why turnarounds fail - best practices
TRANSCRIPT
Why Turnarounds Failto meet management expectations
David MathewsTGE Industrial ServicesCell: 281-507-9386Office: 281-867-9949
TURNAROUND FACTSACCORDING TO CII STUDY
Over 80% of turnarounds experience cost overruns
Approximately 50% of turnarounds suffer schedule slippages
90% report scope growth from 10% to 50%
Unplanned additions cost 30% to 50% more than planned work
Critical part method scheduling is implemented on less than
20% of all turnarounds
Cost control and forecasting is implemented on less than 20% of
all turnarounds
Turnaround staff experiences minimal training in modern
management concepts
Over 90% of critique recommendations are never
implemented
MOST TURNAROUNDS FAIL TO MEET MANAGEMENT EXPECTATIONS
Why Do Turnarounds Fail?
Failure to start early enough Failure to treat as projects Failure to apply Best Practices Failure to assign professional
turnaround management team Failure to control scope
Why Do Turnarounds Succeed?
– TURNAROUNDS CAN BE MANAGED SUCCESSFULLY
– SCHEDULES CAN BE MINIMIZED– COSTS CAN BE REDUCED
MANY BY 10% TO 30%!– 1st QUARTILE PERFORMERS DO IT– WHAT DO THEY DO?
WHAT DO 1ST QUARTILE PERFORMERS DO?
– START EARLY– RECOGNIZE AND MANAGE TURNAROUNDS AS PROJECTS– IMPLEMENT BEST PRACTICES– STRONG MANAGEMENT SPONSORSHIP– TURNAROUND PHILOSOPHY – DEFINITION & PURPOSE– RECOGNIZE AND MANAGE THE TURNAROUND PROCESS– STRONG EMPHASIS ON FEL– COMMITMENT TO PROJECT CONTROLS– APPLY THE RIGHT MANAGEMENT RESOURCES– APPLY ENOUGH MANAGEMENT RESOURCES– AGGRESSIVELY MANAGE AND CONTROL SCOPE– AGGRESSIVELY MANAGE AND CONTROL PERFORMANCE– BENCHMARK FOR CONTINUOUS IMPROVEMENT
Start Early
Turnaround Phase Milestone Plan
Ability to Influence Performance
HighHigh
Ability to Ability to Influence Influence
PerformancePerformance
Start Complete
LowLow
HighHigh
Project Project ExpendituresExpenditures
LowLow
Time
Scoping
Planning & Scheduling
Turnaround
Start-up
Conceptual Planning
Pre-T/A
Problems Here:
Are the result of Failings Here:
Not enough Welders? Then didn’t adequately plan the welding work!
80% Impact! 20% Impact!
TURNAROUND PROCESS- ABILITY TO INFLUENCE PERFORMANCE
Conceptual Development
TIMEMonths
90%
80%
70%
60%
Scope Development
Pre-Turnaround
TurnaroundExecution
&Control
Post-Turnaround
50%
40%
30%
20%
10%
COST
Detailed Planning & Scheduling
Contracting Strategy
Buy Long Lead Items
ResourceLeveling
ContractorSelection
INFLUENCE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Form TurnaroundTeam
Start Early The Planning Process on most
turnarounds should begin 12 to 18 months prior to Turnaround start.
Pre T/A activities should be scheduled and tracked just as aggressively as the turnaround activities.
Virtually ALL Failures during Turnaround Execution can be traced to a failing in the Pre Turnaround Process.
TURNAROUND MISSION
05/01/23
Turnaround Mission, Objectives & Customer
Establish clear, objective, written mission and objective
Return the unit to “as designed” condition Implement approved capital projects The “customer” of a turnaround team should be
the unit, the asset or the corporation, as opposed to the traditional view that operations or some other group is the customer.
BEST PRACTICES
Project Management Approach -Application of CII Best Practices Alignment
Benchmarking and metrics
Change management Constructability Design effectiveness Disputes prevention &
resolution Implementation of
products
Materials management Partnering Planning for startup Pre-project planning Quality management Team building Zero accidents
techniques
Additional Best Practices for Turnarounds
Defined turnaround “purpose”
– What it is– What it is not
Strong management support Robust scoping process Aggressive change
management Start early – with adequate
resources Documented project
execution plan Documented roles &
responsibilities Develop Alliances
Archive historical data Build templates by equipment Emphasis on project controls All activities scheduled Pre-turnaround schedule –
and accountability! Involve all parties – early –
including contractors Conduct schedule reviews Conduct risk analysis Conduct readiness reviews Documented pre-turnaround
milestone schedule Capital & maintenance fully
integrated Lessons learned
05/01/23
0.00
0.50
1.00
1.50
2.00
2.50
Rec
orda
ble
Inci
dent
Rat
e
Implement all ImplementMost
Implementonly a few
Results of Implementing Best Practices
0.00
0.79
2.37
CII Study – Correlation of Best Practices to Safety Performance
Control Scope
Scope
#1 Cause of cost over runs on projects?– SCOPE CREEP
#1 Cause of cost over runs on turnarounds?– SCOPE CREEP!
