Page 1: Winchester Medical Center Campus Expansion June 21, 2011

Winchester Medical Center Campus Expansion

June 21, 2011

Page 2: Winchester Medical Center Campus Expansion June 21, 2011

CONTENTS

1. PROJECT UPDATE

2. EXTERIOR CONSTRUCTION

3. INTERIOR CONSTRUCTION

4. LOOK AHEAD SCHEDULE (3 Months)

VALLEY HEALTH - WINCHESTER MEDICAL CENTER

WMC Campus Expansion

June 21, 2011

Page 3: Winchester Medical Center Campus Expansion June 21, 2011

1. Heart and Vascular – Phase II, III and IV interior renovation underway

2. Laboratory – complete

3. North Tower – canopy steel forthcoming, exterior close-in nearing completion, interior gwb ongoing

4. Loading Dock – all bays open, new walls almost complete, new ceiling install forthcoming

PROJECT UPDATE

VALLEY HEALTH - WINCHESTER MEDICAL CENTER

WMC Campus Expansion

June 21, 2011

Page 4: Winchester Medical Center Campus Expansion June 21, 2011

VALLEY HEALTH - WINCHESTER MEDICAL CENTER

WMC Campus Expansion

AERIAL FROM NORTH

June 21, 2011

Page 5: Winchester Medical Center Campus Expansion June 21, 2011

VALLEY HEALTH - WINCHESTER MEDICAL CENTER

WMC Campus Expansion

AERIAL FROM WEST

June 21, 2011

Page 6: Winchester Medical Center Campus Expansion June 21, 2011

VALLEY HEALTH - WINCHESTER MEDICAL CENTER

WMC Campus Expansion

AERIAL FROM SOUTHEAST

June 21, 2011

Page 7: Winchester Medical Center Campus Expansion June 21, 2011

VALLEY HEALTH - WINCHESTER MEDICAL CENTER

WMC Campus Expansion

AERIAL FROM NORTHWEST

June 21, 2011

Page 8: Winchester Medical Center Campus Expansion June 21, 2011

VALLEY HEALTH - WINCHESTER MEDICAL CENTER

WMC Campus Expansion

TOWER ELEVATION

June 21, 2011

Page 9: Winchester Medical Center Campus Expansion June 21, 2011

VALLEY HEALTH - WINCHESTER MEDICAL CENTER

WMC Campus Expansion

MAIN ED ENTRY PROGRESS

June 21, 2011

Page 10: Winchester Medical Center Campus Expansion June 21, 2011

VALLEY HEALTH - WINCHESTER MEDICAL CENTER

WMC Campus Expansion

OBS UNIT OVER ED

June 21, 2011

Page 11: Winchester Medical Center Campus Expansion June 21, 2011

VALLEY HEALTH - WINCHESTER MEDICAL CENTER

WMC Campus Expansion

PEDESTRIAN BRIDGE TO EAST

June 21, 2011

Page 12: Winchester Medical Center Campus Expansion June 21, 2011

VALLEY HEALTH - WINCHESTER MEDICAL CENTER

WMC Campus Expansion

LDR CABINETRY MOCK-UP

June 21, 2011

Page 13: Winchester Medical Center Campus Expansion June 21, 2011

VALLEY HEALTH - WINCHESTER MEDICAL CENTER

WMC Campus Expansion

ICU CORRIDOR AT NURSES STATION

June 21, 2011

Page 14: Winchester Medical Center Campus Expansion June 21, 2011

VALLEY HEALTH - WINCHESTER MEDICAL CENTER

WMC Campus Expansion

ICU NURSES STATION

June 21, 2011

Page 15: Winchester Medical Center Campus Expansion June 21, 2011

VALLEY HEALTH - WINCHESTER MEDICAL CENTER

WMC Campus Expansion

ICU ROOM PROGRESS

June 21, 2011

Page 16: Winchester Medical Center Campus Expansion June 21, 2011

VALLEY HEALTH - WINCHESTER MEDICAL CENTER

WMC Campus Expansion

LOOK AHEAD SCHEDULEJune 2011  

continue exterior window installation

continue elevator installation

continue above ceiling work in ED

complete above ceiling and utility work at Loading Dock

continue interior renovation of Heart and Vascular

wk of 6/6/11 begin interior wall close-in

wk of 6/6/11 begin erection of canopy steel

wk of 6/6/11 turn on new AC units

wk of 6/13/11 begin exterior skin of ED and Boiler Plant

wk of 6/20/11 begin sitework at ED

wk of 6/20/11 begin curtainwall installation at stairs

June 21, 2011

Page 17: Winchester Medical Center Campus Expansion June 21, 2011

VALLEY HEALTH - WINCHESTER MEDICAL CENTER

WMC Campus Expansion

LOOK AHEAD SCHEDULEJuly 2011  

complete exterior window installation

continue elevator installation

continue above ceiling work in ED

continue interior renovation of Heart and Vascular

complete exterior of ED and Boiler Plant

complete curtainwall installation at stairs

continue canopy installation

wk of 7/11/11 begin interior finish install

June 21, 2011

Page 18: Winchester Medical Center Campus Expansion June 21, 2011

VALLEY HEALTH - WINCHESTER MEDICAL CENTER

WMC Campus Expansion

LOOK AHEAD SCHEDULE

June 21, 2011

August 2011  

continue elevator installation

continue above ceiling work in ED

continue interior renovation of Heart and Vascular

continue interior finish install

continue canopy installation

wk of 8/22/11 start final inspections @ ED

wk of 8/15/11 begin medical equipment installation @ ED