers, Inc.

    Typical Collector Substation Topology

    POWER Engineers, Inc.

    Wind Turbine Generator Types

    Type A Simple Induction Machine

    Type B Wound Rotor Induction withVariable Resistance

    Type C Doubly-fed Induction

    Type D Full Converter Interface

    generator

    full power

    Plant

    Feedersac

    to

    dc

    dc

    to

    ac

    generator

    partial power

    PlantFeeders

    acto

    dc

    dcto

    ac

    generator

    Slip power

    as heat loss

    PlantFeeders

    PF controlcapacitors

    ac

    to

    dc

    generator

    PlantFeeders

    PF controlcapacitors

    Type A Type B Type C Type D

  • 8/3/2019 Wind Collector

    5/14

    POWER Engineers, Inc.

    Utility Interface

    Utility requirements for protection &control vary with location, voltage level

    Determine protection scheme,communication, control, & datarequirements as early as possible

    Consider protection signaling, breakerfailure transfer trip, remote metering &

    control

    POWER Engineers, Inc.

    Transmission Line Protection

    WTGs may not provide large or enduringcurrents for line faults

    Frequently, the wind park is served by anew OPGW-equipped line

    Dual, high-speed protection schemes are

    typical and increasingly likely withincreasing line voltage and/or decreasingline length

  • 8/3/2019 Wind Collector

    6/14

    POWER Engineers, Inc.

    Transmission Line Protection

    In POTT schemes, use weak-infeed logicat the wind plant terminal

    DCB and line-current differential schemesare only impacted in sensitivity

    In all cases, a time-stepped backupscheme should be provided for whencommunications are out

    Many lines are initiallyor are likely tobecomethree-terminal lines.

    POWER Engineers, Inc.

    Three-Terminal Line Protection

    DCB over fiber with channel-lossmonitoring is preferred

    Several modern line-current differentialrelays support three-terminalapplications, consult with your vendor(s)

    POTT performs acceptably but needsweak-infeed logic to improvedependability

    Inter-tie utility will have the final word

  • 8/3/2019 Wind Collector

    7/14

    POWER Engineers, Inc.

    Transmission-Voltage Bus Protection

    Frequently not required as a result ofstation topology and placement ofinstrument transformers to protect thebus in the line or transformer zones

    When required, this protection needntbe exotic, high-impedance busdifferential will typically serve

    POWER Engineers, Inc.

    Collector Sub Transformer Protection

    Transformer top ratings from 100 MVA to230 MVA

    Usually the key single wind plant asset

    Dual differential is typically desired andemployed

  • 8/3/2019 Wind Collector

    8/14

    POWER Engineers, Inc.

    Collector Sub Transformer Protection

    Ground faults near the neutral ofgrounded wye windings may not drawsignificant phase current

    Consider restricted earth fault protectionfor improved sensitivity to low-windingground faults

    Monitor non-electrical trips (sudden

    pressure, temperature) using thetransformer relay for SOE & reporting

    POWER Engineers, Inc.

    Collector-Voltage Bus Protection

    34.5 kV buses may have very high faultduties (>40 kA)

    Bus faults yield high arc flash hazard,particularly in indoor switchgearinstallations

    Smaller installations may or may notinclude a bus main breaker

    Fast bus fault clearing is desirable

  • 8/3/2019 Wind Collector

    9/14

    POWER Engineers, Inc.

    Collector-Voltage Bus Protection

    High-speed bus protection through high-impedance differential or zone-interlockprotection is usually employed

    Particularly in switchgear applications,match the CT ratio and C-rating of CTsemployed in high-impedance schemes.The C-rating should be at least C200

    Backup bus time-overcurrent should be

    employed in the bus main-breakerprotection set, or in the transformer relay

    POWER Engineers, Inc.

    Collector Protection (Phase Faults)

    Coordinate with WTG step-uptransformer fuses

    Coordination with other WTGprotection is not a concern

    Cold-load pickup is not a concern,but transformer inrush may be

  • 8/3/2019 Wind Collector

    10/14

    POWER Engineers, Inc.

    Collector Protection (Phase Faults)

    Directional supervision may permit moresensitive pickup settings

    Fault duties may not offer discriminationneeded to employ an instantaneouselement

    POWER Engineers, Inc.

    Collector Protection (Phase Faults)

    Skinny laterals near the substation cancause challenges

    High available fault duties make itdifficult to protect lateral cable andcoordinate with WTG fuse.

  • 8/3/2019 Wind Collector

    11/14

    POWER Engineers, Inc.

    Collector Protection (Phase Faults)

    POWER Engineers, Inc.

    Collector Protection (Ground Faults)

    Ground fault protection can be mademore sensitive than distribution feederprotection; no single-phase laterals andlittle natural unbalance

    Be aware of cable neutral I2t rating

    Account for the effects of the WTGs andtheir step-up transformers

  • 8/3/2019 Wind Collector

    12/14

    POWER Engineers, Inc.

    Collector Protection (Ground Faults)

    POWER Engineers, Inc.

    Collector Protection (Ground Faults)

  • 8/3/2019 Wind Collector

    13/14

    POWER Engineers, Inc.

    Capacitor Bank Protection

    Overcurrent-based protection detectscatastrophic faults

    Coordinate phase overcurrent elementswith capacitor fuses and trip thecapacitor breaker

    Capacitor breaker must be rated forthis duty

    POWER Engineers, Inc.

    Capacitor Bank Protection

    Voltage-balance-based protection detectsnon-catastrophic capacitor fuseoperations

    Alarm/Trip before voltage on remaininghealthy capacitors exceeds 110% of

    rating Refer to IEEE C37.99 Guide for Shunt

    Capacitor Bank Protection

  • 8/3/2019 Wind Collector

    14/14

    POWER Engineers, Inc.

    Key Points

    Negotiate transmission protection,signaling, and data exchangerequirements early in the project

    Consider transmission relay selection andperformance for three-terminal lines

    Analyze protection scheme for gaps dueto single-point failures

    POWER Engineers, Inc.

    Key Points

    Confirm transformer and collector-voltage bus protection speed andadequacy

    Examine collector cable and neutral faultwithstand capabilities when coordinating

    collector elements