western dedicated freight corridor project- phase 2 (125 km) from april 2006 to august 2011. - phase...

8
Western Dedicated Freight Corridor project Backbone of DMIC (Delhi-Mumbai Industrial Corridor) The Western DFC project (Delhi–Mumbai: 1,500 km) will focus on: (1) construction of new dedicated freight lines (2) installation of automated signal & telecommunication (3) introduction of electric locomotives with high-speed & high-capacity transportation Procurement for Civil and Signalling Packages have been started W W - Kolkata Eastern Western (Phase 1) Ludiana Rewari Dadri Vadodara Delhi Mumbai 425 km 950 km 127 km DelhiMumbai DFC Western 1,500 km Corridor Western (Phase 2)

Upload: others

Post on 11-Jul-2020

4 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Western Dedicated Freight Corridor project- Phase 2 (125 km) from April 2006 to August 2011. - Phase 3 (116 km) from June 2011 to April 2016 . [Result] • 2.5 million people use the

Western Dedicated Freight Corridor project

Backbone of DMIC (Delhi-Mumbai Industrial Corridor)

The Western DFC project (Delhi–Mumbai: 1,500 km) will focus on:

(1) construction of new dedicated freight lines

(2) installation of automated signal & telecommunication

(3) introduction of electric locomotives with high-speed & high-capacity transportation

Procurement for Civil and Signalling Packages have been started

W

W

- W

-

Kolkata

Eastern

Western (Phase 1)

Ludiana

Rewari

Dadri

Vadodara

Delhi

Mumbai

425 km

950 km

127 km

Delhi~Mumbai

DFC Western

1,500 km

Corridor

Western (Phase 2)

Page 2: Western Dedicated Freight Corridor project- Phase 2 (125 km) from April 2006 to August 2011. - Phase 3 (116 km) from June 2011 to April 2016 . [Result] • 2.5 million people use the

(人)

9

0

100

200

300

400

500

600

700

800

2009 2010 2011 2012 2013 2014

295 298

268

363

234 282

368 322

610 610 659

792

Number of People

Exchange(FY)

インド人研修員 日本人専門家・調査団

18.55 16.81

26.93 24.8

34.82

37.76

0

5

10

15

20

25

30

35

40

2009 2010 2011 2012 2013 2014

Commitment Amount (FY)

Achievements in India (Technical Cooperation)

(JPY 100 million)

Indian Participant for Training

Japanese Expert / Study Team

Number of People

Page 3: Western Dedicated Freight Corridor project- Phase 2 (125 km) from April 2006 to August 2011. - Phase 3 (116 km) from June 2011 to April 2016 . [Result] • 2.5 million people use the

Implications of JICA Good Practices in India for other Emerging Countries

- Toward Win-Win Relationship -

Katsuo Matsumoto Deputy Director General, South Asia Department

Japan International Cooperation Agency

10

ESRI International Conference 30 October 2015

Page 4: Western Dedicated Freight Corridor project- Phase 2 (125 km) from April 2006 to August 2011. - Phase 3 (116 km) from June 2011 to April 2016 . [Result] • 2.5 million people use the

1. Quality Infrastructure (Delhi Metro and Purulia Pumped Storage Station) - JAPAN Brand with Competitive Lifecycle Cost

2. Corridor Approach (DMIC and CBIC) - From Planning to Implementation

3. Alignment with “Make in India” (Investment Promotion Program) - Involvement of Private Sector / Investors

OUTLINE

Page 5: Western Dedicated Freight Corridor project- Phase 2 (125 km) from April 2006 to August 2011. - Phase 3 (116 km) from June 2011 to April 2016 . [Result] • 2.5 million people use the

1. Quality Infrastructure (reliable, sustainable and resilient ) Massive demand for Infrastructure Key driver for direct investment & economic development Life-cycle Cost Saving backs country economy in a long run

2. Corridor Approach Suitable allotment of resources: royal road for development Project prioritization at the level of semi-region (corridor)

3. Alignment with “Make in India” Policy promotion and easing regulations Delivering real private sector’s voices to Government Timely input and support when required (urgent small infra.) Manufacturing Sectory↑ = Employment↑ = Consumption↑ = Boost in economy↑

Implications of JICA Good Practices in India For other Emerging Countries

12

Page 6: Western Dedicated Freight Corridor project- Phase 2 (125 km) from April 2006 to August 2011. - Phase 3 (116 km) from June 2011 to April 2016 . [Result] • 2.5 million people use the

1-1 Quality Infra: Delhi Mass Rapid Transport System Project

[Background] • Sharp increase in the population of urban Delhi 9.42 M in 1991 → 16.75 M in 2011 • Deterioration of environmental damage and traffic congestion due to an increased

number of automobiles. Number of registered cars in Delhi: 1.83 M in 1990 → 6.93 M in 2011

[Project summary] The project consists of the construction of a rapid transport system (public works, electric / telecommunication / signal works, etc.) and the procurement of vehicles. - Phase 1 (65 km) from October 1998 to November 2006. - Phase 2 (125 km) from April 2006 to August 2011. - Phase 3 (116 km) from June 2011 to April 2016.

[Result] • 2.5 million people use the metro every day (cf. 3 million people use underground railways per day in London). • The system has contributed to decreasing the number of vehicles by 120,000. • “Regenerative brake system” , introduced to metro as Japanese company’s energy-

efficient technology is expected to reduce CO2 emission by 22 million tons (total reduction between 2002 and 2032), which was registered in the United Nations as the world’s first CDM project in the railway sector.

13

Page 7: Western Dedicated Freight Corridor project- Phase 2 (125 km) from April 2006 to August 2011. - Phase 3 (116 km) from June 2011 to April 2016 . [Result] • 2.5 million people use the

1-2 Quality Infra: Purulia Pumped Storage Project

[Background] • Constant power shortage

Since 1998, about 11% to 13% of the peak-hour supply capacity; about 6% to 8% of the annual supply

• Necessity for well-balanced composition of electrical source Under the power structure where thermal power generation exceeded 90% of the total, it was necessary to eliminate the peak-hour supply-demand gap by developing a pumped storage hydropower by the use of nighttime surplus power supplied from thermal power plants.

[Project summary] In the Purulia district 300 km to the northwest of Kolkata City in the Province of West Bengal, the peak-hour power supply capacity is improved by the construction of a pumped storage power plant with an output of 900 MW (225 MW × 4 generating units) and electric transmission and substation facilities for the plant.

[Result] • The pumped storage power plant with four generating units of 225 MW is still the largest in India. • The plant has been operating without any serious trouble since the beginning of operation in 2008.

14

Page 8: Western Dedicated Freight Corridor project- Phase 2 (125 km) from April 2006 to August 2011. - Phase 3 (116 km) from June 2011 to April 2016 . [Result] • 2.5 million people use the

15

DMIC and CBIC are being supported by GoI and GoJ.

Delhi-Mumbai Industrial Corridor

Bengaluru-Mumbai

Economic Corridor

Chennai-Bengaluru Industrial Corridor

Amritsar- Kolkata Industrial Corridor

2-1 Corridor Approach : Industrial Corridors under Development (DMIC & CBIC)

• ~15% y-o-y growth in manufacturing sector to achieve 25% contribution to GDP by 2022

• 100 million jobs by 2022 • Skill development for inclusive growth • Improved technology orientation &

value addition • Global Competitiveness • Environmental sustainability

National Manufacturing Plan Targets