Scoping Process Scoping process aimed at eliminating all non-essential, non-
turnaround scope items. Scoping team comprised of engineers, designers, operations
personnel and others to assess the condition of unit equipment and to identify gaps between current condition and as designed condition.
Apply a comprehensive scope quantification, control and change process during the course of turnaround planning & execution.
Plant turnaround scoping processes are often ineffective and can represent the primary source of cost and schedule over runs. Loop-holes in the scoping process can allow for significant scope growth after the scope freeze.
PROJECT CONTROLS
05/01/23
Turnaround Project Controls
Implement a comprehensive project controls system to include estimating, planning, cost engineering, CPM scheduling, software etc.
Develop standard estimates, work packages and schedules to be utilized across multiple sites.
Most turnaround project controls are fragmented, ineffective and do not effectively utilize modern project controls software and methodology.
Resource Leveling
Allows work to be done by fewer people over the entire time.
Avoids hiring, screening and processing people for a short period.
Supports Supervision Buy-In Maximizes Use of Tools and Equipment Promotes Better Use of Management Support Minimizes the “infrastructure” required
RESOURCE REQUIREMENTSEarly Schedule
Time Units2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36
0
50
100
150
200
250
300
350
400
EARLYEARLY
LATELATE
LEVELEDLEVELED
AvailableAvailableResourcesResources
Res
ourc
e R
equi
rem
ents
RESOURCE REQUIREMENTS (cont)Late Schedule
Time Units2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36
0
50
100
150
200
250
300
350
400
Res
ourc
e R
equi
rem
ents
EARLYEARLY
LATELATE
LEVELEDLEVELED
AvailableAvailableResourcesResources
RESOURCE REQUIREMENTS (cont)
Leveled Schedule
Time Units2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36
0
50
100
150
200
250
300
350
400
Res
ourc
e R
equi
rem
ents
EARLYEARLY
LATELATE
LEVELEDLEVELED
AvailableAvailableResourcesResources
Risk Analysis (Primavera Risk)
Provides accurate probability of success. Identifies potential problem areas. Basis for critical management decisions. Develops list of key milestones. Establishes best and worst case scenarios for
both cost and schedule. Increases confidence in schedule/budget. Supports subcontracting evaluations and
decisions.
Turnaround Cost Control
Earned Value Management System Earned vs. Actual – Productivity Factor Cost Variance Schedule Variance Real Time Information
The Objective should be “Decision Quality Information” not necessarily Accounting Level of Accuracy
PROCUREMENT AND CONTRACTS
Procurement and Sub-Contractors Turnaround Procurement strategy to include
early procurement management involvement in the FEL stage.
Develop contractor selection process aligned with performance objectives of turnaround.
Standardization of materials, services, procedures, specifications; and multi site vendor/sub-contractor alliances.
Turnaround procurement is often reactionary, fragmented and sub-optimized. Procurement decisions are often made at a management level, and a late date that is not conducive to producing low cost solutions.
EXECUTION MANAGEMENT
Execution Methods – Example Areas
Productivity Management Safety Audits & Management Permit Management Process Schedule & Cost Control
– Status each shift– Daily Status Meetings & Reports
Small Tools & Mobile Equipment Work Hours QA/QC Process Flange Management Procedure (Leak Free Start-up)
SAFETY
Safety
Implement aggressive Safety Management program in FEL stage.
Incorporate Safety considerations in all phases of scoping, planning, scheduling & execution.
Control execution to plan to avoid unplanned work.
Turnaround Critique
“Lessons Learned” Meeting Identify “Well Dones” & Opportunities for
Improvement Produce Final Job Report Serves as Basis for Continuous Improvement Implement “Lessons Learned” on Future
Turnaround
Summary
How DoTurnarounds Succeed?
Start Early Treat Turnarounds as projects Apply Best Practices Assign Professional Turnaround
Management Control Scope
05/01/23
OPPORTUNITIES FOR TURNAROUND IMPROVEMENT
Contractors and Manpower:
Just the Tip of the Iceberg
-Scope Control/Optimization-Program Management
-Project Controls-Procurement &
Subcontracts-Contractor Selection-Best Practices
-Productive Planning-Safety Management-Materials Management-Resource Leveling-Schedule Optimization-Sub Contractor Management-Execution Methods-Turnaround Critique
The Real Opportunities:
ADDITIONAL INFORMATION
The following slides are excerpts from another presentation that details the different stages of turnarounds and some of the activities that should be executed at each stage.
Conceptual Development Activities
Identify Turnaround Sponsor Form Management Team and define responsibilities. Define turnaround philosophy and goals. Review previous turnaround history. Review lessons learned from past turnarounds. Establish major work items, both expense and
capital. Develop scope criteria based on the philosophy. Develop contractor strategy. Create turnaround preparation milestone schedule Develop cost control and tracking process.
Conceptual Development Deliverables Turnaround Execution Plan Preliminary work list. Basic cost estimates (±30%). Estimated duration. Turnaround preparation milestone schedule. Manpower forecast for turnaround planning resources. Organization structure. Quality assurance, quality-control requirements. Completion of this stage can be 12-15 months before
starting the next turnaround.
Scope Development – Sources
Work order system. Capital works. Compliance items. HazOp study outputs. Operational requirements. Process engineering requirements. Environmental, safety, and health needs. Maintenance requirements. Maintainability, reliability, and constructability reviews. Resolution of conflicting needs. Long lead-time material procurement.
Scope Development - Deliverables
Work development deliverables include: Integrated plan (schedule, equipment, and resources). Preliminary critical path schedule. Refined budget estimate (±20%). Updated preliminary and approved work list. Long lead-time materials ordered. Critical lift plans. Additional work approval process. Work scope frozen. This stage should be completed 12-15 months before
the shutdown.
Detailed Planning & Scheduling- Activites
Final work list. Work Packages. Final plan for equipment cleaning and personnel entry. Contracting plan in place and all major contracts let. Critical-path schedule. Detailed execution plans. Detailed safety plan. Additional work approval process. Turnover of all capital work. Completion of materials procurement plan. Final estimate. Definition of format and frequency of performance and progress
reports.
Detailed Planning & Scheduling - Deliverables
Integrated execution plan (finalized on critical and sub-critical work).
Final budget estimates (±10%). Final work list. “What if” scenarios. Lifting plans. Mobile equipment requirements. Detailed shop loading plans. Risk Assessments. complete this detailed planning stage 4-6 months
before the turnaround.
Pre-Turnaround Activities Safety plan implementation. Operations training. Maintenance and contractor training and orientation. Team building. Environmental, safety, and management of change (MOC)
requirement review. Beginning the prefabrication work. Beginning the on-site pre-shutdown work. Detail of shutdown and unit clean-out sequences. Prepare temporary connections. Identify blind locations and hang the blinds. Install temporary offices, stores, and tool houses. Mobilize the execution team. Cost tracking and reporting. Detailed execution plan. Shutdown and clean-out plan. Work performance. Turnovers. Start-up plan.
Pre-Turnaround - Deliverables
Final execution plan. Completion of pre-shutdown work. Training the execution team. Developed turnaround organization charts. Creation of a reporting plan. Completion of field mobilization. Finalized shutdown meeting procedures. Beginning of communications-alignment meetings.
Turnaround Execution - Activities
Unit and equipment shutdown and preparation for entry. Daily turnaround meetings. Schedule reviews and updates. Daily cost tracking and reporting. Documenting MOC requirements. Additional work review and processing. Tracking additional work and scope changes. Ensuring that records reflect as-found conditions. Documenting all repairs. Documenting all inspections. Prestart-up safety review.
Turnaround Execution - Deliverables
Turnaround executed per the plan and Schedule.
Objectives met. Contingency plans reassessed as needed. Prestart-up safety review. Start-up on schedule. Release to operations.
Post Turnaround - Activities
Demobilization of contractors. Post-turnaround unit and lay-down area clean up. Resolution and disposal of excess material. Repair and inspection history reports. Updating the turnaround historical database. Post-turnaround MOC requirements. Freezing the turnaround accounts. Issuing the final cost report. Lessons learned and recommendations for future
turnarounds. Preparing the final turnaround report.
Post Turnaround - Deliverables
Post-turnaround unit and lay-down area clean up.
Planned run length. Improvement opportunities. Final reports. Final audit report of performance and adherence
to the work process. This stage should be completed 1-2 months after
the turnaround.